background image

 INVESTIGATION 

 

REPORT 1/06 

 1 

Nuclear Reactor Regulation 

Translation 1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

MANAGEMENT OF SAFETY REQUIREMENTS IN SUBCONTRACTING DURING THE 
OLKILUOTO 3 NUCLEAR POWER PLANT CONSTRUCTION PHASE 

CONTENTS 
 

1. BACKGROUND AND OBJECTIVES OF INVESTIGATION ............................................................................... 2 

2. PERFORMANCE DEMONSTRATING GOOD SAFETY CULTURE................................................................... 2 

2.1  Indicators of good safety culture ................................................................................................................. 2 

2.2  Safety culture in the construction of a nuclear power plant ........................................................................ 3 

3. CASE STUDIES ....................................................................................................................................................... 6 

3.1 Concrete base slab........................................................................................................................................ 6 

3.1.1 Background information on base slab............................................................................................ 6 

3.1.2  Work practices generally followed in construction....................................................................... 8 

3.1.3  Division of work and operation at Olkiluoto .............................................................................. 10 

3.1.4   Summary of problems that disturbed the concreting of base slab.............................................. 22 

3.1.5  Investigation team's assessment of the acceptability of the concrete slab................................... 26 

3.2  Containment steel liner.............................................................................................................................. 28 

3.2.1  Background information on containment.................................................................................... 28 

3.2.2 Manufacturing of steel liner......................................................................................................... 28 

3.2.3  Observations made in the manufacturing of steel liner ............................................................... 31 

3.3  Polar crane and material hatch .................................................................................................................. 36 

3.3.1  Background information on polar crane and material hatch ....................................................... 36 

3.3.2  Observations in connection to acquisition of polar crane and material hatch ............................. 38 

4. MANAGEMENT OF THE OL3 CONSTRUCTION PROJECT AND QUALITY MANAGEMENT.................. 40 

4.1 Management systems ................................................................................................................................. 40 

4.1.1 TVO’s management system and cooperation with FANP ........................................................... 40 

4.1.2 CFS management system ............................................................................................................. 42 

4.2 Assessment of management and quality management ............................................................................... 44 

4.2.1 General observations.................................................................................................................... 44 

4.2.2 Observations concerning TVO..................................................................................................... 47 

4.2.3 Observations concerning FANP................................................................................................... 51 

5. STUK'S OPERATION AS REGULATOR OF NUCLEAR POWER PLANT  CONSTRUCTION...................... 55 

5.1 Oversight system and implementation ....................................................................................................... 55 

5.2 Observations on STUK's activities............................................................................................................. 55 

6. RECOMMENDATIONS TO FANP, TVO AND STUK ........................................................................................ 57 

7. REFERENCES........................................................................................................................................................ 61 

8. APPENDICES......................................................................................................................................................... 62 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 2 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

3.

 

1. 

BACKGROUND AND OBJECTIVES OF INVESTIGATION 

 
The Radiation and Nuclear Safety Authority (STUK) concluded in connection with the 
construction of the Olkiluoto 3 nuclear power plant that the performance of the 
organisations involved in the project and the interaction between the organisations did 
not in all respects meet the expectations that STUK has on good safety culture during 
the construction phase of a power plant. The identified problems had already impeded 
progress of the project and possibly increased schedule-related pressures during the 
later stages of the project.  
 
STUK considers important that problems during construction and manufacturing will 
not result in impaired quality of the final products, or even in uncertainty about the 
achieved quality. For this reason, the performance of the organisations involved in the 
construction of the Olkiluoto 3 nuclear power plant unit should be improved. In order to 
identify the needs for improvement, STUK appointed an investigation team and asked 
the team to present an assessment of the performance of the organisations in the light of 
certain case studies that were selected as examples. In addition, STUK asked the 
investigation team to present recommendations for improving the performance of the 
licensee Teollisuuden Voima Oy (TVO), and the vendor consortium CFS, formed by 
Framatome ANP (FANP, currently Areva NP) and Siemens AG. Within the project, 
Framatome is responsible for the reactor island and Siemens for the turbine island. As 
the construction project proceeds, STUK will assess how these recommendations have 
been materialized in the operations of the parties.  
 
The investigation team also analysed the needs for development in STUK's own 
operations and issued recommendations for this purpose. 
 
The task given to the investigation team is shown in Appendix 1, and the composition 
of the team in Appendix 2. The investigation entailed interviews of persons in different 
capacities in organizations (TVO, CFS, FANP, subcontractor, research institute) that 
have taken part in the Olkiluoto 3 project, as well as a visit to the Olkiluoto 3 
construction site and the concrete batching plant. The investigation programme is 
shown in Appendix 3. Appendix 4 contains a description of STUK’s activities as the 
regulatory organisation for the nuclear power plant construction project. 
 

2.

 

PERFORMANCE DEMONSTRATING GOOD SAFETY CULTURE  

 

2.1  Indicators of good safety culture  

In safety-critical fields the organisations are expected to possess an ability also to 
manage situations that are difficult to predict. The characteristics of organisations 
operating with high reliability include a serious attitude towards even small errors, an 
overall assessment of situations, emphasis on professional competence over 
organisational status, and avoiding over-simplification in the analysis of important 
issues [1].  
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 3 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

Within the field of nuclear power, an assessment of the performance of organisations 
focuses on attitudes toward safety, and how safety is ensured. Each organisation has its 
own perception of the importance of striving to ensure safety, and how safety can be 
achieved. These perceptions are usually unconscious and commonly shared, and they 
influence practical operations. For this reason they can be referred to as the safety 
culture. 
 
The conditions in the Construction Licence, the YVL Guide 1.4 [2], as well as the OL3 
project plan prepared by TVO require a high-level safety culture in the design, 
construction and operation of the nuclear power plant. In discussions on safety culture 
within the nuclear power field, reference is usually made to IAEA's guidance that, since 
the Chernobyl accident, has emphasised the safety significance of organisational 
factors. IAEA has defined safety culture in the INSAG-4 report [3] as follows: 

"Safety 

culture is that assembly of characteristics and attitudes in organisations and 
individuals which establishes that, as an overriding priority, nuclear plant safety issues 
receive the attention warranted by their significance."

 

 
When assessing whether the safety culture of an organisation is "good" or "bad", 
attention is in practice paid at least to the following issues (INSAG-15) [4]: 
-

 

Visible management commitment to safety. 

-

 

Conservative decision-making, i.e. the safer alternative is chosen in uncertain 
situations. 

-

 

Compliance with specifications and regulations. 

-

 

Reporting of nonconformancies and the aim to learn from them.  

-

 

Questioning of performance that jeopardise safety.  

 
The indicators of good safety culture can be analysed when assessing both the operation 
of a nuclear power plant and the performance of subcontractors involved in the 
construction project. The important thing is the attitude towards safety and how it is 
shown in practice.  
 
IAEA has suggested that there can be different levels of safety culture [5]. In the most 
advanced safety cultures each member of the organisation is considered able to 
influence safety. The attitudes and the behaviour of the staff are influenced through e.g. 
training, communication and leadership. In advanced safety cultures safety is not 
emphasised merely for reasons of publicity and external pressures. 

 

2.2  Safety culture in the construction of a nuclear power plant 

The technical and organisational preconditions for the safe operation of a nuclear power 
plant are created during the construction phase of the plant.  
 
A basic principle established and proven in the nuclear power industry is “defence in 
depth principle” meaning in-depth assurance of safety. The first layer of this principle 
is to ensure undisturbed normal operation of the plant. This presupposes that the 
reliability and high quality of equipment is ensured for the safety-classified systems as 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 4 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

well as for the entire process of power production. Good safety culture is characterised 
by that work practices at the site are in every respect carefull and consistent, and 
without distinction between activities on structures or equipment that are important to 
safety or classified non-nuclear. In addition to this, the quality and reliability of safety-
classified equipment is ensured through additional requirements according to the 
relevant safety class. The special requirements for such equipment are taken into 
consideration e.g. in the dimensioning of structures, the properties of materials, type 
tests and the quality control programme.  
 
It should be borne in mind that the culture and the work practices for the future 
operation of the plant are at least partly created during the construction stage. In other 
words, the construction of the plant and the manufacture of the components for the 
plant represent activities that are equally critical to safety as the operation of the plant.  
 
Efficient and reliable operation of individuals and organisations is of crucial importance 
in the assurance of safety. The professional competence and the vigilance of 
individuals, as well as the ability of organisations to openly deal with matters may 
reveal and prevent e.g. deficiencies in design or uncertainty factors involved in 
manufacturing. On the other hand, incompetence and hiding of errors made in the 
manufacturing process may impair quality in a way that is not easy to detect in the final 
product.  
 
The organisation that bears total responsibility for the construction of the nuclear power 
plant is obliged to ensure that every organisation and individual involved in the 
construction process recognises the quality expectations that apply to their work. It is 
unrealistic to expect that all the persons working at the construction site or in the 
manufacturing of components understand without explanation the significance of their 
own work as a part in ensuring nuclear safety. For this reason training shall be provided 
for them on the safety significance of their work and the expectations that apply to 
quality.  
 
In construction and manufacturing industry, the safety culture is usually considered to 
be connected with occupational safety. In the construction of a nuclear power plant, it is 
important that the wider significance of safety and the respective implications for work 
practices are recognised. Regardless of their tasks, every employee should be aware of 
the properties of the final product that are particularly important in terms of safety. It is 
also important that factors relevant to safety in each specific work object are brought 
out and explained before work is started. An overall understanding of the principles 
followed to ensure safety of a nuclear power plant, and of the work practices adopted in 
the nuclear field also help in perceiving the expectations that apply to one's own work.  
 
When building up a safety culture, the basic values familiar to professional workers 
have to be emphasised in the training and guidance for the employees: responsibility for 
faultless performance of one's own work and professional pride on the skills required to 
achieve high quality. In addition, everybody should assume responsibility for necessary 
interaction with others involved in the project, to ensure everyone can succeed in his 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 5 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

own work. It is also important that the principle of openness is made clear to ensure that 
any non-conformancies detected in construction or manufacturing are brought up, and 
to emphasise the right and duty of everybody involved in the project to react to 
non-conformancies. In unclear and unpredicted situations the employees must 
comprehend the need to discontinue their work and to eliminate the problems before 
resuming work. The general objectives that apply to the construction of a nuclear power 
plant are very similar to those during the operation of the plant: the objective is that the 
performance of work is designed, implemented and documented as well as possible, 
and that indifferent attitudes towards problems or to the quality of the final product are 
not tolerated. 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 6 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

3.

 

CASE STUDIES 

 
The investigation team assessed the performance of TVO, the plant vendor and STUK 
in the light of three case studies selected as examples. The investigation report refers 
generally to the performance of the consortium (CFS) that supplies the plant, but also to 
the performance of FANP in cases where the investigation team could distinguish 
which consortium partner was concerned. The example cases are the concreting of the 
base slab, the manufacturing of the steel liner for the reactor inner containment, and the 
selection of manufacturer as well as the start of the design process for the polar crane 
and the material hatch in the containment. The background and the sequence of events 
in these three cases are described below. 
 

3.1 Concrete base slab 

3.1.1 Background information on base slab 

Parties to the contract responsible for concrete fabrication 

The parties to the contract were the plant builder (Framatome ANP, FANP), the 
structural designer of the base slab (Finnprima), the concrete supplier (Forssan Betoni 
Oy) and the contractor that performed the concreting work (Hartela Oy). 
 

Requirements for and construction of base slab 

The reactor building, the safeguard buildings and the fuel building share a common 
base slab.  
 
The design requirements used in the dimensioning of the base slab have been defined 
by FANP as part of the containment design. The essential safety requirement is that the 
slab must withstand not only the expected loads, but also dynamic loads (impacts, 
vibration) in conjunction to potential accidents, as well as an internal over-pressure in 
the containment. In other words, the design bases of the slab include loads during the 
construction stage, loads during plant operation, loads caused by internal accidents or 
external collisions against the plant, as well as earthquakes. Security against collapsing 
of the entire construction based on the slab as a result of earthquake or collision loads 
has also been required. The design requirements have been approved by STUK as part 
of the pre-inspection documentation of the containment.  
 
IAEA's safety standard 50-C-QA [6] concerning quality assurance presupposes that a 
graded approach during the different phases of the nuclear power plant's life cycle is 
used in the definition of requirement levels for functions in the quality management 
system of the plant. The level of and the need for quality assurance and control during 
construction is determined on the basis of the object's nuclear safety classification and 
structural classification based on the building regulations. 
 
The nuclear safety classification of the base slab is SC3 in the parts under the safeguard 
buildings and the fuel building, and SC2 in the reactor building. However, pursuant to 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 7 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

the proposal of TVO, and approved by STUK, the entire concreting and reinforcement 
work for the base slab have been carried out and inspected applying the same SC2 
requirements to the whole base slab, in compliance with YVL Guide 4.1 [7]. 
 
According to the Finnish Building Code Part B4, Concrete Structures, the base slab is 
assigned to structural class 1. Structures and structural parts may be assigned to a 
certain class, provided the design and work specifications of that class are complied 
with. The structural designer and the concrete work supervisor shall possess the 
qualifications for the class in question. Structures and structural parts, whose design is 
considered to require special qualifications or with which the assurance of structural 
functionality requires special care, are implemented in structural class 1. 
 
The base slab is 103.1 m wide and 100.8 m long. The thickness of the slab under the 
reactor building is 3.15 m and under the safeguard buildings 1.5 m. The slab is over its 
entire area supported on rock (design strength 140 MPa). A ca. 1.5 m thick levelling 
concrete is first cast on the excavated rock structure (strength class C32/40 according to 
Eurocode 2, K40 according to the Finnish Building Code Part B4). The levelling 
concrete and the slab are not anchored to the rock. The strength class of the base slab 
concrete is K40-1 (compressive strength 40 MPa, structural class 1), the reinforcement 
consists of ribbed bars A500 HW (yield strength, 500 MPa). The design life is 65 years 
and the exposure classes are XC2, XS1 and XA1 according to EN 206-1, i.e. resistance 
to chemical exposure caused by carbonation, chlorides and sulphates. 
 

Structural design of base slab 

Finnprima Oy carried out the detailed design of the structures in compliance with the 
requirements of Part B4 of the Finnish Building Code (RakMK) and the Eurocode 2, 
prEN 1992-1-1, April 2003, which applies to design of concrete structures. The 
fulfilment of the design requirements for the base slab has been verified on the basis of 
structural calculations reported by Finnprima and reviewed by STUK. The structural 
calculations are based on linear FE structural analyses (compying with the theory of 
elasticity). STUK also required that the design calculations shall be verified by means 
of non-linear FE analyses (that take into consideration cracks in the structures and 
plasticizing of materials). 
 

Special features of base slab in comparison with common concreting projects 

The base slab differs from common concrete structures by its massiveness and large 
size. Moreover, concreting had to be completed without breaks, as casting joints were 
not allowed in the base slab of the reactor building. Continuous concreting of structures 
of this size is extremely rare in Finland. 
 
In massive concrete structures, temperatures tend to rise considerably during the curing 
process due to hydratation heat, and temperature gradients are usually high. The high 
temperature gradient in the concrete may cause cracks in the curing structure, and a 
high temperature may result in loss of strength in the concrete. Due to the cracking risk 
caused by the high temperature gradient and the loss of strength caused by high 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 8 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

temperature, measures are usually taken with massive concrete structures to restrict the  
temperature rise. In order to limit the increase in temperature, the binder used in the 
base slab concrete contains an abundance of furnace slag instead of Portland cement, 
since the heat production rate of furnace slag during curing is considerably slower. 
Abundant use of furnace slag also improves the chemical resistance of concrete. 
 
The concrete composition used in the base slab is not used in conventional construction 
work, and in that sense it is rare. Similar mixes are mainly used only in massive 
structures. The type of concrete used in the base slab cannot be considered to pose any 
special difficulties in fabrication or concreting, provided the concrete mix has been 
validated with sufficient preliminary tests. 
 

3.1.2  Work practices generally followed in construction  

Designing concrete composition  

The common practice followed in concrete construction is that the structural designer 
specifies the requirements for cured concrete. Normal requirements specified by 
structural designers include strength (here K40-1) and durability (here XC2, XS1 and 
XA1). The requirements have an effect e.g. to the amount of binder (cement and 
furnace slag) and to the water-binder ratio of the concrete. The water-binder ratio 
affects the strength and the durability properties of concrete.  
 
Requirements on fresh concrete are normally not specified by the structural designer 
but by the concreting contractors - in this case Hartela Oy. In some special projects the 
structural designer may define additional requirements for concreting. A typical 
example is that he defines the maximum temperature that the structure may not exceed 
during the curing of the concrete (e.g. 55ÂşC). Most Finnish structural designers do not 
possess enough practical expertise in concrete material technology to make them 
qualified to design the final composition. 
 
The builder (or the concreting contractor) usually always orders the concrete on the 
basis of the specified requirements, with the concrete supplied directly into the 
formwork. The supplier of the concrete is responsible for the compliance of the 
concrete with the requirements specified by the structural designer and with the 
requirements that concern the manufacture (concreting) of the structure, specified by 
the builder. Such requirements apply to the pumpability, compactibility, consistency, 
setting time, and the rate of strength development, among others. 
 
The final concrete mix is usually designed by the concrete supplier, as they know their 
own materials (particularly the aggregate) and have the laboratory facilities for 
performance of tests to support the design process. The final mix is always influenced 
not only by the requirements specified by the structural designer, but also by 
requirements that concern placeability. In order to enable casting and compacting of the 
concrete, it must be easily workable, it may not become segregated, and it must be 
pumpable as required. Detailed mix design requires knowledge of the aggregate to be 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 9 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

used, and the additives (e.g. plasticizers and retarders) that need to be used if required 
to ensure the desired workability properties.  
 
If the water-cement ratio is relatively low, plasticizers are used to ensure good 
pumpability and workability of concrete. Plasticizers reduce friction between the 
ingredients of fresh concrete during casting. Plasticizers do not affect the properties of 
cured concrete. The amount of plasticizer must be exactly correct to provide the desired 
effect. The plasticizers of different manufacturers give the desired effect with different 
mixing ratios and, therefore, preliminary tests must be separately carried out for the 
plasticizer that will be used. 
 
Plasticizers can, however, be used for affecting pumpability to a limited degree only, 
and the effect of too low water-binder ratio cannot be compensated by merely adding 
plasticizer. In addition, aggregate has a significant effect on pumpability. Crushed 
aggregate is worse from the point of pumpability than natural aggregate.   
 
In demanding construction projects the correctness of the concrete mix has to be 
validated by preliminary tests. The mix proportion is changed and fine-tuned as 
required on the basis of the test results. If changes are made, the preliminary tests have 
to be repeated. The more the composition differs from conventionally used mixes, the 
more work and preliminary tests are required to determine the mix proportion. The 
determination of the final concrete composition is always an "iteration" process.  
 
Pumpability test is usually conducted last. By then other tests have already been 
performed to verify that the properties of the concrete meet the requirements. If 
pumping problems are encountered, the mix proportion is changed and tests are 
repeated. 
 
If preliminary tests show that the concrete meeting the requirements cannot be 
fabricated and poured within the restrictions that concern the concrete mix, the concrete 
supplier shall contact the structural designer. The structural designer and the concrete 
supplier then together agree on the changes required in the restrictions that concern the 
mix proportion.  
 

Quality control for concrete  

The quality control tests to be performed during fabrication, as well as their total 
number and documentation, are defined in the quality control plan. When the quality 
control plan is drawn up the complexity of the concreting process, the size of the 
concreted area as well as the conditions need to be taken into consideration. During 
concreting, tests are made on fresh concrete according to the quality control plan, both 
at the batching plant and on the concreting site. In addition, test specimens are cast for 
the tests of the properties of the hardened concrete.  
 
The quality of the concrete in a completed (hardened) structure can always be analysed 
by means of samples taken of the structure. The required number of core samples is 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 10 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

drilled   from the structure at desired points. The core samples are used to produce test 
specimens for tests of desired properties. The specimens are usually tested in 
compliance with standards. If no applicable standard is available, other commonly used 
testing methods are employed. The properties that can be determined include e.g. 
compressive strength and porosity of concrete. 
 
The internal structure of concrete can be studied by making thin sections of the drilled 
samples, and subjecting them to a microscopic analysis. 

 

3.1.3  Division of work and operation at Olkiluoto 

Selection of concrete supplier and base slab concreting contractor, and concrete delivery 

agreement 

The consortium started the process for the selection of concrete supplier in the autumn 
of 2004. The person responsible for the matter was an employee of the consortium, who 
at the time worked in Germany and later acted on the site as FANP's supervisor of the 
batching plant. The call for tenders was sent to four potential concrete suppliers named 
in the Main Contract. According to the information received in the interviews, the call 
for tenders contained the technical specifications and the YVL Guide 4.1 [7] was 
appended. No other requirements were specified in the call for tenders in terms of 
requirements concerning quality control in a nuclear power plant construction project 
(e.g. the requirement for a laboratory) or any other special requirements, such as 
reference to IAEA's safety standard IAEA 50-C-QA. 
 
