background image

 
 
 
 
 
 
 
 
 
 
 

United States Government Accountability Office

 

GAO 

Testimony 
Before the Subcommittee on Space and 
Aeronautics, Committee on Science, 
Space and Technology, House of 
Representatives

COMMERCIAL LAUNCH 
VEHICLES 

NASA Taking Measures to 
Manage Delays and Risks 

Statement of Cristina T. Chaplain, Director  
Acquisition and Sourcing Management 
 
 

 

For Release on Delivery 
Expected at 10:00 a.m. EST 
Thursday, May 26, 2011 

 
 

 

GAO-11-692T 

background image

Accountability • Integrity • Reliability 

 

Highlights of 

GAO-11-692T

, a report to the 

Subcommittee on Space and Aeronautics, 
Committee on Science, Space, and 
Technology, House of Representatives 

 

May 26, 2011 

COMMERCIAL LAUNCH VEHICLES 

NASA Takin

g

 Measures to Mana

g

e Delays and Risks 

 

Why GAO Did This Study 

Since the National Aeronautics and 
Space Administration (NASA) created 
the strategy for the Commercial 
Orbital Transportation Services 
(COTS) project in 2005, the space 
landscape has changed significantly—
the Space Shuttle program is retiring 
and the Ares I will not be available—
increasing the importance of the 
timely development of COTS vehicles. 
The lack of alternatives for supplying 
the International Space Station and 
launching science missions have all 
contributed to an increased need for 
the COTS vehicles. The two COTS 
project partners, Orbital and SpaceX, 
have made progress in the 
development of their respective 
vehicles; however, both providers are 
behind schedule. As a result, the 
project recently received an additional 
$300 million to augment development 
efforts with risk reduction milestones. 

This testimony focuses on: (1) COTS 
development activities, including the 
recent funding increase; (2) the 
extent to which any COTS 
demonstration delays have affected 
commercial resupply services (CRS) 
missions and NASA’s plans for 
meeting the space station’s cargo 
resupply needs; and (3) lessons 
learned from NASA’s acquisition 
approach for COTS. 

To prepare this statement, GAO used 
its prior relevant work and conducted 
additional audit work, such as 
analyzing each partner’s agreement 
with NASA and interviewing NASA 
officials. New data in this statement 
was discussed with agency and 
company officials who provided 
technical comments, which we 
included as appropriate.

What GAO Found

 

SpaceX and Orbital continue to make progress completing milestones under 
their COTS agreements with NASA, but both partners are working under 
aggressive schedules and have experienced delays in completing 
demonstration missions. SpaceX successfully flew its first demonstration 
mission in December 2010, but the mission was 18 months late and the 
company’s second and third demonstration missions have been delayed by 
almost 2 years due to design, development, and production challenges with 
the Dragon spacecraft and Falcon 9 launch vehicle. Orbital faced technical 
challenges developing the Taurus II launch vehicle and the Cygnus spacecraft 
and in constructing launch facilities, leading to multiple delays in completing 
program milestones, including its demonstration mission. NASA has amended 
its agreements with the partners to include a number of new milestones, such 
as additional ground and flight tests, to reduce remaining developmental and 
schedule risks; most of the new milestones completed thus far were finished 
on time, but many milestones remain. 

Based on the current launch dates for SpaceX’s and Orbital’s upcoming COTS 
demonstration missions, it is likely that neither will launch its initial CRS 
mission on time, but NASA has taken steps to mitigate the short-term impact 
to the space station. The launch windows for SpaceX’s first and second CRS 
flights are scheduled to occur either before or during its upcoming COTS 
demonstration flights and will need to be rescheduled. Orbital’s first CRS 
flight will also likely shift due to a Taurus II test flight. NASA officials said that 
the agency will have to renegotiate the number of flights needed from each 
partner and re-baseline the launch windows for future CRS missions once 
COTS demonstration flights are completed. NASA has taken steps to mitigate 
the short-term impact of CRS delays through prepositioning of cargo, some of 
which will be delivered on the last space shuttle flight. Despite these efforts, 
NASA officials said they would still need one flight in 2012 from SpaceX’s and 
Orbital’s vehicles to meet science-related cargo needs.  

In considering the use of a Space Act agreement for COTS, NASA identified 
several advantages. These advantages include sharing costs with agreement 
partners and promoting innovation in the private sector. A disadvantage, 
however, is that NASA is limited in its ability to influence agreement partners 
in their approach. At the time the agreements were awarded, NASA was 
willing to accept the risks of using a Space Act agreement given the goals of 
the project and alternative vehicles that were available to deliver goods to the 
space station. As the project has progressed, however, and these alternatives 
are no longer viable or available, NASA has become less willing to accept the 
risk involved and has taken steps aimed at risk mitigation. Given a critical 
need, the risk is present that the government will be required to make 
additional investments to meet mission needs. The amount of investment can 
be lessened by ensuring that accurate knowledge about requirements, cost, 
schedule, and risks is achieved early on. GAO has made recommendations to 
NASA and NASA is taking steps to help ensure that these fundamentals are 
present in its major development efforts to increase the likelihood of success. 

View 

GAO-11-692T 

or key components. 

For more information, contact Cristina 
Chaplain at (202) 512-4841 or 
chaplainc@gao.gov. 

 

 United States Government Accountability Office 

background image

 
 
 
 

Page 1 

GAO-11-692T   

 

 

Mr. Chairman and Members of the Subcommittee: 

Thank you for inviting me here today to discuss the status of the National 
Aeronautics and Space Administration’s (NASA) Commercial Orbital 
Transportation Services (COTS) project. GAO conducted work examining 
the COTS project in 2009 and reported that progress was being made, but 
several risks persisted given aggressive project schedules.

