background image

 
 
 
 
 
 
 
 
 
 
 

GAO 

 

United States Government Accountability Office

Report to Congressional Addressees

NASA

Commercial Partners 
Are Making Progress, 
but Face Aggressive 
Schedules to 
Demonstrate Critical 
Space Station Cargo 
Transport Capabilities 

 

 

June 2009 
 

 

 

 

GAO-09-618 

background image

What GAO Found

United States Government Accountability Office

Why GAO Did This Study

H

ighlights

Accountability Integrity Reliability

June 2009

 
 

NASA

Commercial Partner

s

 Are Makin

g

 Pro

g

re

ss

, but Face 

A

gg

re

ss

ive 

S

chedule

s

 to Demon

s

trate Critical 

S

pace 

S

tation Car

g

o Tran

s

port Capabilitie

s

 

Highlights of 

GAO-09-618

, a report to 

congressional addressees 

After the planned retirement of the 
space shuttle in 2010, the National 
Aeronautics and Space 
Administration (NASA) will face a 
cargo resupply shortfall for the 
International Space Station of 
approximately 40 metric tons 
between 2010 and 2015.  NASA 
budgeted $500 million in seed 
money to commercial partners to 
develop new cargo transport 
capabilities through its Commercial 
Orbital Transportation Services 
(COTS) project.  NASA used its 
other transaction authority to 
award agreements to commercial 
partners.  These agreements are 
not federal government contracts, 
and are therefore generally not 
subject to federal laws and 
regulations that apply to federal 
government contracts. 
 
GAO previously reported concerns 
about whether COTS vehicles 
would be developed in time to meet 
the shortfall.  Subsequently, GAO 
was directed by the explanatory 
statement accompanying the 
Consolidated Appropriations Act, 
2008, to examine NASA’s 
management of the COTS project 
and its expenditures.  In addition, 
GAO was asked to examine  
(1) NASA’s reliance on commercial 
partners to meet the space station’s 
cargo resupply needs; and  
(2) progress or challenges in 
developing commercial space 
transport capabilities. 
  
GAO analyzed NASA reports, 
briefings, and other information 
and held interviews with NASA and 
commercial partner officials. NASA 
concurred with GAO’s findings. 
 

During the course of our review, we found NASA’s management of the COTS 
project has generally adhered to critical project management tools and 
activities and the vast majority of project expenditures were for milestone 
payments to COTS partners.  NASA has established fixed-price, performance-
based milestones in its agreements with commercial partners and partners are 
only paid once the milestone has been successfully completed.  NASA has also 
taken several steps since the beginning of the COTS project to ensure that 
risks were identified, assessed, and documented, and that mitigation plans 
were in place to reduce these risks.  NASA has communicated regularly with 
its partners through quarterly and milestone reviews and provided them with 
technical expertise to assist in their development efforts and to facilitate 
integration with the space station.  As of the end of fiscal year 2008, NASA has 
spent $290.1 million, with 95 percent of project funding spent on milestone 
payments to COTS partners.  
 
The vehicles being developed by commercial partners Space Exploration 
Technologies Corporation (SpaceX) and Orbital Sciences Corporation 
(Orbital) through the COTS project have become essential to NASA’s ability to 
fully utilize the space station after its assembly is completed and the space 
shuttle is retired in 2010.  NASA estimates that it will need a total of 82.7 
metric tons of dry cargo delivered to the space station between 2010 and 2015 
to meet crew needs and to support maintenance and scientific experiments.  
Commercial partners’ vehicles will transport almost half of this cargo and are 
scheduled to fly more cargo delivery missions than the space shuttle and 
international partners’ vehicles combined—including 14 of the last 19 
missions.  Delays in the availability of commercial partners’ vehicles to fill the 
cargo resupply gap would result in diminished usage of the space station. 
 
While SpaceX and Orbital have completed most of the development 
milestones required thus far on time, both companies are working under 
aggressive schedules and have recently experienced schedule slips that have 
delayed upcoming demonstration launch dates by several months.  SpaceX 
successfully completed its first 14 development milestones on time and is in 
the process of testing, fabricating, and assembling key components.  However, 
a schedule slip in the development of its launch vehicle has contributed to 
anticipated delays of 2 to 4 months in most of its remaining milestones, 
including upcoming demonstration missions.  Its first demonstration mission 
has been delayed from June 2009 to no earlier than September 2009, and its 
third demonstration mission has been delayed from March 2010 to no earlier 
than May 2010.  NASA is currently evaluating the effect of potential further 
delays.  Orbital has successfully completed 7 of 19 development milestones 
thus far, but has experienced delays in the development of its launch vehicle.  
Orbital and NASA have recently amended their agreement to demonstrate a 
different cargo transport capability than had been originally planned, delaying 
its demonstration mission date from December 2010 until March 2011. 

View GAO-09-618 or key components.

 

For more information, contact Cristina 
Chaplain at (202) 512-4841 or 
chaplainc@gao.gov. 

background image

 
 
 
 
 
 
 
 
 
 
 

Page i 

GAO-09-618 

Contents 

Letter  

1

 

Background 3 
NASA Has Adhered to Critical Project Management Tools and 

Project Expenditures Track Closely with Achieved Milestones 

NASA Will Rely on Commercial Partners to Meet Much of the 

Space Station Cargo Resupply Needs 

15 

Commercial Partners Are Making Progress, but Face Challenges 

Meeting Aggressive Development Schedules 

18 

Concluding Observations 

30 

Agency Comments and Our Evaluation 

30 

Appendix I 

Scope and Methodology 

33 

 

Appendix II 

Comments from the National Aeronautics and Space 
Administration 

35 

 

Appendix III 

GAO Contact and Staff Acknowledgments 

36 

 

Tables 

Table 1: COTS Project Funding, Obligations, and Expenditures 

through Fiscal Year 2008 

13 

Table 2: SpaceX’s Progress Completing COTS Development 

Milestones 19 

Table 3: Orbital’s Progress Completing COTS Development 

Milestones 25 

 

Figures 

Figure 1: Key Events in the Commercial Orbital Transportation 

Services Project 

Figure 2: COTS Project Expenditures to Partners and Project 

Operations through Fiscal Year 2008 

14 

Figure 3: NASA’s Strategy for Meeting Space Station Usable Dry 

Cargo Needs—2010 to 2015 

16 

 

 NASA's COTS Project 

background image

 
 
 
 
 
 
 
 
 
 
 

 

 

 

 

 

 

 

 

 

Abbreviations 

ATK 

Alliant Techsystems, Inc. 

CDR 

critical design review 

COTS Commercial 

Orbital 

Transportation Services 

CRS 

Commercial Resupply Services 

DOD 

Department of Defense  

FAA 

Federal Aviation Administration  

NASA 

National Aeronautics and Space Administration 

Orbital 

Orbital Sciences Corporation  

PDR 

preliminary design review 

RpK Rocketplane 

Kistler 

SLC-40 

Space Launch Complex 40 

SpaceX 

Space Exploration Technologies Corporation  

USAF 

U.S. Air Force 

This is a work of the U.S. government and is not subject to copyright protection in the 
United States. The published product may be reproduced and distributed in its entirety 
without further permission from GAO. However, because this work may contain 
copyrighted images or other material, permission from the copyright holder may be 
necessary if you wish to reproduce this material separately. 

Page ii 

GAO-09-618  NASA's COTS Project 

background image

 
 
 

Page 1 

GAO-09-618 

                                                                                                                                   

United States Government Accountability Office
Washington, DC 20548 

   

June 16, 2009 

Congressional Addressees 

After the planned retirement of the space shuttle in 2010, the United States 
will lack a domestic capability to send crew and cargo to the International 
Space Station. As a consequence, the National Aeronautics and Space 
Administration (NASA) faces a cargo resupply shortfall of 40 metric tons 
(approximately 88,000 pounds) between 2010 and 2015 that cannot be met 
by international partners’ space vehicles.

1

 To fill the gap, NASA plans to 

rely on vehicles being developed by the private sector through NASA’s 
Commercial Orbital Transportation Services (COTS) project. However, we 
previously reported concerns about whether these vehicles will be 
developed in time to address the shortfall.

2

 

GAO was directed through the explanatory statement accompanying the 
Consolidated Appropriations Act, 2008 to review NASA’s management of 
the COTS project and its expenditures, the first objective of this report.

3

 

Subsequently, you asked us to cover two additional objectives: examine 
the extent to which (1) NASA is reliant on commercial partners to meet 
the space station’s cargo resupply needs, and (2) commercial partners 
have made progress or experienced challenges in developing cargo 
transport capabilities. 

To examine NASA’s management of the COTS project and its 
expenditures, we interviewed NASA and company officials and analyzed 
project documentation, including agreements between NASA and its 
commercial partners, NASA’s guidance for implementing these 
agreements, development milestone and quarterly reviews and other 
briefings, and project funding and expenditures data. We also evaluated 
NASA’s management of the COTS project by comparing COTS 
management activities with critical project management tools and 

 

1

The 40 metric ton shortfall refers to usable cargo, which does not include the mass of any 

required packing materials and/or flight support equipment. Usable cargo combined with 
packing materials and/or flight support equipment is referred to as customer cargo.  

2

GAO, 

NASA: Challenges in Completing and Sustaining the International Space Station

GAO-08-581T

 (Washington, D.C.: April 24, 2008). 

3

See Explanatory Statement, Cong. Rec. H 15471, 15821 (daily ed. Dec. 17, 2007) and the 

Consolidated Appropriations Act, 2008, Pub. L. No. 110-161, § 4 (2007). 

 NASA's COTS Project 

background image

 

 

 

 
 

activities identified in NASA guidance and in prior GAO work on NASA 
projects with similarities to COTS. 

To determine the extent to which NASA is reliant on commercial partners 
to meet the space station’s cargo resupply needs, we interviewed NASA 
officials and reviewed International Space Station program office 
documentation on the space station’s cargo resupply needs and risks, 
NASA’s plans to meet its cargo resupply needs between 2010 and 2015, and 
international and commercial partners’ vehicle capabilities. We also 
reviewed NASA studies that assessed the impact of the COTS project on 
NASA’s cargo resupply strategy. 

To determine the extent to which commercial partners have made 
progress or experienced challenges in developing cargo transport 
capabilities, we reviewed each partner’s agreement with NASA, 
commercial partners’ supporting documentation submitted for each 
milestone, partners’ development schedules and technical risks, NASA’s 
requirements for integrating with the space station, commercial 
transportation space regulations, launch safety requirements, and prior 
GAO work. We also conducted field visits and interviewed commercial 
partners to determine partners’ progress against performance milestones 
and to identify development challenges. 

We conducted this performance audit from July 2008 to June 2009 in 
accordance with generally accepted government auditing standards. Those 
standards require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings and 
conclusions based on our audit objectives. We believe that the evidence 
obtained provides a reasonable basis for our findings and conclusions 
based on our audit objectives. 