The consortium FANP-Siemens (CFS) selected Forssan Betoni from the four potential 
concrete suppliers apparently on price grounds, although the small size of the company 
was considered a risk. However, Forssan Betoni had taken part in some large-scale 
construction projects before, such as bridges and power plants, and according to CFS 
the company fulfilled the criteria defined for the selection.  
 
At the time the agreement was concluded, Forssan Betoni was not required to have a 
valid certified ISO 9001 quality system, although most of the other candidates were 
already at the time using an ISO 9000-based quality system. In connection with the 
signing of the agreement, the requirement for a quality system to be realised later was 
specified. Forssan Betoni declared that they were working on their ISO 9001:2000 
certification, and that the certificate would be applied for during the concrete deliveries. 
According to the consortium's interpretation the fact that the company was being 
inspected by an organisation (SFS-Inspecta) approved by the Finnish Ministry of the 
Environment, as referred to in Annex 1 of YVL Guide 4.1, was a sufficient validation 
for quality. TVO made no complaints  on the selected supplier.  
 
No training related to safety culture was provided to the personnel of Forssan Betoni 
before the concreting of the base slab. All the parties (FANP, TVO, Forssan Betoni) 
considered the site introduction training and the occupational safety training included in 
it, which is required for the granting of an access permit, to be sufficient.  

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 11 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

 
According to information received from a representative of Forssan Betoni, the 
concrete delivery agreement contained the requirement that the order for concrete 
would in each situation be sent to the batching plant two weeks before the concreting 
was to be started, regardless of the size of the concreting area. For large concreting 
jobs, the placing of an order two weeks in advance can be justified, but for smaller 
concreting jobs the requirement that FANP specified for itself is unusual. Another 
unusual aspect of the agreement was that no responsibility for the pumpability or 
castability of the concrete was defined for the concrete supplier. The responsibility for 
the pumping and casting into the formwork rested completely with the builder (FANP) 
and the contractor it had assigned to carry out the concreting work. These factors 
suggest that the persons who concluded the agreement are not very familiar with the 
practical aspects of construction projects. 
 
Hartela was chosen by FANP as the concreting contractor from among several 
candidates. The selection was strongly influenced by TVO's request to employ Finnish 
contractors on the site. 
 
According to TVO's representatives the Main Contract specifies that the responsibility 
for the batching plant, the composition of concrete and the concreting work rests solely 
with FANP, and TVO merely supervises work in its capacity as the orderer and 
licensee. 
 

Batching plants 

Forssan Betoni set up three batching plants for concrete deliveries. Batching plants 
Olkiluoto 1 and 2 are located in immediate vicinity of the power plant construction site, 
and batching plant no. 3 in the area of Interrock. The Olkiluoto 1 and 2 are new plants, 
and plant no. 3 was built in 1999. Concrete for the water tunnels and the harbour, where 
TVO acted as the builder and Lemcon as the contractor before the construction site was 
handed over of the consortium, was delivered from batching plant no. 3. 
 
On 17.92004 SFS-Inspecta Sertifiointi Oy conducted an intial inspection at the batching 
plant in the Interrock area and approved it into their inspection programme on 
30.9.2004. SFS-Inspecta Sertifiointi Oy conducted on 15.3.2005 an initial inspection at 
the new batching plants no. 1 and 2 and approved them into their inspection programme 
on 16.3 2005. After the initial approval, SFS Inspecta controls the quality of the plants 
by making inspections at the plants a few times every year. 
 
TVO conducted several inspections at batching plants no. 1 and 2 before the concreting 
of the base slab. At that time, production at the plants had not yet been started. TVO 
was represented in the inspections by the supervisor of concrete fabrication and a 
representative of quality control. The inspections were based on check lists that listed 
the issues covered in the inspection. Some minor deficiencies and remarks were 
recorded in the inspection reports.  
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 12 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

When TVO inspected batching plant no. 1 (29.-30.3.2005) and batching plant no. 2 
(11.4.2005), the plant facilities had not yet been finalised, but the deficiencies were not 
considered to be so significant that fabrication of concrete could not be started. The 
laboratory and the storage facilities for materials and test specimens were still in the 
Interrock area. It was noted that there was no camera controlling of the fabrication 
process. Water supply had not been connected and the foundation on the buffer water 
tank had not been built. As far as quality control was concerned, the quality manual and 
the graphic presentation of quality control measurementswere noted to be missing. 
TVO sent the inspection reports to FANP by a cover letter on 19.4.2005 for further 
actions.  
 
TVO had already before made inspections at batching plant no. 3, which is located in 
the Interrock area. In a follow-up inspection conducted in December 2004, the 
acceptance of cement was found to deviate from the requirements of Finnish Building 
Code of Concrete Structures B4 (RakMK B4, By50). The batching plant operating 
records were still under development at the time of the inspection. It was noted in the 
inspection that the graphic presentation of the quality control measurements as well as 
vibration limit measurement equipment earlier required by TVO were missing from the 
plant (the code RakMK B4 does not separately require the measurement of vibration 
limit). In a repeated inspection on 20.1.2005, TVO concluded that these deficiencies 
had been eliminated and there were no obstacles with respect to the concrete batching 
plant to the manufacturing of safety class 3 concrete structures for the inlet and outlet of 
the seawater tunnels. 
 
TVO and FANP audited the main office of Forssan Betoni on 4.5.2005. Three critical 
non-conformancies were found in the performance of Forssan Betoni, which together 
with four minor non-conformancies prove that at the time of the audit the quality 
system of the company and compliance of operation with the quality system were partly 
still at design stage. A quality management system compliant with ISO 9001 was under 
construction, and according to plans was to be certified within a few months. 
Deficiencies detected in the recording of documents as well as deficiencies in the 
definition of interfaces between Forssan Betoni, the client and the design organisation, 
were also defined as critical non-conformancies. The recording of documents received 
by Forssan Betoni or submitted by Forssan Betoni to the client or to the subcontractors, 
was not included in the document processing routine. Due to deficiencies in the 
definition of the interfaces Forssan Betoni was using a concrete specification that had 
not been officially approved by FANP.  
 
The minor non-conformancies detected in the audit included the lack of an official 
reporting practice related to quality issues between the OL3 batching plant and the head 
office of Forssan Betoni in Forssa. Deficiencies were also found in the documentation 
of the examination and approval of the results of tests performed by Forssan Betoni. 
The quality system of Forssan Betoni did not describe in detail the procedures 
regarding the traceability of concrete. The availability of quality records was not 
verified and the requirements of IAEA's quality standards were not taken into 
consideration in the quality management system.  

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 13 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

 
Forssan Betoni did not obtain the ISO9001 certificates until after the concreting of the 
base slab on 14.2.2006. The Olkiluoto 1 and 2 batching plants have valid NQA 
certificate no. 20620/7 and batching plant 3 (in Interrock area) NQA certificate no. 
20620/6. 

 

Design of concrete composition, and preliminary tests 

The mix of the base slab concrete was designed by a concrete specialist (expert A) 
employed by Finnprima and with experience on massive concrete structures. In 
addition to the normal strength and durablity requirements he, thus, also specified the 
maximum amounts of binders in order to restrict the generation of heat. The design of 
the base plate concrete composition was based on the technical and quality 
requirements specified for the concrete, including e.g. compressive strength and 
exposure class (durability) requirements. The designer specified the binder amounts 
that fulfilled the exposure class requirements (cement 80 

kg/m

3

, furnace slag 

240 kg/m

3

) and the water-binder ratio (0.45). The designer also specified the maximum 

amount of binder (320 kg/m

3

). This was specified due to the massiveness of the 

structure, where temperatures during curing need to be restricted to restrict thermal 
stresses that result in a cracking risk. Forssan Betoni also ensured through their 
examinations that heat generation would not be too great. The water-binder ratio of the 
concrete was determined taking into account the influence of the ratio on the strength 
and the durability properties of concrete. If the designed water-binder ratio is exceeded, 
in other words more water is used than specified, the strength and the durability 
properties of concrete are impaired.  
 
Expert A did not determine the detailed final composition of the concrete, nor had 
FANP ordered it from Finnprima. For instance, expert A could not take pumpability 
into consideration, as he did not know the aggregates or the pumping lengths. Expert A 
stated in the interviews that his design was not intended as the final composition of the 
concrete, he merely gave on the basis of the technical and quality requirements the 
conditions (specifications) that the final composition should fulfill. The responsibility 
for the detailed design of the concrete composition was left to the concrete supplier. 
 
According to the Project Manager responsible for the operation of the batching plant of 
Forssan Betoni (hereinafter the batching plant manager), expert A determined the mix 
composition of the concrete in terms of the binders "to the kilogram". In his opinion 
Forssan Betoni had in practice no possibility at all to influence the composition of the 
concrete. In the interview the batching plant manager, however, questioned the 
requirements (primarily those concerning durability) set by expert A on the base slab 
and, based on this, he also questioned the whole design. In his opinion the specified 
mix proportions made it impossible to reach good pumpability due to the very strictly 
set limits.   
 
Expert A admitted in the interview that the water-binder ratio defined by him at 0.45 
results with the restricted amount of binder to such a small amount of water in the 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 14 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

concrete that without a good plasticizer it would be impossible to achieve good 
workability for the concrete. According to him the workability and pumpability of the 
concrete could have been improved by increasing the amount of both binder and water. 
According to Forssan Betoni, however, both expert A and FANP specifically denied 
this procedure in several instances. The batching plant manager told in the interview 
that he had noticed problems in the workability of the concrete, and had for this reason 
contacted expert A, who had said that the plasticizer should be changed. 
 
Forssan Betoni drew up the preliminary test programme and performed the preliminary 
tests. The preliminary test programme and the test results were approved by FANP on 
25.05.2005 and by TVO on 17.06.2005. In the conclusions of the test result report, 
Forssan Betoni has drawn attention to the fact that if the amount of binder is reduced 
and the water-binder ratio kept unchanged (0.45), this may result in extremely dry 
composition, which will make the concrete very difficult to place and impossible to 
pump. The representative of Forssan Betoni told the investigating group that they also 
proposed pumpability tests to be arranged but here was no reply to their proposal. 
 
According to Forssan Betoni, they did not have the permission to be in direct contact 
with the designer but to deliver all information via FANP.  
 
The test programme and the test results were submitted to STUK for information. 
STUK does not issue a separate approval for concrete. STUK approves the start of 
concreting in connection with the inspection of readiness for concreting and, according 
to the YVL Guide 4.1, the approved composition of concrete may not be changed 
during concreting. 
 
As concerns the mix composition of the base slab concrete, TVO asked FANP for 
preliminary results of the tests performed on the concrete, for the results of fresh 
concrete and for the test results obtained with the new plasticizer. Between June and 
September TVO reminded the consortium in writing several times of the YVL Guides 
and of STUK's involvement in the approval of concrete. The comments made by TVO 
concerned e.g. workability and castability. TVO reminded also the fact that if the 
composition of the approved concrete is changed, the preliminary tests have to be 
performed again and the results submitted to STUK for information before the 
inspection of readiness for concreting is performed. 
 
According to the information that has been received, no external parties were present in 
the preliminary tests. External supervision is not a common practice in general. 
According to expert B, who was hired by FANP and represented the Polytechnic of 
Kymenlaakso (KyAMK), the amount of water in the preliminary tests performed due to 
the change of the plasticizer was larger than the amount of water in the designed 
composition of the concrete. This opinion is based on the comparison of compressive 
strength results from tests performed by KyAMK and Forssan Betoni. In the 
compressive strength analyses performed by KyAMK the obtained strengths have 
corresponded to the results obtained from the test specimens produced by Forssan 
Betoni. The test specimens of KyAMK were produced at the batching plant during the 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 15 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

concreting of the base slab using premixed fresh concrete, and their water content was 
higher than in the designed and approved composition. Expert B determined the 
amounts of water in these test specimens on the basis of batch reports and 
measurements of the water content of the aggregate. 
 
According to expert B the designed mix composition of concrete has been defined "too 
tight". Variation in the quality of the different components has not been taken in 
consideration in the preliminary test plans. 
 
According to both FANP's Deputy Site Manager and Finnprima's expert A, Forssan 
Betoni did not clearly enough bring up the fact that the designed composition is defined 
too "tight" and the required workability and pumpability cannot be achieved without 
changes in the mix proportions. The concern expressed by Forssan Betoni is, however, 
clearly indicated also in the result report dated 24.5.2005 and delivered to STUK for 
information and in the copy of the same report received from Forssan Betoni, where it 
is seen crossed out (according to Forssan Betoni FANP had crossed it out).  
 

Observations and course of events prior to concreting of reactor building base slab 

Construction works were implemented at several points in the plant area with TVO as 
the developer before the consortium started the actual construction of the plant. These 
included e.g. construction of water tunnels and the port. Forssan Betoni's batching plant 
no. 3 in the Interrock area delivered the concrete for these works. The requirements for 
the composition of the concrete were defined by the same expert A employed by 
Finnprima, who also took part in the design of the mix composition of the base slab 
concrete.  
 
According to TVO's Site Manager initial problems were also encountered with the 
pumpability of the concrete in the construction works carried out with TVO as the 
developer, and the composition of concrete had to be fine-tuned by regulating the 
amount of filler (the finest part of aggregate). The batching plant manager confirmed 
this. After the mix composition was fine-tuned, the concreting was completed as 
planned.  
 
Levelling concrete of the base was cast before the concreting of the base slab started. 
According to FANP's representative the concrete mix composition defined for the base 
slab was used for the levelling concrete in March, and at that point a pumpability test 
was performed on the base slab concrete. A representative of Forssan Betoni had been 
invited to the pumping test. In connection with the placing of the levelling concrete, 
variations were detected in the quality (consistency) of the concrete and also 
segregation. Hartela's employees who implemented the concreting also brought up on 
several occasions the variations in the quality of concrete. FANP believed that after 
Forssan Betoni had been contacted and criticism given, the variations in quality would 
be eliminated and the quality of the concrete would be as planned. According to 
Forssan Betoni, the problems were not, however, specified in a way that would have 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 16 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

made it possible to correct them, and their written request to FANP for detailing the 
presented criticism was not replied. 
 
Due to the variation in the consistency of the concrete, detected in the concreting of the 
base slab for fuel building UFA (concreted on 12.-14.8.2005) and safeguard buildings 
2-3 UJH/UJK (concreted on 1.-2.9.2005), a new plasticizer was taken in use for the 
concreting of the reactor building base slab. The new plasticizer had been proven less 
sensitive to the accuracy of batching. In addition, a retarder was introduced to the 
composition, in order to prevent the previous concrete layer from setting before the 
next layer is concreted. New preliminary tests were performed on 15.9.2005 using the 
new plasticizer and the retarder, as required by YVL Guide 4.1. The purpose of the 
preliminary tests was to determine compressive strength, consistency and setting time. 
No pumpability test was performed. 
 
In the first inspection of readiness for concreting of the reactor plant on 23.09.2005 
only 7-day compressive strengths of the concrete were available. At that point TVO 
stated that on the basis of the available compressive strength results it was not possible 
to assess with certainty that the required strength would be achieved after 91 days, and 
thereby readiness for concreting was not sufficient. FANP and TVO decided to conduct 
a new inspection on 26.9.2005. 
 
In the inspection on 26.9.2005 FANP assessed on the basis of the additional results the 
development of the strength of the concrete and the achievement of the required 
strength (91 days). TVO still did not consider the assessment sufficiently reliable. 
FANP and TVO agreed to conduct a new inspection on 30.9.2005, when the 15-day 
compressive strength values would be available.  
 
STUK granted a concreting permission for the reactor building base slab on 30.9.2005. 
The approval of concrete strength was at that point based on 15-day compressive 
strength results and on the assessment made on the basis of these results by FANP's 
experts of the 28 and 91-day strengths and of the strength variation range.  

 
Concreting of reactor building base slab 

The base slab was concreted in three stages as follows: 
 

•

 

In August, base slab of fuel building UFA, 12.-14.8.2005. Amount of concrete ca. 
1500 m

3

 

•

 

In September, base slab of safeguard buildings 2-3UJH/UJK, 1.-2.9.2006. Amount 
of concrete ca. 2000 m

3

•

 

Base slab of reactor building UJA as well as safeguard buildings 1 and 4UJH/UJK 
3.-8.10.2005. Amount of concrete ca. 12 000m

3

 
Variation in the consistency of the concrete between different truck loads was detected 
in connection with the concreting of the base slab for fuel building UFA and for 
safeguard buildings 2-3UJH/UJK. This variation had also been observed during the 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 17 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

concreting of the levelling concrete (STUK's memorandum 6.3.2006). The variation 
was interpreted to be caused by the plasticizer and the accurate dosing it requires. As a 
result, a new plasticizer was taken in use, as described above. 
 
For the concreting of fuel building UFA in August, FANP issued the order to start 
concreting with a very short notice time. The two-week notice time specified in the 
agreement was not complied with in this case. Considerable difficulties were 
encountered in the concreting process, as the contractor (Hartela) did not have enough 
time to properly prepare for concreting. The levelling and the steel trowelling of the 
slab surface, in particular, were not done properly because the workers were too tired. 
This does not, however, have any influence on the strength or durability of the concrete. 
In subsequent concreting operations Hartela was prepared for this and had hired extra 
workers.  
 
The Polytechnic of Kymenlaakso (KyAMK) controlled the quality of concrete during 
the concreting of the base slab of reactor building UJA and safeguard buildings 1 and 
4UJH/UJK. The party in charge of the management of construction work of the reactor 
building (FANP) had ordered expert C, employed by a German company, to act as 
FANP's expert at the batching plant. 
 
According to information received from TVO, the large base slab concreting operation 
on 3 October was started using the designed and approved composition of concrete. 
TVO's supervisors detected problems in the concreting work on the afternoon of the 
first concreting day (3.10.2005 at ca. 16.00). Problems were encountered with the 
pumpability of the concrete, resulting in e.g. concrete pumps breaking down. TVO’s 
supervisors inquired at the site for possible reasons why the pumps had failed or 
become clogged. The next morning, TVO contacted FANP's representatives by e-mail 
on 4.10. enquiring whether changes had been made in the composition during the 
concreting operation. FANP informed that no changes had been made in the 
composition of concrete. 
 
However, Forssan Betoni and expert B have told that expert C, who acted at the 
batching plant as FANP's expert, reduced the amount of filler in the aggregate. 
Problems persisted, and according to the batching plant manager the composition was 
changed again 24 hours later back to almost the original composition. The amount of 
filler was still a bit smaller than in the designed composition. 
 
The Site Quality Manager who supervised the concreting operation on behalf of the 
consortium also told that expert C had ordered changes to be made at the batching plant 
in the composition of the concrete on the basis of the consistency measurements 
performed by KyAMK.  
 
According to TVO's Site Manager, the rest of the concreting operation went as planned. 
In the Site Manager's opinion the representative of STUK had not been informed about 
the change in the composition of concrete. 
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 18 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

After the concreting operation, TVO contacted FANP several times (by e-mail), trying 
to find out if the composition of concrete had been changed during the concreting 
operation. On 5.10.2005, for example, TVO asked FANP to submit the batch reports 
for the concrete fabrication batches. Despite several requests, these reports were not 
submitted to TVO. 
 
After the concreting operation, the concreting contractor Hartela drew up two 
nonconformity reports. The non-conformance report dated 15.11.2005 (Hartela NCR 
0030) reported the disappearance of the compressive strength test specimens for 32UJH 
and 33UJH equipment pit. The non-conformance report dated 19.01.2006 (Hartela 
NCR 0029) stated that the reference strength of the concrete according to the site test 
specimens did not meet the requirement in area 2-3UJH. 
 

Course of events after concreting of the reactor building base slab 

Claims for submittal of batch reports of fabrication batches 

Since FANP did not, despite several requests, submit the batch reports, TVO conducted 
on 14.10.2005 an inspection at the batching plant. Present in the inspection were the 
supervisor of concrete fabrication and the quality control expert from TVO, the Site 
Quality Manager from the consortium as well as the person responsible for the 
supervision of the batching plant for FANP. In this inspection, the representative of 
TVO concluded that considerable changes had been made in the composition of 
concrete during the concreting of the UJA building. In the inspection, TVO's 
representatives asked for copies of the batch reports, but FANP refused to produce 
them. It was agreed in the inspection that TVO would send an official request for the 
copies to FANP. 
 
FANP informed TVO by an official letter on 20.10.2005 that the batch reports would 
not be submitted until in connection with the completion of the plant. 
 