1

 Since NASA 

devised its strategy for the COTS project in 2005, the space landscape has 
changed quite significantly, increasing the importance of the timely 
development and success of COTS vehicles to NASA. Specifically, with the 
impending retirement of the space shuttle in July 2011, the United States 
will lack a domestic capability to send crew and cargo to the International 
Space Station and face a cargo resupply shortfall between 2012 and 2020 
that cannot be met by international partners’ space vehicles alone.

2

 The 

Ares I project, which was originally intended to be operational in 2010 and 
to fill the gap between the retirement of the Space Shuttle program and the 
availability of the COTS vehicles, pushed its launch readiness date to 2015 
and is now being restructured into a new program that will not be 
operational until at least 2016. Further, the Delta II launch vehicle, which 
has carried the majority of NASA’s science missions over the last several 
years, is retiring, the impact of which is beginning to be felt by NASA’s 
science projects.

3

 These changes have resulted in an increased need for 

the vehicles being developed for COTS not only to address the cargo 
resupply shortfall as intended, but also to support a large number of future 
science missions at a reasonable cost to NASA. While COTS partners have 
made progress in the development of their vehicles, they have also 
experienced delays and NASA has provided additional funding to the 
partners to reduce the risk that their vehicles would experience further 
delays. 

Against this backdrop, my testimony today will focus on: (1) the COTS 
development activities, including a discussion of the need for the recent 

                                                                                                                                    

1

GAO, 

NASA: Commercial Partners Are Making Progress, but Face Aggressive Schedules 

to Demonstrate Critical Space Station Cargo Transport Capabilities, 

GAO-09-618

 

(Washington, D.C.: June 16, 2009). 

2

International partners’ vehicles include the Russian Federal Space Agency’s Progress 

(cargo) and Soyuz (crew), the European Space Agency’s Automated Transfer Vehicle 
(cargo), and the Japan Aerospace Exploration Agency’s H-II Transfer Vehicle (cargo). 

3

GAO, 

NASA: Medium Launch Transition Strategy Leverages Ongoing Investments but is 

Not Without Risk, 

GAO-11-107

 (Washington, D.C.: Nov. 22, 2010). 

background image

 
 
 
 

funding augmentation; (2) the extent to which any COTS demonstration 
delays have affected Commercial Resupply Services (CRS) missions to the 
space station and NASA’s plans for meeting space station cargo resupply 
needs; and (3) lessons learned from NASA’s acquisition approach for 
COTS. 

In preparing this statement, we relied on our prior report related to the 
COTS project and conducted additional audit work in May 2011 to update 
information from that report.

4

 Specifically, we analyzed each COTS 

partner’s agreement with NASA, amendments to those agreements, 
documentation from NASA and partner quarterly program management 
reviews, and each partner’s CRS contract. We interviewed NASA COTS 
and International Space Station program officials and company officials. 
We discussed new information presented in this statement with agency 
and company officials who provided technical comments that we 
incorporated as appropriate. Our prior work on the COTS project, as well 
as the work conducted for this statement, was performed in accordance 
with generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, appropriate 
evidence to provide a reasonable basis for our findings and conclusions 
based on our audit objectives. We believe that the evidence obtained 
provides a reasonable basis for our findings and conclusions based on our 
audit objectives. 

 
In 2004, President George W. Bush announced his Vision for Space 
Exploration that included direction for NASA to pursue commercial 
opportunities for providing transportation and other services to support 
the space station after 2010. When the project was established in 2005, the 
approach that NASA laid out was a marked change in philosophy for how 
the agency planned to service the space station—by encouraging 
innovation in the private sector with the eventual goal of buying services 
at a reasonable price. As a result, the agency chose to utilize its other 
transaction authority under the National Aeronautics and Space Act of 
1958,

5

 as opposed to a more traditional Federal Acquisition Regulation 

(FAR) based contract. Generally speaking, other transaction authority 

Background 

                                                                                                                                    

4

GAO-09-618

5

Pub. L. No. 85-568, § 203 (1958). This act is commonly referred to as the Space Act and 

agreements signed utilizing NASA’s other transaction authority are known as Space Act 
agreements. 

Page 2 

GAO-11-692T   

background image

 
 
 
 

enhances the government’s ability to acquire cutting-edge science and 
technology, in part through attracting companies that typically have not 
pursued government contracts because of the cost and impact of 
complying with government procurement requirements. These types of 
agreements are not considered federal government contracts, and are 
therefore generally not subject to those federal laws and regulations that 
apply to federal government contracts. 

NASA established the Commercial Crew and Cargo program office at 
Johnson Space Center in 2005 and budgeted $500 million for fiscal years 
2006 through 2010 for the development and demonstration of cargo 
transport capabilities. COTS partners, Orbital Sciences Corporation 
(Orbital) and Space Exploration Technologies Corporation (SpaceX), have 
also made significant investments in developing these capabilities. The 
COTS project was originally intended to be executed in two sequential 
phases: (1) private industry development of cargo transport capabilities in 
coordination with NASA and (2) procurement of commercial resupply 
services to the space station once cargo transport capabilities had been 
successfully demonstrated. In August 2006, NASA competitively awarded a 
$278 million Space Act agreement to SpaceX to develop and demonstrate 
end-to-end transportation systems, including the development of the 
Falcon 9 launch vehicle and Dragon spacecraft, ground operations, and 
berthing with the space station. In February 2008, NASA awarded a $170 
million Space Act agreement to Orbital to develop two COTS cargo 
capabilities, unpressurized and pressurized

6

 cargo delivery and disposal, 

to culminate in one demonstration flight of its Taurus II launch vehicle an
Cygnus spacecraft.