 

Page 2 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

Since the 1980s, U.S. law and policy have directed NASA to encourage 
growth and promote opportunities within the commercial space industry.

4

 

NASA’s Authorization Act of 2005 directed NASA to work closely with the 
private sector to encourage entrepreneurs to develop new means to 
launch satellites, crew, or cargo, and to contract for crew and cargo 
transport services to the space station.

5

 In accordance with its long-term 

goals, NASA plans to retire the space shuttle upon completing assembly of 
the space station in 2010. NASA plans on using a mixed fleet of vehicles, 
including those developed by international partners, to service the space 
station.

6

 However, international partners’ vehicles alone cannot fully 

satisfy the space station’s cargo resupply needs. Without a domestic cargo 
resupply capability to augment this mixed fleet approach, NASA faces a 40 
metric ton (approximately 88,000 pounds) usable cargo resupply shortfall 
between 2010 and 2015.

7

 

Background 

In November 2005, NASA established the Commercial Crew and Cargo 
program office at Johnson Space Center to challenge the commercial 
space industry to establish capabilities and services that can open new 
space markets and support the space station’s crew and cargo 
transportation needs. NASA directed the program office to establish the 
COTS project and budgeted $500 million for fiscal years 2006 through 2010 
for the development and demonstration of cargo transport capabilities. 

                                                                                                                                    

4

National Aeronautics and Space Administration Authorization Act of 1985, Pub. L. No. 98-

361, § 110 (c), (1984) (codified as amended at 42 U.S.C. § 2451) declared that the general 
welfare of the United States requires that NASA seek and encourage, to the maximum 
extent possible, the fullest commercial use of space. The Commercial Space Act of 1998, 
Pub. L. No. 105-303, § 101, directed NASA to identify opportunities for the private sector to 
play a role in servicing the International Space Station. Following the Space Shuttle 
Columbia disaster in 2003, President George W. Bush’s 

A Renewed Spirit of Discovery: The 

President’s Vision for U.S. Space Exploration 

called for the shuttle’s retirement in 2010 

upon completing space station assembly, and for pursuit of commercial opportunities for 
providing transportation and other services. The August 2006 U.S. National Space Policy 
also directed departments and agencies to encourage innovation in the commercial space 
sector. 

5

National Aeronautics and Space Administration Authorization Act of 2005, Pub. L. No. 109-

155, § 101. 

6

International partners’ vehicles include the Russian Federal Space Agency’s Progress 

(cargo) and Soyuz (crew), the European Space Agency’s Automated Transfer Vehicle 
(cargo), and the Japan Aerospace Exploration Agency’s H-II Transfer Vehicle (cargo), 
which is currently in development. 

7

The 40 metric ton shortfall includes 36.9 metric tons of dry usable cargo and 3.1 metric 

tons for water, propellant, and atmospheric gases. Dry usable cargo includes food, spare 
parts, and materials to support scientific experiments. 

Page 3 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

NASA structured the COTS project as a partnership with the commercial 
space industry, sharing the risks, costs, and rewards of developing new 
space transportation capabilities. NASA expected commercial partners 
participating in the project to develop their own technology solutions to 
meet NASA’s crew and cargo needs and raise additional funding to 
demonstrate their solutions. Once the capabilities have been 
demonstrated, NASA and other customers would be able to purchase 
space transportation services directly from commercial partners. 

The COTS project was originally intended to be executed in two sequential 
phases: (1) private industry development and demonstration of cargo and 
crew transport capabilities in coordination with NASA and (2) 
procurement of commercial resupply services to the space station once 
cargo transport capabilities had been successfully demonstrated. NASA 
asked commercial partners to meet the following cargo transport 
capabilities: capability A—external cargo delivery (unpressurized) and 
disposal; capability B—internal cargo delivery (pressurized) and disposal; 
capability C—internal cargo delivery and return to Earth; and capability 
D—crew transportation. The COTS project is initially focused on 
developing cargo transport capabilities because NASA has identified cargo 
transport as a more pressing need and incremental step toward crew 
transport. Furthermore, the Commercial Crew and Cargo program office 
reported that it has not yet received funding for crew transport capability 
development.

8

 

NASA designed the COTS project to be a technology development and 
demonstration effort. To implement the COTS project, NASA issued Space 
Act agreements utilizing its “other transaction authority” under the 
National Aeronautics and Space Act of 1958.

9

 Generally speaking, other 

transaction authority enhances the government’s ability to acquire cutting-
edge science and technology, in part through attracting companies that 
typically have not pursued government contracts because of the cost and 
impact of complying with government procurement requirements. These 
types of agreements are not federal government contracts, and are 

                                                                                                                                    

8

The National Aeronautics and Space Administration Authorization Act of 2008, Pub. L. No. 

110-422, § 101 authorized $100 million for COTS demonstration of a crew transport 
capability, but the COTS program office has not yet received any funding for this capability. 

9

Pub. L. No. 85-568, § 203 (1958). This act is commonly referred to as the Space Act and 

agreements signed utilizing NASA’s other transaction authority are known as Space Act 
agreements. 

Page 4 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

therefore generally not subject to those federal laws and regulations that 
apply to federal government contracts. Consequently, agreements formed 
using other transaction authority permit considerable latitude by agencies 
and companies in negotiating agreement terms. NASA has established 
guidance on how to implement agreements under this authority. 

In August 2006, NASA competitively awarded Space Act agreements to 
two commercial partners, Space Exploration Technologies Corporation 
(SpaceX) and Rocketplane Kistler (RpK), to develop and demonstrate end-
to-end transportation systems, including the development of launch and 
space vehicles, ground and mission operations, and berthing with the 
space station. SpaceX was awarded a $278 million agreement to develop 
and demonstrate the three COTS cargo capabilities. The agreement was 
amended in February 2008 to reschedule milestones, including the three 
demonstration flights to occur from June 2009 through March 2010.

10

 

NASA’s agreement with SpaceX includes an option for SpaceX to 
demonstrate crew transport capabilities. RpK was awarded a $207 million 
agreement, but the agreement was terminated in October 2007 after RpK 
had missed financial and technical milestones. NASA held a second 
competition and awarded Orbital Sciences Corporation (Orbital) a $170 
million agreement in February 2008 to develop two of the COTS cargo 
capabilities (unpressurized and pressurized cargo delivery and disposal), 
culminating in an unpressurized demonstration flight scheduled for 
December 2010. In March 2009, Orbital and NASA amended this 
agreement, removing its unpressurized cargo demonstration and replacing 
it with a pressurized demonstration, scheduled for March 2011.

11

 Each 

partner proposed its own development milestone schedule in their 
respective agreements, which were then negotiated and agreed to by 
NASA. NASA conducts milestone reviews to determine whether the 
milestone has been met and payment only occurs if the partner has 
successfully completed the milestone. Five additional companies signed 
nonreimbursable agreements with NASA, but these partners have either 

                                                                                                                                    

10

SpaceX officials reported to NASA in January 2009 that they expected a 2- to 4-month 

delay for most of the remaining milestones, including the first and third demonstration 
flights. 

11

This amendment was made because NASA awarded a commercial resupply services 

contract to Orbital in December 2008 in which NASA ordered pressurized cargo delivery 
and disposal services rather than unpressurized cargo delivery and disposal services. The 
commercial resupply services contract was a separate procurement from NASA’s February 
2008 Space Act agreement with Orbital. 

Page 5 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

terminated their agreements or made limited progress due in part to 
difficulty attracting external investment. 

In order to demonstrate cargo transport capabilities, commercial partners 
must comply with NASA and the Federal Aviation Administration (FAA) 
requirements or regulations, and SpaceX must satisfy U.S. Air Force 
(USAF) requirements since it is launching from Cape Canaveral Air Force 
Station. 

 

Space Station Integration.

 The International Space Station program 

office manages the process of integrating COTS vehicles with the space 
station. Before COTS partners’ vehicles may approach and berth with the 
space station, they must provide verification that all of the technical 
requirements described in NASA’s International Space Station to 
Commercial Orbital Transportation Services Interface Requirements 
Document have been met and NASA must approve each requirement’s 
closure.

 The partners must also pass three rounds of review by the 

International Space Station program office’s Safety Review Panel.

 

 

 

Launch Range Safety.

 The USAF 45th Space Wing manages, monitors, 

and enforces launch range safety requirements for users, including 
SpaceX, at Cape Canaveral Air Force Station. SpaceX must demonstrate 
that its operations meet the 45th Space Wing’s launch range safety 
requirements or that it can provide an equivalent level of safety.

 USAF 

launch range safety requirements may be modified by users to meet the 
specifications of a given launch, with the USAF’s approval of the changes. 
Orbital’s demonstration launch is planned to take place at Wallops Flight 

                                                                                                                                    

12

NASA’s International Space Station to Commercial Orbital Transportation Services 

Interface Requirements Document defines the applicable physical and functional interface 
requirements between COTS partners’ visiting vehicles and space station systems. 

13

The purpose of the International Space Station Safety Review Panel is to independently 

identify and track all critical hazards that visiting space vehicles may pose to the space 
station and its crew and to evaluate plans to mitigate these hazards. The Safety Review 
Panel is comprised of NASA and contractor personnel from across the agency. The panel 
holds three reviews that generally correspond with COTS partners’ preliminary design 
review, critical design review, and fabrication and testing activities. COTS partners must 
complete all three phases of the Safety Review Panel process before they are allowed to 
berth with the space station. 

14

The USAF 45th Space Wing’s Range Safety Office is responsible for ensuring the public’s 

safety both within and beyond the launch range user’s complex and the safety of nearby 
range sites. The launch range safety requirements are published in U.S. Air Force Space 
Command Manual 91-710. 

Page 6 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

Facility, Virginia, where launch range safety requirements are overseen by 
NASA.

15

 

 

 

Launch Licensing.

 The FAA’s Office of Commercial Space 

Transportation has the authority to issue licenses for commercial launches 
and reentries and launch and reentry site operations.

16

 The FAA reviews 

and makes a decision on an application within 180 days of receiving a 
complete application.

17

 Prior to accepting the application, the FAA can 

review draft applications and provide feedback to the applicant. 
 

Prior to the successful demonstration of COTS cargo transport 
capabilities, NASA put the International Space Station program office in 
charge of procuring commercial resupply services to the space station 
rather than the Commercial Crew and Cargo program office. The 
International Space Station program office awarded, under a separately 
competed procurement from COTS, two commercial resupply services 
contracts in December 2008 to SpaceX and Orbital to deliver at least 40 
metric tons (approximately 88,000 pounds) to the space station between 
2010 and 2015.