This resulted in active correspondence between TVO and FANP, and on 14.11.2005 
FANP agreed to submit the requested batch reports. The reports were delivered to TVO 
on 21.11.2005. On the basis of the batch reports TVO concluded that the composition 
of concrete had been changed during the concreting operation. TVO prepared a draft 
non-conformance report on 23.11.2005. The actual non-conformance report (no. 0593) 
was drawn up by TVO on 14.12.2005 and the next day TVO informed STUK by e-mail 
of the non-conformance report that had been entered in the Kronodoc folder. Kronodoc 
is a system where STUK can in advance read material that will be later provided on 
paper. 
 
In a letter dated 20.12.2005, FANP still denied that any changes had been made in the 
mix composition of concrete. In addition, FANP refused to accept receipt of the 
non-conformance reports and asked TVO to withdraw them. 
 
In a letter dated 5.1.2006 TVO refused to withdraw the non-conformance reports and 
asked FANP to make a proposal for action to be taken by 10.1.2006. 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 19 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

 
At the end of January (26.1.06) and at the beginning of February (3.2.06 and 8.2.06) 
FANP submitted non-conformance reports to TVO for examination, concerning 
concrete structures in the base slab of the reactor building. TVO forwarded the 
non-conformance reports immediately to STUK for information. 
 

Report by Polytechnic of Kymenlaakso (KyAMK)  

The preliminary report by KyAMK (drawn up by expert B) on the tests performed 
during the concreting operation was submitted to FANP (to the site) in November 
(dated 13.11.2005, received at site on 14.11.2005). The report was preliminary because 
the 91-day results for the concrete were missing (the quality assessment age for 
concrete is 91 days). The report did, however, show considerable variation in the 
water-binder ratio in some batches. Towards the end of the concreting operation, the 
water-binder ratio exceeded the designed value, and varied between 0.53 and 0.56. The 
highest single value was 0.64. 
 
The site did not forward KyAMK’s preliminary report either to TVO or to STUK. 
According to the information that was received the report was not sent to FANP's head 
office, either. The report was studied by FANP's Site Manager and his deputy. FANP 
also asked the batching plant to provide the batch reports for making more detailed 
analyses as, according to them, no conclusions could be drawn without binding results. 
According to FANP's Deputy Site Manager the report was not forwarded to the other 
parties due to its preliminary nature. FANP had decided to distribute the report only 
after the final results were available. 
 
According to the Deputy Site Manager, FANP's perception was that the changes made 
in the composition of concrete during the concreting of the reactor building base slab 
were not relevant.  
 
The preliminary report by KyAMK (copy) was sent to Forssan Betoni on 20.11.2005. 
Forssan Betoni did not comment the report at this point.  
 
The Civil Work Contract Manager of FANP's parent company Areva arrived at the site 
in mid-January to settle a contractual problem between FANP and Boygues, the 
contractor of the containment. Boygues had informed that they would terminate the 
contract because they did not trust the batching plant’s capability to deliver appropriate 
concrete. After Hartela had sent a letter (non-conformance report) informing about the 
disappearance of the test specimens, the Contract Manager responsible for civil work 
had an investigation made by a party independent of the batching plants, the Technical 
University of Darmstadt. 
 

Report by the Technical University of Darmstadt 

Representatives of the Technical University of Darmstadt visited the batching plant and 
recorded several deficiencies (10 findings), but some of them were clearly based on 
misunderstanding. According to their inspection aggregates were not stored in silos, 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 20 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

which resulted in a number of findings: there was no layer at the bottom of the storage 
pile to prevent mixing with soil, the particle size fractions had not been properly 
marked and the aggregate piles were not covered which, according to the inspectors, 
caused a risk of mixing and exposed the piles to rain and snow. In fact, the aggregate 
used for the concrete of the base slab was delivered by the supplier directly into silos 
without any intermediate storage. The aggregate piles detected in the inspection served 
as 2-hour stockpiles, in case transports had been delayed. According to the inspection, 
laboratory equipment had not been maintained in regulatory condition. This referred to 
the set of sieves, but the bowl that had been inspected was not part of the set. 
Deficiencies were also found in the storage of test specimens. According to the 
batching plant manager the test specimens were being transferred from one storage pool 
to another at the time of the inspection, which is why some of the test specimens were 
on a work table, in "dry" condition. The training level and qualifications of the staff 
could not be established in the inspection, as no documents concerning this were 
available. Nor was the Quality Control Plan for concrete production available. 
According to Forssan Betoni, the documents could not be presented because the 
inspection was made at a time when the English-speaking project manager of Forssan 
Betoni was absent. 
 
Areva's Contract Manager responsible for civil work contacted the batching plant 
manager and emphasised in this discussion the critical status of concrete in terms of 
safety. He also warned the manager that the operation of the batching plant might have 
to be discontinued. A list of corrective action concerning the batching plant was drawn 
up (on 17.1.2006). The Contract Manager responsible for civil work also contacted the 
Managing Director of Forssan Betoni. Forssan Betoni was not able to implement the 
corrective action in the tight schedule demanded by FANP. After this, the Stop Work 
Order for the manufacturing of concrete at the batching plant was issued by FANP’s 
Site Manager for the first time on 24.01.2006. According to the Civil Work Contract 
Manager the discontinuation of operation was specifically based on the Darmstadt 
report. The batching plant manager said that in his opinion the report was goal-directed. 
FANP informed TVO about the discontinuation of operation at the batching plant by a 
letter dated 26.1.2006. 
 
To TVO, the discontinuation of operation at the batching plant came as a surprise and 
TVO enquired about the reasons for the discontinuation. 
 
FANP informed TVO on 30.1.2006 that the batching plant had been given a permission 
to resume operation. 
 
At the beginning of February, Areva's Civil Work Contract Manager heard for the first 
time about the report by KyAMK. He did not know why the report had not been 
distributed widely enough for information within the FANP organisation. Having read 
the report, he found the problem to be serious. The subject matter content of the report 
was examined in Darmstadt. After discussions with several persons concerning 
KyAMK's report, the Contract Manager responsible for civil work decided to 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 21 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

discontinue the operation of the batching plant the second time. Operation was 
discontinued again on 6.2.2006. 
 
In a meeting between FANP and TVO on 3.2.2006, FANP informed that the 
water-binder ratio had exceeded the design requirements. STUK was informed of the 
matter in a meeting held on 9.2.2006. 
 
The report of the Technical University of Darmstadt draws an unfair picture of Forssan 
Betoni's operation in terms of the storage of aggregates. The manager of Forssan 
Betoni's batching plant did not find the competence of the inspectors very high, either, 
as observations were made of matters that had no part in the production process. The 
inspection had been carried out in the absence of the batching plant manager. 
 
According to Areva's Civil Work Contract Manager most designed compositions of 
concrete are such that they cannot be properly fabricated or poured. New preliminary 
tests were performed on the mix compositions in Darmstadt. The Contract Manager 
expressed his concern on the attitude of Forssan Betoni and its owner company. 
 

Inspections for the re-start of batching plant  

FANP/TVO presented on 28.2.2006 to STUK the investigations that had been 
conducted by that time, as well as their opinion of the conditions on which concrete 
fabrication could be continued. FANP's representative presented in the meeting the 
plans that they had drawn up, and which had been approved by TVO, for short-term 
and long-term corrective action. 
 
TVO submitted the following clarifications concerning the batching plant and quality 
control at the plant to STUK on 8.3. and 9.3.2006: 
 

•

 

Clarifications for the development of quality control at the batching plant  

•

 

OL3-specific QA manual of Forssan Betoni, including procedures and 
documentation 

•

 

Forssan Betoni, QA manual ISO 9001:2000  

•

 

Clarifications concerning FANP's and TVO's intensified efforts for the control of 
the quality of concrete and the batching plant  

•

 

Work specification concerning the batching plant and transports.  

•

 

Quality plan concerning the batching plant and transports. 

•

 

Inspection plan for the batching plant before re-start of operation. 

•

 

Complementing of FANP and TVO organisations for quality control of concrete 
and the batching plant. 

•

 

Report of the Technical University of Darmstadt on corrective action implemented 
at the batching plant. 

 
In addition, TVO submitted to STUK for approval the corrective actions required by 
critical non-conformance reports and the other non-conformance reports for 
information.  

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 22 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

 
An inspection of the readiness for resuming operation was conducted at the batching 
plant on Friday 10.3.2006. The inspection was performed in compliance with the 
sequence outlined in the specifically prepared plan, CW Inspection & Test Plan, 
Fabrication of ready-mix concrete, Re-start of Batching Plant, 6.3.2006. 
 
In the inspection, it was noted that the control and traceability of the water-binder ratio 
had still not been arranged in the required manner, despite the fact that the 
non-conformancies in the quality of the base slab concrete were primarily due to 
variation in the water-binder ratio. It was also concluded that the safety culture training 
referred to in the OL3 quality plan of Forssan Betoni had not been provided. 
 
Due to these deficiencies, TVO refused to issue permission for re-starting of the 
batching plant. STUK agreed. It was decided that the next re-start inspection would be 
performed after the deficiencies had been corrected. 
 
The new re-start inspection of the OL3 mixing plant was conducted at the Olkiluoto 
batching plant of Forssan Betoni on Wednesday 15.3.2006. FANP and TVO signed a 
report which stated that the required short-term corrective actions had been taken and 
the operation of the batching plants of Forssan Betoni could be resumed. STUK's 
inspector stated that STUK had no comments to make on the report.  
 
On 28.3.2006 TVO audited Forssan Betoni's Olkiluoto batching plants no. 1 and 2. In 
the audit, 10 findings were still made, 4 of them non-conformancies. For example, the 
inaccuracy of measurements of furnace slag exceeded the tolerance allowed by the 
concrete norms (10 % > permitted 3 %). A positive finding was that the traceability of 
the water-binder ratio in the batch report and the delivery note had been sorted out 
swiftly and well. One of the three recommendations issued was that special attention 
should be paid on motivating the personnel. 
 

3.1.4   Summary of problems that disturbed the concreting of base slab 

Selection of concrete supplier, and purchase agreement 

The procedure followed in the selection of the concrete supplier for the OL-3 project 
did not in all respects meet the requirements of FANP's quality system. At least the 
following deviations were found in the selection process: 
 
-

 

The call for tenders did not specifically state that special requirements are 
placed on quality management in the construction of a nuclear power plant. 
The requirements for quality management should have been stated so clearly 
that the tenderers would have been able to assess the amount of extra work 
required to meet them, and later operate without unpredicted cost pressures 
due to quality control. 

-

 

The key criterion applied to the comparison of the tenders was the price of 

concrete production. 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 23 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

-

 

The quality system of Forssan Betoni did not at the selection stage meet the 

requirements of ISO 9001. 

-

 

The quality system of the consortium requires that each subcontractor prepares 

a quality plan before work is started. However, Forssan Betoni did not receive 
the specifications for the preparation of the plan until February 2006, and 
prepared their quality plan after that.  

 
The delivery of concrete to the pump is not acommonly used limit. Usually the concrete 
supplier is responsible for the concrete properties up to the concreting site (formwork). 
Due to the specified delivery limit, the concrete supplier had no interest based on an 
agreement to pay sufficient attention to the pumpability of concrete.  
 
For large-scale concreting operations, the required two-week notice time for concrete 
orders is justified. FANP did not respect this requirement in the concreting of the base 
slab for fuel building (UFA) 12.-14.8.2005, but submitted the notice of the start of 
concreting on the day that concreting was started. For this reason, the concreting 
contractor Hartela did not have enough time to properly prepare for the operation (did 
not manage to acquire a sufficient number of workers) and this influenced the progress 
of concreting operation particularly at the finishing stages. On the other hand, the 
required two-week notice time that FANP specified for itself is unusual in smaller 
concreting operations, and indicates that the persons who concluded the agreement are 
not very familiar with the practices followed in construction projects. 
 

The acquisition followed the agreed procedures in main parts. However, the special 
features of nuclear power plant construction were not clearly emphasised and no 
OL3-specific quality plan, nor inclusion of IAEA's requirements for quality 
management in the plan was required of the tenderers at the tendering stage. These 
were not required until the audit that TVO carried out in the head office of Forssan 
Betoni in the spring in 2005. 

 

Batching plants and their staff 

The Olkiluoto batching plants no. 1 and 2 were new plants. The start-up of operation 
and the commissioning of new machinery and equipment always takes time, but the 
technical conditions for the production of good quality did exist at the time the base 
slab was concreted. 
 

Forssan Betoni had no experience in a nuclear power plant construction prior to the 
OL3 project and all the quality requirements applied to nuclear power construction 
were not brought up at the tendering stage. Also, the special safety requirements in the 
nuclear field were not emphasised by FANP in the training of the batching plant staff 
before concrete fabrication was started. After the site was handed over, the consortium 
and Forssan Betoni discussed the quality requirements and the work practices 
repeatedly, and Forssan Betoni felt that requirements outside the agreement were 
placed on them.  

 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 24 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

The staff at the batching plants possessed the required qualifications. However, several 
features in the performance of Forssan Betoni came up during the investigation that are 
not in accordance with a high-level quality and safety culture. Practices followed in the 
nuclear field, but deviating from practices normally followed in construction work, 
were not fully observed. For instance, concrete fabrication was not implemented 
according to the specifications and requirements, non-conformancies were not reported 
without delay, and there were delays in corrective actions for the reported 
non-conformancies.  
 
The responsibility of the batching plant manager for the quality of concrete was not 
clear, as experts hired by the consortium assumed a significant role in the determination 
of the composition of concrete, and the changes in the composition were also during the 
concreting operation made in collaboration with the consortium's expert. In the 
interview, the batching plant manager stated that in his opinion the changing of the 
composition was not a relevant issue. He mainly considered it to be an inconvenience, 
as it resulted in pumps breaking down. 
 
Several of the interviewed persons commented on the difficulties they had in 
cooperation with the staff at the batching plants. According to their experience, the staff 
at the batching plants did not take variations in the quality of concrete seriously enough 
and did not actively try to sort out the problems together with the other parties.  
 

However, it is not right to blame an individual supplier for the poor safety culture, as 
the consortium's practices in the selection and guidance of the concrete supplier were 
deficient. The consortium should acknowledge the fact that jobs in the nuclear field are 
rare and it is therefore to be expected that nuclear safety is not the number one priority 
in the subcontracting companies operating in different fields. 
 

Some of the interviewees questioned the professional competence of the staff at the 
batching plants with respect to concrete fabrication, and language skills were suspected 
of having caused problems, as well. Yet, there are no grounds for these perceptions 
concerning the competence and the language skills of the staff, and the negative views 
may have been presented to serve a purpose. From the point of the agreement, it is not 
justified to make the language skills an issue, as the contract between CFS and Forssan 
Betoni defines Finnish as the language to be used at the site.  
 

Forssan Betoni and its parent company Lemminkäinen voiced their outrage on how the 
quality of the base slab and the operation of the batching plant were presented in public 
after the concreting of the base slab. They emphasised that the concreting was 
completed and the quality of the concrete is good. Attitudes of this kind in the 
management do not promote the development of a quality and safety oriented 
atmosphere in an organisation. 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 25 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 
 

Preparations for base slab concreting 

Variations were detected in the quality of concrete (consistency, segregation, 
pumpability) in several contexts before the concreting of reactor building base slab. 
Observations were made at least in preliminary tests, the concreting of levelling 
concrete, the concreting of base slab for fuel building UFA and the concreting of base 
slab for safeguard buildings 2-3UJH/UJK. 
 
In other words, the experts of all the parties were aware of the problems connected with 
concreting, but active measures to correct the situation in good time before the 
concreting of the reactor base slab were not taken. Attempts to correct the situation 
were not started until in the autumn just before the planned start of concreting, when 
e.g. the plasticizer was changed and a retarder was added in order to increase the 
workability time. 
 
In practice, cooperation between the structural designer and the concrete supplier has 
been virtually non-existent. FANP has actually required that all communication be 
handled through them. FANP trusted that Forssan Betoni would implement the 
corrective action once problems had been occured in previous concreting operations 
and the matter had been reminded. FANP did not check whether the corrective actions 
had actually been taken.  
 
FANP's Deputy Site Manager hired expert B from the Polytechnic of Kymenlaakso 
(KyAMK) as an independent quality controller for the concreting of the reactor 
building base slab. The Deputy Site Manager assumed that the factors detected in the 
mix composition before the concreting operation had been corrected. Several experts, 
including expert A who designed the mix composition, expert B and the German expert 
C had seen the composition of concrete, but did not warn about any problems. 

 

Concreting of base slab 

According to the information received and the results obtained in the investigation, the 
quality control personnel of FANP did not identify serious quality problems during the 
work. 
 
The composition of concrete had been changed during the concreting operation, which 
is in violation of YVL Guide 4.1. According to FANP the change was not relevant, but 
this claim can be questioned as the change exceeded the limits specified in the Finnish 
Building Code Part B4, Concrete Structures for weighing accuracy (±3 %). Only 
changes within these limits can be interpreted as non-relevant. In all other cases the 
influence of the change should be analysed. 
 
During the concreting operation it was not clear to the parties involved, Forssan Betoni 
or FANP, who was responsible for the composition of mixes. In this case the quality of 
concrete was changed on an order given by FANP. 
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 26 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

Course of events after the concreting of reactor building base slab 

Information about the results of the KyAMK report was not distributed widely enough 
even within FANP. The relevant results were presented already in the preliminary 
report. Leaving the report without forwarding to and the concealing of the results from 
TVO and STUK do not reflect an open attitude toward problems which would be in line 
with good quality culture.  
 
The disappearance of the compressive strength test specimens made by Hartela 
indicates deficiencies in quality control. 
 

Conclusions 

The construction of the base slab was impeded by the following factors: 

•

 

No appointed responsible manager at the site unambiguously in charge of the base 
slab fabrication, with authority to issue orders that are binding to all parties.  

•

 

The base slab delivery chain did not share a common perception of the safety 
significance of the quality of concrete. 

•

 

In the selection of the concrete supplier, the special quality requirements applied in 
a nuclear power plant construction were not brought up in the tender invitations, 
whereas cost factors were strongly emphasised in the selection. 

•

 

No training was provided to the staff involved in the fabrication of concrete 
concerning practices in the nuclear field and the safety significance of their own 
work.  

•

 

The division of the concrete supply contract resulted in interfaces, the management 
of which failed.   

•

 

In quality control, too much trust was placed on the responsible attitude of the 
parties in the elimination of the detected problems.  

•

 

Responsibilities were unclear and problems existed in communication with respect 
to the design of the mix composition, fabrication of concrete and quality assurance.  

•

 

The problems observed in previous concreting operations did not result in effective 
corrective actions implemented in time.  

•

 

The approved composition of concrete and the concreting specifications were not 
adhered to in concrete fabrication. 

•

 

Quality non-conformancies connected with the composition of concrete and 
concreting were not handled without delay and in an open manner. 

•

 

The handling of quality problems in the base slab concrete has been characterised 
by a search for guilty parties instead of focusing on developing the practices.  

 

3.1.5  Investigation team's assessment of the acceptability of the concrete slab 

The water-cement ratio of concrete influences the strength and the durability of 
concrete. A higher-than-designed water-cement ratio reduces the compression strength 
and impairs the resistance of concrete against environmental impacts.  
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 27 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

Despite the higher water-cement ratio, almost all the 91-day reference strengths 
determined for the concrete samples taken of the base slab fulfil the requirement 
specified for K40 (C32/49) strength class concrete. The 91-day strength has been below 
the value required of strength class K40 only in area 2-3UJH, and even there the value 
is only slightly below the required value. None of the additional samples that were 
taken were below the required strength class value. STUK has approved the test results.  
 
When assessing the compressive strength of concrete, it should be borne in mind that 
the development of strength does not stop at the age 91 days when the quality is 
determined, but continues as the age of concrete increases. In addition to age, the 
composition of mix and the conditions also influence the development of strength. For 
concrete that contains furnace slag, the development of strength continues for a long 
time. On the basis of experience gained from previously built structures, the increase in 
strength is usually considerable in comparison with the 91-day results. 
 
As a result of what has been presented above, the concrete of the base slab can be 
considered to meet the specified requirements for compressive strength. 
 
Concerning durability requirements, the concrete meets the specified requirements in 
terms of exposure classes XC2 (carbonation) and XS1 (chlorides). 
 
Due to the higher-than-designed water-cement ratio, the concrete does not meet the 
requirement of exposure class XA1 (chemically aggressive substances). Owing to the 
high amount of furnace slag, however, the chemical resistance of the concrete is in 
practice very good. As the concrete is ageing and its strength is increasing, its density 
will also increase, which further improves its chemical resistance. 
 