                                                                                                                                   

7

 

Before either partner had successfully demonstrated its COTS cargo 
transport capabilities, the International Space Station program office 
awarded two CRS contracts in December 2008 to Orbital and SpaceX 
under a separate competitive procurement from COTS. These FAR-based 
contracts were for the delivery of at least 40 metric tons (approximately 

 

6

Pressurized cargo refers to cargo that is carried inside the spacecraft.  This cargo includes 

items such as food, water, and materials to support scientific experiments. 

7

NASA originally awarded a $207 million Space Act agreement to Rocketplane Kistler 

(RpK), but the agreement was terminated in October 2007 after RpK had missed technical 
and financial milestones. Subsequently, Orbital was awarded the remaining funds—$170 
million. In March 2009, Orbital and NASA amended this agreement, removing its 
unpressurized cargo demonstration and replacing it with a pressurized demonstration, 
scheduled for March 2011. 

Page 3 

GAO-11-692T   

background image

 
 
 
 

88,000 pounds) to the space station between 2010 and 2015. Orbital was 
awarded 8 cargo resupply missions for approximately $1.9 billion and 
SpaceX was awarded 12 cargo resupply missions for approximately $1.6 
billion. 

In June 2009, we found that while SpaceX and Orbital had made progress 
against development milestones, the companies were working under 
aggressive schedules and had experienced schedule slips that delayed 
upcoming demonstration launch dates by several months. In addition, we 
reported that the vehicles being developed through the COTS project were 
essential to NASA’s ability to fully utilize the space station after its 
assembly was completed and the space shuttle was retired. Finally, we 
found that NASA’s management of the COTS project generally adhered to 
critical project management tools and activities. 

Since our 2009 report, the two COTS project partners, Orbital and SpaceX, 
have made progress in the development of their respective vehicles. 
SpaceX successfully flew its first COTS demonstration mission in 
December 2010 and Orbital is planning to fly its COTS demonstration 
mission in December 2011. Both providers, however, are behind 
schedule—SpaceX’s first COTS demonstration mission slipped 18 months 
and Orbital’s first mission was initially planned for March 2011. Such 
delays are not atypical of development efforts, especially efforts that are 
operating under such aggressive schedules. Nonetheless, the criticality of 
these vehicles to the space station’s operations, as well as NASA’s ability 
to affordably execute its science missions has heightened the importance 
of their timely and successful completion and lessened the level of risk 
that NASA is willing to accept in this regard. As a result, the project 
recently requested and received an additional $300 million to augment the 
partner development efforts with, according to NASA, risk reduction 
milestones. 

 

Page 4 

GAO-11-692T   

background image

 
 
 
 

 

 

 

 

 

 

Demonstration 
Missions Have Been 
Delayed, but Progress 
Against New 
Milestones Could 
Reduce Further 
Technical and 
Schedule Risk 

 

SpaceX: Performance 
Against Prior Milestones 

SpaceX has successfully completed 18 of 22 milestones to date, but has 
experienced lengthy delays in completing key milestones since we last 
reported on the company’s progress in June 2009. SpaceX’s agreement 
with NASA established 22 development milestones that SpaceX must 
complete in order to successfully demonstrate COTS cargo capabilities. 
SpaceX’s first demonstration mission readiness review was completed 15 
months behind schedule and its successful first demonstration mission 
was flown in December 2010, 18 months late. The company’s second and 
third demonstration missions have been delayed by almost 2 years to 
November 2011 and January 2012, respectively.

8

 Several factors 

contributed to the delay in SpaceX’s first demonstration mission readiness 
review and demonstration mission. These factors include, among others, 
delays associated with (1) launching the maiden Falcon 9 (non-COTS 
mission), such as Falcon 9 software and database development; (2) 
suppliers; (3) design instability and production; (4) Dragon spacecraft 
testing and software development; and (5) obtaining flight safety system 
approval. For example, SpaceX encountered welding issues during 
production of the Dragon propellant tanks and also had to redesign the 
Dragon’s battery. 

In preparing for its second COTS demonstration flight, SpaceX has 
experienced additional design, development, and production delays. For 
example, several propulsion-related components needed to be redesigned, 

                                                                                                                                    

8

According to the COTS program manager, NASA is also discussing with SpaceX about the 

possibility of combining the second and third demonstration missions into a single mission. 
SpaceX officials told us they have already begun building the Dragon spacecraft for the 
second COTS demonstration mission so that it can be fully capable of berthing with the 
space station. 

Page 5 

GAO-11-692T   

background image

 
 
 
 

the Dragon spacecraft’s navigation sensor experienced development 
testing delays, and delays were experienced with launch vehicle tank 
production. For example, SpaceX’s decision to incorporate design changes 
to meet future CRS mission requirements has delayed the company’s 
second demonstration mission. Integration challenges on the maiden 
Falcon 9 launch and the first COTS demonstration mission have also kept 
SpaceX engineers from moving on to the second COTS demonstration 
mission. 

SpaceX officials cited the completion of Dragon development efforts,  
NASA’s safety verification process associated with berthing with the space 
station, and transitioning into efficient production of the Falcon 9 and 
Dragon to support space station resupply missions as key drivers of 
technical and schedule risk going forward. For completing 18 of the 22 
milestones, SpaceX has received $258 million in milestone payments thus 
far, with $20 million yet to be paid. Appendix I describes SpaceX’s 
progress meeting the COTS development milestones in its agreement with 
NASA. 