18

 NASA’s current plan estimates that commercial partners 

will transport 36.9 metric tons (approximately 81,400 pounds) of usable 
dry cargo and 3.1 metric tons (approximately 6,800 pounds) of water, 

                                                                                                                                    

15

NASA’s top-level launch range safety requirements are set by NASA Procedural 

Requirements, NPR 8715.5, under the responsibility of NASA’s Office of Safety and Mission 
Assurance. Vehicles launched from NASA’s Wallops Flight Facility must also comply with 
the Range Safety Manual for Goddard Space Flight Center / Wallops Flight Facility (RSM-
2002 Rev. B). 

16

FAA issues several commercial space licenses, including (1) launch license (for 

expendable launch vehicles), (2) a reusable launch vehicle mission license, (3) a re-entry 
license, and (4) a launch or re-entry site operator license. FAA requires a launch license for 
SpaceX’s Falcon 9 launch vehicle and a re-entry license for its Dragon space vehicle. 
Orbital must obtain a launch license for its Taurus II launch vehicle and a re-entry license 
for its Cygnus space vehicle. 

17

Commercial Space Launch Act, Pub. L. No. 98-575, § 9 (1984) (as amended), codified at 49 

U.S.C. § 70105. 

18

These contracts also include a clause guaranteeing a minimum of 3 metric tons in return 

cargo downmass. 

Page 7 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

propellant, and atmospheric gas.

19

 SpaceX was awarded 12 cargo resupply 

missions for approximately $1.6 billion and Orbital was awarded eight 
cargo resupply missions for approximately $1.9 billion. Figure 1 provides a 
timeline of key events in the COTS project. 

billion. Figure 1 provides a 

timeline of key events in the COTS project. 

Figure 1: Key Events in the Commercial Orbital Transportation Services Project 

Figure 1: Key Events in the Commercial Orbital Transportation Services Project 

2005

2006

2007

2008

2009

2010

2011-2015

Commercial
Orbital
Tran

s

portation

S

ervice

s

(COT

S

) Project 

NA

S

e

s

t

ab

li

s

he

s

 

Commerci

a

Crew 

a

nd C

a

rgo 

progr

a

m office 

(Nov. 2005)

NA

S

A i

ssu

e

s

 

fir

s

t COT

S

 

a

nno

u

ncement 

for propo

sa

l

s

 

(J

a

n. 2006) 

NA

S

a

w

a

rd

s

 

a

greement

s

 to 

S

p

a

ceX 

a

nd 

RpK
(A

u

g. 2006)

NA

S

termin

a

te

s

 it

s

 

a

greement with 

RpK 

a

fter it 

mi

ss

ed fin

a

nci

a

a

nd technic

a

mile

s

tone

s

(Oct. 2007)  

NA

S

A i

ssu

e

s

 

s

econd COT

S

 

a

nno

u

ncement 

for propo

sa

l

s

 

(Oct. 2007)

NA

S

a

w

a

rd

s

 

a

greement to 

Or

b

it

a

l

(Fe

b

. 2008)

S

p

a

ceX to 

cond

u

ct two 

COT

S

 

demon

s

tr

a

tion 

mi

ss

ion

s

 (J

u

n. 

a

nd Nov. 2009)

a

S

p

a

ceX to 

cond

u

ct third 

COT

S

 demon-

s

tr

a

tion mi

ss

ion 

(M

a

r. 2010)

b

Or

b

it

a

l to cond

u

ct 

COT

S

 demon-

s

tr

a

tion mi

ss

ion 

(M

a

r. 2011)

c

Commercial 
Re

s

upply 

S

ervice

s

(CR

S

) Contract

NA

S

A i

ssu

e

s

  

CR

S

 req

u

e

s

t

for propo

sa

l

(Apr. 2008)

NA

S

a

w

a

rd

s

 

CR

S

 contr

a

ct

s

 

(Dec. 2008)

S

p

a

ceX to 

deliver c

a

rgo 

to 

s

p

a

ce 

s

t

a

tion in initi

a

CR

S

 mi

ss

ion

By 2011, NA

S

a

nticip

a

te

s

 

commerci

a

p

a

rtner

s

 will 

b

ab

le to deliver 

c

a

rgo to the 

s

p

a

ce 

s

t

a

tion 

u

nder 

s

ep

a

r

a

te 

CR

S

 contr

a

ct

s

S

o

u

rce: GAO 

a

n

a

ly

s

i

s

 of NA

S

A d

a

t

a

.

a

NASA reported in February 2009 that SpaceX plans to delay its first demonstration flight from June 

2009 to no earlier than September 2009. 

b

NASA also reported in February 2009 that SpaceX plans to delay its third demonstration flight from 

March 2010 to no earlier than May 2010. 

c

NASA and Orbital amended the original agreement to replace Orbital’s unpressurized cargo 

capability demonstration milestones with pressurized ones and changed the date of the 
demonstration mission from December 2010 to March 2011. 

                                                                                                                                    

19

NASA awarded SpaceX and Orbital indefinite-delivery / indefinite-quantity contracts, 

which provide for an indefinite quantity, within stated limits, of supplies or services during 
a fixed period. The contracts contain firm-fixed-price contract line items, where a specified 
price is paid regardless of the contractor’s costs, thereby minimizing the financial risk to 
the government. NASA issues orders under these contracts for cargo resupply missions. 
Each mission is divided into a series of performance milestones with set payments. NASA 
may withhold milestone payments due to non performance. To earn the full amount for 
each mission, a partner must complete all milestones, including the successful delivery of 
cargo to the space station. 

Page 8 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

NASA Has Adhered to 
Critical Project 
Management Tools 
and Project 
Expenditures Track 
Closely with Achieved 
Milestones 

During the course of our review, we found NASA’s management of the 
COTS project has generally adhered to critical project management tools 
and activities and the vast majority of project expenditures were for 
milestone payments to COTS partners. Because the COTS project utilized 
NASA’s other transaction authority to enter into agreements, NASA was 
not required to follow its program management requirements. However, it 
used them as a guide to ensure that it had the proper planning 
documentation in place. NASA has established fixed-price, performance-
based milestones in its agreements with commercial partners and only 
pays them once the milestone has been successfully completed. NASA has 
also taken several steps since the beginning of the COTS project to ensure 
that risks were identified, assessed, and documented, and that mitigation 
plans were in place to reduce these risks. NASA has communicated 
regularly with its partners through quarterly and milestone reviews and 
provided them with technical expertise to assist in their development 
efforts and to facilitate integration with the space station. For example, 
NASA created the Transportation Integration Office to streamline the 
requirements for integrating with the space station and provided access to 
critical space station integration technologies. As of the end of fiscal year 
2008, 95 percent of project funding had been spent on milestone payments, 
3 percent on project operations, and the remaining 2 percent had been 
obligated, but not yet expended. 

 

NASA’s Use of Critical 
Project Management Tools 
Has Enabled It to Monitor 
Partners’ Development 
Efforts 

Undertaking ambitious, technically challenging efforts like the COTS 
project—which involves multiple contractors and technologies that have 
yet to be fully developed and proven—requires careful oversight and 
management. Due to the COTS project’s emphasis on partnering with the 
private sector, NASA served in a supervisory or advisory role rather than 
being in charge of developing the COTS project’s space and launch 
vehicles. In this capacity, for example, NASA was responsible for 
reviewing milestone documentation, including risk assessments, making 
associated milestone payments, and sharing technical expertise. NASA’s 
Space Act Agreements Guide and prior GAO work have identified several 
critical project management tools and activities which NASA generally 
followed, including (1) developing program planning documentation; (2) 
establishing performance-based, fixed-price milestones; (3) developing 
risk management plans; and (4) facilitating communication and 
coordination between NASA and its partners. Our prior work on NASA 
development programs with similarities to COTS, such as the X-33 

Page 9 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

program, has shown that not carefully implementing such project 
management tools and activities is a recipe for failure.

20

 

Due to NASA’s use of its other transaction authority for the COTS project 
and because it did not intend to take ownership of any flight or ground 
systems, it was not required to follow its program management 
requirements, which included developing program authorization and 
planning documentation. Nonetheless, NASA used these management 
requirements as a guide to ensure that it had the proper program 
authorization and planning documentation in place for the COTS project. 
Such plans help define realistic time frames, identify responsibility for key 
tasks and deliverables, and provide a yardstick by which to measure the 
progress of the effort. NASA developed a program authorization document 
that outlined NASA’s management structure, project objectives, 
acquisition strategy, project scope, funding profile, and planned program 
reviews. In addition, the first performance milestone in NASA’s 
agreements with its commercial partners required the partners to develop 
a program or project management plan that included the overall project 
schedule with milestones and described how the partner would manage 
the development process and identify and mitigate risks. Each commercial 
partner successfully passed this milestone. 

Program Planning 
Documentation 

NASA has established fixed-price, performance-based milestones in its 
agreements with commercial partners that include entrance and success 
criteria, payment amounts, and specific due dates. NASA reviews the 
documentation submitted for each milestone—which includes design 
documentation, risk identification and mitigation strategies, development 
schedules, and test plans and results—and only pays its partners once it 
has determined the milestone has been successfully completed. Our prior 
work has emphasized the importance of developing performance-based 
milestones with fixed payments in order to minimize financial and 

Performance-Based Milestones 

                                                                                                                                    

20

GAO, 

Space Transportation: Critical Areas NASA Needs to Address in Managing Its 

Reusable Launch Vehicle Program

GAO-01-826T 

(Washington, D.C.: June 20, 2001). The X-

33 program was part of an effort to build a full-scale, commercially developed, reusable 
launch vehicle reaching orbit in one stage. NASA’s goal was to reduce payload launch costs 
from $10,000 per pound on the space shuttle to $1,000 per pound by using innovative design 
methods, streamlined acquisition procedures, and creating industry-led partnerships with 
cost sharing to manage the development of advanced technology demonstration vehicles. 
The program did not adhere to critical project management tools and activities and was 
terminated due to significant cost increases. 

Page 10 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

performance risks.

21

 NASA’s use of performance-based milestones has 

enabled it to minimize these risks. For example, NASA modified its 
agreement with SpaceX in February 2008 to include several milestones 
that were focused on conducting tests of critical hardware, such as the 
space vehicle’s thrusters and the launch vehicle’s first-stage engines. 
SpaceX passed these milestones on time, successfully demonstrating the 
maturation of key technologies. In another instance, NASA terminated an 
agreement with RpK when it failed to meet financial and technical 
milestones. NASA paid RpK only for the milestones that it completed 
($32.1 million) and was able to award the remaining funding—$170 
million—to Orbital approximately 4 months later. 

Although NASA has held partners responsible for their own risk 
management planning, it has taken several steps since the inception of the 
COTS project to ensure that risks were identified, assessed, and 
documented, and that mitigation plans were in place to reduce these risks. 
Our prior work has highlighted the importance of risk management plans, 
which identify, assess, and document risks associated with cost, schedule, 
and technical aspects of a project and determine the procedures that will 
be used to manage those risks.

