background image

 

Board of Governors 

 

GOV

/2006/53

Date: 31 August 2006

Original: English

For official use only 

 

Item 8(c) of the provisional agenda 
(GOV/2006/50) 
 
 

 

Implementation of the NPT Safeguards 

Agreement in the Islamic Republic of Iran 

 

 

Report by the Director General 

 

 

1.

 

On 8 June 2006, the Director General reported on the implementation of the NPT Safeguards 

Agreement in the Islamic Republic of Iran (Iran) (GOV/2006/38). This report covers developments 
since that date. 

2.

 

On 31 July 2006, the United Nations Security Council adopted resolution 1696 (2006), which, 

inter alia, 

•

 

called upon Iran without further delay to take the steps required by the Board of Governors in 
its resolution GOV/2006/14, which are essential to build confidence in the exclusively 
peaceful purpose of its nuclear programme and to resolve outstanding questions; 

•

 

demanded, in this context, that Iran shall suspend all enrichment-related and reprocessing 
activities, including research and development, to be verified by the Agency; 

•

 

underlined the necessity of the Agency continuing its work to clarify all outstanding issues 
relating to Iran’s nuclear programme; 

•

 

called upon Iran to act in accordance with the provisions of the Additional Protocol and to 
implement without delay all transparency measures as the Agency may request in support of 
its ongoing investigations; and 

•

 

requested by 31 August a report from the Director General primarily on whether Iran has 
established full and sustained suspension of all activities mentioned in this resolution, as well 
as on the process of Iranian compliance with all the steps required by the Board and with the 
above provisions of this resolution, to the Board of Governors and in parallel to the Security 
Council for its consideration. 

3.

 

This report is being submitted to the Board and in parallel to the Security Council. 

 

 

 

 

Derestricted 14 September

 2006 

(This document has been derestricted at the meeting of the Board on 14 September 2006)

 

background image

GOV/2006/53 
Page 2 
 

A.

 

Suspension of Enrichment Related Activities 

4.

 

Iran has continued the testing of P-1 centrifuges in the Pilot Fuel Enrichment Plant (PFEP). Since 

6 June 2006, centrifuges in the single machine test stand and in the 10-machine and 20-machine 
cascades have been run mostly under vacuum, but with the feeding of UF

6

 into single machines of the 

20-machine cascade for short periods of time. Between  6 and 8 June 2006,  the  164-machine  cascade 
was also tested with UF

6.

 Further testing of the 164-machine cascade with UF

was carried out 

between 23 June and 8 July 2006. During these tests, a total of approximately 6 kg of UF

6

 was fed into 

the machines and enriched to various levels of U-235. The feeding of UF

6

 into the 164-machine 

cascade was resumed on 24 August 2006. 

5.

 

In June 2006, Iran stated that it had achieved enrichment levels of 5% U-235 in a test run in the 

164-machine cascade. Iran provided measurement results from the on-line mass spectrometer to 
substantiate this statement. The Agency collected environmental samples, the results of which are still 
pending. Iran has refused the Agency access to operating records concerning product and tail assays 
which the Agency requires to complete its auditing activities. However, on 30 August 2006, Iran 
provided the Agency with some information about product assays, which the Agency is currently 
assessing. 

6.

 

The installation of a second 164-machine cascade is proceeding. Iran has informed the Agency 

that it expects to be able to run the cascade under vacuum in September 2006. In August 2006, the 
Agency installed additional cameras to monitor this cascade. The Agency has also proposed the 
implementation of remote monitoring to compensate for the fact that measures normally used for 
verification at operational enrichment facilities (e.g. limited frequency unannounced access) are not 
feasible at PFEP. However, Iran continues to decline to discuss the implementation of remote 
monitoring at PFEP. 

7.

 

On 26 July 2006, design information verification (DIV) was carried out at the Fuel Enrichment 

Plant (FEP) at Natanz, where construction was ongoing. In the course of the inspectors’ visit to Iran 
between 11 and 16 August 2006, Iran declined to provide the Agency with access to carry out DIV at 
FEP, stating that the frequency of DIV activities was, in its view, too high and that the Agency had 
performed 3 DIVs there in 2003, 3 DIVs in 2004, 15 DIVs in 2005 and 12 DIVs as of August 2006. 
Iran also expressed concern about the frequency of DIV at PFEP, the Uranium Conversion Facility 
(UCF) and the Iran Nuclear Research Reactor (IR-40). The Agency explained that DIV was an 
ongoing and continuing process, and that it is carried out during all construction, commissioning, 
operation and subsequent phases of a facility to establish the safeguards measures to be implemented 
and to ensure that there are no undeclared design features which would permit the diversion of nuclear 
material. Between December 2003 and February 2006, the Agency, with the consent of Iran, also took 
advantage of DIV activities to monitor Iran’s suspension of enrichment activities. The Agency 
explained that DIV also enables the Director General to fulfil the reporting requirements set by the 
Board of Governors and the Security Council

Between  26 and 30 August 2006, Iran allowed the 

Agency access to carry out DIV at FEP and at the other facilities mentioned above. 