Orbital: Performance 
Against Prior Milestones 

Orbital has successfully completed 15 of 19 COTS milestones to date—8 
more than when we initially reported on the program in June 2009. 
Programmatic changes and developmental difficulties, however, have led 
to multiple delays of several months’ duration and further delays are 
projected for completing the remaining milestones. For example, 
according to Orbital officials, the demonstration mission of Orbital’s 
Taurus II launch vehicle and Cygnus spacecraft has been delayed primarily 
due to an increase in design effort to develop a pressurized cargo carrier in 
place of the original Cygnus unpressurized cargo design. After NASA 
awarded Orbital a CRS contract for eight pressurized cargo missions, 
NASA and Orbital amended their COTS demonstration agreement to 
replace the unpressurized cargo demonstration mission with a pressurized 
cargo demonstration. This delayed existing milestones, and the schedule 
was revised to shift the COTS demonstration mission from December 2010 
to March 2011. Since that time, the schedule for some of Orbital’s 
milestones has been revised again and the demonstration mission is now 
planned for December 2011. 

COTS program and Orbital officials also noted technical challenges as 
reasons for milestone delays. For example, Orbital officials said there are 
several critical Taurus II engine and stage one system tests that need to be 
completed by the end of the summer, but that the risk inherent in these 
tests is mitigated through an incremental approach to testing. Specifically, 
single engine testing has been successfully completed, and testing will be 

Page 6 

GAO-11-692T   

background image

 
 
 
 

extended this summer to the full stage one (i.e., two-engine) testing. COTS 
program and Orbital officials also noted delays in Cygnus avionics 
manufacturing, primarily driven by design modifications aimed at 
increasing the safety and robustness of the system. According to these 
officials, integration and assembly of the first Cygnus spacecraft has begun 
and is now in the initial electrical testing phase. 

Additionally, the completion of the company’s launch facilities at the Mid-
Atlantic Regional Space Port in Wallops Island, Virginia, remains the key 
component of program risk. NASA COTS program and Orbital officials cite 
completion of the Wallops Island launch facilities as the critical factor for 
meeting the COTS demonstration mission schedule. Orbital officials said 
additional resources have been allocated to development of the launch 
complex to mitigate further slips, and an around-the-clock schedule will be 
initiated later this summer to expedite the completion of verification 
testing of the liquid fueling facility, which is the primary risk factor in 
completing the launch facility. 

For completing 15 of the 19 milestones, Orbital has received $157.5 
million, with $12.5 million remaining to be paid. Appendix I depicts 
Orbital’s progress in meeting the COTS development milestones in its 
agreement with NASA. 

 

Risk Reduction Milestones 
Recently Added to COTS 
Agreements 

In addition to the prior milestones negotiated under the COTS project, 
NASA has amended its agreements with SpaceX and Orbital to include a 
number of additional milestones aimed at reducing remaining 
developmental and schedule risks. COTS officials told us that some 
milestones reflect basic risk reduction measures, such as thermal vacuum 
testing, that NASA would normally require on launch vehicle or spacecraft 
development. A series of amendments were negotiated from December 
2010 to May 2011 after Congress authorized $300 million for commercial 
cargo efforts in fiscal year 2011. These amendments add milestones to (1) 
augment ground and flight testing, (2) accelerate development of 
enhanced cargo capabilities, or (3) further develop the ground 
infrastructure needed for commercial cargo capabilities. These milestones 
were added incrementally due to NASA operating under continuing 
resolutions through the first half of fiscal year 2011. 

Page 7 

GAO-11-692T   

background image

 
 
 
 

In May 2009, the President established a Review of U.S. Human Space 
Flight Plans Committee composed of space industry experts, former 
astronauts, government officials, and academics.

9

 In its report, the 

committee stated that it was concerned that the space station, and 
particularly its utilization, may be at risk after Shuttle retirement as NASA 
would be reliant on a combination of new international vehicles and as-
yet-unproven U.S. commercial vehicles for cargo transport. The committee 
concluded that it might be prudent to strengthen the incentives to the 
commercial providers to meet the schedule milestones. NASA officials 
stated that if funding were available, negotiating additional, risk reduction 
milestones would improve the chance of mission success, referring 
specifically to the companies’ COTS demonstration missions. Of the $300 
million, $236 million, divided equally between SpaceX and Orbital, will be 
paid upon completion of the additional milestones.

10

 Additionally, NASA 

officials stated the International Space Station program office will pay 
SpaceX and Orbital $10 million each to fund early cargo delivery to the 
space station on the companies’ final COTS demonstration missions. The 
COTS program manager stated that SpaceX and Orbital recognize their 
responsibility under the COTS agreements for any cost overruns 
associated with their development efforts, and that the companies did not 
come to NASA with a request for additional funding. 

SpaceX has completed 4 of its new milestones on time but has 
experienced minor delays in completing 3 others. SpaceX’s agreement 
with NASA was amended three times between December 2010 and May 
2011 to add 18 development milestones that SpaceX must complete in 
order to successfully demonstrate COTS cargo capabilities. Some of the 
new milestones, for example, are designed to increase NASA’s confidence 
that SpaceX’s Dragon spacecraft will successfully fly approach trajectories 
to the space station while others are intended to improve engine 
acceptance rates and vehicle production time frames. Milestones 
completed thus far include a test of the spacecraft’s navigation sensor and 
thermal vacuum tests. For completing 7 of the 18 milestones, SpaceX has 

                                                                                                                                    

9

Review of U.S. Human Spaceflight Plans Committee, 

Seeking a Human Spaceflight 

Program Worthy of a Great Nation

 (Washington, D.C.: October 2009). 

10

The COTS program manager reported that $34 million of the $300 million was for NASA 

Headquarters and Johnson Space Center program support and administration as well as 
technical and mission support for the remaining COTS demonstration flights and $10 
million would be spent on milestone payments for Orbital’s Milestones 20 and 21 and 
SpaceX’s Milestone 22. 