22

 These plans help ensure that a system will 

meet performance requirements and be delivered on schedule and within 
budget. In our prior work, we found that NASA did not prepare risk 
management plans for both the X-33 and X-34 programs until several years 
after they were initiated. Both programs were subsequently terminated 
because of significant cost increases caused by problems developing the 
necessary technologies and flight demonstration vehicles. Through the 
COTS announcement for proposal process, NASA required companies to 
identify programmatic and technical risks and strategies for mitigating 
each risk. After each partner had been awarded an agreement, NASA 
required them to develop program or project management plans that 
outlined each partner’s risk management approach and identified key 
project risks and mitigation efforts. Furthermore, the Commercial Crew 
and Cargo program office has continued to monitor these risks through 
quarterly and milestone design reviews with its partners. The program 
office has also ensured that these project and program office-specific risks 

Risk Management Plans 

                                                                                                                                    

21

GAO, 

Department of Homeland Security: Improvements Could Further Enhance Ability 

to Acquire Innovative Technologies Using Other Transaction Authority

GAO-08-1088 

(Washington, D.C.: Sept. 23, 2008). 

22

GAO-01-826T

Page 11 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

and mitigations have been reported to senior NASA management through 
program management reviews. 

NASA and its partners have successfully fulfilled their respective 
responsibilities as outlined in the agreements, which has helped to 
facilitate communication and coordination between the parties. Our prior 
work has found that ambitious, technically challenging efforts require a 
high level of communication and coordination.

23

 For example, in the case 

of the X-33 program, ineffective communication between NASA and its 
contractor regarding concerns about the X-33’s fuel tank design 
contributed to its failure. The COTS partners’ agreements outline several 
responsibilities that are directly related to fostering communication and 
coordination, such as holding quarterly and milestone reviews and 
providing partners with technical expertise to assist with their 
development efforts and to facilitate integration with the space station. In 
addition, NASA and SpaceX have amended their agreement to define how 
they will collaborate to integrate critical communications hardware into 
the space station and to test a relative navigation sensor. NASA has 
worked closely with SpaceX, as these items will be flown on an upcoming 
space shuttle flight. Another example of NASA’s efforts to facilitate 
communication and coordination with its partners is through the creation 
of the Transportation Integration Office within the International Space 
Station program office. This office has streamlined the requirements for 
integrating with the space station and provided access to critical space 
station integration technologies, such as the grapple fixtures, Common 
Berthing Mechanism design, and Japan Aerospace Exploration Agency’s 
proximity operations communications system.

24

 NASA has also assigned a 

project executive for each partner to provide day-to-day oversight of the 
partners’ development efforts and to coordinate technical assistance. 

Facilitating Communication 
and Coordination 

 

                                                                                                                                    

23

GAO-01-826T

24

Proximity operations refer to maneuvers by vehicles visiting the space station that are 

conducted in close proximity to the space station. These operations include maneuvers to 
properly position the space vehicle in relation to the space station so that it can be 
captured by the space station’s robotic arm prior to berthing. 

Page 12 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

As of the end of fiscal year 2008, 95 percent of project funding had been 
spent on milestone payments, 3 percent on project operations, and the 
remaining 2 percent had been obligated, but not yet expended.

25

 NASA’s 

Administrator budgeted $500 million in 2005 for the development and 
demonstration of cargo transport capabilities between fiscal years 2006 
and 2010.

26

 For fiscal year 2009, NASA requested $173 million in funding 

for the COTS project and plans to request $31.3 million for fiscal year 2010. 
See table 1 below for COTS project funding, obligations, and expenditures 
through fiscal year 2008. 

Vast Majority of Project 
Expenditures Are for 
Milestone Payments to 
COTS Partners 

Table 1: COTS Project Funding, Obligations, and Expenditures through Fiscal Year 
200

8

 

Dollars in millions 

Fiscal year 

Project funding

Obligations

Expenditures

2005  

$22.

8

N/A

a

N/A

2006 51.3

63.6

39.1

2007 91.1

99.0

93.7

200

8

 130.5

133.1

157.3

Total $295.7

$295.7

$290.1

Source: NASA. 

a

NASA did not obligate fiscal year 2005 funding until fiscal year 2006. Therefore, fiscal year 2005 

funding was included in all fiscal year 2006 calculations. 

 

Figure 2 illustrates how the $290.1 million in project expenditures have 
been divided between COTS partners’ milestone payments and project 
operations from fiscal years 2006 to 2008. 

                                                                                                                                    

25

COTS project operations expenditures include funding for civil service labor; civil service 

travel; technical assistance provided to COTS partners; and procurement activities, which 
consist of technical and business support, information technology, and safety and mission 
assurance. 

26

The International Space Station program office’s Transportation Integration Office has 

estimated that it will spend an additional $56 million to support COTS partners’ space 
station integration efforts. 

Page 13 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

Figure 2: COTS Project Expenditures to Partners and Project Operations through 
Fiscal Year 200

8

 

$

9

$

32.1

$

50

$

199

S

o

u

rce: NA

S

A.

Project oper

a

tion

s

Rocketpl

a

ne Ki

s

tler

Or

b

it

a

l

S

p

a

ceX

Doll

a

r

s

 in million

s

 

In fiscal year 2009, SpaceX has received an additional $35 million for 
completing two milestones, bringing its total milestone payments to date 
to $234 million.

27

 SpaceX could potentially earn an additional $44 million in 

future milestone payments. Orbital has been paid $30 million for 
completing three milestones in fiscal year 2009, increasing its total 
milestone payments to date to $80 million.

28

 Orbital has $90 million 

remaining in potential milestone payments. 

                                                                                                                                    

27

SpaceX completed milestone 13, Demo 2 / Demo 3 System Critical Design Review, in 

December 2008 ($25 million) and milestone 14, its third and final financial milestone, in 
March 2009 ($10 million). 

28

NASA paid Orbital for milestone 6, Pressurized Cargo Module Preliminary Design Review, 

in November 2008 ($10 million); milestone 8, Instrumentation Program and Command List, 
in March 2009 ($10 million); and milestone 9, Completion of International Space Station 
Phase 1 Safety Review, in March 2009 ($10 million). 

Page 14 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

The vehicles being developed by commercial partners have become 
essential to NASA’s ability to fully utilize the space station after the 
retirement of the space shuttle in 2010. NASA’s 2006 Strategic Plan 
established a goal of supporting a crew of six astronauts on the space 
station by the end of 2009 in order to fully utilize the space station’s 
research capabilities. NASA is in the process of installing the necessary 
equipment to support a six-person crew, and has estimated that the space 
station’s final construction cost will be $31 billion.

29

 NASA estimates that it 

will need 82.7 metric tons (approximately 182,000 pounds) of usable dry 
cargo delivered to the space station between 2010 and 2015 to meet crew 
needs and to support maintenance and scientific experiments. NASA plans 
to transport this cargo using several vehicles, including the space shuttle 
and commercial and international partners’ vehicles.

30

 Between 2010 and 

2015, commercial partners’ vehicles will transport almost half of this cargo 
and are scheduled to fly more cargo delivery missions than the space 
shuttle and international partners’ vehicles combined—including 14 of the 
last 19 missions. Furthermore, after the retirement of the space shuttle, 
SpaceX’s space vehicle will be the only vehicle capable of safely returning 
significant amounts of cargo to Earth—which is an essential capability to 
accomplish NASA’s scientific research program.

31

 Figure 3 outlines 

NASA’s strategy for meeting the space station’s usable dry cargo resupply
needs between 2010 and 2015, identifies which vehicles are capable of 
returning cargo to Earth, and highlights NASA’s increasing relianc
commercial partners’ vehicles. Figure 3 does not include the amount of 
propellant, water, and atmospheric gas to be delivered to the space station 
between 2010 and 2015 nor does it depict the maximum cargo mass 
delivery capacities of each vehicle, which range from more than 17 metric 

NASA Will Rely on 
Commercial Partners 
to Meet Much of the 
Space Station Cargo 
Resupply Needs 

 

e on U.S. 

                                                                                                                                    

29

Equipment necessary to support a six-person crew includes systems for oxygen recycling, 

removal of carbon dioxide, and transforming urine into water. NASA plans to install a new 
module, known as Tranquility (formerly Node 3), in February 2010 and it will hold some of 
this equipment. In addition to the $31 billion for the space station’s construction, NASA 
expects sustainment costs through the space station’s planned retirement in fiscal year 
2016 to total $11 billion. 

30

The European Space Agency’s Automated Transfer Vehicle successfully completed its 

first demonstration mission to dock with the space station in April 2008. The Japan 
Aerospace Exploration Agency has yet to attempt a demonstration mission for its H-II 
Transfer Vehicle. The first demonstration mission is planned for September 2009. 

31

SpaceX’s Dragon is designed to return up to 2.5 metric tons (approximately 5,500 pounds) 

to Earth, but will likely be limited by volume constraints to about 1.7 metric tons (3,748 
pounds). The international partners’ vehicles and Orbital’s Cygnus do not provide this 
capability. NASA could use the Russian crew transport vehicle to carry a small amount of 
cargo (50 kg) to Earth, but this vehicle cannot bring experiments to Earth for assessment. 

Page 15 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

tons for the space shuttle to as little as 2 metric tons for Orbital’s space 
vehicle in its standard configuration. 

Figure 

3

: NASA’s Strategy for Meeting Space Station Usable Dry Cargo Needs—2010 to 2015 

2010

S

pace vehicle

s

 

(number of 

mi

ss

ion

s

 planned)

2011

2012

2013

2014

2015

Total:  82.7

metric ton

s

car

g

o ma

ss

 

Total:        38
mi

ss

ion

s

 

planned

C

a

rgo mi

ss

ion to the 

s

p

a

ce 

s

t

a

tion

 

Commercial 
partner

s’

vehicle

s

S

pace 

s

huttle 

European 
Automated 
Tran

s

fer 

Vehicle

Ru

ss

ian 

Pro

g

re

ss

Japane

s

H-II Tran

s

fer 

Vehicle

Undetermined 
vehicle

b

S

o

u

rce: GAO 

a

n

a

ly

s

i

s

 of NA

S

A d

a

t

a

.

36.9

9.8

4.0

6.6

24.0

1.4

Car

g

o ma

ss

 to 

be delivered 

(metric tons)

Capable of 

returnin

g

 

car

g

o to earth

(20)

(4)

(

3

)

(4)

(6)

(1)

a

Note: This figure reflects NASA’s November 200

8

 estimate of the space station’s projected usable dry 

cargo needs and identifies which vehicles are capable of returning cargo to Earth. Propellant, water, 
and atmospheric gas are not included in these figures. The exact cargo mix for a particular mission is 
not determined until several months prior to launch and the cargo mass to be delivered for a 
particular mission may therefore be subject to change. 

a

Of the two commercial providers, only SpaceX’s Dragon space vehicle is designed to return cargo to 

Earth. 

b

The International Space Station program office has reported that the vehicle that will be used for this 

2015 mission has not been determined, and it will depend on what is needed to decommission the 
space station in late 2015 or early 2016. 