With respect to durability requirements, it should be noted that they apply to the side 
surfaces of the base slab. Damages to the surface parts take place very slowly. The 
binder composition that has been used (more than 70% furnace slag) is normally used 
in extremely demanding environmental conditions in which chlorides are present, and 
where the corrosion risk of the concrete due to other chemical substances is 
considerable. Nevertheless, to ensure base slab chemical resitance TVO has announced 
that it will in any case require the protection of the base slab against external moisture 
and the impurities it will bring along. 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 28 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 
 

3.2  Containment steel liner 

 

3.2.1  Background information on containment 

Contractual parties responsible for the manufacture of steel liner 

The parties to the contract were the builder (Framatome ANP, FANP), the structural 
designer and supplier of the steel liner (Babcock Noell Nuclear GmbH) and their 
subcontractor (= as the manufacturer), a Polish Engineering Works (Energomontaz-
Polnoc Gdynia (EPG)). 
 

Purpose and structure of containment 

The nuclear safety related purpose of the containment is to prevent release of 
radioactive materials into the environment and to protect the reactor coolant circuit and 
the safety systems against external events. The containment is a cylindrical double 
containment that is about 60 m high and has a diameter of about 45 m. The walls and 
the dome of the inner containment are made of pre-stressed concrete. A steel liner is 
installed on the inside of the concrete structure. The inner containment can resist the 
over-pressures and the temperatures caused by accident situations, without loosing its 
tightness. The outer containment is an extremely massive reinforced concrete structure 
that can withstand e.g. airplane crashes.  
 
The reactor and the entire rector coolant circuit (the primary circuit), parts of the steam 
and feedwater systems as well as equipment of the safety systems are installed inside 
the containment. The containment is normally accessed through a personnel airlock. A 
backup airlock is also provided for emergencies. The material hatch of the containment 
can be temporarily opened during outages, if required for maintenance purposes. These 
airlocks are integral parts of the steel liner and the surrounding concrete. 
 
In an accident situation the inner containment is isolated by closing the exit routes from 
the building. This prevents the release of radioactive materials into the environment. 
The steel liner including all its penetrations and hatches is assigned to safety class 2. 
 

3.2.2 Manufacturing of steel liner 

Method of manufacturing 

The steel liner is made of 6 mm thick structural steel. The steel plates are joined 
together at the engineering works by welding them into 30-degree segments, the surface 
of which is then finished (sandblasting + coating). The segments are transported to the 
port and welded into 180-degree sections. At the site, the sections are first joined 
together into rings and the rings are then assembled to make up the complete liner as 
the construction of the containment progresses. 
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 29 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

According to the welding specification applied to the manufacturing of the steel liner, 
the root gap between the plates, which is to be filled with the welding material, is 2-5 
mm. The welding procedure have been carried out using this gap size. The use of 
ceramic weld support in the welding process has been approved later.  
 

Selection of steel liner supplier 

Several potential steel liner suppliers were indicated in the Main Contract. FANP called 
tenders for detailed design and manufacturing from four Finnish and five Central 
European companies, but only two of them submitted a tender. As the steel liner is a 
SC2 steel structure, the manufacturer needs to be approved by STUK. In addition, 
STUK performs several construction inspections during the manufacturing of the 
structure [8]. 
 
Babcock Noell Nuclear GmbH (BNN) was selected as the supplier. The selection 
process followed Framatome ANP's standard procedure and was based on both 
technical and commercial selection criteria. The division of work between FANP and 
the supplier is that FANP performs the required basic design work and lays out the 
requirements in the project specification. The supplier is responsible for detailed 
design, taking the requirements of the project specification into consideration, and 
prepares the detailed construction plan on the basis of these. The steel liner is 
manufactured according to the approved construction plan.  
 

Selection of steel liner manufacturer 

Babcock Noell Nuclear GmbH selected as their subcontractor (=the manufacturer) the 
Polish Engineering Works Energomontaz-Polnoc Gdynia (EPG). The representatives of 
FANP told in the interviews that the selection of the manufacturer came as a surprise to 
them. The contracts concluded between FANP and various suppliers refer to the use of 
subcontractors, but FANP has no real say in their selection. The interviewed 
representatives of TVO had also been surprised by the selection of the manufacturer. 
The feedback on the selected manufacturer obtained from a Finnish company given as 
reference was reasonably good, but emphasised the importance of constant supervision 
to ensure that the desired final product would be achieved.  
 
FANP, TVO and STUK audited the Polish manufacturing company on 29-30.3. 2005. 
The audit focused on e.g. materials handling, welding, dimensional control, 
sandblasting, coating, transport logistics as well as inspection, testing and quality 
management procedures. During the audit, 8 non-conformancies were recorded which 
required corrective actions. Two of the non-conformancies concerned filler metals used 
in welding, for which no handling or storage specifications had been drawn up, and for 
which humidity and temperature reports for the storage facility were missing. Weld 
inspection procedures were incomplete, and no systematic procedure existed for the 
daily control of welding reports. In addition, the usability of the liquids for the 
development of X-ray films could not be verified. Deficiencies were also found in the 
calibration of micrometers in the DT laboratory.  
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 30 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

TVO had earlier performed a pre-audit in March 2005, in which 11 non-conformancies 
had been recorded. Corrective actions had, however, been completed on them by the 
time of the actual audit.  
 
An application was submitted to STUK in compliance with YVL Guide 3.4 [9] for the 
approval of Energomontaz-Polnoc Gdynia as a manufacturer of nuclear pressure 
equipment. The NDT testing organisation of the company was approved according to 
YVL Guide 1.3 [10] for the test methods used during manufacturing (radiographic, 
ultrasonic, liquid penetrant, magnetic powder, and leakage testing). In terms of welding 
technology, the construction is demanding and NDT inspections are really important in 
manual welding due to the large number of run-on and run-off points in the welds.  
 
STUK has approved the construction plan of the steel liner and numerous subsequent 
additions to it. The steel liner is considered as a nuclear power plant steel structure 
according to YVL Guide 4.2 (the bearing steel structures of a reactor containment made 
of concrete) [11]. 
 
The manufacturing process in Poland is supervised by the quality controllers of FANP 
and BNN as specified in the quality control programme of the construction plan. The 
quality controllers of TVO also visit the engineering works weekly to supervise 
manufacturing. STUK performs construction inspections on prefabricated components 
before coating in compliance with YVL Guide 1.15 [8] as the manufacturing 
progresses. TVO's representative will also be present in these inspections. 
 

Requirements specified for quality assurance of steel liner manufacturing 

In order to ensure the quality of the steel liner, FANP defined the following activities: 
 

1.

 

Qualitative assessment of the  BNN the EPG and the testing organisation based 
on documentation, and their comparison with valid (ISO) standards and YVL 
Guides. 

2.

 

Verification of fulfilment of requirements by audits performed by TVO and 
STUK. 

3.

 

Inspection performed by TVO of construction plan documentation drawn up by 
FANP/BNN/EPG and submittal of the construction plan to STUK for approval. 

4.

 

Starting permission for manufacturing. 

5.

 

Maintenance of the quality level of the manufacturer through training (repeated 
training events) of the entire personnel, from the top executives to the workers, 
based on important/current issues related to manufacturing, and on FANP's 
requirements (taking into consideration also the comments made by TVO and 
STUK in connection with their control efforts). 

6.

 

Inspection of the manufacturing documentation of FANP/BNN/EPG with 
respect to each plate part, segment and the dome. 

7.

 

Starting permissions granted separately for each separate segment and part. 

 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 31 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

For the bottom part AS10 of the steel liner (the base plate and the bottom part of the 
wall welded to it), FANP defined the control phases as follows: 
 

1.

 

Prefabrication of segments, conical parts and base parts at the engineering 
works under continuous control of FANP, BNN and EPG. Random test type 
inspections by TVO and STUK. 

2.

 

Inspection of all welds by FANP, BNN and EPG, as well as by TVO and 
STUK, after which coating permission is granted. 

3.

 

Sandblasting of parts to class SA 2½ and 80 µm coating with zinc-silicate paint 
under control of the parties referred to above. 

4.

 

Inspection of coating by TVO (and STUK), after which transport permission to 
the port of Gdynia for sub-assembly. 

5.

 

Assembly of the base part halves by means of a steel frame under continuous 
control of FANP, BNN and EPG. Random test type inspections by TVO and 
STUK. 

6.

 

Sandblasting of the halves to class SA 2½ and 80 µm coating with zinc-silicate 
paint under control of the parties referred to above. 

7.

 

Inspection of coating by TVO (and STUK), after which shipment permission to 
Olkiluoto. 

 
The manufacturing and control phases of the cylinder rings and the dome are 
analogous. 
 

3.2.3  Observations made in the manufacturing of steel liner 

Deficiencies and problems in manufacturing 

Some schedule-related problems were encountered in the submittal of the construction 
plan before the start-up of production, due to the obviously incomplete state of the 
design. The construction plan submitted to STUK was incomplete and has been later 
supplemented on several occasions. This has required extra work from the various 
parties and made the approval process difficult (schedules, perception of the whole). In 
addition, due to this process the manufacturer has not always known what the most 
recent updated version of the design drawings is. For this reason, holes for pipe 
penetrations were cut in wrong places as instructed in the old design drawings, and the 
holes had to be patched up later.  
 
From controlling point of view, the relatively long "control / supply / production chain" 
(STUK->TVO->FANP->BNN->EPG) has proven problematic. It causes delays e.g. in 
communication, the handling of critical non-conformance reports, and the 
implementation of corrective actions related to production. In addition to the long 
"chain", there are also considerable differences in cultural attitudes as well as in 
problem handling and solving skills (e.g. "instability" of the arch detected in the stud 
welding of anchoring plates) and in the implementation of corrective actions. Unclear 
responsibilities are also emphasised in the different parts of the "chain" (e.g. quality 
assurance). 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 32 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

 
As production has progressed in Poland, TVO and STUK have implemented oversight 
activities on a regular basis. For STUK, regulatory control has consisted of construction 
inspections of subsections and components, such as penetrations and anchoring plates, 
as specified in YVL Guide 1.15. Perhaps the worst deficiency in the performance of 
construction inspections has been the fact that the inspection documentation has fallen 
way behind production. This makes it very difficult to perform construction inspections 
which are required in order to enable the manufacturer to proceed to the next work 
stage (=sandblasting + coating) in an optimum production schedule. STUK has made 
several admonitions about this to TVO (most recently in February 2006) and TVO has 
correspondingly informed FANP on the matter by letter, at least on two occasions. As a 
result, the situation has slightly improved lately, although it has not been corrected to 
the desired level, yet.  
 
The production conditions at the engineering works of EPG are at a modest level, 
considering that safety class 2 components are welded and finished there. Deficiencies 
can be found in e.g. lighting, cleanness and temperatures. Manual welding can in a case 
like this also be considered quite a primitive choice.  
 
The EPG has experience in the manufacturing of large-scale steel structures for 
conventional applications, but no earlier experience in deliveries to nuclear power 
plants. For this reason, FANP's requirement for repeated training events to maintain the 
quality level of the manufacturer was justified. However, in practice no training was 
provided although the requirement is recorded in EPG's Quality Manual. No training on 
the promotion of safety culture has been provided, either. 
 
It has also been observed that FANP has left the control of actual production too much 
to BNN (at times FANP’s control has appeared to be completely based on random 
tests). FANP's performance combined with the limited experience of BNN's supervisor 
in this type of manufacturing has resulted in obvious delays in e.g. the handling of 
documents, the solving of problems and the implementation of corrective actions. For 
these reasons TVO and STUK have in practice had to assume the responsibility of the 
plant supplier in carrying out inspections (control). This has been justified to ensure 
that corrective actions are initiated without delay, but FANP has failed to react to this 
by sufficiently improving its own performance.  
 
The problem is that the manufacturing schedule of EPG is constantly "alive". The EPG 
does not manufacture the steel liner according to a steady schedule, but accepts other 
orders in-between depending on the market situation and their own production capacity. 
This results in production breaks from time to time in the manufacturing of the steel 
liner, while at other times the schedule is excessively tight. On the other hand, it has not 
always been possible to continue the manufacturing of the steel liner as scheduled, due 
to deficient construction plans. 
 
During the manufacturing of the steel liner at EPG, in a regular construction inspection 
the inspector of STUK and the quality controller of TVO noticed excessive root gaps in 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 33 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

the welds between plates. In terms of welding technology, the use of weld support 
makes it possible to use larger root gaps, and the manufacturer has started to take 
advantage of this in the welding process. The use of a larger root gap in the welding 
process does not comply with the original welding specification, qualified by procedure 
tests. The problem of an excessive root gap in the welding of the components was 
detected twice in the autumn of 2005, and STUK sent a remark of this to TVO. The 
inspectors of TVO and STUK stopped production to take corrective action. A non-
conformance report was drawn up and it was assured that the problem would not occur 
again. 
 
In connection with a construction inspection performed by STUK in the port of Gdynia 
in Poland (on 10.5.), it was noticed that the problem re-appeared in the assembly of the 
segment sections. The measured root gap in the horizontal weld was ca. 7.5 mm at its 
maximum, instead of specified 2-5 mm. STUK's inspector discussed the problem in 
Poland with the representatives of TVO, BNN and the consortium, and later in Finland 
with TVO's quality controllers. In TVO's opinion this operation is not acceptable and 
TVO is investigating a resolution to the problem. 
 

Errors in the manufacturing of steel liner 

The following errors, for example, have occurred in the production, and required 
repairs and extra tests: 
 

1.

 

Root gap exceeded the maximum specified gap of 5 mm in manufacturing at the 
Engineering Works (and prior to that the introduction of weld support to the 
welding process). 

2.

 

Root gap increased to 7.5 mm in the assembly process carried out in the port 
(observed on 10.5.2006). 

3.

 

Use of non-approved welding method for repairs (repairs using electrode 
welding, although the only approved welding method is flux cored arc welding). 

4.

 

Holes for pipe penetrations cut in wrong locations (old design drawings) 

5.

 

Defective anchoring plates (deficiencies in stud welding, observed on 15.3.06) 
in the steel liner jacket. 

 
Repeated use of an excessive root gap is a clear quality non-conformance to the 
officially approved procedure and absolutely unacceptable to this extent. A situation 
like this should not be possible in a well functioning quality system. Quality control 
based on the welding specification shall be continuous, and every worker must be 
responsible for the quality of his own work. In this project the next control step is 
defined so that FANP's quality controller controls the compliance of the performance 
with specifications and the fulfilment of quality requirements. The inspection following 
that is performed by TVO's quality control inspector. STUK is not responsible for 
quality control during production, but only for the conduct of of the prescibed 
construction inspections. In addition, the quality system requires traceability in a 
situation where it is possible that a defective product has passed through quality control 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 34 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

during production. In this case it is not clear how widely excessive root gaps have been 
used in the welding processes. 
 
The acceptability of the welds that do not conform to the welding specification has 
been subsequently verified by additional qualification tests. STUK has approved the 
programme of the welding procedure test and seen the preliminary results. The result 
report has not yet been submitted to STUK for review. According to TVO, the primary 
objective will, however, be to improve the accuracy of manufacturing and the 
construction practices. 
 
The use of a non-approved welding method (the 3rd non-conformancy above) was 
detected in a construction inspection performed by STUK. The manufacturer had 
decided to modify their earlier work practices and chose an unqualified method instead 
of having recorded and reported a non-conformancy, proposed corrective actions, and 
waited for approval before continuing the work. The welds produced using a wrong 
method were removed by grinding and re-welded using a qualified method. 
 
The cutting of pipe penetration holes in wrong places was due to the use of non-
approved design documents. Information about changed location of the holes did not 
reach the manufacturer before the work was started. The manufacturing of the 
respective parts of the steel liner was started with FANP's permission before the design 
documents had been approved. The holes were detected in TVO's control inspections. 
They were patched up using appropriate methods and the result of the repair was 
verified by X-raying.  
 
In connection with the construction inspection of the installation welding of the jacket 
(AS 20 ring), defects were detected in the anchoring plates welded to the steel liner. 
The stud welding of the anchoring plates had failed in some of the studs welded on the 
edges of the plates. This was shown as an inconsistent "collar" at the root of the stud. 
The plates had to be removed and new plates with correctly welded studs were joined to 
the steel liner. 
 
A clear deviation from specifications is the waviness of the bottom part AS10 of the 
steel liner. In its final place, the bottom shold be as flat as possible to minimize the ai 
pockets between the liner and the concrete, in order to avoid corrosion of the liner in 
the long term. The bottom structure without stiffeners was a choice made by the 
designer. The defined waviness tolerance may not have been realistic, taking into 
consideration the problems connected with manufacturing (=welding). In order to 
evaluate the possible problems caused by waviness, the steel liner was subjected to a 
water filling test. In its final location in the containment, concrete will be placed into 
the steel liner, and the purpose of the water filling test was to simulate the weight of the 
concrete. On the basis of the results of the test, it was concluded that the load 
straightens the steel liner, and the waviness exceeding the tolerance is not significant. 
Nevertheless, in order to eliminate the possibility of air pockets, concrete will be 
injected between the steel liner and the base plate after concreting work inside the steel 
liner have proceeded to a suitable point. For the injection work grooves have been 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 35 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

milled to the surface of the base plate and through them the grout will penetrate the 
whole area of the plate. 
 

Conclusions 

The following factors have impeded the manufacturing of the steel liner: 

•

 

Responsibility for the selection and control of the manufacturer was left to the 
subcontractor. 

•

 

Requirements on quality and the supervision of manufacturing were not 
emphasized at the design and tendering stage, and came as a surprise to the 
manufacturer. 

•

 

The working practices and equipment used by the manufacturer are outdated for 
this type of manufacturing. 

•

 

Permissions have been granted by FANP for the continuation of manufacturing in 
situations where the design of the phases and the approval of the design documents 
have not been completed. 

•

 

The safety significance of the welds of the steel liner has not been emphasised to 
the workers involved in manufacturing, and no training has been provided to 
themconcerning quality management practices in the  nuclear field. 

•

 

The inspection documentation of the steel liner has not been available in full in 
construction inspections. 

•

 

The long supplier chain has slowed down the non-conformance handling process. 

•

 

The quality control implemented by the subcontractor and the plant supplier has 
been deficient, and required extra activities from TVO and STUK. 

 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 36 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

 

3.3  Polar crane and material hatch 

The deliveries of the polar crane for the reactor hall and the material hatch for the 
containment are at the design stage, and their manufacturing has not yet been started. 
The common denominator for these deliveries is the same designer and manufacturer. 
The background information of both deliveries and the progress of the deliveries so far 
are described briefly below. 
 

 
3.3.1  Background information on polar crane and material hatch 

Contractual parties responsible for the manufacturing of polar crane and material hatch 

The parties to the contract were the plant vendor (Framatome ANP, FANP) and the 
structural designer and manufacturer of the polar crane and the material hatch (Eiffel). 
 

General information on the company 

Eiffel is part of the Eiffage Group and employs 1060 people. The company specialises 
in the manufacturing of large-scale steel structures, such as bridges, locks, towers and 
pressure vessels. Polar cranes represent only a small part of the product range. The 
polar crane and the material hatch will be manufactured in Lauterbourg near Strasbourg 
and designed in Colombes, Paris. 
 

Requirements specified for polar crane and its construction  

A so-called polar crane will be installed in the top part of the reactor hall at the 
Olkiluoto 3 nuclear power plant unit. There are tens of cranes in use at the nuclear 
power plant, but only the cranes used in the transfer of nuclear fuel or in other safety 
significant lifting operations are under special control of STUK. The polar crane is one 
of these, and it is assigned to safety class 3.  
 
Due to the circular shape of the reactor hall, the crane construction must also be 
designed with a special rotating crane bridge. A rail is mounted in the top part of the 
wall construction in the reactor hall, and the crane bridge will rotate on this rail. 
Because of the movement that differs from that of a normal gantry crane, cranes of this 
type are referred to as polar cranes.  
 
The span of the polar crane bridge is 44.3 m and the maximum capacity of the main 
lifting gear is 320 tons. There are two smaller lifting gears in the crane, as well (35 t 
and 5 t). 
 

Selection of polar crane designer and manufacturer 

Four potential polar crane suppliers were indicated in the Main Contract. FANP invited 
tenders for detailed design and manufacturing from three Central European companies 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 37 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

and one Finnish company. The French company Eiffel was selected as the supplier. 
Eiffel is on FANP’s list of approved suppliers. 
 
Eiffel's engineering works in Lauterbourg produces great numbers of large-scale steel 
structures, and the manufacturing of a unit the size of polar crane does not differ much 
from their production in general. This company has experience in the manufacturing of 
polar cranes for nuclear power plants. The most recent delivery was in 1998 to a 
Chinese nuclear power plant.   
 