Page 8 

GAO-11-692T   

background image

 
 
 
 

received $40 million in milestone payments thus far, with $78 million yet to 
be paid. 

Orbital has completed 4 of its 10 new milestones on schedule and 1 of the 
new milestones was delayed by about 1 month. In concurrence with 
NASA’s request, Orbital agreed to add an initial flight test of the Taurus II 
launch vehicle to reduce overall cargo service risk. The test flight not only 
separates the risks of the first flight of Taurus II from the risks of the first 
flight of the Cygnus spacecraft, but provides the opportunity to measure 
the Taurus II flight environments using an instrumented Cygnus mass 
simulator. The Taurus II test flight is scheduled for October 2011. Overall 
technical risks associated with Cygnus development are expected to be 
reduced through additional software and avionics tests. Milestones 
completed thus far include early mission analyses and reviews, as well as 
delivery of mission hardware. For completing the first 5 new milestones, 
Orbital has received $69 million, with $49 million remaining to be paid. 
Appendix I describes SpaceX’s and Orbital’s progress meeting the new 
COTS development milestones in their agreements with NASA. 

 
Based on the current launch dates for SpaceX’s and Orbital’s upcoming 
COTS demonstration missions, it is likely that both commercial partners 
will not launch their initial CRS missions on time, but NASA has taken 
steps to mitigate the short-term impact to the space station. The launch 
window for SpaceX’s first CRS flight is from April to June 2011 and from 
October to December 2011 for its second CRS flight. These launch 
windows are either scheduled to occur before or during SpaceX’s 
upcoming COTS demonstration flights and thus will need to be 
rescheduled. In the case of Orbital, NASA officials told us that the launch 
window for its first CRS flight is from January to March 2012, but will 
likely slip from those dates given the Taurus II test flight added to its 
milestone schedule. NASA officials added that once SpaceX and Orbital 
have finished completing their COTS demonstration flights, NASA will 
have to renegotiate the number of flights needed from each partner and re-
baseline the launch windows for future CRS missions. 

COTS Delays Will 
Likely Cause 
Resupply Flights to 
Slip, but NASA Has 
Taken Steps to 
Mitigate Short-Term 
Impact 

International Space Station program officials told us they have taken steps 
to mitigate the short-term impact of CRS flight delays through 
prepositioning of cargo on the last space shuttle flights, including cargo 
that is being launched on the planned contingency space shuttle flight in 
early July 2011. Officials added that these flights and the planned 
European Space Agency’s Automated Transfer Vehicle and Japan’s H-II 
Transfer Vehicle flights in 2012 will carry enough cargo to sustain the six 

Page 9 

GAO-11-692T   

background image

 
 
 
 

person space station crew through 2012 and to meet science-related cargo 
needs through most of 2012. Despite these steps, NASA officials said they 
would still need one flight each from SpaceX’s and Orbital’s vehicles in 
order to meet science-related cargo needs in 2012. Beyond 2012, NASA is 
highly dependent on SpaceX’s and Orbital’s vehicles in order to fully utilize 
the space station. For example, we reported in April 2011 that 29 percent 
of the flights planned to support space station operations through 2020 
were dependent on those vehicles.

11

 In addition, NASA officials confirmed 

that the agency has no plans to purchase additional cargo flights on 
Russian Progress vehicles beyond 2011 and the European Space Agency 
and the Japan Aerospace Exploration Agency have no current plans to 
manufacture additional vehicles beyond their existing commitments or to 
accelerate production of planned vehicles. We reported previously that if 
the COTS vehicles are delayed, NASA officials said they would pursue a 
course of “graceful degradation” of the space station until conditions 
improve. In such conditions, the space station would only conduct 
minimal science experiments.

12

 

 
NASA’s intended use of the COTS Space Act agreements was to stimulate 
the space industry rather than acquiring goods and services for its direct 
use. Traditional FAR contracts are to be used when NASA is procuring 
something for the government’s direct benefit.

13

 NASA policy provides that 

funded Space Act agreements can only be used if no other instrument, 
such as a traditional FAR contract, can be used.

14

 Therefore, Space Act 

agreements and FAR-based contracts are to be used for different 
purposes. In considering the use of funded Space Act agreements for 
COTS, NASA identified several advantages. For example: 

Even With Identified 
Advantages, NASA 
Has Taken Measures 
to Address Risks to 
COTS Strategy 

•

 

The government can share costs with the agreement partner with fixed 
government investment. 

•

 

Payment to partner is made only after successful completion of 
performance-based milestones. 

                                                                                                                                    

11

GAO, 

International Space Station (ISS) â€“ Ongoing Assessments for Life Extension 

Appear to be Supported

GAO-11-519R

 (Washington, D.C.: Apr. 11, 2011). 

12

GAO, 

International Space Station: Significant Challenges May Limit Onboard 

Research

GAO-10-9

 (Washington, D.C.: Nov. 25, 2009). 

13

31 U.S.C. Â§ 6303. 

14

NASA Policy Directive 1050.1I, Authority to Enter into Space Act Agreements (Dec. 23, 

2008). 

Page 10 

GAO-11-692T   

background image

 
 
 
 

•

 

The government can terminate the agreement if the partner is not 
reasonably meeting milestones. 

•

 

Limited government requirements allow optimization of systems to 
meet company’s commercial business needs. 

 

These types of agreements can also have disadvantages, however. For 
example, Space Act agreements may have more limited options for 
oversight as compared to other science mission and human spaceflight 
development efforts that are accomplished under more traditional FAR 
contracts. NASA identified other disadvantages of using a Space Act 
agreement. For example: 

•

 

The government has limited ability to influence agreement partners in 
their approach. 