Page 16 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

Other options for transporting cargo to the space station are limited. NASA 
has purchased the equivalent of three Russian Progress vehicles for use in 
2010 and 2011, but it has no plans to purchase any additional vehicles 
beyond 2011.

32

 According to NASA officials, there is a 24- to 30-month lead 

time to manufacture the Progress should NASA decide to procure 
additional vehicles. NASA plans to use six Japanese H-II Transfer Vehicles 
for missions between 2010 and 2015 and four European Automated 
Transfer Vehicles between 2010 and 2013. NASA officials told us that the 
Japanese and European space agencies have no plans to manufacture 
additional vehicles beyond their current commitments. In addition, 
NASA’s new crew exploration and launch vehicles, Orion and Ares I, 
designed to replace the space shuttle, are not expected to be available 
until 2015.

33

 

Delays in the availability of commercial vehicles to fill the cargo resupply 
gap would result in diminished usage of the space station. The 
International Space Station program office has identified the 40 metric ton 
(approximately 88,000 pound) cargo resupply shortfall as a top program 
risk, and its risk summary report states that a delay in 2010 in the 
availability of commercial partners’ vehicles would lead to a significant 
scaling back of NASA’s use of the space station for scientific research. If 
there were a delay in 2011, NASA could no longer maintain a space station 
crew of six astronauts and its ability to conduct scientific research would 
be compromised. 

 

                                                                                                                                    

32

Space Station program officials told us that they expect Russia to launch six Progress 

flights each year between 2009 and 2011. They stated the NASA cargo will be spread across 
four Progress flights in 2009 and will represent the equivalent cargo capacity of a single 
Progress (1.4 metric tons). NASA will be procuring the equivalent of two Progress vehicles 
in 2010 and one Progress vehicle in 2011. 

33

These vehicles were designed to implement President George W. Bush’s 

A Renewed 

Spirit of Discovery: The President’s Vision for U.S. Space Exploration

, which included a 

return to the moon and future exploration of Mars. NASA had also planned to utilize these 
vehicles to transport cargo to the space station as early as 2011. However, schedule and 
technical setbacks have delayed the anticipated availability of these vehicles until 2015. 

Page 17 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

While SpaceX and Orbital have completed most of the development 
milestones required thus far on time, both companies are working under 
aggressive schedules and have recently experienced schedule slips which 
have delayed upcoming demonstration launch dates by several months. 
SpaceX successfully completed its first 14 development milestones on 
time and is in the process of testing, fabricating, and assembling key 
components. However, a schedule slip in the development of its launch 
vehicle’s second-stage engine components has contributed to anticipated 
delays of 2 to 4 months in most of its remaining milestones, including 
upcoming demonstration missions. NASA is currently evaluating the effect 
of potential further delays. Orbital has successfully completed 7 of 19 
development milestones thus far, including several preliminary design 
reviews (PDR), but has experienced delays in the development of its 
launch vehicle’s first-stage engine components. Orbital and NASA recently 
amended their Space Act agreement to conduct a pressurized cargo 
delivery and disposal demonstration mission instead of an unpressurized 
mission, delaying its demonstration mission date by 3 months, from 
December 2010 until March 2011. 

Commercial Partners 
Are Making Progress, 
but Face Challenges 
Meeting Aggressive 
Development 
Schedules 

Space development programs are by nature complex and rife with 
technical obstacles that can easily result in development delays. In our 
recent report on selected large-scale NASA projects, we found that 10 of 
the 13 projects that we reviewed had experienced significant cost and/or 
schedule growth from their project baselines.

34

 Commercial partners must 

develop and demonstrate new launch and space vehicles, launch and 
mission operations capabilities, and achieve integration with the space 
station in a 3- to 4-year period. 

 

SpaceX Has Made Progress 
Completing Milestones as 
Scheduled, but Challenges 
Are Likely to Delay 
Demonstration Missions 

SpaceX completed its first 14 development milestones on time, and has 
made progress developing its space transport capabilities; however, 
several schedule and regulatory challenges are likely to delay upcoming 
demonstration missions by at least 2 to 4 months. SpaceX’s agreement 
with NASA established 22 development milestones that SpaceX must 
complete in order to successfully demonstrate COTS cargo capabilities. 
Although it completed its first 14 COTS development milestones on 

                                                                                                                                    

34

GAO, 

NASA: Assessments of Selected Large-Scale Projects

GAO-09-306SP 

(Washington, 

D.C.: Mar. 2, 2009). For purposes of our analysis, significant cost and schedule growth 
occurs when a project’s cost and/or its schedule growth exceeds the thresholds established 
for Congressional reporting. 

See 

42 U.S.C. § 16613. Of the projects that we reviewed with 

launch delays, delays ranged from 5 months to as many as 26 months. 

Page 18 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

schedule, SpaceX experienced a delay completing the fabrication, 
assembly, and integration of its launch vehicle’s second-stage components, 
and delayed its first demonstration mission readiness review (milestone 
15) from March 2009 until no earlier than June 2009. In addition, SpaceX 
has a significant amount of work remaining to complete technical 
requirements for integrating its space vehicle with the space station. 
SpaceX must also obtain required licenses and approvals from the FAA 
and the USAF before its scheduled demonstration mission launch dates. 
SpaceX has informed NASA that its first demonstration mission will be 
delayed from June 2009 until no earlier than September 2009, and its third 
demonstration mission is likely to be delayed from March 2010 to no 
earlier than May 2010.

35

 NASA reported it has yet to modify SpaceX’s 

agreement to reflect these changes, but it is closely monitoring SpaceX’s 
activity and is consulting with SpaceX to ascertain the cause of SpaceX’s 
failure to meet milestone 15 in the timeframe identified in the current 
agreement.

36

 SpaceX has received $234 million in milestone payments thus 

far, with $44 million yet to be paid. Table 2 describes SpaceX’s progress 
meeting the COTS milestones in its agreement with NASA. 

Table 2: SpaceX’s Progress Completing COTS Development Milestones 

Milestone 
number  

Milestone description 

Scheduled 
completion date 

Completed 
on time 

Payment 

amount 

(millions)

Project Management Plan Review 

Sept. 2006 

9

 $23.1

Demo 1 System Re

q

uirements Review 

Nov. 2006 

9

 

5

Demo 1 Preliminary Design Review 

Feb. 2007 

9

 

1

8

.1

Financing Round 1 

Mar. 2007 

9

 10

Demo 2 System Re

q

uirements Review 

Mar. 2007 

9

 31.1

Demo 1 System Critical Design Review 

Aug. 2007 

9

 

8

.1

Demo 3 System Re

q

uirements Review 

Oct. 2007 

9

 22.3

8

 

Demo 2 Preliminary Design Review 

Dec. 2007 

9

 21.1

Draco Initial Hot-Fire 

Mar. 200

8

 

9

 

6

                                                                                                                                    

35

SpaceX has not announced plans to delay to its second demonstration mission, scheduled 

for November 2009. 

36

According to NASA’s agreements with the partners, should either partner fail to meet 

milestones, NASA and the partner must meet to determine why the failure occurred and 
whether it is in the best interests of the parties to continue the agreement. NASA may 
terminate the agreement 30 days after providing written notification to the partner that it 
has failed to perform. 

Page 19 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

Milestone 
number  

Milestone description 

Scheduled 
completion date 

Completed 
on time 

Payment 

amount 

(millions)

10 

Financing Round 2 

Mar. 200

8

 

9

 10

11 

Demo 3 Preliminary Design Review 

Jun. 200

8

 

9

 22

12 

Multi-engine Test 

Sept. 200

8

 

9

 22

13 

Demo 2/Demo 3 System Critical Design Review 

Dec. 200

8

 

9

 25

14 

Financing Round 3 

Mar. 2009 

9

 10

15 

Demo 1 Readiness Review 

Mar. 2009  

 

5

16 

Communications Unit Flight Unit Design, Accept, Delivery 

May 2009 

 

9

17 

Demo 1 Mission 

Jun. 2009 

 

5

1

8

 

Demo 2 Readiness Review 

Sept. 2009 

 

5

19 

Demo 2 Mission 

Nov. 2009 

 

5

20 

Cargo Integration Demonstration 

Jan. 2010 

 

5

21 

Demo 3 Readiness Review 

Jan. 2010 

 

5

22 

Demo 3 Mission 

Mar. 2010 

 

5

  

 

Total: 

$27

8

 million for 

the completion of 

all milestones

$234 million paid 

to date

Source: NASA and SpaceX. 

Note: SpaceX did not complete milestone 15 in March 2009 as scheduled. NASA reported that 
SpaceX has delayed delivery of milestone 15 from March 2009 until no earlier than June 2009. In 
addition, SpaceX has informed NASA that it anticipates a 2 to 4 month delay in most of its remaining 
milestones; including a delay in its first demonstration mission (milestone 17) from June 2009 until no 
earlier than September 2009, and a delay in its third demonstration milestone (milestone 22) from 
March 2010 until no earlier than May 2010. 

 

To accomplish its COTS objectives, SpaceX is developing a medium-class 
launch vehicle (Falcon 9) and a space vehicle (Dragon), which is designed 
to ferry crew and cargo to and from the space station.

37

 The Falcon 9 

launch vehicle is a two-stage rocket that uses nine liquid-fueled engines for 

SpaceX’s Technical Approach 
and Development Status 

                                                                                                                                    

37

SpaceX’s technical approach is intended to meet each of the four COTS capabilities: 

capability A—unpressurized cargo delivery and disposal, capability B—pressurized cargo 
delivery and disposal, capability C—pressurized cargo delivery and return to Earth, and 
capability D—crew transportation. SpaceX’s Space Act agreement includes an option to 
demonstrate crew transportation. COTS project officials told us that they have not yet 
received funding for crew transport capability development. 

Page 20 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

its first-stage booster and one similar engine for its second-stage booster.

38

 

The Falcon 9 is designed to lift payloads, such as the Dragon spacecraft, 
into various orbits—including low-Earth orbit where the space station is 
located. On a single mission, the Dragon spacecraft is designed to deliver 
and dispose of 3 metric tons (approximately 6,600 pounds) of cargo 
distributed between its pressurized and unpressurized cargo carriers. 
Dragon is designed to return up to 2.5 metric tons (approximately 5,500 
pounds) of pressurized cargo mass to Earth, but will likely be limited by 
volume constraints to about 1.7 metric tons (3,748 pounds).

39

 SpaceX 

reported that it is developing and manufacturing almost all of the 
components for the Falcon 9 and Dragon in-house to keep development 
costs low and to remove dependencies on external suppliers. For example, 
SpaceX is developing a thermal protection system to enable the Dragon to 
safely re-enter the Earth’s atmosphere, and its own hardware and software 
components to enable the Dragon to integrate with the space station. A 
summary of SpaceX’s progress developing its COTS system is provided 
below. 