B.

 

Suspension of Reprocessing Activities 

8.

 

The Agency has been monitoring the use of hot cells at the Tehran Research Reactor and the 

Molybdenum, Iodine and Xenon Radioisotope Production Facility, and the construction of hot cells at 
the IR-40, through inspections, DIV and satellite imagery. There are no indications of ongoing 
reprocessing activities in Iran. 

background image

GOV/2006/53 

Page 3 

 

C.

 

Heavy Water Research Reactor 

9.

 

On 12 July and 30 August 2006, the Agency carried out DIV at the IR-40 reactor at Arak. 

Construction of the facility is continuing. 

D.

 

Outstanding Issues 

10.

 

As indicated in the Director General’s report of April 2006 (GOV/2006/27, para. 6), on 

27 April 2006, the Agency received from Iran a letter in which it was stated that “Iran is fully prepared 
to continue granting the Agency’s inspection in accordance with the Comprehensive Safeguards 
provided that the Iran’s nuclear dossier will remain, in full, in the framework of the Agency and under 
its safeguards, the Islamic Republic of Iran is prepared to resolve the remaining outstanding issues 
reflected in [the Director General’s] report GOV/2006/15 of 27 February 2006, in accordance with the 
international laws and norms. In this regard, Iran will provide a time table within next three weeks.” 
No such timetable has as yet been received. 

D.1.

 

Enrichment Programme 

D.1.1.

 

Contamination 

11.

 

There has been no further progress on the resolution of the contamination issue (GOV/2006/27, 

paras 8–9). As mentioned in the Director General’s last report (GOV/2006/38, para. 4), given the 
difficulty of establishing a definitive conclusion in connection with this long outstanding issue, a full 
understanding of the scope and chronology of Iran’s centrifuge enrichment programme, as well as full 
implementation of the Additional Protocol, are necessary for the Agency to be able to provide credible 
assurances regarding the absence of undeclared nuclear material and activities in Iran. These are also 
essential for clarification of the source of the uranium particle contamination found at the technical 
university, as discussed in paragraph 24 below. 

D.1.2.

 

Acquisition of P-1 and P-2 Centrifuge Technology 

12.

 

The Agency has continued its investigation of the outstanding questions related to Iran’s P-1 and 

P-2 centrifuge programmes (GOV/2006/27, paras 10–14). However, Iran has not made any new 
information available to the Agency. 

13.

 

As indicated in the Director General’s last report, following public statements made by high level 

Iranian officials that Iran was conducting research on new types of centrifuges, the Agency wrote to 
Iran on 24 April 2006 seeking clarification of the scope and content of such research (GOV/2006/38, 
para. 6). On 16 June 2006, the Agency received from Iran a letter stating, inter alia, that Iran was 
studying different types of centrifuge machines, and that this was â€śan ongoing and progressing R&D 
activity without using nuclear materials.” 

D.2.

 

Uranium Metal 

14.

 

The Agency is carrying out investigations on information and documentation which may have 

been provided to Iran by foreign intermediaries (GOV/2006/27, paras 15–16; GOV/2006/38, para. 7). 
To understand the full scope of the offers made by the intermediaries to Iran, it is still necessary for 
the Agency to have a copy of the 15-page document describing the procedures for the reduction of UF

6

 

to uranium metal and the casting and machining of enriched and depleted uranium metal into 
hemispheres (first mentioned in GOV/2005/87, para. 6). Iran continued to decline the Agency’s 
request to have a copy of the document, but had agreed to allow the Agency to review the document, 
to take notes from it and to keep it under seal in Iran. In the course of a visit to Iran 

background image

GOV/2006/53 
Page 4 
 

in mid-August 2006, Agency inspectors continued their examination of the document. However, Iran 
informed the inspectors that the taking of notes would not be permitted, and the notes which had been 
taken thus far by the inspectors during that visit had to be destroyed. The document remains under seal 
in Iran. 

D.3.

 

Plutonium Experiments 

15.

 

The Agency has continued to seek clarification from Iran about its plutonium separation 

experiments (GOV/2006/38, paras 8–9). Since the Director General’s last report, the Agency has been 
able to evaluate the explanations provided by Iran in June and examine the copy of the notebook kept 
by the researcher responsible for the plutonium experiments, and has concluded that they did not 
provide sufficient clarification of the outstanding issues. In an effort to acquire further information 
about the irradiation parameters, the Agency also met, on 11 July 2006, with a reactor operator and the 
researcher, who also did not provide the data necessary to clarify the issues. Iran has stated that no 
other relevant information is available. 

16.

 

In a letter dated 10 August 2006, the Agency informed Iran that, given the information received 

from Iran to date, the Agency would not be able to resolve the outstanding inconsistencies unless 
additional information were made available by Iran. 

17.