•

 

The government lacks additional management tools (beyond 
performance payments at milestones) to incentivize partners to meet 
technical and schedule performance. 

 

Given the intended goals of the project and the availability of alternative 
vehicles to deliver goods to the space station when the COTS agreements 
were signed, NASA was willing to accept the risks associated with the 
disadvantages of using a Space Act agreement.

15

 As the project has 

progressed, however, and these alternatives are no longer viable or 
available, NASA has become less willing to accept the risks involved. As a 
result, the agency took steps aimed at risk mitigation, primarily through 
additional funding. 

I would like to point out that neither Space Act agreements nor more 
traditional FAR contracts guarantee positive outcomes. Further, many of 
the advantages and disadvantages identified by NASA for using a Space 
Act agreement can also be present when using FAR-based contracts, 
depending on how the instrument is managed or written. For example, 
both a FAR contract and a Space Act agreement can provide for cost 
sharing and the government also has the ability to terminate a FAR 
contract or a Space Act agreement if it is dissatisfied with performance. 

                                                                                                                                    

15

NASA goals were to: (1) implement Space Exploration policy with investments to 

stimulate the commercial space industry; (2) facilitate U.S. private industry demonstrations 
of cargo and crew space transportation capabilities with the goal of achieving safe, reliable, 
cost-effective access to low-Earth orbit; and (3) create a market environment where 
commercial services are available to the government and private sector customers. 

Page 11 

GAO-11-692T   

background image

 
 
 
 

The ineffective management of the instrument can be an important 
contributor to poor outcomes. For example, although a Space Act 
agreement may lack management tools to incentivize partners, we have 
reported in the past that award fees, which are intended to incentivize 
performance on FAR-based contracts, are not always applied in an 
effective manner or even tied to outcomes.

16

 Additionally, the oversight 

that NASA conducts under a FAR-based contract has not always been used 
effectively to ensure that projects meet cost and schedule baselines.

17

 

Even with the advantages and disadvantages that can be present in various 
instruments, given a critical need, the government bears the risk for having 
to make additional investments to get what it wants, when it wants it. The 
additional investment required, however, can be lessened by ensuring that 
accurate knowledge about requirements, cost, schedule, and risks is 
achieved early on. We have reported for years that disciplined processes 
are key to ensuring that what is being proposed can actually be 
accomplished within the constraints that bind the project, whether they 
are cost, schedule, technical, or any other number of constraints.

18

 We 

have made recommendations to NASA and NASA is taking steps to 
address these recommendations to help ensure that these fundamentals 
are present in its major development efforts to increase the likelihood of 
success. 

 

 

Mr. Chairman, this concludes my prepared statement. I would be happy to 
respond to any questions you may have at this time. 

                                                                                                                                    

16

GAO, 

NASA Procurement: Use of Award Fees for Achieving Program Outcomes Should 

Be Improved

GAO-07-58

 (Washington, D.C.: Jan. 17, 2007). 

17

GAO, 

NASA: Assessments of Selected Large-Scale Projects

GAO-11-239SP

 (Washington, 

D.C.: Mar. 3, 2011). 

18

GAO, 

NASA: Assessments of Selected Large-Scale Projects

GAO-09-306SP

 (Washington, 

D.C.: Mar. 2, 2009); GAO, 

NASA: Assessments of Selected Large-Scale Projects

GAO-10-227SP

 (Washington, D.C.: Feb. 1, 2010); and 

GAO-11-239SP

Page 12 

GAO-11-692T   

background image

 
 
 
 

Appendix I: COTS Partners’ Progress 
Completing Prior and New Milestones 

Table 1: SpaceX’s Progress Completing Prior COTS Development Milestones 

Milestone 
number  

Milestone description 

Scheduled 
completion  
date 

Completed  
on time (Yes/No) 

Delay if 
applicable 
(months) 

Payment 
amount 
(millions) 

Project Management Plan Review 

Sept. 2006 

$23.1 

Demo 1 System Requirements Review  Nov. 2006 

$5 

Demo 1 Preliminary Design Review 

Feb. 2007 

$18.1 

Financing Round 1 

Mar. 2007 

$10 

Demo 2 System Requirements Review  Mar. 2007 

$31.1 

Demo 1 System Critical Design Review  Aug. 2007 

$8.1 

Demo 3 System Requirements Review  Oct. 2007 

$22.3 

Demo 2 Preliminary Design Review 

Dec. 2007 

$21.1 

Draco Initial Hot-Fire 

Mar. 2008 

$6 

10 

Financing Round 2 

Mar. 2008 

$10 

11 

Demo 3 Preliminary Design Review 

Jun. 2008 

$22 

12 

Multi-engine Test 

Sept. 2008 

$22 

13 

Demo 2/Demo 3 System Critical 
Design Review 

Dec. 2008 

$25 

14 

Financing Round 3 

Mar. 2009 

$10 

15 

Demo 1 Readiness Review 

Mar. 2009 

15 

$5 

16 

Communications Unit Flight Unit 
Design, Accept, Delivery 

May 2009 

$9 

17 

Demo 1 Mission 

Jun. 2009 

18 

$5 

18 

Demo 2 Readiness Review 

Sept. 2009

a

 N 

24 

(projected) 

$5 

19 

Demo 2 Mission 

Nov. 2009

a

 N 

24 

(projected) 

$5 

20 

Cargo Integration Demonstration 

Jan. 2010 

$5 

21 

Demo 3 Readiness Review 

Jan. 2010

a

 N 

23 

(projected) 

$5 

22 

Demo 3 Mission 

Mar. 2010

a

 N 

22 

(projected) 

$5 

 

 

 

 

Total: 

$278 million for 
the completion 
of all 
milestones 

$258 million 
paid to date 

Source: NASA and SpaceX. 

a

NASA is currently reviewing a proposed amendment that would change the completion dates for 

milestones 18, 19, 21, and 22. In particular, Demo Mission 2 (milestone 19) would take place in 
November 2011 and Demo Mission 3 in January 2012. 