Launch vehicle.

 SpaceX has made progress developing and testing the 

first-stage engines on its Falcon 9 launch vehicle; however, it has 
experienced a schedule slip in the development, assembly, and integration 
of the Falcon 9’s second-stage engine components. From the beginning of 
the COTS project, SpaceX has tracked the development of its nine first-
stage engines as a significant technological risk and has conducted several 
multi-engine tests at the company’s Texas testing facility to reduce this 
risk. SpaceX reported that it successfully completed a 178-second test of 

                                                                                                                                    

38

The Falcon 9’s first- and second-stage engines are derived from engines used in SpaceX’s 

Falcon 1 launch vehicle, which had its first successful orbital launch in September 2008. 
The Falcon 1 uses one Merlin 1C engine for its first-stage booster, while the Falcon 9 uses 
nine similar engines for its first-stage and a single engine modified to operate in a space 
environment for its second-stage booster. The Merlin engines are fueled by liquid oxygen 
and rocket propellant grade kerosene. SpaceX plans to retrieve its first- and second-stage 
engines after launch and refurbish them for use in other missions. 

39

The Dragon will be propelled by 18 “Draco” thruster engines which are fueled by nitrogen 

tetroxide and monomethylhydrazine hypergolic fuels. Because the Dragon is yet to be fully 
qualified and flown, the ultimate cargo capacity of this vehicle is yet to be known. SpaceX 
estimates the upmass cargo capacity of the vehicle may be as high as 3.3 metric tons 
(approximately 7,300 pounds). The Dragon’s cargo capacity for a given mission will also 
vary depending on the density and volume of the cargo and how it is packed. SpaceX 
estimates that the Dragon is likely to carry about 2.55 metric tons (approximately 5,620 
pounds) of cargo on a typical mission. To demonstrate this capability, SpaceX plans to 
carry 1.7 metric tons (3,748 pounds) of pressurized and 0.85 metric tons (1,874 pounds) of 
unpressurized simulated cargo on its third demonstration mission. 

Page 21 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

its nine engines intended to simulate operations during a typical COTS 
launch. SpaceX also reported that it completed qualification testing of 
these engines in December 2008; however, NASA’s Commercial Crew and 
Cargo program manager reported that NASA has yet to review the 
documentation for these and other qualification tests conducted by 
SpaceX, but plans on doing so during milestone 15, SpaceX’s first 
demonstration mission readiness review. This review has been delayed 
from March 2009 until no earlier than June 2009, in part to provide SpaceX 
with more time to address issues with the fabrication, assembly, and 
integration of the Falcon 9’s second stage components. For example, 
SpaceX experienced a 3-month delay in the delivery of the domes that go 
on top of its second-stage booster, which delayed its ability to integrate 
these components as scheduled. Although SpaceX recently reported that it 
completed a 6-minute firing of its second-stage engine, additional testing 
remains before the Falcon 9 second-stage engine components can be 
qualified for flight and integrated with the corresponding tanks and 
structures. 

Space vehicle.

 SpaceX has made progress developing key components 

for its Dragon space vehicle; however it faces an aggressive schedule 
completing technical requirements to integrate the Dragon with the space 
station. SpaceX reported that it has completed 120 hot-fire tests of the 
Dragon’s engines—including a 15-minute firing in a vacuum chamber 
designed to simulate orbital firing operations. According to NASA, SpaceX 
considers these engines sufficiently qualified for SpaceX’s first 
demonstration mission, which does not include integration with the space 
station. However, NASA reported that SpaceX must modify the design of 
its thruster valves and will need to requalify these engines before it can 
attempt its third demonstration mission, when it will first attempt to 
integrate with the space station. SpaceX is also manufacturing its own 
heat-shield tiles for the Dragon’s thermal protection system, and reported 
that it has completed qualification testing and analyses of its material at 
NASA’s Ames Research Center. 

Before SpaceX can attempt its third demonstration mission, it must 
demonstrate that it has met all of the technical requirements in NASA’s 
International Space Station to COTS Interface Requirements Document. 
For example, SpaceX must develop and test new hardware and software 
components designed to enable the Dragon to share positioning data and 

Page 22 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

communicate with the space station.

40

 SpaceX and NASA have made 

arrangements to fly the two components on separate space shuttle 
missions scheduled this summer in order to conduct development tests on 
them prior to SpaceX’s second demonstration mission, scheduled for 
November 2009. SpaceX and NASA have set a goal for SpaceX to 
demonstrate compliance with 75 percent of NASA’s space station interface 
requirements by the second demonstration mission, with the remaining 25 
percent to be completed before the third demonstration mission. NASA 
officials reported that SpaceX’s schedule to complete its space station 
integration activities is aggressive and that all aspects of integrating a new 
space vehicle with the space station are technically challenging. 

Launch readiness.

 Before SpaceX may launch its first demonstration 

mission from the USAF’s Space Launch Complex 40 (SLC-40), it must 
receive the approval of the 45th Space Wing Commander that its launch 
infrastructure and operations meet the USAF’s launch range safety 
requirements. SpaceX has cited the range safety approval process as a 
significant risk that could result in schedule slips. SpaceX has made 
progress addressing many of the USAF’s requirements, and it has installed 
launch infrastructure at SLC-40—including components of the Falcon 9 
fueling system and the hangar structure where the Falcon 9 stages will be 
integrated and mated with the Dragon space vehicle.

41

 However, officials 

from the 45th Space Wing expressed concerns that SpaceX’s aggressive 
schedule may not give SpaceX sufficient time to submit its requests to 
modify USAF range safety requirements or give the USAF sufficient time 
to review, validate, and approve SpaceX’s facilities and launch operations 
before upcoming demonstrations. USAF officials reported that SpaceX has 
yet to submit its requests to modify Dragon fueling requirements, which 

                                                                                                                                    

40

The two components in development by SpaceX to enable these operations are its relative 

navigation sensor, known as DragonEye, and its COTS ultra high frequency 
communications unit. SpaceX is equipping its Dragon with three DragonEye units to create 
a redundant system for the Dragon to share positioning data with the space station during 
proximity operations. The ultra high frequency communications units will be installed in 
both the Dragon and the space station to transmit telemetry data during proximity 
operations. 

41

The Falcon 9 fueling system includes tanks and distribution systems for liquid oxygen and 

rocket propellant grade kerosene, helium, and nitrogen. SpaceX reported that the hangar is 
operational for the integration of its launch and space vehicles; however, the hangar has 
yet to be approved for Dragon fueling. SpaceX reported that it has also fabricated, 
assembled, and successfully completed a dry-run test of its transporter erector system, 
which will be used to transport the integrated Falcon 9 and Dragon from the hangar and 
erect it for launch. 

Page 23 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

the USAF considers to be a potential public safety hazard, and subject to 
its review and approval. SpaceX reported that it intends to submit its 
requests to modify these requirements in the summer of 2009. SpaceX 
plans to conduct independent tests to demonstrate that its launch facilities 
meet USAF requirements for a launch safety critical design review (CDR) 
that will also be held in the summer of 2009. 

Prior to its first demonstration mission, SpaceX must also receive from the 
FAA a launch license for the Falcon 9 and a re-entry license for the Dragon 
space vehicle. FAA reported that SpaceX has yet to submit a sufficiently 
complete launch license application for the Falcon 9 for SpaceX’s first 
COTS demonstration mission.

42

 However, in April 2009 FAA accepted a 

sufficiently complete re-entry license application from SpaceX for the 
Dragon space vehicle. FAA must decide within 180 days after accepting a 
license application whether to approve it. FAA officials reported that they 
do not anticipate making a determination much sooner than 180 days after 
acceptance of SpaceX’s applications. Although it remains to be seen when 
SpaceX will deliver and the FAA will accept its Falcon 9 launch license 
application for the first COTS demonstration, there appears to be little 
margin for SpaceX to obtain its FAA-required licenses in time for its 
September 2009 COTS demonstration mission. 

 

Orbital Has Completed 
Several Preliminary Design 
Reviews, but Faces 
Challenges Completing 
Development in Time for 
Its Demonstration Mission 

Orbital—which entered the COTS project about 18 months after SpaceX—
has successfully completed 7 of 19 required milestones thus far, including 
several preliminary design reviews for its systems, but challenges lie ahead 
in its efforts to complete its recently revised milestone schedule. Orbital’s 
February 2008 agreement with NASA required it to conduct a single 
mission demonstrating the capability to deliver unpressurized cargo to the 
space station. Although Orbital was preparing a preliminary design of a 
pressurized cargo module, it was not required in its agreement with NASA 
to demonstrate this capability. However, in December 2008 NASA awarded 
Orbital a commercial resupply services contract calling for eight 
pressurized cargo missions, but no unpressurized missions. Subsequently, 
in March 2009, Orbital and NASA amended their COTS demonstration 

                                                                                                                                    

42

FAA reported that SpaceX has submitted and FAA has accepted a sufficiently complete 

launch license for a separate, non-COTS Falcon 9 mission. SpaceX intends to attempt an 
inaugural Falcon 9 demonstration mission prior to attempting its first COTS demonstration 
mission. NASA officials reported that they did not have a firm launch date for this inaugural 
Falcon 9 mission, but said that SpaceX is working toward a launch in late summer or early 
fall 2009.  

Page 24 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

agreement and replaced the unpressurized demonstration with a 
pressurized one. This required adding several new milestones to 
demonstrate this capability and delaying existing milestones, including 
Orbital’s single demonstration mission from December 2010 until March 
2011. Orbital has completed a PDR for its pressurized cargo capability and 
other development milestones for its Taurus II launch vehicle.

43

 However, 

Orbital reported that it has experienced delays completing design reviews 
for the first-stage engine components for its launch vehicle, which have 
resulted in further compressing its already aggressive development 
schedule. In addition, NASA reported that Orbital faces an aggressive 
schedule to complete the technical requirements to integrate its space 
vehicle with the space station. Orbital has received $80 million in 
milestone payments thus far, with $90 million yet to be paid (see table 3). 

