A W O R L D B A N K G R O U P G L O B A L E N V I R O N M E N T FA C I L I T Y P R O G R A M P U B L I C AT I O N
WORLD BANK GEF
Assessment of the World Bank/GEF Strategy
for the Market Development of
Concentrating Solar Thermal Power
1
W
ORLD
B
ANK
GEF
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
G
ROUP
/GEF
S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
G
LOBAL
E
NVIRONMENT
F
ACILITY
P
ROGRAM
T
HE
W
ORLD
B
ANK
ii
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
© 2006
The International Bank for Reconstruction and Development/THE WORLD BANK
1818 H Street, NW
Washington, D.C. 20433, U.S.A.
Manufactured in the United States of America
Cover design based on work by Jim Cantrell
Cover image: Schott AG/Solargenix Energy/Handout/epa/Corbis
All rights reserved
The World Bank has used its best efforts to ensure that the information contained
within this report is accurate, however, it cannot guarantee its accuracy. The rep-
resentations, interpretations, and conclusions expressed herein do not necessarily
refl ect the views of the Executive Directors of the World Bank or the government
that they represent.
Rights and Permissions
The material in this publication is copyrighted. Copying and/or transmitting portions
or all of this work without permission may be a violation of applicable law. The
International Bank for Reconstruction and Development/The World Bank encourages
dissemination of its work and will normally grant permission to reproduce portions
of the work promptly. For permission to photocopy or reprint any part of this work,
please send a request with complete information to the Copyright Clearance Center
Inc., 222 Rosewood Drive, Danvers MA 01923, USA; telephone: 978-750-8400;
fax: 978-750-4470; Internet: www.copyright.com.
iii
F
O R E W O R D
I
n many of the World Bank’s client countries, solar energy is
available in abundance and could play a key role in meeting
the electricity needs of these countries. Although pioneering
work in the area of solar thermal electricity generation took
place in the United States and Europe during the 1980s, in the
developing countries such work accelerated rapidly with the launch
of the World Bank/GEF solar thermal projects.
The World Bank/GEF program is currently supporting solar thermal
projects in Morocco, Egypt, and Mexico. In view of the cost con-
siderations associated with solar thermal technology, these projects
use the integrated solar combined cycle (ISCC) confi guration, which
combines the benefi ts of renewable energy with conventional fos-
sil-fuel-based power plants.
This study presents an independent review of the implementation
progress for these projects in the context of the long-term strategy
for solar thermal development. The study team undertook extensive
consultations with stakeholders and made some specifi c recom-
mendations with regard to project implementation. In particular,
they emphasized the need for fl exibility in technology choice and
implementation approach, given the changing nature of this industry
worldwide and the availability of more suppliers.
There is now a renewed enthusiasm for solar energy development
around the world. Project development and implementation is
moving at a fast pace, especially in Europe. The new-found enthu-
siasm is largely built around strong national policy commitments
that reduce the revenue risks faced by developers. This study also
recognizes the need for a solid policy platform to sustain solar-
thermal-based electricity generation efforts. However, in order to
reach commercial competitiveness, this industry would need a
signifi cantly higher order of capacity additions, which can be real-
ized only through large national programs in both the developed
and developing worlds.
The solar thermal projects supported under the World Bank/GEF
program played a catalytic role in the development of the industry
during a period when there was a low level of activity globally.
We hope that our partners can benefi t from this independent review
and successfully implement the fi rst set of solar thermal electricity
generation projects in the developing world.
Warren Evans
Sector Director
Environment Department
iv
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
v
C
O N T E N T S
Executive Summary
.................................................................................................................
ii
1
Setting the Context ............................................................................................................ 1
1.1 Operational Programs of the Global Environment Facility .................................................
1
1.2 CSP funding within Operational Program 7 ...................................................................
1
1.3 Lessons from past studies on the GEF solar thermal portfolio ..............................................
2
1.4 Aims of the Study .....................................................................................................
6
1.5 Scope of Work ........................................................................................................
6
2
Concentrating Solar Thermal Power (CSP) Development ...........................................................
