Page 1 of 2
Radiogram No. 8975u
Form 24 for 11/05/08
KOMPARUS SYSTEM R&R
GMT
CREW
ACTIVITY
06:00-06:10
CDR, FE-1
Morning Inspection
06:00-06:05
SLEEP - Data Log (FE2)
06:05-06:15
FE-2
Morning Inspection
06:10-06:40 CDR,
FE-1
06:15-06:45 FE-2
Post-sleep
06:40-07:30 CDR,
FE-1
06:45-07:30 FE-2
BREAKFAST
07:30-07:45
Daily Planning Conference
(S-band)
07:45-08:10
Prep for Work
08:10-09:50 CDR,
FE-1
Komparus
А
3 System R&R(
КД
-
МПА
-01 removal).
Tagup with specialists as
necessary (S-band)
08:10-08:15
Connect DCP Power Cable
08:15-09:45
Physical Exercise (RED)
09:45-10:45
FE-2
Physical Exercise (CEVIS)
CDR
Physical Exercise (RED)
09:50-11:20
FE-1
Physical Exercise (TVIS), day 4
10:45-11:10
Restart JEU and EXT2 power
11:10-11:20
FE-2
PTU ELBOW activation and configuration for inspection
11:20-13:00 CDR,
FE-1
Komparus
А
3 System R&R (Remove boxes
ТА
601
БКЗ
-1,
ТА
601
БКЗ
-2,
КС
1-
МПА
-01).
Tagup with specialists as necessary (S-band)
11:20-12:20
Hardware Pre-pack for Return on Shuttle Flight ULF2
12:40-12:45
Cupola RWS PCS Power Up
12:45-13:05
FE-2
Starting DOUG software to support SSRMS ops
13:00-13:05 FE-1
On MCC Go
ISS O2 repress from Progress 365
СрПК
(start) /
13:05-14:05
LUNCH
14:05-14:10
FE-1
ISS O2 repress from Progress 365
СрПК
(terminate)
14:05-14:35
CDR, FE-2
SSRMS External Stowage Platform 3 (ESP-3) Grapple
14:10-16:10 FE-1
Removal of Komparus A3 units (de-mate connectors from
КР
-
МПА
and
КД
-
МПА
)
Tagup with specialists as necessary (S-band)
14:35-15:05
Demating Umbilical Mechanism Assembly (UMA) and Deploying Capture Latch
Assembly (CLA)
15:05-17:05
CDR, FE-2
SSRMS Grappling LAB PDGF
16:10-16:40
Cleaning LIV TVS Voltage Converter Ventilation Grille
16:40-17:15
FE-1
Elektron Purge / r/g
17:05-18:05 CDR
Physical Exercise (CEVIS)
17:05-17:10
PCS power down
17:10-17:50
FE-2
СОЖ
Maintenance.
Verify
ИП
-1 sensor installation
17:15-18:15
FE-1
Physical Exercise (VELO+RED), Day 4
17:55-18:55
FE-2
Evening Work Prep
18:15-18:30 FE-1
Replacement
of
ИК
0501 CO2 filter unit
(Install #031
ш
/
к
008546R,
Page 2 of 2
СМ
1
РО
_4_449_1 bag #363-25. Discard the removed unit. Update IMS.)
18:15-19:15 CDR
18:30-19:15 FE-1
Evening Work Prep
18:55-19:05
PTU ELBOW reconfig for stowage and deactivation
19:05-19:15
FE-2
JEMRMS Deactivation Prep
19:15-19:30
Daily Planning Conference
(S-band)
19:30-20:30 FE-2
19:30-21:30 CDR,
FE-1
Presleep (Dinner, Daily Food Prep, Evening Toilet)
20:30-21:00 Crew
conference
21:00-21:25
Presleep (Dinner, Daily Food Prep, Evening Toilet)
21:25-21:30
FE-2
Log entry reminder
21:30-06:00
SLEEP
Task List
FE-1
IMS Update
Notes:
1. SM Window #9 shutter opening is at crew discretion with
Report to MCC
2. See OSTP for references to US activities.
End of Radiogram