 

The depleted uranium targets which had been irradiated in the course of the plutonium 

experiments are stored in containers located at the Karaj Waste Storage Facility (GOV/2005/67, para. 
24). On 8 August 2005, the Agency took environmental samples from one of those containers. The 
results from their analysis, recently finalized by the Agency, indicate the presence of high enriched 
uranium particles. On 15 August 2006, Iran was requested to provide information about the source of 
the contamination and the past use of the containers. 

E.

 

Other Implementation Issues 

E.1.

 

Uranium Conversion 

18.

 

Since the Director General’s last report to the Board, the Agency has completed its assessment of 

the results of the physical inventory verification (PIV) of nuclear material at UCF carried out between 
20 and 24 May 2006 (GOV/2006/38, para. 11). The Agency concluded that the physical inventory as 
declared by Iran was consistent with the results of the PIV, within the measurement uncertainties 
normally associated with similar size conversion plants. 

19.

 

In April 2006, the movement of a 48X UF

6

 cylinder

1

 by the operator into and out of one of the 

withdrawal stations without prior notification to the Agency resulted in a loss of continuity of 
knowledge of nuclear material in the process. However, in light of the results of the PIV, the Agency 
will continue to follow up on this question as a routine part of its verification of the correctness and 
completeness of Iran’s declarations. 

20.

 

On 27 June 2006, Iran provided the Agency with the anticipated operational programme for UCF, 

including details of the new conversion campaign involving approximately 160 tonnes of uranium ore 
concentrate which was begun on 6 June 2006 and is expected to be completed by January 2007. As of 
25 August 2006, approximately 26 tonnes of uranium in the form of UF

6

 had been produced during 

this campaign. All UF

6

 produced at UCF remains under Agency containment and surveillance. In a 

__________________________________________________________________________________ 

1

 A standard 48X cylinder is capable of containing up to 9.5 tonnes of UF

6

background image

GOV/2006/53 

Page 5 

 

letter dated 18 July 2006, Iran informed the Agency of its intention to build at UCF a “standby” 
process line for converting ammonium uranyl carbonate to UO

2

E.2.

 

Other Matters 

21.

 

On 8 July 2006, DIV was carried out at the Fuel Manufacturing Plant (FMP) at Esfahan. Iran 

informed the inspectors that full commissioning of the FMP is scheduled for 2007. The civil 
engineering construction of the facility is approximately 80% completed and equipment is being 
installed. 

22.

 

There are no new developments to report with respect to the other implementation issues referred 

to in the previous report (GOV/2006/38, para. 14; GOV/2006/27, paras 19 and 20). 

23.

 

Between the end of July 2006 and 29 August 2006, Iran declined to provide one-year multiple 

entry visas to designated Agency inspectors as agreed to by Iran in the Subsidiary Arrangements to its 
Safeguards Agreement. On 30 August 2006, Iran provided such visas for two inspectors, and on 
31 August 2006 informed the Agency that “following the normal administration process the multiple 
one year visa for remaining designated inspectors will be issued by 10 September 2006”. 

F.

 

Transparency Measures 

24.

 

Analysis of the environmental samples taken from equipment at a technical university in 

January 2006, referred to in paragraph 25 of GOV/2006/27, showed a small number of particles of 
natural and high enriched uranium. This equipment had been shown to the Agency in connection with 
its investigation into efforts made by the Physics Research Centre (PHRC) to acquire dual use material 
and equipment (GOV/2006/27, paras 24–25). 

25.

 

Iran has not yet responded to the Agency’s requests for clarification concerning, and access to 

carry out environmental sampling of, other equipment and materials related to the PHRC. Nor has Iran 
provided the Agency with access to interview the other former Head of the PHRC. As noted in 
GOV/2006/38, paragraph 17, the clarification and access sought by the Agency have taken on added 
importance in light of the results of the environmental sampling referred to in the previous paragraph. 

26.

 

The Agency has continued to follow up on information concerning studies related to the so-called 

Green Salt Project, to high explosives testing and to the design of a missile re-entry vehicle 
(GOV/2006/27, paras 27–29). However, Iran has not expressed any readiness to discuss these topics 
since the issuance of the Director General’s report in February 2006 (GOV/2006/15, paras 38–39). 

G.

 

Summary 

27.

 

Iran has been providing the Agency with access to nuclear material and facilities, and has 

provided the required reports. Although Iran has provided the Agency with some information 
concerning product assays at PFEP, Iran continues to decline Agency access to certain operating 
records at PFEP. 

28.

 

Iran has not addressed the long outstanding verification issues or provided the necessary 

transparency to remove uncertainties associated with some of its activities. Iran has not suspended its 
enrichment related activities; nor has Iran acted in accordance with the provisions of the Additional 
Protocol. 

29.

 

The Agency will continue to pursue its investigation of all remaining outstanding issues relevant 

to Iran’s nuclear activities. However, the Agency remains unable to make further progress in its efforts 
to verify the correctness and completeness of Iran’s declarations with a view to confirming the 

background image

GOV/2006/53 
Page 6 
 

peaceful nature of Iran’s nuclear programme. The Director General will continue to report as 
appropriate.