In the call for tender, Eiffel was required to include IAEA's safety requirement 50-C-
QA [6] or the requirements of some other nuclear standard in their quality system or in 
the project-specific quality plan, since the polar crane and the material hatch are safety 
classified equipments. According to FANP, Eiffel has been qualified pursuant to 
FRA/N/100E/OL3. The quality system of the manufacturer carries the ISO 9001:2000 
certificate. In addition, nuclear standards are included in project specifications as 
requirements. 
 

Progress of the polar crane delivery 

The project specification of the polar crane was approved (20.12.2005) by a decision of 
STUK, which contained eight admonitions. The admonitions mainly concerned 
consideration of standards and regulations, and their updating in the project 
specification and in its requirements.  
 
The construction plan of the polar crane was in mid-March 2006 in approval review 
between TVO and Framatome, but had not yet been submitted to STUK for approval.  
 

Requirements specified for the material hatch and its construction  

The diameter of the material hatch located in the reactor hall is 8.3 m. The lock is 
opened by lifting it up along rails. The material hatch is used during annual outages and 
repair shutdowns to transport large equipment into or out of the reactor hall. The 
material hatch, together with the steel liner as a whole, is assigned to safety class 2. 
 

Selection of material hatch designer and manufacturer 

Five potential material hatch suppliers were indicated in the Main Contract. FANP 
invited tenders for detailed design and manufacturing from four Central European 
companies and one Finnish company. The French company Eiffel was selected as the 
supplier.  

 

Progress of the material hatch delivery 

TVO audited Eiffel in mid-March 2006, and the questions connected with the material 
hatch were dealt with in this context. At the time, the design of the material hatch had 
proceeded to almost half way.  
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 38 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

3.3.2  Observations in connection to acquisition of polar crane and material hatch 

Quality management implemented by FANP  

FANP audited Eiffel's design activities in December 2005 and the factory in March 
2006. In other words, in this case FANP audited both the design and the manufacturing 
organisation. However, the audits were late, as they were conducted about a year after 
the project had started. No significant remarks were made in FANP's audit of the design 
activities.  
 

Audits performed by TVO on Eiffel 

TVO performed an audit on Eiffel on 14.-15.2.2006. The purpose was to assess Eiffel's 
design, manufacturing and quality management activities, and other preconditions for 
operation. Activities related to design were assessed in Paris and issues connected with 
manufacturing in Lauterbourg.  

 

The audit produced 12 recorded findings and 8 recommendations. The findings and 
recommendations were focused primarily on the safety culture, manufacturing methods 
and meeting practices.  
 

At the time of the audit, the design organisation had worked on the OL3 project for 
about a year. The construction plan for the polar crane was being examined by TVO 
and FANP, but has not yet been submitted to STUK for approval. It was also 
established during the audit that about half of the design work for the material hatch 
had already been completed, but the engineering works did not have reports of design 
review meetings available for inspection. Eiffel had understood that independent 
reviews of the design activities could be realised by organising weekly meetings of the 
technical design team. 
 
IAEA's safety standard 50-C-QA or some corresponding requirement had not been 
taken into consideration in the quality system. According to the information received in 
the audit, Eiffel had not been informed of the requirement. Two non-conformancies 
related to this observation were recorded in the audit; one of them concerned safety 
culture training to personnel involved in the OL3 project. 

 
The other non-conformancy that concerned forwarding of safety requirements was that 
Eiffel did not have STUK's decision on the project specification (29.12.2005). Also, the 
supplier had old versions of YVL Guides 1.4 [2] and 5.8.[12]. In the project 
specification, compliance with renewed versions had been required. A recommendation 
connected with this was that all the applicable YVL Guides shall be made available to 
all the employees in electronic form, e.g. in the company's intranet system. 
 
As factory facilities are not particularly clean, it was recommended that the facility in 
which I&C and electrical components are installed should be separated from the other 
production facilities due to dirt and dust. The other recommendations concerned 
harmonising the acquisition of outsourced components, clarifying the procedures for 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 39 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

acceptance of incoming material, and including change management procedures in the 
quality plan. It was also recommended that Eiffel conduct an internal audit focusing on 
the OL3 project.  
 
The audit also revealed several deficiencies in the practices of the engineering works, 
such as incorrect use of a hoisting hook for lifting plates. The calibration dates of some 
equipment and welding machines had expired. Deficiencies were also found in the 
quality control of welding materials and filler metals. Heat treatment specifications 
were not available in the heat treatment room.  
 

Eiffel's design and manufacturing organisations have initiated measures to implement 
corrective action on the basis of these non-conformancies, and the safety of the nuclear 
power plant under construction has not been considered to be endangered in this case. 
 

Conclusions 

The result of the audit conducted by TVO on Eiffel confirmed the impression that 
TVO's audits are more detailed and produce more findings than FANP's audits. Along 
with the other examples, this case also showed that the special requirements that are 
applied in the nuclear field are not properly forwarded from the plant supplier to the 
subcontractor.  

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 40 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

4. MANAGEMENT OF THE OL3 CONSTRUCTION PROJECT AND QUALITY 
MANAGEMENT  
 
4.1 Management systems  

 The main parties to the OL3 project are the licensee TVO who has ordered the OL3 
nuclear power plant unit and the power plant vendor CFS that is a consortium formed 
by Framatome ANP (FANP) and Siemens GmbH. The reactor island will be supplied 
by FANP. The main focus of this investigation has been on the performance of FANP 
with the exception of activities and findings that clearly relate to the whole consortium. 
In these cases the whole consortium is referred to in the text.  

 

4.1.1 TVO’s management system and cooperation with FANP  

TVO’s role  

In the OL3 project plan, TVO defines its own role as follows: 

“The OL3 project is 

responsible for project management and for coordinating and supervising all the works 
and services related to it. Particular effort is directed to safety culture and quality 
management”

. TVO as the Construction License holder is responsible for assuring 

safety and quality at the power plant under construction.  
 
The OL3 safety and quality culture management process described in the TVO’s 
quality system is applied only to TVO’s own organisation. For example, it describes the 
assessment of the operations of TVO's own personnel. The creation of safety and 
quality culture in the supply chain and in the construction organisation takes place 
indirectly, since the plant vendor is responsible for construction and for the selection 
and management of the subcontractors that participate in construction.  
 
 In the Main Contract, TVO has transferred the responsibility for licensability to CFS, 
as well as the implementation of the works, the selection and management of 
subcontractors and the site management. In practice this means that after the handover 
of the site in February 2005, TVO does not communicate directly with the 
subcontractors, except for TVO's audits and control activities. In all other respects TVO 
receives information about the progress and the quality of the subcontractors' work 
through the consortium, and STUK, in turn, receives this information from TVO.  

  
Quality management  

The quality policy of the OL3 project clearly emphasises the key significance of quality 
management to the successful implementation of the project.  
 
Quality management in the OL3 project is organised to be a part of the management 
activities and it is divided into quality control (QC), on one hand, and quality assurance 
(QA), on the other hand.  
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 41 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

There are 12 permanent employees in the quality management unit of the OL3 project; 
eight of them are quality assurance engineers. In addition there are external part-time 
QA engineers and auditors. Further, the OL3 project QC team for plant technology 
engineering consists of altogether nine people, part of them working as inspectors in 
the manufacturing locations. The OL3 project QC team for construction technology 
engineering comprises 13 people. TVO ensures the quality of construction and the 
equipment by means of audits of organisations’ activities performed by the QA staff, as 
well as by inspections and quality control of structures and equipment carried out by 
the QC officers.  

  
Training  

Introduction training organised by TVO is only provided to TVO's own personnel and 
consultants employed by TVO on a regular basis. Introduction training and other 
guidance provided by TVO is the key channel in providing basic knowledge and safety 
culture of the nuclear field to the personnel involved in the OL3 project. Training has 
been designed presuming that the personnel employed by TVO for the OL3 project 
primarily comes from outside the nuclear field. It takes time before a clear 
understanding is reached in the OL3 project of the safety principles to be complied with 
in the construction and operation of a nuclear power plant, and of the roles of the 
various organisations. Opinions were expressed in the interviews that STUK was at this 
stage considered as part of safety assurance mechanisms.  
 
According to the interviews, an important objective in the training provided to TVO's 
own OL3 personnel is that CFS and its subcontractors can be supervised in a consistent 
manner. On the other hand, safety training directed to the subcontractor's employees 
was not emphasised by the OL3 management. On the contrary, some interviewees 
expressed opinions that it is impossible to define a training material that all the parties 
involved in the project should understand. Furthermore, some interviewees were also of 
the opinion that the special characteristics and the rules of the nuclear field are obvious 
to all involved and need not to be separately communicated.  

  
Supervising CFS and its subcontractors  

Any non-conformancies found as a result of TVO's quality control or quality assurance 
or in connection with some other activities are each recorded in a specific 
non-conformance report, and reported to CFS. In other words, non-conformance 
reporting is the most important tool of the quality system that can be used to deal with 
any problems detected in transferring safety requirements or in technical quality.  
 
In the interviews, the OL3 project management was asked what the key mechanisms 
are for transferring safety and quality culture to the supply chain and to the construction 
organisation. According to the interviewees, the key mechanisms for creating or 
transferring safety and quality culture to the plant supplier and its subcontractors 
include supervision and reaction to non-conformancies. In other words, TVO's 
operating model appears to be based on a belief that CFS and its subcontractors will 
during the project learn to fulfil the strict requirements of TVO and the authorities, 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 42 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

which are specified in various meetings and audits, in the review of design 
documentation and in construction inspections.   

 
TVO's participation in selection of subcontractors  

The procedures for the selection of suppliers and subcontractors in the OL3 project are 
for TVO's part described in Chapter 7.4 of the OL3 quality manual, "Purchasing". The 
quality manual is part of TVO's management system.  The Main Contract for supplying 
the plant concluded between TVO and CFS also discusses issues connected with the 
selection of suppliers.  
 
At the subcontractor selection stage, TVO has the opportunity to draw attention to the 
requirement that preconditions for fulfilment of quality and safety requirements are 
verified in the selection process.  
 
CFS guidelines describe how information is provided to TVO and how TVO can 
influence the selection of subcontractors. For minor purchases, CFS informs TVO 
about the sending calls for tenders case by case or on TVO’s request. For minor 
purchases, TVO may recommend some subcontractors to CFS. CFS takes the 
recommended subcontractors into consideration in the tender competition, provided 
this does not significantly delay the process. TVO is informed about the selected minor 
suppliers in the monthly reports.  
 
For major purchases, CFS informs TVO before the tender invitations are sent to 
potential suppliers as well as after the selection of the supplier. TVO is provided the 
opportunity to influence the content of the tender invitation and the selection of the 
supplier but in certain cases TVO has to pay for the requested change of supplier.  

 

4.1.2 CFS management system  

CFS’s role  

CFS is responsible for the licensability of the OL3 plant, implementation of the project, 
selection and management of subcontractors and site management. Each of the 
consortium partners deals with its own area of the scope of the delivery. FANP is 
responsible for the reactor island structures and equipment on which this investigation 
focuses, and Siemens for the turbine island. CFS is responsible for transferring the 
technical safety requirements to its subcontractors. The responsibility for the selection 
and management of subcontractors entails that CFS is also responsible for explaining 
the safety relevance of their work for all the companies and every individual involved 
in the construction of OL3.  

 
Quality management  

The quality management model of the OL3 project comprises several steps, starting 
with the quality assurance programme of CFS and the quality policy of FANP, and 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 43 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

ending with the quality management procedures that the subcontractors are required to 
follow.  
 
FANP's general quality management system (Plants QEM Manual Rev. F, Jan 2005) 
emphasises the particular importance of quality management to the successful 
implementation of the project. Quality policy emphasises the independence of the 
Quality and Environmental Management Unit of other project units, its authority to 
verify compliance with the agreed procedures and its authority in all situations that 
might endanger quality.  
 
The quality procedures of CFS that concern purchasing also describe practices for the 
monitoring of agreements and deliveries. These procedures specify that the ability of 
the supplier to deliver the agreed products is controlled continuously and that any 
deficiencies detected are immediately reported to the supplier. All significant 
observations are also communicated to TVO. The monitoring of fulfilment of 
contractual obligations includes control of e.g. quality, compliance with technical 
specifications, compliance with agreed quality assurance procedures, keeping to the 
schedule as well as commercial and contractual questions.  
 
Non-conformancies are in terms of their handling divided into technical, contractual 
and process non-conformancies. Process non-conformancies are handled following the 
procedures presented in the quality assurance programme of the CFS partners.  
 
Quality management at the plant site and its performance are described in the site 
procedures.  
 
FANP's quality assurance organization (SE-G) includes about 50 employees, 13 of 
whom are involved (perform audits) in the Olkiluoto 3 project. Their practical tools are 
the same as those of TVO's corresponding staff; non-conformance reports that call for 
corrective actions and that are used to monitor the implementation of such actions.  
 
According to the views expressed by FANP's representatives, safety is created as a 
result of good quality, and safety culture refers to compliance with the quality system. 
However, a "safety culture programme" has been under development at FANP since 
2004. It is a training program targeted at FANP's top managers. Employees involved in 
the OL3 project and the site management have not yet been covered by this training 
programme.  

 
Training  

After the handover of the site, the plant vendor has been responsible for the site 
introduction training.  The content of this training focuses on occupational safety. The 
introduction training has not specifically emphasised the significance of work to the 
safety of the nuclear power plant under construction, or the quality and quality control 
requirements arising from safety significance, or how it influences the practices. The 
general principles to be followed in order to ensure the safety of a nuclear power plant 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 44 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

have not been presented in the introduction training, either. However, in April 2006 the 
content of the introduction training was supplemented with knowledge content 
designed to promote safety culture.  

 
 Selection of subcontractors  

The purchasing procedures followed by CFS in the OL3 project and the practices for 
the selection of subcontractors are clearly described in the quality systems of both CFS 
consortium partners and in the OL3-specific quality plan.  
 
The criteria defined by CFS for the selection of subcontractors include references from 
similar deliveries, experience of the CFS partners of the supplier from previous projects 
and contracts (including TVO's experience if available), the CFS partners' own 
assessments (based on audits, if necessary), quality certifications, technical expertise 
and ability to implement the project, capability for fulfilling safety requirements, and 
technical properties of the equipment compared with the technical requirements. CFS 
also ensures that the subcontractors apply similar criteria in the selection of their own 
subcontractors.  
 
The documents to be included in the tender invitations are defined in the consortium's 
guidelines. OL3-specific procurement and delivery terms must be included in the 
tender documents. They also describe how subcontractors shall be required to take 
nuclear field specific and OL3-specific requirements into consideration, including 
relevant YVL Guides.  

 

4.2 Assessment of management and quality management  

4.2.1 General observations  

Reasons for and consequences of schedule delays  

Controlled implementation of the OL3 project and keeping to the schedule have been 
hindered by the slow completion of detailed design in relation to how fast the 
constructors and the equipment manufacturers could act if the plans were available in 
time.  
 
When the Main Contract for the plant supply was signed and the Construction License 
was applied for, the basic design of the plant had been completed and the technical 
requirements for the systems had been specified. This means that the lay-out of the 
buildings, the main features of the systems (e.g. the pressures, temperatures, flows for 
process systems, main pipelines and valves, pressure vessel dimensions, and technical 
requirements for pumps) and the locations of the systems in the buildings had been 
defined almost to the final extent. In other words, design had proceeded so far that it 
had been possible to make the required safety analyses and practical preparations for 
the construction project could be started, including equipment purchases and site 
preparation.  
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 45 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

Detailed design (e.g. dimensioning calculations for determination of required concrete 
strengths and reinforcement as well as final site drawings) had not been carried out, and 
the time and the amount of work added for accomlishing the design had clearly been 
under-estimated. An additional problem was caused by the fact that the plant vendor 
was not familiar with the Finnish practices. According to the Finnish requirements, the 
detailed design of the safety cassified systems, structures and equipment is inspected 
both by TVO and STUK. Designs and plans must be approved by all involved parties 
before the manufacturing of equipment and components or structures at site can be 
started. The attempts to keep to the schedule, which had been unrealistic from the 
beginning, has required extra work and thereby further delayed and impeded the 
progress of the project.  
 
According to STUK's experience, the documentation submitted by TVO’s OL3 project 
to STUK is sometimes of poor quality and inspectors are invited to perform 
construction inspections on systems or structures for which the approval of design 
documentation or the quality control documentation has  not yet been completed. Even 
if the situation has improved as the project has progressed, it still appears that due to 
deficient resources and tight schedules TVO is not able to review all the design 
documents with a sufficiently questioning attitude.  
 
The incompleteness of detailed design even at the time of the investigation, and the 
delaying of the construction schedule primarily for this reason, make the overall 
management of the project extremely demanding.  

 
Impact on safety  

TVO's representatives emphasised in the interviews that problems in manufacturing of  
the equipment and in construction only concern the project schedule, and nuclear safety 
has not been endangered because of them. According to TVO’s project management, 
the large number of non-conformancies first of all reflects the accuracy of TVO's 
control activities. Finnish preciseness and attention to details are of a level, which the 
plant vendor did not expect.  In other words, this is a cultural difference, a difference in 
expectations.  
 
The impression obtained during the investigation about the safety impact of the 
non-conformancies is in main parts similar to the view presented by TVO's 
representatives. No compromises have been accepted in the required quality level and 
the tests and inspections that have been performed have proven that this level has been 
achieved, although in some cases only after several corrections.  

 

 

Safety culture  

The case studies seem to indicate that TVO's supervision activities have not reached 
their goal to institute a high-level safety and quality culture in the supply chain and the 
construction organisation. Although an abundance of technical non-conformancies have 
been identified in the manufacturing of different equipment, components, and in 
construction as well, and these have been recorded in non-conformance reports, the 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 46 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

observations made during the investigation show that the plant vendor and its 
subcontractors have not essentially improved their working practices or attitudes 
toward safety. The striving for performance that is careful and faultless to the extent 
possible, as required in the nuclear field, and an open disclosure and prompt 
elimination of non-conformancies have not been emphasised in a clear manner in the 
supply chain.  
 
The investigation showed that in the OL3 project so far there is no clear and commonly 
shared view of what is important at the construction stage for the achievement of the 
safety objectives, and how widely and intensively safety awareness should be 
promoted. According to the opinions expressed in the interviews by TVO's and FANP's 
OL3 project personnel nuclear safety can be ensured by verifying the correct technical 
quality of safety class 1 and 2 equipment, components and structures. Activities on the 
site are generally considered to be non-safety relevant. The role of TVO's safety 
committee has remained quite remote in addressing the non-conformancies found in the 
performance of the parties involved in construction and in discussing safety culture 
issues.  
 
During the investigation it was noticed that the responsible performance required in the 
nuclear field is not self-evident to all employees working on the construction site and in 
the manufacturing organisations. Even strive for flawlessness of one's own work can 
not always be seen, let alone care for the best possible preconditions for others to 
succeed in their work.  

 

 

Quality management  

In general,  the supervision of construction work and equipment manufacture seems to 
have been implemented in the project as planned, and both TVO and the plant vendor 
employ competent persons for this in their organisations. Non-conformancies are 
recorded carefully and their correction is being monitored.  The independent role of 
quality management comes true in this respect. On the other hand, the quality control 
organisation's authority, excutive power and courage to immediately intervene in any 
detected non-conformancies demanding their timely repair do not appear to be 
sufficient.  
 
According to the observations made in the investigation, there is no clear practice for 
the handling of products that do not conform to quality requirements. The ISO 9001 
standard requires that there is a clear procedure for the dealing with non-
conformancies, and the responsibilities and authorities for that have been defined. In 
the OL3 project it is unclear which organisation and person is in different cases 
responsible for the approval of a product not conforming to the specification, and how 
the approval is issued in practice. According to the quality system the designer defines 
the quality requirements for the product, and the production these requirements. In 
some cases the designs are submitted to TVO and also to STUK for approval, and if  
they are changed, the approval procedure has to be repeated. No evidence was found in 
the investigation of this procedure being followed in the case of the bottom part of the 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 47 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

steel liner. Instead, some interviewees mentioned that "the tolerances specified by the 
designer were too tight". According to information received from the consortium's 
Quality Manager, in many cases the specified quality cannot be realised in practice and 
the specification is changed instead. This may be a realistic procedure and acceptable 
as such, but the acceptability of the specification change should still always be proven 
and the related documents examined at the same level that granted the original 
approval.  
 
An examination of audit reports indicated that TVO's auditors had recorded several 
findings concerning safety culture and the lack of related training. No corresponding 
findings had been recorded in audits performed by FANP. All in all, there is a 
consistent difference in the number of findings made in the audits performed by FANP 
and TVO in the same location, with TVO's audits always producing more findings.  