Table 

3

: Orbital’s Progress Completing COTS Development Milestones 

Milestone 
number  

Milestone description 

Scheduled 
completion date 

Completed 
on time 

Payment amount 

(millions)

Program Plan Review 

Mar. 200

8

 

9

 $10

Demo Mission System Re

q

uirements Review 

Jun. 200

8

 

9

a

 20

Unpressurized Cargo Module Preliminary Design Review Jul. 200

8

 

9

  

10

COTS System Preliminary Design Review was milestone 
4, but it has been renumbered as milestone 10 

No longer applicable 

No longer 
applicable 

No longer applicable

COTS Integration/Operations Facility Review 

Sept. 200

8

b

 

9

 10

Pressurized Cargo Module Preliminary Design Review 

Oct. 200

8

 

9

 10

DELETED: Unpressurized Cargo Module Critical Design 
Review 

No longer applicable 

No longer 
applicable 

No longer applicable

8

 Instrumentation 

Program and Command List 

Feb. 2009 

9

 10

Completion of ISS Phase 1 Safety Review 

Mar. 2009 

9

 10

10 

COTS System Preliminary Design Review 

Apr. 2009 

 

20

11 

DELETED: Unpressurized Cargo Module Fabrication 
Started 

No longer applicable 

No longer 
applicable 

No longer applicable

11 

Pressurized Cargo Module Critical Design Review 

Jul. 2009 

 

10

12 

Cygnus Avionics Test 

Aug. 2009 

 

10

13 

Completion of ISS Phase 2 Safety Review 

Aug. 2009 

 

10

14 

COTS System Critical Design Review 

Sept. 2009 

 

10

                                                                                                                                    

43

Generally speaking, most of the Taurus II development milestones are not included in 

Orbital’s agreement with NASA. However, Orbital has invited NASA officials to participate 
in several Taurus II design reviews. Orbital has completed several other development 
milestones for its Taurus II launch vehicle. 

Page 25 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

Milestone 
number  

Milestone description 

Scheduled 
completion date 

Completed 
on time 

Payment amount 

(millions)

15 

Service Module Core Assembly Completed 

Dec. 2009 

 

7.5

16 

Service Module Test Readiness Review 

Apr. 2010 

 

7.5

17 

Service Module Initial Comprehensive Performance Test  Jul. 2010 

  

5

1

8

 

Launch Vehicle Stage 1 Assembly Complete 

Oct. 2010 

  

2.5

19 

Cargo Integration Demonstration 

Dec. 2010 

 

2.5

20 

Mission Readiness Review 

Feb. 2011 

  

2.5

21 

System Demonstration Flight 

Mar. 2011 

  

2.5

 

 

 

Total: 

$170 million for 

completion of all 

milestones

$

8

0 million paid to 

date

Source: NASA and Orbital. 

Note: When Orbital amended its agreement with NASA in March 2009, it deleted milestones 7 and 
11, and moved milestone 4 to become milestone 10. These changes are indicated in this revised 
schedule. 

a

Orbital submitted its milestone documentation for milestones 2 and 3 about 2 weeks later than 

originally planned; however, NASA approved both milestones. Orbital’s demo mission system 
re

q

uirements review (milestone 2) was completed in July 200

8

 and its unpressurized cargo module 

preliminary design review (milestone 3) was completed in August 200

8

b

Milestone 5 (COTS integration/operations facility review) was originally scheduled for October 200

8

but was accelerated to September 200

8

 as re

q

uested by Orbital. Milestone 6 (pressurized cargo 

module preliminary design review) was also accelerated 1 month at Orbital’s re

q

uest from November 

200

8

 to October 200

8

 

Orbital is developing a new, medium-class launch vehicle (Taurus II) and a 
modular visiting vehicle (Cygnus), which is designed to transport 
pressurized cargo to and dispose of trash from the space station.

44

 Orbital 

has teamed with several external space companies to develop the Taurus 
II and serves as its prime integrator.

45

 The first-stage engines, known as 

AJ26-62s, are being developed by Orbital and Aerojet and are derived from 
Russian NK-33 engines. Orbital’s Ukrainian subcontractor Yuzhnoye/ 
Yuzmash is responsible for the development of the first-stage fuel tanks. 
The Taurus II’s second-stage motor, known as the Castor-30, is being 

Orbital’s Technical Approach 
and Development Status 

                                                                                                                                    

44

Orbital’s amended technical approach is designed to meet one of the four COTS 

capabilities, pressurized cargo delivery and disposal (capability B).  

45

The Taurus II is a two-stage rocket with two liquid-fueled engines for its first stage and a 

single solid rocket motor for its upper stage. The first stage engines are fueled by rocket 
propellant grade kerosene and liquid oxygen. Orbital reported that it is also developing an 
optional liquid-fueled third stage engine that will not be used for COTS and commercial 
resupply services missions. 

Page 26 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

developed by Alliant Techsystems, Inc. (ATK), which has developed solid 
rocket motors used by the space shuttle and Japan’s H-IIA launch vehicle. 
The Cygnus space vehicle uses a service module to provide propulsion and 
power to deliver a pressurized cargo module to the space station.

46

 The 

service module draws from the avionics systems of NASA’s Dawn 
spacecraft, developed by Orbital, and propulsion and power systems from 
its flight-proven STAR GEO communications satellites.

47

 To develop its 

pressurized cargo module, Orbital has teamed with Thales-Alenia Space—
which was the prime contractor of several pressurized logistics modules 
currently used by the space shuttle to transport cargo to the space 
station.

48

 A summary of the progress made by Orbital in developing its 

COTS system follows. 

Launch vehicle.

 Orbital has completed several early design reviews of its 

Taurus II launch vehicle; however, delays in the development of first-stage 
tanks and ongoing development tests of first-stage engine components 
have compressed Orbital’s already aggressive development schedule. 
Orbital began Taurus II development as an independent research and 
development project in 2007 and completed a Taurus II system 
requirements review and PDR in July 2007 and February 2008, 
respectively. Orbital officials reported that since joining the COTS project, 
it has completed separate subsystem design reviews with its partners: in 
October 2008, Orbital completed a CDR of the first-stage engine assembly 
with Aerojet, a PDR of the first-stage tanks with Yuzhnoye, and a CDR of 

                                                                                                                                    

46

Orbital’s Cygnus visiting vehicle is not designed to return cargo to Earth, although it can 

dispose of trash from the space station. Orbital estimates that Cygnus will be able to 
deliver or dispose of about 2 metric tons (approximately 4,400 pounds) of pressurized 
cargo on a single mission. Because the Cygnus is yet to be qualified and flown, the final 
cargo capacity of the Cygnus is yet to be known. Once development is completed, Orbital 
estimates that in an enhanced configuration, its pressurized cargo module could provide as 
much as 2.7 metric tons (approximately 5,950 pounds) of cargo delivery and disposal in a 
given mission. The Cygnus’s cargo capacity for a given mission will vary depending on the 
density of the cargo and how it is packed. 

47

Orbital is working with Draper Laboratory to develop guidance, navigation, and fault 

tolerant computer support, and plans to use hardware and software developed by Japan 
Aerospace Exploration Agency for the H-II Transfer Vehicle to facilitate proximity and 
berthing operations with the space station. 

48

Thales-Alenia Space was the prime contractor to NASA and the Italian Space Agency in 

the development of the three multipurpose pressurized logistics modules used by the space 
shuttle to ferry pressurized cargo to and from the space station. Thales-Alenia Space was 
also the prime contractor to the European and Italian Space Agencies for the development 
of Nodes 2 and 3 of the space station. COTS vehicles are intended to berth with the space 
station at Node 2 during their COTS demonstrations. 

Page 27 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

the second-stage motor with ATK in March 2008. However, Orbital 
reported that it has experienced schedule slips for other Taurus II 
development milestones. Orbital’s joint CDR with Aerojet and Yuzhnoye 
for the first-stage engine and tanks slipped 4 months from November 2008 
until March 2009.

 Orbital also delayed a separate CDR with Yuzhnoye for 

the first-stage tanks 6 months from February 2009 to August 2009 to 
address issues with the engine feed lines and fuel tank mass. 

Although Orbital has moved its COTS demonstration date 3 months, from 
December 2010 until March 2011, Orbital’s schedule to complete Taurus II 
first-stage development appears to provide little margin to respond to 
future technical issues, should they arise. Orbital is tracking the delivery of 
its first-stage engine components as a significant Taurus II risk. Its Taurus 
II risk summary report indicates that given the compressed schedule for 
developing these components, there is a possibility that the Taurus II 
program schedule for its COTS demonstration mission may not be met. In 
addition, Orbital and Aerojet are in the process of conducting development 
tests of components from heritage NK-33 rocket engines that will be used 
to produce the Taurus II first-stage engines. Orbital reported that the NK-
33 engines have been in storage since 1972 and tests are being done to 
ensure that components have not degraded over time. 

Space vehicle.

 Orbital has completed several early design reviews of key 

components for its Cygnus space vehicle; however, technical and schedule 
obstacles must be overcome before Orbital may attempt its COTS 
demonstration. Orbital completed a system requirements review for its 
demonstration mission in July 2008, a PDR for its pressurized cargo 
module in October 2008, and the first of three space station Safety Review 
Panel reviews in March 2009. Orbital also reported that procurement of 
long-lead systems for the Cygnus has begun, with production scheduled to 
begin before the end of 2009 and integration tests scheduled to begin in 
February 2010. However, NASA officials reported that Orbital had a late 
start in developing its capabilities to integrate its space vehicle with the 
space station. According to NASA officials, this is due, in part, to Orbital’s 
late entry to the COTS project and because there was some question over 
whether Orbital would demonstrate a pressurized or unpressurized cargo 
delivery capability in its COTS demonstration mission.  

                                                                                                                                    

49

This slip was due, in part, to difficulties establishing and negotiating testing and delivery 

requirements with Yuzhnoye for the development of the first-stage tanks.  

Page 28 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

Orbital’s aggressive schedule could present challenges with completing 
requirements in NASA’s International Space Station to COTS Interface 
Requirements Document in time for its March 2011 demonstration mission 
launch date.

50

 To help address the technical challenges of integrating with 

the space station, Orbital plans to use hardware and software developed 
by Japan Aerospace Exploration Agency for the H-II Transfer Vehicle to 
facilitate proximity and berthing operations. NASA officials reported that 
Orbital may benefit from its partnerships with experienced 
subcontractors, such as Japan Aerospace Exploration Agency and Thales-
Alenia Space, but a significant amount of work remains to be done under a 
compressed development schedule before Orbital can be certified to 
integrate with the space station. 

Launch readiness.