 

 

Page 13 

GAO-11-692T   

background image

 
 
 
 

Table 2: Orbital’s Progress Completing Prior COTS Development Milestones 

Milestone 
number  

Milestone description 

Scheduled 
completion 

date 

Completed  
on time 
(Yes/No) 

Delay, if 
applicable 
(months) 

Payment amount 
(millions) 

Program Plan Review 

Mar. 2008 

$10 

Demo Mission System Requirements Review 

Jun. 2008 

$20 

Unpressurized Cargo Module Preliminary  
Design Review 

Jul. 2008 

$10 

4 DELETED 

COTS System Preliminary Design Review was 
milestone 4, but it has been renumbered as 
milestone 10 

No longer 
applicable 

No longer 
applicable 

No longer applicable 

5 COTS 

Integration/Operations 

Facility Review 

Sept. 2008 

$10 

Pressurized Cargo Module Preliminary Design 
Review 

Oct. 2008 

$10 

7 DELETED 

Unpressurized Cargo Module Critical Design 
Review 

No longer 
applicable 

No longer 
applicable 

No longer applicable 

Instrumentation Program and Command List 

Feb. 2009 

$10 

Completion of ISS Phase 1 Safety Review 

Mar. 2009 

$10 

10 

COTS System Preliminary Design Review 

Apr. 2009 

$20 

11 DELETED 

Unpressurized Cargo Module Fabrication 
Started 

No longer 
applicable 

No longer 
applicable 

No longer applicable 

11 

Pressurized Cargo Module Critical Design 
Review 

Jul. 2009 

$10 

12 

Cygnus Avionics Test 

Aug. 2009 

$10 

13 

Completion of ISS Phase 2 Safety Review 

Aug. 2009 

$10 

14 

COTS System Critical Design Review 

Sept. 2009 

$10 

15 

Service Module Core Assembly Completed 

Dec. 2009 

$7.5 

16 

Service Module Test Readiness Review 

Apr. 2010 

$7.5 

17 

Service Module Initial Comprehensive  
Performance Test  

Jul. 2010

a

 N 

11 

(projected) 

$5 

18 

Launch Vehicle Stage 1 Assembly Complete 

Oct. 2010

a

 N 

11 

(projected) 

$2.5 

19 

Cargo Integration Demonstration 

Dec. 2010 

$2.5 

20 

Mission Readiness Review 

Feb. 2011

a

 N 

(projected) 

$2.5 

21 

System Demonstration Flight 

Mar. 2011

a

 N 

(projected) 

$2.5 

 

 

 

Total: 

 

$170 million for 
completion of all 
milestones $157.5 
million paid to date 

Source: NASA and Orbital. 

Page 14 

GAO-11-692T   

background image

 
 
 
 

Note: When Orbital amended its agreement with NASA in March 2009, it deleted milestones 7 and 
11, and moved milestone 4 to become milestone 10. These changes are indicated in this revised 
schedule. 

a

Milestones 17, 18, 20, and 21 were amended in March 2011 to reflect updated milestone 

descriptions and completion dates. In particular, the System Demonstration Flight (milestone 21) is 
now planned for December 2011. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 15 

GAO-11-692T   

background image

 
 
 
 

Table 3: SpaceX’s Progress Completing New COTS Development Milestones 

Milestone 
number  

Milestone description 

Scheduled 
completion 
date 

Completed on 
time (Yes/No) 

Delay if 
applicable 
(months) 

Payment amount 
(millions) 

23 

Modal Test Plan and Setup 

Nov. 2010 

Y

a

 - 

$5 

24 

Modal Test 

Dec. 2010 

$5 

25 

Light Detection and Ranging (LIDAR) 
Test (open loop) 

Dec. 2010 

$5 

26 

Solar Array Deployment and 
Component Thermal Vacuum Tests 

Dec. 2010 

$5 

27 

Light Detection and Ranging (LIDAR) 
Test Plan (closed loop) 

Mar. 2011 

< 1

$5 

28 

Thermal Vacuum System Test Plan 
and Procurement 

Mar. 2011 

< 1

$5 

29 

Overall Infrastructure Plan and Long 
Lead Procurement 

Mar. 2011 

< 2

$10 

30 

Thermal Vacuum System Tests 

Jul. 2011 

$20 

31 

Test Site Infrastructure Implementation Jun. 2011 

$5 

32 

Dragon Trunk Acoustic Test 

Jun. 2011 

$10 

33 

Light Detection and Ranging (LIDAR) 
Test (closed loop) 

Aug. 2011 

$5 

34 

Design Review of Enhanced Powered 
Cargo Accommodations 

Aug. 2011 

$5 

35 

Design Review of Pressurized Cargo 
Volume Increase 

Aug. 2011 

$5 

36 

Full Dragon Electromagnetic 
Interference/Capability Test and 
Second Flight-Like Hardware in the 
Loop Simulator 

Jul. 2011 

$10 

37 

Dragon Cargo Racks and Hatch 
Simulator 

Aug. 2011 

$3 

38 

Ground Demonstration of Enhanced 
Powered Cargo 

Sept. 2011 

$5 

39 

Launch Site Infrastructure 
Implementation 

Sept. 2011 

$5 

40 Production 

Infrastructure 

Implementation 

Sept. 2011 

$5 

 

 

 

 

Total: 

$118 million for the 
completion of all 
milestones 

$40 million paid to 
date 

Source: NASA and SpaceX. 