  
Training  

The so-called safety culture training to all those participating in the plant delivery, as 
stipulated in IAEA regulations and in discussions between STUK and TVO, has in 
practice not been provided in most cases. One expert of TVO's quality organisation 
stated in the interview that, as far as he knew, this training had not been provided in any 
organisation. It has not been defined what the content of the training should be and who 
should be responsible for its provision. It has not been defined either what level of 
knowledge of the specific requirements of the nuclear field the employees of the plant 
vendor and its subcontractors should possess.  

 
Language problems  

In practice the project language is as a rule English although in some subcontracting 
agreements the language is defined as the language of the subcontracting company. Not 
all parties (e.g. subcontractors) are proficient enough in English to make it certain that 
everything is fully understood.  
 

4.2.2 Observations concerning TVO  

Relationship with plant supplier  

The OL3 management emphasised in the interviews that in the assessment of their role, 
it should be borne in mind that this is a turn-key delivery whereby they have to trust the 
plant supplier and allow it to do things in its own way without too much disturbance. In 
the investigation team's opinion this is not the correct attitude. TVO must control that 
the plant vendor's obligations are fulfilled and the plant vendor also assures the quality 
of the subcontractors' work.  
 
At this stage of construction there has already been many harmful changes in the 
vendor’s site personnel and even the Site Manager has retired and replaced. This has 
made overall management, as well as detection and handling of problems difficult. The 
transfer of responsibilities in such situations has been unclear to all the actors. It is not 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 48 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

clearly stated neither in the joint documents of the parties nor in the project manuals of 
the parties what kind of possibilities TVO has to make certain that appropriate 
measures are employed to ensure stability in FANP's site organisation and that the staff 
is capable of fulfilling their responsibilities and obligations.  

  
Management and promotion of safety culture  

As the holder of the Construction License, TVO is responsible for all issues related to 
safety and quality, and cannot assign this responsibility to the plant supplier or any 
other party by any kind of contract or agreement. A perception of STUK's key role in 
ensuring safety came up in the interviews, but this interpretation must not reduce 
TVO's own responsibility for safety.  
 
The principle of continuous improvement of operation and safety has been adopted at 
TVO's operating nuclear power plant units, but the OL3 project is somewhat separate 
from the operational plants and TVO's traditional culture. TVO's own organization also 
includes a large number of personnel in the OL3 project that has come from outside the 
nuclear field, and appreciation of the safety culture is not yet complete in the project 
organization.   
 
In the OL3 project, TVO's management does not seem to pursue determined 
communication to the actors outside their own organisation with the aim of developing 
a high-level safety culture in the entire construction project. TVO considers the 
responsibility for construction to rest with the plant vendor, with TVO's own focus 
being on commissioning and the operating stages after that.   
 
The interviews gave an impression that inside TVO the schedule-related questions 
connected with organising construction work are the most important issues in handling 
of OL3 project matters. The pressure to keep to the schedule is probably hard for 
TVO's technical experts, as the plant vendor's plans are submitted late and the 
schedules do not allow enough time for their evaluation. It seems that evaluation of the 
design documentation submitted by the plant vendor cannot in all cases be carried out 
with the required accuracy and a questioning attitude. As a result, documentation of 
poor quality is forwarded to STUK. The investigation showed that problems are easily 
multiplied when the plans have been deficient and STUK requires them to be corrected. 
This also involves the risk that problems are not detected, or tackling them at a later 
stage will cause considerable problems if TVO has approved deficient documentation. 
TVO should in situations like this possess enough its own expertise and resources so 
that essential unclarities in the designs can be tackled effectively.  
 
Good safety management entails identification of also weak signals and prevention of 
problems. In the management of the OL3 project main focus has been on solving 
detected problems, however, and no evidence was found of a proactive approach. It 
was not clear even to the responsible management what the potential signals could be 
that would require initiation of preventive action.  
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 49 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

The prevailing perception in the OL3 project about safety and the actions needed to 
ensure safety focuses strongly on the technical quality of safety classified systems, 
stuctures and equipment. TVO audits the plant vendor and its subcontractors in a 
systematic manner, but the way in which TVO intervenes in problems or forecasts 
problems with various parties is not well defined. Within TVO the responsibility for the 
handling of deficiencies in the performance of the subcontractors has been distributed 
in a complex quality organisation, and the individuals and the committee that are 
responsible for safety evaluation do not handle the deficiencies observed in 
performance. In the light of the investigated sample cases, issues connected with the 
quality and reliability of the performance of the plant vendor and its subcontractors are 
handled slowly.  
 
An important factor of safety culture is open disclosure and handling of 
non-conformancies and other problems. TVO has not emphasised the principle of 
openness outside its own organisation, and therefore information about events has not 
in every case been openly communicated to TVO and further to STUK. Only TVO 
employees can record non-conformancies in TVO's KELPO system. According to the 
interviewees, this anonymous mail box system is mainly designed for situations 
endangering occupational safety. The problem with concrete showed that there are no 
tools to bring non-conformancies out, unless enough evidence exists for a 
non-conformance report.  

 
Dealing of non-conformancies and supervision of subcontractors  

TVO has a limited insight of what is happening in the subcontractor network and what 
kind of problems are encountered. The audits are TVO's only direct contact with the 
subcontractors, otherwise interaction with them takes place through the plant vendor. 
Audits are performed both by TVO's own QA and QC engineers and by QC consultants 
employed by TVO. Their responsibility is restricted to the recording of non-
conformancies and to the monitoring of the closing of non-conformancies. TVO's 
representative reacts to every non-conformancy – whether a major or a minor 
non-conformancy – by drawing up a non-conformance report, an NCR report, which is 
submitted to the consortium. It is up to the consortium to decide whether the report is 
presented to the subcontractors. Not all reports are presented to the subcontractors, so 
the procedures for the handling of non-conformancies are deficient in this respect.  

 

On the basis of the interviews, it appears that the quality personnel of TVO has not 
understood that in unclear situations they have the right to suspend work and receive 
the quality data that they need.  
 
Even in cases where the procedure defined in the quality system for the handling of 
non-conformance reports is precisely complied with, it is questionable whether 
corrective actions are taken at the stage that from the point of view of the final result 
would be the best for their implementation. The reason for this is the large number of 
NCR reports and the long time that their distribution and handling takes. During the 
investigation there were some 700 open non-conformancies. When a subcontractor is 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 50 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

found to have a quality problem, the non-conformance report drawn up during the audit 
is sent from the TVO's auditor to the plant supplier, who forwards it to the 
subcontractor and in many cases it is forwarded still further in the subcontractor chain. 
If the observation is made by STUK, yet an additional step is inserted to this path. In 
other words, just writing non-conformance reports is not enough, but TVO must in a 
determined manner ensure that they lead to corrective actions in time.  
 
A concrete demand made by TVO has been that the quality personnel of the consortium 
should be expanded so that the numerous open non-conformancies could be handled 
faster. At the time of the investigation the consortium was trying to increase the number 
of personnel in quality control by making persons working in other projects available to 
the OL3 project.  
 
During the investigation, it turned up that in some cases TVO's quality controllers had 
assumed a guiding role in supervising the work of a subcontractor that had displayed 
poor quality. This is not the correct procedure, either, as the consortium is responsible 
for the guidance and supervision of subcontractors, while TVO is responsible for 
ensuring that this obligation is fulfilled.  
 
TVO has not conducted any systematic analyses of non-conformancies, their types and 
possible common denominators. However, the management of the OL3 project has paid 
attention to the fact that many non-conformancies are repeated from one subcontractor 
to the other. For example, the forwarding of the nuclear field specific and technical 
safety requirements from the consortium to the consortium's subcontractors has been 
deficient in some parts. The consortium seems not to have learned their lesson from 
TVO's previous remarks when they start cooperation with a new subcontractor.  
 
All in all, it is unclear what TVO's means are for verifying that the plant vendor 
systematically verifies the achievement of the required quality level and that the 
performance of subcontractors is of high quality.  

 
Selection of subcontractors  

In the case of a fixed-price contract it is to be expected that money becomes the most 
important criterion in the selection of a subcontractor. TVO has limited possibilities at 
the selection stage of subcontractors to control that quality and safety criteria are given 
a sufficient priority. In practice, if the subcontractors that submitted a tender meet the 
agreed criteria but TVO refuses to approve the lowest price subcontractor with as 
proposed by FANP, TVO has to pay a separate compensation for changing the 
subcontractor. On the basis of the investigated sample cases it was obvious that quality 
and reliability criteria were not always the first priority in decision-making when 
selecting subcontractors.  

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 51 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 
 

4.2.3 Observations concerning FANP  

FANP's organisation and its performance in OL3 project  

In the organisation of  FANP which is an alliance of a French and a German company 
the different organisational cultures can still be distinguished. The OL3 project is the 
first large joint project for the former competitors. As the project also involves 
consortium cooperation between FANP and Siemens the situation is challenging for 
these big international companies. It is also a new thing that the plant vendor has 
assumed overall responsibility for the project.   
 
Although FANP is an experienced vendor of nuclear power plants, in previous projects 
it has assigned the responsibility for construction to other organisations and is therefore 
rather inexperienced as a constructor. The logistic layout of the construction site, the 
contract boundaries and the control of suppliers differ from equipment and component 
supplies. In addition, delays in the construction schedules and the postponement of 
works to another season have created significant additional challenges to total 
management. The incompetence in the constructor role becomes obvious in the 
preparations for concreting of the base slab.   
 
The impression obtained in the interviews was that the structure of the site 
organisation, responsibilities and practices are still unestablished. The structure of the 
organisation has changed several times and some of its management level employees 
have been replaced. Some of the consortium's managers are leased employees. These 
factors reflect in the total management of the project in a negative way. There is 
confusion both among the consortium's own site personnel and among the 
subcontractors about responsibilities.   
 
The weakness of internal communication in the consortium as well as unclear 
responsibilities and authorities in tackling non-conformancies have become apparent 
particularly during the concreting of the base slab for the reactor building. Even inside 
the consortium only a small group was aware of the problems. Despite requests, the 
management of the site organisation has been reluctant to submit e.g. the results of 
concrete mix analyses to TVO. Neither have they submitted the preliminary quality 
control results that indicated non-conformancies to the quality management of the 
consortium, nor to the management in Germany that is responsible for the control of 
subcontractors.   
 
The consortium has a habit of employing new people for problem solving, which seems 
to have resulted in even more confusion about responsibilities. This was the case, for 
example, with the regulation of the workability of concrete when the consortium hired 
an outside concrete expert to the batching plant to carry out the fine adjustment of the 
composition. A new person was also recruited to handle contractual problems, and he 
was obviously given the authority to override the decisions of the site management.  

  

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 52 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 
FANP’s safety culture  

With FANP's long experience in nuclear engineering, it could be assumed that the 
company has a clear safety policy and safety management philosophy.  Instead, only 
the consortium management is so far being trained in safety culture issues.   
 
FANP tries to meet the safety requirements specified by TVO and STUK, but seems 
not to emphasise the fact that nuclear safety should be prioritised already in activities 
during construction and manufacturing. In the interviews, representatives of FANP 
were of the opinion that safety culture is a new name for an old thing. According to 
them, safety and safety culture mean compliance with the quality system.   
 
FANP has not actively and systematically focused efforts on ensuring that the 
subcontractors understand the special features of the nuclear field and the resulting 
requirements concerning work practices, such as e.g. the striving for the best possible 
result, open disclosure of non-conformancies and discontinuation of work if unclarities 
that might influence safety are detected. According to the interviewed representatives 
of the consortium, responsibility for the training of these matters does not rest with 
them. The personnel of the consortium have not proven in their own performance either 
that they understand their responsibility for and authority to intervene in problems, nor 
have they followed the principle of informing about non-conformancies. The most 
serious problem in the handling of non-conformancies revealed in the investigation was 
the quality control report that concerned the concreting of the reactor base slab the 
results of which were available already in November 2005. Effective actions on the 
basis of the report, however, were not taken until in 2006.   
 
There is no clear evidence of TVO's attempts to educate the consortium about the 
principles applied to the nuclear field in Finland or about the safety culture that TVO 
strives to create. According to the interviews, the perception of the representatives of 
FANP concerning management of safety requirements is that they act in this project in 
the same way as in all their other projects, and this is their principle. The public debate 
on safety culture training, raised up in connection with the re-start inspection of 
Forssan Betoni exercised the minds of the FANP representatives. According to the 
persons responsible for FANP's quality management, the requirement for a high safety 
culture that STUK and TVO had put forward had been surprising. The interviewees 
stated, among others, that as safety culture is a concept usually associated with plants 
that are in operation, it has been difficult for them to understand what it could mean at 
the construction stage.   
 
Due to the problems encountered in the sample cases FANP has made communication 
in the non-conformance handling process as a development priority, but sees no reason 
to develop in any other way the procedures employed in the selection and supervision 
of subcontractors.  

  

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 53 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 
 
Selection, training and supervision of subcontractors  

At times, there have been deficiencies in the forwarding of the nuclear field specific 
requirements and technical safety requirements for the OL3 project from FANP to the 
subcontractors. Essential requirements that affect quality and the possible additional 
costs caused by these requirements have not been clearly communicated to the potential 
subcontractors at the call for tender stage. FANP management says that for them the 
problem has been that if strict requirements or special requirements are specified for a 
delivery, companies are not willing to submit tenders in the present market situation 
considering the minor volume of nuclear power construction.   
 
The investigation showed that the procedures described in FANP's quality 
specifications for the selection of subcontractors are not always followed in practice. 
For example, the consortium has not systematically paid attention to whether the 
subcontractors are capable of meeting the requirements of IAEA's safety standard 50-
C-QA. The investigation seems to indicate that the subcontractors' safety and quality 
culture has been noted mostly in TVO's audits.  
 
In the case of a fixed-price contract, it is to be expected that the most important 
criterion in the selection of a subcontractor is the price.  In the case of the steel liner 
supplier, for example, price has been a more significant criterion than technical 
competence. It appears that the consortium can select a more risky but lower cost 
subcontractor, believing that the strict control exercised over the subcontractors during 
the project will make them develop their performance. This kind of strategy is in 
contradiction with the quality policy described in FANP's guidelines. The 
subcontractors' operating cultures change very slowly (just as in all organisations). 
However, suppliers that could provide sufficient quality already at the start of 
cooperation have not been favoured in the selection of subcontractors.   
 
The interviewed representatives of the consortium made it clear that in their opinion 
there was no need to develop the selection procedure of subcontractors because of the 
problems encountered, for example, with concrete or with the manufacturing of the 
containment steel liner. However, they could not give a clear view of why these cases 
involved such a large number of non-conformancies in terms of quality and 
performance.   
 
The consortium mainly intervenes in the performance of the subcontractors only if 
technical quality problems are detected or if non-conformancies are found in TVO's 
audits. It seems that proactive prevention of problems is not working.   
 
The interviews gave an impression that responsibilities in the investigated example 
cases were most unclear. It was a repeated feature that the interviewees had presumed 
that some other party had noted, dealt with or informed about the problems. Still, the 
interviewees did not see any strong need for developing the practices employed for the 
management of subcontractors.   

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 54 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

 
TVO's subcontractor audits have revealed non-conformancies that clearly predict 
problems in manufacturing. FANP's ability to eliminate such non-conformancies prior 
to the start of manufacturing has been poor. The interviews brought up many reasons 
for this:  
 

-

 

The number of subcontractors is large and FANP is not in practice capable of 
exercising true control of the competence and quality of work of all its 
subcontractors.  

-

 

Economic objectives are emphasised at the contract stage and quality issues 
are usually brought up only after manufacturing has started.  

-

 

FANP relies on TVO and STUK to handle any deficiencies.  

-

 

FANP is not familiar with the characteristic features of construction business.  

-

 

The site organisation of the consortium is confused and authorities to deal with 
problems are not clear.  

-

 

Because FANP is experiencing schedule-related pressures the subcontractor's 
preconditions to meet the quality requirements are not always subjected to a 
critical assessment.  

 
The investigation team got the impression that FANP does not prioritise nuclear safety 
over financial and schedule-related objectives. Safety is not the number one guiding 
factor in e.g. the selection of suppliers, content of agreements, selection of tools and 
materials. When minimum criteria are met, FANP seems to select cheaper suppliers 
despite bigger quality risks. FANP does not always enter safety-related requirements in 
the supplier's agreements, but tries to deal with them without incurring any costs. Due 
to the tight cost limits and delays in schedules subcontractors are not willing to meet 
afterwards additional requirements that exceed those specified in their agreements. On 
the other hand, delays in schedules result in more financial pressure.  

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 55 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 
5. STUK'S OPERATION AS REGULATOR OF NUCLEAR POWER PLANT CONSTRUCTION 

 
5.1 Oversight system and implementation  

Both the use of nuclear power and the construction of nuclear power plants are subject 
to licence. The licence applicant or holder can apply from the Government the Decision 
in Principle to launch a nuclear power plant project, the related Construction License 
required for its implementation and the Operating Licence required for its operation.  
 
Oversight of safety during the construction and operation of nuclear power plants is 
responsibility of the Radiation and Nuclear Safety Authority (STUK). Furthermore, 
STUK’s duty in each licensing stage is to draw up safety assessment and statement 
before the Government grants the respective license. 
 
General safety requirements are given in the Government Degrees, and more detailed 
technical requirements are specified in YVL Guides issued by STUK. The YVL Guides 
also provide guidelines concerning STUK’s regulatory control, and specify the 
obligations of the licence applicant/licensee. YVL Guide 1.1 [13] presents a summary 
of STUK's oversight in connection with the review of applications for nuclear facility’s 
licences, as well as during the construction and operation of a nuclear facility. 
 
STUK oversees the construction of the plant and the manufacturing of equipment for 
the plant. The purpose of this oversight is to ensure that the conditions of the 
construction licence, regulations governing pressure equipment, and the plans 
submitted to STUK with the application for the construction licence, which STUK has 
approved, are complied with, and that the nuclear facility is also in other respects built 
in conformity with the regulations of the Nuclear Energy Act. 
 
Appendix 4 presents the stages of the OL3 nuclear plant project, referred to as the FIN5 
project at STUK, the licences and license processes required for the implementation 
and the organisation of STUK’s project, different stages and inspections. STUK’s 
activities in each sample case are not described in more detail, because they were 
already discussed in connection with these cases. Besides observations on STUK’s 
performance in the sample cases there are also other corresponding examples and 
situations that have emerged in the oversight of the OL3 project and have been used as 
basis for the observations discussed below.  

 

5.2 Observations on STUK's activities 

As the sample cases of the investigation indicate, the regulatory oversight by STUK 
control is primarily focused on ensuring the quality and safety of the end products. As 
part of its construction oversight, STUK has developed an inspection programme for 
assessing TVO’s management and quality management procedures, but corresponding 
systematic monitoring is not applied to the activities of other organisations involved in 
the OL3 project. Thus, not enough attention has been paid to the common 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 56 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

organisational background factors of technical problems and their connection to the 
recurring problems has not been analysed. 
 

STUK has no systematic procedure for recording, collecting and analysing signals 
received from different sources about the performance of organisations. Scattered 
signals about weaknesses in the performance of the organisations involved in the 
construction project have not always reached the management of the FIN5 project or 
the department of Nuclear Reactor Regulation to enable STUK to react to them 
effectively.  
 
STUK has required TVO and FANP to define safety culture, and both organisations 
have done it in their quality management guidelines. STUK has examined the 
dissemination of the requirement on good safety culture to other organisations involved 
in the project when participating in audits conducted by TVO. In such instances 
STUK’s inspectors have often recorded in their travel reports that the development of 
the safety culture has not received enough attention in the audited organisations and 
that TVO has given notice of it. However, STUK’s inspectors have not usually 
identified the individual deficiencies observed in the safety culture, and STUK has not 
required TVO specify them in the notices given as part of the audits to provide the 
audited organisation a clearer idea of what is expected from the safety culture.  
 
STUK has repeatedly emphasised the significance of the quality of design documents 
and construction inspection documents to TVO and the plant supplier as a prerequisite 
for smooth progress of the project and for ensuring adequate quality of the end 
products. As the project has advanced, the materials submitted by FANP and some 
experienced subcontractors have improved but extending the learning process to the 
performance of new subcontractors has generally not succeeded.  
 
STUK’s aim to keep things running on schedule as far as possible has in some casess 
made it necessary for STUK to assume responsibility for prompt handling of problems 
it has detected, and even to act as part of the quality assurance chain, when other parties 
have failed to fulfil their obligations. STUK's strong intervention in the detected 
problems in the investigated example cases can be justified in these cases. Although 
STUK has on several occasions told the plant supplier and TVO that safety and quality 
requirements must be met also without direct intervention from authorities, essential 
improvement in this respect has not taken place in the studied cases. 
 