 Orbital has begun the development of its COTS launch 

site at the Mid-Atlantic Regional Spaceport in Wallops Island, Virginia, but 
more work remains to be done to complete NASA’s launch safety 
requirements and acquire FAA launch licenses. As required by its 
agreement, Orbital completed an initial review of the launch site facilities 
to be developed and prepared a concept of operations for its launch 
activities. To support its COTS demonstration mission, Orbital and the 
Mid-Atlantic Regional Spaceport intend to construct several new facilities, 
including a horizontal integration facility (to integrate the Taurus II with 
the Cygnus); a launch pad, mount, and ramp; and separate fueling facilities 
for the Taurus II and the Cygnus. Orbital’s construction schedule indicates 
that its launch pad, mount, and ramp will be completed by the end of 2009. 
Orbital reported that construction of the horizontal integration facility is 
planned for completion in May 2010, and the Cygnus space vehicle fueling 
facility is planned to be completed by October 2010. Before it may attempt 
its demonstration mission, Orbital must receive NASA’s approval that its 
new launch site facilities in development meet NASA’s range safety 
requirements, which apply at the Mid-Atlantic Regional Spaceport. These 
requirements are scheduled for completion by Orbital’s demonstration 
mission readiness review, scheduled for February 2011. Orbital must also 
submit applications to the FAA for a launch license for the Taurus II and a 
re-entry license for the Cygnus space vehicle. A draft of its launch license 

                                                                                                                                    

50

NASA’s International Space Station to COTS Interface Requirements Document requires 

COTS vehicles to have two-fault tolerant systems to mitigate against catastrophic hazards 
that could occur during integrated operations with the space station. Orbital reported that 
it typically builds its components with one-fault tolerance and has cited the development 
and verification of hardware and software needed for space station rendezvous and 
proximity operations as a high risk.  

Page 29 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

application is required as part of its COTS System CDR, scheduled for 
September 2009. 

With the approaching retirement of the space shuttle in 2010, NASA faces 
the difficult challenge of securing sufficient and reliable cargo 
transportation capabilities to the space station from 2010 to 2015. NASA 
has taken several steps recently to finish its $31 billion investment in the 
construction of the space station, which include installing the necessary 
equipment to support a crew of six astronauts and to fully utilize the space 
station’s research capabilities. While commercial partners have made 
progress in developing cargo transportation capabilities, they have 
recently fallen behind their development schedules. Furthermore, the 
most critical steps lie ahead, including successfully launching new 
vehicles and completing integration with the space station. The impending 
retirement of the space shuttle leaves NASA with little margin to address 
future COTS development delays. Should commercial partners suffer 
future delays or be unable to provide cargo resupply services when 
anticipated, NASA will be unable to fully utilize the space station as 
intended. 

Concluding 
Observations 

 
We provided a copy of the draft report to the Department of Defense 
(DOD), FAA, and NASA for comment. We also gave SpaceX and Orbital an 
opportunity to comment on the findings related to their development 
efforts. DOD and FAA did not submit comments. In commenting on a draft 
of our report, NASA found it to be “thorough, objective, and helpful in 
addressing commercial crew and cargo demonstration efforts.” NASA’s 
written comments appear in appendix II. NASA, SpaceX, and Orbital also 
provided technical comments which we have incorporated as appropriate. 

Agency Comments 
and Our Evaluation 

 

 

We will send copies of the report to NASA’s Administrator and interested 
congressional committees. The report will be available at no charge on the 
GAO Web site at http://www.gao.gov. 

Page 30 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

Should you or your staffs have any questions on matters discussed in this 
report, please contact me at (202) 512-4841 or chaplainc@gao.gov. Contact 
points for our Offices of Congressional Relations and Public Affairs may 
be found on the last page of this report. GAO staff who made key 

Cristina Chaplain 

contributions to this report are listed in appendix III. 

Director, Acquisition and Sourcing Management 

Page 31 

GAO-09-618  NASA's COTS Project 

background image

 

 

 

 
 

List of Congressional Addressees 

The Honorable Barbara A. Mikulski 
Chairman 
The Honorable Richard C. Shelby 
Ranking Member 
Subcommittee on Commerce, Justice, Science, 
   and Related Agencies 
Committee on Appropriations 
United States Senate 

The Honorable Alan B. Mollohan 
Chairman 
The Honorable Frank R. Wolf 
Ranking Member 
Subcommittee on Commerce, Justice, Science, 
   and Related Agencies 
Committee on Appropriations 
House of Representatives 

The Honorable Gabrielle Giffords 
Chairwoman 
Subcommittee on Space and Aeronautics 
Committee on Science and Technology 
House of Representatives 

The Honorable Mark Udall 
United States Senate 

Page 32 

GAO-09-618  NASA's COTS Project 

background image

 
Appendix I: Scope and Methodology 
 
 

Appendix I: Scope and Methodology 

To examine the National Aeronautics and Space Administration’s (NASA) 
management of the Commercial Orbital Transportation Services (COTS) 
project and its expenditures, we analyzed project documentation, 
including the Space Act agreements NASA entered into with its 
commercial partners, NASA’s guidance for implementing these 
agreements,

51

 development milestone and quarterly reviews and other 

briefings, and project funding and expenditures. We evaluated NASA’s 
management of the COTS project by comparing COTS management 
activities with critical project management tools and activities identified in 
NASA’s Space Act Agreements Guide and in prior GAO work on NASA 
projects with similarities to COTS.

52

 We also analyzed NASA budget and 

funding documentation, confirmed this data with relevant milestone 
payment documentation, and evaluated the processes used for validating 
expenditures. In addition, we interviewed NASA and company officials to 
assess NASA’s management of the project and to verify project funding 
and expenditures. 

To determine the extent to which NASA is reliant on commercial partners 
to meet the space station’s cargo resupply needs, we reviewed 
International Space Station program office documentation on the space 
station’s cargo resupply needs and risks, NASA’s plans to meet its cargo 
resupply needs between 2010 and 2015, and international and commercial 
partners’ vehicle capabilities. We interviewed officials at NASA’s 
Commercial Crew and Cargo and International Space Station program 
offices to confirm NASA’s cargo resupply plans and to verify cargo 
resupply needs and risks and vehicle capabilities. We also reviewed NASA 
studies that assessed the impact of the COTS project on NASA’s cargo 
resupply strategy. 

To determine the extent to which commercial partners have made 
progress or experienced challenges in developing cargo transport 
capabilities, we reviewed each partner’s agreement with NASA, supporting 
documentation submitted by commercial partners to NASA for each 
milestone, partners’ development schedules and technical risks, NASA’s 

                                                                                                                                    

51

NASA Advisory Implementing Instruction (NAII) 1050-1A is also known as NASA’s Space 

Act Agreements Guide. 

52

GAO, 

Space Transportation: Critical Areas NASA Needs to Address in Managing Its 

Reusable Launch Vehicle Program

GAO-01-826T

 (Washington, D.C.: June 20, 2001). 

Page 33 

GAO-09-618  NASA's COTS Project 

background image

 
Appendix I: Scope and Methodology 
 
 

requirements for integrating with the space station,

53

 and prior GAO 

reports. We also reviewed the commercial transportation space 
regulations of the Federal Aviation Administration’s Office of Commercial 
Space Transportation

54

 and U.S. Air Force Space Command’s range safety 

requirements

55

 to evaluate commercial partners’ progress in obtaining 

required licenses and in developing their launch sites and operations 
procedures. We conducted field visits and interviewed commercial 
partners to determine partners’ development progress against 
performance milestones and to identify technical and schedule challenges. 
In addition, we interviewed officials at NASA’s Headquarters, Johnson 
Space Center, and Wallops Flight Facility; the Federal Aviation 
Administration’s (FAA) Office of Commercial Space Transportation; 
Patrick Air Force Base and Cape Canaveral Air Force Station; and Mid-
Atlantic Regional Spaceport. Our review did not attempt to independently 
identify risks and challenges or assess whether a partner successfully 
accomplished a particular milestone. We relied on the commercial 
partners’ assessments of the technical challenges they faced and NASA’s 
determination that a milestone had been successfully completed. 

                                                                                                                                    

53

The International Space Station to Commercial Orbital Transportation Services Interface 

Requirements Document (SSP 50808) provides interface and performance requirements 
between the space station and COTS partners, performance and design requirements for 
the COTS ground systems supporting COTS vehicle flights to space station, and design 
requirements on the COTS vehicle to ensure safe integration with the space station. 

54

The commercial space licensing regulations are outlined at 14 C.F.R. §§ 413-437 (2009). 

55

The range safety requirements are published in U.S. Air Force Space Command Manual 

91-710, which is divided into seven volumes. 

Page 34 

GAO-09-618  NASA's COTS Project 

background image

 

Appendix II: Comments from the National 
Aeronautics and Space Administration 

 
 

Appendix II: Comments from the National 
Aeronautics and Space Administration 

 

 

 

Page 35 

GAO-09-618  NASA's COTS Project 

background image

 
Appendix III: GAO Contact and Staff 
Acknowledgments 
 
 

Appendix III: GAO Contact and Staff 
Acknowledgments 

Cristina Chaplain, (202) 512-4841 or chaplainc@gao.gov 

 
In addition to the individual named above, Jim Morrison, Assistant 
Director; Matt Barranca; Greg Campbell; Brian Hartman; Jeff Hartnett; 
Arturo Holguin; Kenneth E. Patton; Tim Persons; and Alyssa Weir made 
contributions to this report. 

Page 36 

GAO-09-618  NASA's COTS Project 

GAO Contact 

Acknowledgments 

(120765) 

background image

 
 
 
 
 
 
 
 
 
 
 
 
 

 
 
 
 
 

 

 

GAO’s Mission 

The Government Accountability Office, the audit, evaluation, and 
investigative arm of Congress, exists to support Congress in meeting its 
constitutional responsibilities and to help improve the performance and 
accountability of the federal government for the American people. GAO 
examines the use of public funds; evaluates federal programs and policies; 
and provides analyses, recommendations, and other assistance to help 
Congress make informed oversight, policy, and funding decisions. GAO’s 
commitment to good government is reflected in its core values of 
accountability, integrity, and reliability. 

The fastest and easiest way to obtain copies of GAO documents at no cost 
is through GAO’s Web site (

www.gao.gov

). Each weekday afternoon, GAO 

posts on its Web site newly released reports, testimony, and 
correspondence. To have GAO e-mail you a list of newly posted products, 
go to 

www.gao.gov

 and select “E-mail Updates.” 

Obtaining Copies of 
GAO Reports and 
Testimony 

Order by Phone 

The price of each GAO publication reflects GAO’s actual cost of 
production and distribution and depends on the number of pages in the 
publication and whether the publication is printed in color or black and 
white. Pricing and ordering information is posted on GAO’s Web site, 

http://www.gao.gov/ordering.htm

.  

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or  
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card, 
MasterCard, Visa, check, or money order. Call for additional information. 

Contact: 

Web site: 

www.gao.gov/fraudnet/fraudnet.htm 

E-mail: 

fraudnet@gao.gov

 

Automated answering system: (800) 424-5454 or (202) 512-7470 

Ralph Dawn, Managing Director, 

dawnr@gao.gov

, (202) 512-4400 

U.S. Government Accountability Office, 441 G Street NW, Room 7125 
Washington, DC 20548 

To Report Fraud, 
Waste, and Abuse in 
Federal Programs 

Congressional 
Relations 

Chuck Young, Managing Director, 

youngc1@gao.gov

, (202) 512-4800 

U.S. Government Accountability Office, 441 G Street NW, Room 7149  
Washington, DC 20548 

Public Affairs 

 

Ple

as

e Print on Recycled P

a

per

 


Document Outline