Page 16 

GAO-11-692T   

background image

 
 
 
 

a

The fifth amendment to SpaceX’s agreement with NASA included Milestone 23 with a due date of 

November 2010. Because NASA did not sign this amendment until December 2010 and SpaceX 
completed the milestone that same month, NASA views this milestone as having been completed on 
time. 

b

SpaceX successfully completed Milestone 27 on April 18, 2011. 

c

SpaceX successfully completed Milestone 28 on April 28, 2011. 

d

SpaceX successfully completed Milestone 29 on May 10, 2011. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 17 

GAO-11-692T   

background image

 
 
 
 

Table 4: Orbital’s Progress Completing New COTS Development Milestones 

Milestone 
number  

Milestone description 

Scheduled 
completion  
date 

Completed on 
time (Yes/No) 

Delay, if 
applicable 
(months) 

Payment 
amount 
(millions) 

22 

Mission Concept Review for Taurus II 
Maiden Test Flight  

Dec. 2010 

$20 

23 

Taurus II Maiden Flight Preliminary 
Mission Analysis 

Feb. 2011 

$10 

24 

Cygnus Mass Simulator Design Review 

Mar. 2011 

$10 

25 

Installation of Additional Processor in the 
Loop Simulators 

Apr. 2011 

< 1

$5 

26 

PROX Flight Equivalent Unit Test Unit 

May 2011 

$5 

27 

Taurus II Maiden Flight Stage 1 Core 
delivered to Wallops Flight Facility (WFF) 

Apr. 2011 

$24 

28 

Taurus II Maiden Flight Upper Stage 
delivered to WFF 

Jun. 2011 

$20 

29 

Taurus II Maiden Flight Cygnus Mass 
Simulator at WFF in preparation for 
integration with Taurus II Maiden Flight 
Launch Vehicle 

Jun. 2011 

$10 

30 

Taurus II Maiden Flight Launch Vehicle 
Stage 1 Assembly Complete 

Jul. 2011 

$10 

31 

Taurus II Maiden Flight 

Oct. 2011 

$4 

 

 

 

 

Total: 

$118 million for 
the completion 
of all milestones

$69 million paid 
to date 

Source: NASA and Orbital 

a

Orbital successfully completed Milestone 25 on May 20, 2011. 

 

 

Page 18 

GAO-11-692T   

background image

 
 
 
 

Appendix II: GAO Contacts and Staff 
Acknowledgments 

For questions about this statement, please contact me at (202) 512-4841 or 
chaplainc@gao.gov. Contact points for our Offices of Congressional 
Relations and Public Affairs may be found on the last page of this 
testimony. 

 
Individuals making key contributions to this statement include Shelby S. 
Oakley, Assistant Director; Jeff Hartnett; Andrew Redd; Megan Porter; 
Laura Greifner; and Alyssa Weir. 

Page 19 

GAO-11-692T   

GAO Contacts 

Staff 
Acknowledgments 

(121001) 

background image

 
 
 

 

This is a work of the U.S. government and is not subject to copyright protection in the 
United States. The published product may be reproduced and distributed in its entirety 
without further permission from GAO. However, because this work may contain 
copyrighted images or other material, permission from the copyright holder may be 
necessary if you wish to reproduce this material separately. 

 

background image

 
 
 
 
 
 
 
 
 
 
 
 
 

 
 
 
 
 

 

 

GAO’s Mission 

The Government Accountability Office, the audit, evaluation, and 
investigative arm of Congress, exists to support Congress in meeting its 
constitutional responsibilities and to help improve the performance and 
accountability of the federal government for the American people. GAO 
examines the use of public funds; evaluates federal programs and policies; 
and provides analyses, recommendations, and other assistance to help 
Congress make informed oversight, policy, and funding decisions. GAO’s 
commitment to good government is reflected in its core values of 
accountability, integrity, and reliability. 

The fastest and easiest way to obtain copies of GAO documents at no cost 
is through GAO’s Web site (

www.gao.gov

). Each weekday afternoon, GAO 

posts on its Web site newly released reports, testimony, and 
correspondence. To have GAO e-mail you a list of newly posted products, 
go to 

www.gao.gov

 and select “E-mail Updates.” 

Obtaining Copies of 
GAO Reports and 
Testimony 

Order by Phone 

The price of each GAO publication reflects GAO’s actual cost of 
production and distribution and depends on the number of pages in the 
publication and whether the publication is printed in color or black and 
white. Pricing and ordering information is posted on GAO’s Web site, 

http://www.gao.gov/ordering.htm

.  

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or  
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card, 
MasterCard, Visa, check, or money order. Call for additional information. 

Contact: 

Web site: 

www.gao.gov/fraudnet/fraudnet.htm 

E-mail: 

fraudnet@gao.gov

 

Automated answering system: (800) 424-5454 or (202) 512-7470 

Ralph Dawn, Managing Director, 

dawnr@gao.gov

, (202) 512-4400 

U.S. Government Accountability Office, 441 G Street NW, Room 7125 
Washington, DC 20548 

To Report Fraud, 
Waste, and Abuse in 
Federal Programs 

Congressional 
Relations 

Chuck Young, Managing Director, 

youngc1@gao.gov

, (202) 512-4800 

U.S. Government Accountability Office, 441 G Street NW, Room 7149  
Washington, DC 20548 

Public Affairs 

 

Ple

as

e Print on Recycled P

a

per

 


Document Outline