On the other hand, the investigation also revealed that in some cases STUK’s 
representatives failed to require correction of problems detected by them when they 
should have been corrected without delay to make for easy correction and to avoid new 
problems. As the problems observed by STUK’s inspector were recorded in documents 
presented to TVO or sometimes only communicated orally and without stressing the 
urgency of the measures to be taken, the information was slow to reach the parties who 
should have taken the corrective action.  
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 57 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

The FIN5/OL3 project includes a lot of meetings between STUK's own personnel, with 
representatives of TVO, and often also with representatives of the plant supplier. The 
status of different meetings and possible decisions taken in them seems to be unclear to 
some parties outside STUK, although STUK has emphasised that it does not make 
formal decisions on the acceptability of technical solutions in the meetings. In the light 
of the observations of the investigation team, a systematic method for distribution of 
the minutes of the meetings to ensure smooth flow of information has not been defined, 
and responsibilities for monitoring the fulfilment of the recorded obligations have 
generally not been specified. 
  

 

6. RECOMMENDATIONS TO FANP, TVO AND STUK 

 

The following recommendations based on the main observations of the investigation 
team are made to the plant vendor, the licensee, and the regulatory body.  
 
The recommendations are numbered to facilitate their further processing. The numbers 
do not indicate the priority or order of implementing of the actions to be taken.  

 

FANP  

1.

 

FANP should see to it that all design documents it submits to TVO, including those 
prepared by the subcontractors are, of the scope and quality that no considerable 
amendments or changes are required afterwards. 

2.

 

The site organisation of FANP should be made aware of its definite responsibility 
for ensuring the quality of all subcontractors operating on the site. It is particularly 
important that a responsible manager is appointed for each work entity at the 
construction site, with undisputable authority to give work-related orders. 

3.

 

FANP should intensify the guidance to its subcontractors to ensure that they fulfil 
their tasks in the manner expected by FANP and produce acceptable quality. 
FANP's management should make it clear to its personnel that they have to inform 
the management without delay of the detected quality problems. 

4.

 

An improved practise should be developed for the distribution and dealing of 
non-conformance reports, to ensure timely initiation of corrective action. 

5.

 

The principles defined in FANP's own quality procedures should be adhered to in 
the selection of subcontractors. In particular, it should be verified that the 
subcontractor already at the time of signing the contract is capable of producing the 
expected quality and performing in compliance with the requirements of the nuclear 
field. Tender invitations and purchase agreements should clearly provide all 
information on quality control requirements typical for nuclear power plant 
construction and exceeding the conventional standards applied in the branch. 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 58 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

6.

 

Site introduction training should include general information about the special 
requirements to be met in the construction of a nuclear power plant as well as 
guidance on practices for ensuring nuclear safety. Corresponding training should 
also be provided for the personnel of manufacturers that fabricate equipment 
specifically designed for the nuclear power plant. 

7.

 

The significance of open disclosure of any detected problems and errors made as 
well as the obligation to discontinue the conduct of work in unclear situations 
should be emphasised at all levels of FANP's own organisation as well as to the 
subcontractors. 

8.

 

Remarks made during audits and inspections should be analysed systematically in 
order to identify recurring observations. Particular attention should be paid to 
observations concerning deficiencies and problems in the performance of the 
subcontractors' organisations. 

9.

 

FANP should assess together with TVO why most of the non-conformancies 
recorded in TVO's audits have not been noted in FANP's own audits of respective 
organizations. 

10.

 

Before starting demanding jobs at site, a thorough pre-job briefing should be 
organised for all persons involved. Examples of issues to be covered include the 
significance of the job to safety, the responsibilities and authorities of different 
actors, the schedule, work stages and critical points, overall coordination of work 
and actions to be taken in potential problem situations. In this context the potential 
problems foreseen by the persons implementing the work should be discussed. Pre-
job briefing is particularly important for work implemented jointly by several 
organisations. 

11.

 

FANP should make it clear which requirements stipulated in IAEA's safety 
standards concerning quality systems and safety culture are to be taken into account 
when assessing the performance of the organisations involved in the construction of 
the plant and the manufacture of components. Special attention should be paid to 
these issues in the selection and guidance of subcontractors. 

 

TVO  

1.

 

TVO’s management should communicate clearly to the entire personnel of the OL3 
project that, in spite of the turn-key delivery, TVO is ultimately responsible for the 
safety of the power plant and that this responsibility cannot be assigned to the 
vendor by the terms of supply contract.  

2.

 

The management of TVO should regularly inform the site managers and 
supervisors of the consortium CFS and its subcontractors about the safety and 
quality objectives of the OL3 project and the related practical operating methods. It 
should also be ensured that both TVO's own and the consortium’s site personnel 
have understood these objectives and implement them in their work. 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 59 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

3.

 

TVO should ensure that its own project personnel strictly follow the general 
principles for nuclear power plant safety in their operations. It is of particular 
importance that the safety first approach is consistently applied in all decisions and 
acts of the project management. 

4.

 

TVO should ensure that the site introduction training provided by CFS gives 
everyone coming to the site sufficient basic knowledge of the special requirements 
related to the work methods in the construction of a nuclear power plant. 

5.

 

TVO should ensure that the tender invitations sent out by CFS as well as purchase 
agreements with subcontractors include information about the quality assurance 
requirements for the delivery in question that are normally applied in nuclear plant 
construction and exceed the conventional standards applied in the branch. 

6.

 

TVO should emphasise to its own quality control staff the importance of effectively 
dealing with detected non-conformancies, and should develop its own practices to 
ensure that this staff has sufficient authority and can bring the observations 
recorded in non-conformance reports to corrective process without any detrimental 
delay. 

7.

 

TVO should together with CFS create practices that ensure open, consistent and 
prompt reporting of non-conformancies to both TVO and all other parties expected 
to deal with those non-conformancies. TVO should also remind CFS of TVO's right 
to discontinue work and receive the desired quality data. 

8.

 

TVO should ensure that the OL3 project has sufficient resources to examine the 
design documents submitted by the vendor and to effectively deal with any 
concerns raised in the design documentation before it approves start of 
manufacturing or submits the documents to STUK for approval. 

9.

 

TVO should systematically analyse the remarks made in audits and inspections in 
order to identify any recurring observations. 

10.

 

TVO should together with FANP clearly specify which requirements stipulated in 
IAEA's safety standards concerning quality systems and safety culture are to be 
taken into account when assessing the performance of the organisations involved in 
the construction of the plant and manufacturing of components. The specified 
requirements should be clearly communicated to all TVO's experts who take part in 
audits and inspections. 

 
STUK  

1.

 

The findings of STUK inspectors should be systematically collected and analysed 
with the intent to identify recurring deficiencies. Particular attention should be paid 
to observations concerning weaknesses and problems in the management of 
organisations. STUK's management should regularly discuss the results of analysis 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 60 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

with TVO's management to eliminate the identified problems and to improve the 
quality of operations. 

2.

 

In case STUK’s inspectors notice during audits that the quality systems and safety 
culture of the audited organisation are not on the level required by IAEA safety 
standards, they should ensure that TVO’s representatives present the detected 
non-conformancies and requirements on corrective actions in the most concrete and 
unambiguous manner. For this, STUK’s management should clarify to their 
inspectors which requirements concerning quality systems and safety culture, 
provided by the IAEA safety standards, should be examined with particular care in 
evaluating the performance of organisations that participate in the construction of 
the power plant and manufacturing of equipment, and indicate STUK’s 
expectations with regard to meeting the requirements. 

3.

 

STUK's inspectors should actively demand TVOs representatives to take immediate 
corrective actions for elimination of any detected problems, where prompt actions 
are well founded to facilitate correction or to avoid new problems, and other parties 
have not taken the necessary action. 

4.

 

If quality deficiencies are detected in structures and equipment during STUK 
inspections, the performance of quality control organisations should also be 
assessed, in addition to production processes and products. STUK’s management 
should ensure that it receives without delay a report and description of any 
occasions where the manufacturer or the builder is not producing sufficiently high 
quality and the quality control personnel of neither the consortium nor TVO has not 
demanded effective corrective action. Significant deficiencies detected in the 
performance of organisations should be discussed with TVO’s project management. 

5.

 

STUK should develop a practice that supplements the inspection records and other 
reports and allows direct communication of the most important quality problems 
and other deficiencies to the project managements of both STUK and TVO so that 
corrective actions can be initiated on an optimal schedule. 

6.

 

STUK should together with TVO find a way for improving the quality of all design 
and construction inspection documents submitted to STUK to a level that would 
eliminate the need of revisions, and repeated handling. 

7.

 

In order to improve communication within STUK one should define the standard 
distribution of minutes of various meetings related to the OL3 project, as well as the 
obligation to get acquainted with these minutes. Also, a procedure should be 
defined for monitoring the implementation of the obligations recorded in the 
minutes. 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 61 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

 

7. REFERENCES  

 
[1] Weick, K. & Sutcliffe, K. (2001), Managing the Unexpected. Assuring High Performance in an  
Age of Complexity. Jossey-Bass, San Francisco.  
 
[2] YVL 1.4 Quality assurance of nuclear power plants, 20.9.1991, renewed draft 3.8.2000 (only in 
Finnish).  
 
[3] IAEA Safety series No. 75-INSAG-4 (1991). Safety Culture. International Atomic Energy 
Agency, Vienna.  
 
[4] IAEA INSAG-15 (2002). Key Practical Issues in Strengthening Safety Culture. International  
Atomic Energy Agency, Vienna.  
 
[5] IAEA Safety Report (1998). Developing safety culture. Practical suggestions to assist progress.  
International Atomic Energy Agency, Vienna.  
 
[6] IAEA Safety Series No. 50-C-QA (1996). Code on the Safety of Nuclear Power Plants: Quality  
Assurance, Vienna.  
 
[7] YVL 4.1 Concrete structures for nuclear facilities, 22.5.1992.  
 
[8] YVL 1.15 Mechanical components and structures in nuclear installations. Construction 
inspection, 19.12.1995 (only in Finnish).  
 
[9] YVL 3.4 Approval of the manufacturer of nuclear pressure equipment, 14.1.2004.  
 
[10] YVL 1.3 Mechanical components and structures of nuclear facilities. Approval of testing and 
inspection organisations, 17.3.2003.  
 
[11] YVL 4.2 Steel structures for nuclear facilities, 19.12.2001.  
 
[12] YVL 5.8 Hoisting appliances and fuel handling equipment at nuclear facilities, 5.1.1987. 
 
[13] YVL 1.1 Regulatory control of safety at nuclear facilities, 10.2.2006. 

 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 62 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

 

8. APPENDICES  

 

1. Assignment and objectives of investigation 
 
2. Investigation team and performance of investigation 
 
3. Investigation programme and schedule 
 
4. STUK's operation in control of nuclear power plant construction 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 63 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

APPENDIX 1.  

ASSIGNMENT AND OBJECTIVES OF INVESTIGATION 

INVESTIGATION OF OPERATIONAL EVENTS 1/2006  

OLKILUOTO 3 – MANAGEMENT OF SAFETY REQUIREMENTS IN CONSTRUCTION 
STAGE PURCHASES FOR A NUCLEAR POWER PLANT  
 

The quality non-conformancies detected in the concrete used for the base slab of the plant 
unit under construction in Olkiluoto brought out the need at the Finnish Radiation and 
Nuclear Safety Authority (STUK) to investigate the procedures used in selecting 
subcontractors, their prerequisites for meeting set requirements and the supervision of their 
operation. The subcontracting for Olkiluoto 3 is done by the vendor, FANP. Teollisuuden 
Voima Oy (TVO) is informed about the selected suppliers. 
 
The investigation set up by STUK is looking into the management of safety requirements in 
subcontracting and in purchases of structures, equipment and components during the nuclear 
power plant construction phase. The selection and control of the suppliers of the concrete 
base slab and the containment inner steel liner, as well as the the polar crane and the material 
hatch, are used as sample cases in the investigation. The tasks of the investigation team are:  
 

•

 

to determine and assess any negligence in complying with requirements in selecting and 
supervising suppliers of safety significant structures, equipment and components 

•

 

to determine and assess any quality management deficiencies in the performance of TVO 
or the plant vendor in selecting and controlling suppliers 

•

 

to determine and assess  TVO’s and the vendor’s management views and the attitudes on 
requirements for the selection and control of suppliers, non-conformancies, inspections 
and implementation of corrective actions 

•

 

to establish TVO’s and the vendor’s procedures for tender invitations, selection of 
approved suppliers, training of the subcontractors' personnel, supervision of 
subcontractors as well as the various parties’ quality management, and practices for 
approval of test results 

•

 

to establish the passege of information in the selected sample cases 

•

 

STUK's regulatory oversight. 

 
Investigation manager Mrs. Seija Suksi (STUK) acts as the leader of the investigation team. 
Experts in quality management,  safety culture and various technical fields from STUK and 
outside STUK will be assigned to the team. The investigation team will make its 
recommendations by the end of March, and the investigation report will be completed by the 
end of April 2006.  
 
 
 

Director 

    Lasse 

Reiman 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 64 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

 

APPENDIX 2.        1 (2)  

 

INVESTIGATION TEAM AND PERFORMANCE OF INVESTIGATION 

Mrs. Seija Suksi, investigation manager (STUK), acted as the coordinator and leader of 
the investigation team. The investigation team consisted of the following experts in 
quality management, management, safety culture and various technical fields, both 
from within and outside STUK: 
 

Expert 

Organisation, task 

Focal area in investigation 

Suksi, Seija 

STUK, investigation 
manager 

Root cause analysis, regulatory control 

Koskinen, Kaisa 

STUK, development 
manager 

Quality management 

Valkila, Aila 

Aila Valkila Oy, managing 
director 

Quality management 

Koivula, Nina 

STUK, inspector 

Human and organisational factors 

Oedewald, Pia 

VTT, researcher 

Safety culture  

Pitkänen, Pertti 

VTT, senior researcher 

Concrete structures, characteristics of 
concrete 

 
The investigation team availed of the services of the following STUK’s experts for the 
sample cases: 
 

Expert 

Organisation, task 

Focal area in investigation 

Myllymäki, Jukka 

STUK, senior inspector 

Concrete structures, construction plans 

Lehto, Rauno 

STUK, inspector 

Mechanical components, lifting 
equipment 

Cederberg, Mark 

STUK, senior inspector 

Materials and welding technology, 
construction inspection 

 
 

Conduct of investigation 

The input documentation reviewed by the investigation team consists of possible 
non-conformance reports or description prepared by the licensee of the event or 
non-conformance under investigation, inspection reports by STUK in the area, 
memoranda and minutes of meetings as well as other associated documents and 
records. The details of the event are looked into on the plant site on the basis of 
interviews and by studying the event and its handling, decisions made, correspondence, 
contracts, work orders, test reports, procedures, etc. 

 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 65 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

Comprehensive background material was collected in support of this study consisting 
of the following documents: 

-

 

description of the consortium's organisation as well as descriptions of 
management and responsibilities  

-

 

the consortium's procedures related to approval and control of suppliers  

-

 

TVO's project quality manual and, particularly, procedures and descriptions 
related to approval and control of suppliers 

-

 

TVO's project plan (including a description of the project organisation and 
tasks) 

-

 

STUK's FIN5 project plan 

-

 

Inspection reports  on  quality management and quality assurance belongin to 
STUK's Construction Inspection Programme (RTO), decisions and minutes of 
meetings 

-

 

key technical (general) documentation and inspection memoranda for the sample 
cases. 

 

The first week of the investigation was spent studying the subject areas through 
presentations requested from STUK's experts, the FIN5 project and sub-project 
managers, as well as the responsible coordinators of the Olkiluoto 3 project and the 
quality and purchasing managers of CFS. People performing various tasks in the 
Olkiluoto 3 project (TVO, CFS, FANP, subcontractor, research institute) were 
interviewed during the second week, and the investigation team visited the Olkiluoto 3 
construction site and the concrete batching plant. Detailed notes were made of all 
presentations and interviews. Daily observations were collected onto a form designed 
for the purpose and/or during discussions conducted at the end of the day. The writing 
of the report and the formulating of recommendations started in the third week. The 
investigation programme is shown in Appendix 3. 

 

background image

 INVESTIGATION 

 

REPORT 1/06 

 66 

Nuclear Reactor Regulation 

Translation 1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

APPENDIX 3.  

1 (2)  

INVESTIGATION PROGRAMME AND SCHEDULE  

Week 1 (weeks 12 - 13) 

 Wed 15/3

 

 

Thu 16/3 

STUK 

STUK 

Fri 17/3 
STUK 

Sat 18/3 
 

Sun 19/3 
 

Mon 20/3 
STUK 

Tue 21/3 
STUK 

Investigation areas 
Management, QC/QA 
Safety culture, HOF 
Root cause analysis 
Sample cases 

•

 

concrete 

•

 

liner 

•

 

polar crane 

Organising 
 
Start-up 
 
Introduction 
 
Planning 
 
Presentations: 
-FIN5 project (KiA) 
-KOLA (JMo) 

Presentations: 
RAKE 
-concrete  
(HSk, JMy) 
 
OL3 project 
organisation (TV) 
 
Preparing questions to 
TVO and CFS 

OL3 project 
presentations: 
at 9 - 15 

Herkko Plit 
Markku Pitko 
Timo Kallio 
Jukka Kangas 
Dieter Kreckel 
Herbert Scramm 
T. Kammerzell 

 

Presentations, 
interviews and 
discussions  
 
- FIN5 ( PT) 
- liner (MC) 
 

Interviews and 
discussions  
- Polar crane (RLe) 
 
Summary of 
observations 
 
Preparing for TVO's 
interviews 
-list of questions 

Safety and risk analyses 
Regulatory control 

Daily observations (1) 

Daily observations (2) 

Discussion on 
presentations 

 

 

Daily observations 
(3) 

 

 

Week 2 (weeks 13 - 14) 

 Wed 22/3

 

 

Thu 23/3 

STUK 

TVO 

Fri 24/3 
TVO  

Sat 25/3 
 

Sun 26/3 
 

Mon 27/3 
STUK 

Tue 28/3 
STUK 

Investigation areas 
Management, QC/QA 

Area-specific 
observations / 
drafting report  
 

Safety culture, HOF 
Root cause analysis 

Interviews 
At 8 - 16:30 
TVO personnel: 

H. Plit / NS 
M. Pitko NQ/QM 
M. Landman N 
J. Ala-aho NQ/QA 
R. Hiekkanen 
NC/QC 

Interviews 
at 8 - 14:30 
TVO personnel 

Kervinen NC/QC 
Ala-aho (mat.) 
Van Graan FANP 
Mannola TVO/ns 
Levonen NL 
Jääskeläinen(mat.) 

from 12 on: 
Analysing TVO 
interviews 

Sample cases 

concrete 
liner 
polar crane 

Discussion on 
interviews 

Interviews 
at 8 â€“ 17:30 
TVO personnel 
- Onnela NQ/QA 
- Manninen NC/Site 
- Visit to site 
- Jääskeläinen NC/QC 
 
Forssan Betoni: 
- Bergman 
- Batching plant 

Safety and risk analyses 
Regulatory control 

Travelling to Rauma  

at 18 - 19:30 Discussion 

at 15:30 - 20  
Travelling to Helsinki 
 

 

 

Review of area-
specific summaries / 
observations 

Teamwork 
 
at 11 - 14:30 
Interview of D. 
Kreckel  
 
- Analysing the 
interview 
 
- Making appoints for 
next day interviews  

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 67 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 
 

Week 3 (weeks 14 - 15) 

 Wed 29/3

 

 

Thu 30/3 

TVO 

STUK 

Fri 31/3 
STUK 

Sat 1/4 
 

Sun 2/4 
 

Mon 3/4 
STUK 

Tue 4/4 
STUK 

Investigation areas 
Management, QC/QA 
Safety culture, HOF 
Root cause analysis 

Writing report 
 
 

Sample cases 

•

 

concrete 

•

 

liner 

•

 

polar crane 

 
 
 
 

Safety and risk analyses 
Regulatory control 

Interviews 
FANP personnel: 
-

 

H. Beaumont 

-

 

W. Ă–rtel 

-

 

Heudes 

-

 

H. Sinisalo 

-

 

L. Sikiö 

 
KymAmkk 
- S. Matala 
 

Draft report 
- writing 
 
-verifying facts and 
observations 

Draft report 
- writing 
- compiling 
 
at 14 -15:30 
Interview of Aki 
Meuronen 
 
Key observations 
 
Drafts of focal areas to 
team members for 
reading 

 

 

Review of draft report 
 
 
Summary 
- Key observations 
 
(Recommendations) 
 

Agreeing on reporting 
of preliminary results 

 

Week 4 (weeks 15 - 16) 

 Wed 5/4

 

 

Thu 6/4 

STUK 

STUK 

Fri 7/4 
STUK 

Sat 8/4 
 

Sun 9/4 
 

Tue 25/4 
STUK 

Mon 5/6 
STUK 

Investigation areas 

Preliminary results 
reported: 
JL, LR, MlJ, PT 

Management, QC/QA 
Safety culture, HOF 
Root cause analysis 
Sample cases 

•

 

concrete 

•

 

liner 

•

 

polar crane 

TVO's clarification: 
(for information) 
Additional material for 
investigation team 
 
- description 
- causes 
- corrective action 
- further analyses 
 

Review of TVO's 
clarification 
 
SSu, KaK, NiK,  
PP, PO 
 
Impact on 
conclusions drawn in 
investigation 
 
 

 
Draft report 

Review of draft 
report  
 
AVa, PO, KaK, NiK, 
MC, SSu,  
JL 
 
writing report: during 
26.4. to 22.5. 
 
22.5. –draft version 
to OL3 project and 
STUK management 

Going through draft 
report 
 
AVa, PP, PO, KaK, 
NiK, MC, JMy 
JL 
 
Finalising draft report 
 

Safety and risk analyses 
Regulatory control 

 

 

 

 

 

22.5.2006 
preliminary draft for 
comments: TVO, 
STUK 

8.6.2006 draft for 
comments: 
TVO, STUK 

 

background image

 INVESTIGATION 

 

REPORT 1/06 

 68 

Nuclear Reactor Regulation 

Translation 1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

APPENDIX 4.   

1 (9)  

 

STUK AS REGULATOR OF NUCLEAR POWER PLANT CONSTRUCTION  

 
Licenses and safety regulation stibulated in the Nuclear Energy Act  

Starting a project for constructing a major nuclear facility necessitates a Decision in 
Principle made by the Government and ratified by Parliament. As the next step, a 
Construction Licence is required for the implementation of the project, and the 
operation of a nuclear power plant requires an Operating Licence granted for a 
specified period of time. The Operating Licence can be renewed by application. The 
licensing process and the responsibilities and obligations of the involved parties are 
stipulated in the Nuclear Energy Act and the Nuclear Energy Decree. The licenses are 
granted by the Government. The licensing process is administered by the Ministry of 
Trade and Industry. For each license,, the Ministry has to request a statement from 
STUK which includes a safety assessment. 
 
General safety requirements are given in Government Decrees, and more detailed 
technical requirements are specified in YVL Guides published by STUK. The YVL 
Guides also provide instructions concerning nuclear safety oversight by STUK and 
specify the obligations to the licence applicant/licensee. YVL Guide 1.1 [13] presents a 
summary of STUK's oversight activities in connection with the review of applications 
for nuclear plant licences, as well as during the construction and operation of a nuclear 
facility. 
 
After the Construction Licence has been granted, STUK conducts regulatory oversight 
of the construction of the plant and the manufacture of equipment for the plant. The 
purpose of this oversight is to ensure that the conditions of the Construction Licence, 
the regulations in force for the pressure equipment, and the plans reviewed and 
approved by STUK are complied with, and that the nuclear facility also in other 
respects is built in conformity with regulations based on the Nuclear Energy Act. A 
particular objective of oversight is to ensure that the work methods applied during 
construction produce high quality. 

 

Control stages of plant project 

In November 2000, Teollisuuden Voima Oy submitted an application for a Decision in 
Principle (DiP) on the construction of a new nuclear power plant. Even before this, an 
Environmental Impact Assessment had been completed as stipulated by the 
environmental legislation. Concurrently with the Environmental Impact Assessment 
process, started early 1998, STUK had at TVO's request assessed the key safety 
features of the proposed plant alternatives. On the basis of this extensive preliminary 
work, STUK was able to produce the required safety assessment and a statement on the 
application for the Ministry of Trade and Industry after a short period of preparation 
already in February 2001. The safety assessment was supplemented in January 2002 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 69 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

with respect to external threats such as airplane crashes, due to the terrorist attacks that 
had taken place in the United States in September 2001. 

 

The Government made a Decision in Principle on the construction of a new nuclear 
power plant on 17.1.2002. The decision included a statement where the Government 
indicated that it expects the new nuclear power plant to be built in compliance with 
stringent safety requirements. Subsequently, the DiP was submitted to Parliament for 
ratification. STUK's experts were heard by several parliamentary committees, along 
with many other invited experts, during the deliberation process. The Parliament 
ratified the Government resolution in May 2002. 
 
The DiP made it possible for TVO to call for tenders for the delivery of the plant. 
Tenders were called in September 2002 and submitted in March 2003. In December 
2003 TVO concluded an agreement with the consortium formed by Framatome ANP 
and Siemens on turn-key delivery of an 1600 MW nuclear power plant. TVO submitted 
an application for a Construction License to the Government on January 8. 2004. 
 
TVO started submitting the documents specified in the Nuclear Energy Decree to 
STUK on the same day the Construction License application was submitted to the 
Ministry. STUK started examining the documents immediately. Supplementary 
documentation was submitted throughout the year as requested by STUK, and matters 
were discussed in numerous meetings between TVO, the plant vendor and STUK's 
experts. As a result of the review, STUK prepared a statement and an attached safety 
assessment, and submitted these to the Ministry of Trade and Industry in January 2005. 
The Government granted a Construction License for the plant on February 17. 2005. 
 
Since the launching of the construction project, STUK has reviewed detailed design 
documents and conducted regulatory oversight of the manufacture of equipment as well 
as construction activities. 

 

STUK's preparation for the project  

STUK had maintained its preparedness for the control of a new plant project 
continuously since the existing Finnish nuclear power plants went online at the 
beginning of the 1980s. This preparedness included studying the development of light 
water reactors, updating the safety requirements specified in the YVL Guides according 
to most recent developments, and interaction with power utilities in order to 
consistently improve the safety of existing nuclear power plants. When the Finnish 
utilities applied jointly for a Decision in Principle on a new nuclear facility at the 
beginning of the 1990s, STUK assessed in the course of about three years plant 
alternatives, which were the predecessors of certain plant types considered for the 
current project. 
 
Once the current project took shape, STUK studied the proposed plant alternatives and 
took part in the environmental impact assessment process. 
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 70 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

An essential task before launching the project was to update the regulations of the YVL 
Guides concerning safety and regulatory control. Updating of the Guides continued 
until the main contract on the new plant was ready to be signed. TVO was provided 
information about the status of the Guides and about planned new requirements on a 
regular basis. 
 
The preparations intensified after the Parliament ratified the Decision in Principle made 
by the Government. In the summer of 2002, the Nuclear Reactor Regulation (YTO) of 
STUK set up a special project group referred to as FIN5. The team consists of the 
Project Manager and sub-project managers for various sub-projects. The total number 
of sub-projects is 11, and each represents a specific field of technology. The project 
team is responsible for the planning and implementation of regulatory control of the 
plant project, and for the monitoring of the progress of oversight activities. The project 
team also assesses and inspects the quality of the licence applicant's and the plant 
vendor's project management. The project team is responsible for ensuring that the 
work of the YTO personnel proceeds as planned at different stages of the project. Team 
members also parcipated assessment and inspections in their respective technical fields. 
 
The project plan that covers STUK's duties from the preparation stage to the granting of 
the operating licence was completed in January 2003. It describes the different parties 
involved in the project and their duties, the steering of the project, the division of the 
project into stages, and the key tasks in implementing oversight at different stages, as 
well as the interaction with various stakeholders. 
 
Before the application for the Construction License was submitted, STUK's activities 
focused on the preparation of plans for oversight activities, as well as on contacts with 
the license applicant to ensure a smooth process. Sub-project plans identified and 
prioritised the most important tasks in terms of the Construction License process and 
the resources required for the work. The plans also paid attention to the interfaces 
between the sub-projects to ensure comprehensive oversight. In addition, the sub-
projects specified the needs for external support in control activities. Discussions were 
conducted and experiences exchanged with authorities in other countries concerning 
nuclear power plant licensing procedures, requirements for different plant alternatives 
and experience in the construction of plants. The availability of international 
consultants was also investigated for areas where Finnish expertise is limited or a third 
party assessment is possibly required. The discussions were related to such topics as 
automation, accident analyses and control room design. 
 
One of the project group's key tasks was to develop requirement management for 
systematic control of the implementation of safety requirements during the entire 
project. In addition to development work, this involved the conversion of the most 
significant YVL Guides influencing the design of the plant into a requirement 
management system. The system is used to monitor fulfilment of the requirements and 
control of fulfilment at the plant construction and commissioning stage. 
 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 71 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

Discussions were conducted with TVO about the detailed requirements of the content 
of the licence documents and about their submittal schedule, as well as about the time 
STUK needed for their review. STUK and TVO also organised an extensive seminar 
where discussions were held separately with each plant supplier about the interpretation 
of safety requirements for the plant alternative in question. At TVO's request, several 
separate meetings were also organised between STUK and the experts of the plant 
suppliers that had submitted a tender. 
 
The plant supplier that was finally selected had already before the conclusion of the 
supply contract ordered the reactor pressure vessel at their own risk. At TVO's request, 
STUK started inspecting the design, manufacture and quality control of the pressure 
vessel. The manufacturing process of the reactor pressure vessel continues for several 
years, and inspections of the manufacturing process have continued uninterrupted since 
the granting of the Construction License. 

 

Review of the application for a Construction License 

During 2004 STUK reviewed the application for the Construction License and prepared 
its safety assessment. TVO submitted the documents related to the Construction 
License to STUK at the beginning of January 2004. Technical documentation was 
supplemented during 2004 as design progressed, and the designs were modified to 
some extent on the basis of issues raised by STUK. STUK also reviewed the quality 
management system of the project as part of the safety assessment. 
 
The review of documentation, which was mainly implemented by STUK’s own 
experts, formed the basis for the assessment of the plant’s safety. Independent reference 
analyses were ordered from external experts, concerning e.g. plant behaviour in 
transients and accidents, and the radiation effects of potential transients and accidents. 
STUK also supplemented its own review by an external expert statement on the design 
of the reactor coolant circuit, as well as by an external investigation on how to consider 
airplane crashes in design. Expert statements were also requested on e.g. automation 
systems, emergency core cooling systems, the water chemistry of reactor coolant, the 
design of plant buildings, fire safety and protection against weather and 
electromagnetic phenomena. Moreover, STUK had analyses and tests performed 
concerning the management of severe accidents and the assessment of the impact of 
airplane crashes. Plans connected with emergency and security arrangements as well as 
fire safety were examined in collaboration with other authorities. 
 
As a result of the review, STUK prepared a statement supported by an attached safety 
assessment, and submitted these to the Ministry of Trade and Industry in January 2005. 
The submittal also included a separate statement of the Advisory Committee on 
Nuclear Safety. STUK's conclusion was that the new nuclear power plant can be built 
as a safe plant. However, in order to meet Finnish safety requirements, STUK's 
statement called for some changes in the design of the plant. The changes concerned 
improvement of the reliability of safety functions. STUK's statement also required that 
as the detailed design of the plant continues during the construction project, the 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 72 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

continuation of STUK's inspections and control has to be ensured and sufficient time 
shall be reserved for them. STUK also pointed out that TVO must ensure sufficient 
expertise of its personnel. The concern was expressed as follows: 

”TVO shall ensure 

that sufficient expertise is maintained also during future operation of the plant. Due to 
the characteristic features of the new plant and the technologies utilised in it, TVO 
should ensure that its organisation reinforced during the construction period retains 
sufficient expertise also when entering the commissioning stage, particularly in the 
fields of nuclear safety, mechanical technology and automation technology.”

 

 

STUK’s statement, safety assessment and the statement of the Advisory Committee on 
Nuclear Safety can be read in their entirety on STUK’s Web pages (www.stuk.fi).  

 

Oversight of plant project during construction 

Regulatory control of plant technology 

As the first thing, STUK reviews the design of systems, which specify the requirements 
and the boundary conditions for the design of structures and components. The 
subsequent review of the design of structures and components used in a safety 
classified system cannot be started until STUK has found that the information provided 
on the system in question is sufficient and acceptable. The extent of regulatory control 
and the specified requirements are determined considering the safety class of structures 
and components. 
 
The regulatory control of safety-critical buildings as well as concrete and steel 
structures entails e.g. review of the design documents of structures, inspections of 
readiness for starting of work on site, manufacturing inspections, construction 
inspections of steel structures, and commissioning inspections. In lower safety classes, 
inspections of concrete and steel structures can also be performed by certified experts 
employed with  organisations authorized by STUK. 
 
Regulatory control of pressure equipment and other mechanical equipment used in 
nuclear power plants entails review of design documentation for the equipment, 
approval of manufacturers, manufacturing inspections, construction inspections and 
commissioning inspections. STUK may authorise separate inspection and testing 
companies to perform certain inspections in lower safety classes. 
 
Furthermore, STUK oversees the design, manufacturing and installation of electrical 
and automation equipment used in nuclear power plants, as well as the design, 
manufacturing, transport, storage, handling and use of nuclear fuel. 

  
Conduct of OL3 design  review 

The acceptability of the main features of the plant's basic design and the systems was 
assessed in connection with the review of the application for the Construction License. 
STUK started the review of detailed design of process systems at the beginning of 2005 
which also continues in 2006. 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 73 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

 
So far, the review of detailed equipment design has focused on the reactor and its 
coolant circuit. STUK has reviewed the design documents and manufacturing and 
quality control plans of the reactor pressure vessel, the steam generators, the 
pressurizer, the reactor coolant pumps and the control rod mechanisms before the 
manufacturing of the equipment was started. respective documents of the internals of 
the reactor pressure vessel and the steam generators have also been reviewed.  
 
As far as the design of concrete and steel structures is concerned, STUK has reviewed 
the design documentation of safety class 2 classified parts of the containment and the 
safeguard buildings. STUK also reviewed the detailed design documents for the base 
slab under the containment and the safeguard buildings before the concreting was 
started. In the case of steel structures, review has focused on the design documents and 
manufacturing plans of the inner containment steel liner.  

  
Regulatory control of manufacturing and construction  

The purpose of a construction inspection is to verify that the component or structure 
has been manufactured and its quality has been controlled in compliance with the 
approved construction plan. The construction inspection is usually performed on an 
individual component after manufacturing, before the component is installed. However, 
for parts that cannot be inspected easily after manufacturing, inspections are performed 
as manufacturing and assembly proceeds. The construction inspection covers the 
records of manufacturing and quality control, as well as witnessing the pressure, load, 
tightness, or performance tests, depending on the component type. 
 
As far as the main components of the reactor coolant circuit are concerned, STUK 
controlled the manufacturing of forgings for the reactor pressure vessel and the steam 
generators at Japan Steel Works (JSW). The completed forgings were subjected to 
construction inspections, after which STUK gave permission for the shipment of the 
reactor pressure vessel parts to Mitsubishi Heavy Industries (MHI) in Japan and of the 
steam generator parts to the Chalon plant in France. The last forgings were completed 
and shipped from the JSW plant in the spring of 2005. The welding of the first steam 
generator parts started at the Chalon plant in September 2004 under a conditional 
permission granted by STUK, as the inspection of the plant's design bases had not yet 
been completed at the time. MHI commenced the manufacturing of the reactor pressure 
in January 2005 after STUK granted permission for it. STUK's inspectors have 
observed the manufacturing of the reactor pressure vessel and the steam generators as 
well as the internals of these components by means of regular inspection visits to the 
manufacturing sites. STUK has also observed the manufacturing of other primary 
components (pressurizer, reactor coolant pumps, reactor coolant piping and control rod 
mechanisms) by visits to the manufacturing sites. The total number of inspections 
performed by STUK for the Olkiluoto 3 project in 2005 was almost 300. 
 
Before manufacturing started, STUK audited the manufacturers of the main 
components of the reactor coolant circuit and the connecting parts in order to verify 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 74 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

fulfilment of the requirements of YVL Guides. Based on the Nuclear Energy Act, 
STUK has upon TVO's application approved two manufacturers of main nuclear 
components and almost 40 other manufacturers of nuclear pressure equipment. In 
relation to the manufacturing of the primary components, STUK has on TVO's 
application approved 130 testing organisations to perform destructive and non-
destructive tests on mechanical components and structures. STUK has further on TVO's 
application approved three inspection organisations to perform tasks related to the 
approval of the design and manufacturing of mechanical components and structures 
falling under safety classes 3 and 4. STUK has also audited the manufacturers, testing 
and inspection organisations approved by it and verified that their performance meets 
the requirements of YVL Guides 3.4 [9] and 1.3 [10]. 
 
STUK observed the preparatory work made on the plant site by performing inspections 
of excavated rock faces and by overseeing the construction of seawater intake and 
discharge structures. STUK approved the plans for the construction of these structures 
in July 2004. The approvals were at the time conditional as the review of the plant's 
design basis was still under way. STUK also inspected the coupling of the so-called 
technical ring running round the Olkiluoto 3 site with the construction site. The 
technical ring contains e.g. electricity supplies, firewater supplies and drain connections 
for the construction site.  
 
STUK has conducted regulatory oversight of the construction of the plant by means of 
regular visits to the plant site. STUK has inspected the readiness for all concreting 
operations that are relevant to safety, and issued permissions for starting the concreting 
operations. In 2005, STUK performed 4 inspections of readiness for concreting. As far 
as steel structures are concerned, STUK's oversight has focused on the manufacturing 
of the steel liner. 

 

Assessment of performance of organisations involved in construction 

Assessment of TVO's operation 

The assessment of TVO's performance at the preparation and Construction License 
stage was based on an assessment of TVO's quality management system, the quality of 
documents prepared by TVO and the review of the results of safety assessments 
prepared by TVO. At the Construction Licence stage STUK also audited TVO's project 
activities in Olkiluoto. The audits focused the project management and resources, 
handling of safety issues and project management procedures, quality management and 
management of documents. As a result of the audits, STUK required more specific 
procedures particularly in the assessment of safety and handling of safety issues, such 
as identification of safety issues, their handling within the organisation and decision-
making. STUK also reviewed the safety provisions of the operating units (OL1 and 
OL2) against any possible risks arising from the construction of Olkiluoto 3. TVO has 
taken appropriate measures to improve its operations as suggested by STUK.  
 
At the construction stage, corresponding audits will be performed regularly as part of 
the Construction Inspection Programme.  

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 75 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 
  
Assessment of plant vendor and its subcontractors  

The assessment of the performance of the plant vendor started already at the 
Construction License stage and has continued during the construction stage. The 
assessment is based on the review of the quality management systems, quality plans 
and manuals describing the activities, on audits to verify activities as well as on 
interaction with the plant supplier in meetings.  
 
At the Construction License stage STUK participated in almost all TVO audits of the 
activities of the plant vendor. The purpose of the audits was to verify the competence of 
the plant vendor to provide high-quality design and construction. The audits focused on 
quality management, procedures of project management and design activities in various 
fields of technology. 
 
STUK also performed its own audits of the design activities of the plant vendor in the 
autumn of 2005. These covered the plant vendor's requirements management, handling 
of design changes, management of interfaces between different technological fields, 
layout design, and radiation safety, as well as the utilisation of the probabilistic safety 
analysis in support of detailed design. Certain development needs were identified in the 
audits and the plant vendor started improvement of the work processes in compliance 
with issued recommendations. 
 
STUK participated already at the Construction License stage as an observer in audits of 
the plant vendor's main safety-related subcontractors. In the construction stage, STUK 
has by March 2006 participated in about 30 audits conducted by TVO of equipment 
suppliers. The purpose of the audits has been to verify the competence of the suppliers 
to participate in the new plant project. Need of development has been found in the 
performance of several equipment suppliers. In order to correct the situation, suppliers 
have, for instance, been required to prepare special Olkiluoto 3-specific quality plans. 

 
Construction Inspection Programme  

In early 2005, STUK started an inspection programme for the construction stage. The 
inspection programme is prepared every six months, and it focuses on the assessment 
of TVO's activies in order to ensure the high quality of the new nuclear power plant 
project. The programme is focused on the project's main functions, such as 
management, quality management, project management, and handling of safety issues, 
as well as quality assurance, training and radiation safety. Various fields of technology 
are also inspected. 
 
As a result of the Construction Inspection Programme, STUK has been able to get a 
concrete and realistic visio of TVO's project management, resources, handling of safety 
issues and quality management, as well as its activities that support these main 
functions. The performance of TVO has been found satisfactory in terms of 
management, although some development needs have been identified. For example, 
STUK has required that the internal audit activities of the project shall be further 

 

background image

RADIATION AND NUCLEAR SAFETY 
AUTHORITY 

INVESTIGATION 
REPORT 1/06 

 76 

 Translation 

1.9.2006 

 

 

 

 

 

 10.7.2006 

 

 

developed and that TVO must verify that the quality systems of subcontractors who 
manufacture safety-critical components meet the quality management requirements 
specified in IAEA's safety standard. On the basis of inspections of the leadership 
system, TVO has been required to improve its handling of safety issues and the control 
of construction. TVO has submitted plans for corrective actions on the basis of the 
comments made as a result of inspections.  

 

 


Document Outline