8
2.1 Ongoing CSP market development worldwide ...............................................................
8
2.2 Technological paths of Concentrating Solar Thermal Power plants ...................................... 14
2.3 Cost reduction comparison of CSP technology ............................................................... 25
3
CSP Risk Analysis ............................................................................................................. 34
3.1 Technological risks related to the WB/GEF portfolio ....................................................... 35
3.2 Financial/commercial risks related to the WB/GEF portfolio ............................................ 39
3.3 Regulatory/institutional risks related to the WB/GEF portfolio ........................................... 43
3.4 Strategic risks related to the WB/GEF portfolio .............................................................. 45
3.5 Overall risk evaluation ............................................................................................... 49
4
The Status of the WB/GEF CSP Portfolio .............................................................................. 52
4.1 Status of the WB/GEF portfolio and possible development .............................................. 52
4.2 Status of the WB/GEF portfolio by country ................................................................... 54
5
Long-term CSP development scenarios for the World Bank/GEF ................................................ 63
5.1 “Scenario” discussion of strategic aspects for WB/GEF in the development of CSP .............. 64
5.2 The First Round: “Falling Dominos” ............................................................................... 67
5.3 The First Round: “Getting to the harbor” ........................................................................ 68
5.4 The Second Round: “Wait and See” ............................................................................ 70
5.5 The Second Round: “2-Track Approach” ....................................................................... 71
5.6 The Second Round: “Specializing“ .............................................................................. 72
vi
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
6
Short- and long-term recommendations for the WB/GEF strategy for CSP
in the context of a long-term vision for CSP ............................................................................ 73
6.1 Long-term vision for CSP ............................................................................................ 73
6.2 Criteria describing the success of a long-term CSP strategy ............................................... 79
6.3 New market initiatives and their relevance in a long-term strategy for CSP ........................... 86
6.4 The possible role of the Clean Development Mechanism in project fi nancing:
How to cross the bridge toward competitiveness ............................................................ 88
6.5 Central questions for determining the role of the WB/GEF
in the realization of the CSP vision ............................................................................... 89
6.6 Answers to the questions addressing the short-term development
of the WB/GEF CSP portfolio .................................................................................... 91
6.7 Answers to the questions addressing the long-term development
of the WB/GEF CSP portfolio .................................................................................... 106
References
............................................................................................................................ 114
Annex 1
: Characterization of the Status of Important Ongoing CSP Projects Worldwide
(Description of each project according to a set of criteria) ................................................ 118
Annex 2
: The Framework for CSP in China ................................................................................. 139
Annex 3
: CSP Technology Options ........................................................................................... 143
Annex 4
: Characterization of the GEF Four-Country Portfolio (Description of each
of the four projects according to a set of criteria) ............................................................ 145
Egypt ............................................................................................................... 146
India ............................................................................................................... 159
Mexico ............................................................................................................ 167
Morocco .......................................................................................................... 174
Annex 5
: List of interviewed persons .......................................................................................... 183
Figures
Figure 1:
“Gap” identifi cation in technology transfer ............................................................
5
Figure 2:
Short-term and possible medium- to long-term development
of CSP technology worldwide (yearly installed MWe) ............................................. 11
Figure 3:
Short-term and possible medium- to long-term development
of CSP technology worldwide (cumulative installed MWe) ....................................... 12
Figure 4:
Example of part load behavior of a steam turbine .................................................. 18
Figure 5:
Load curves used for the annual performance calculation ......................................... 20
Figure 6:
Results of annual performance calculation for ISCCS and CC .................................. 21
Figure 7:
Specifi c CO
2
emissions for different sites, plant confi gurations,
operational modes, and solar fi eld sizes .............................................................. 22
vii
C
ONTENTS
Figure 8:
Solar LEC for different sizes, plant confi gurations, operational modes,
and solar fi eld areas ........................................................................................ 24
Figure 9:
Progress ratio for different producing branches ...................................................... 26
Figure 10: Specifi c investment costs of wind energy converters over time ................................... 27
Figure 11: Specifi c investment costs of photovoltaics as a function
of cumulative production volume ......................................................................... 27
Figure 12: Development of installed wind capacity in Germany ............................................... 28
Figure 13: Development of the worldwide installed PV capacity and annual growth rate .............. 28
Figure 14: Enermodal Study—Experience curves for different assumptions on the progress ratio ..... 29
Figure 15: Development of levelized electricity costs and revenues from the
power exchange market referred to by LEC of fossil power plants (plant
project interest rate 8 percent) ............................................................................ 31
Figure 16: Comparison of the different market development assumptions
of the CSP studies in comparison with the German wind market
development and the GMI—goal (cost competitiveness after
cumulative installed power of 5 GW in 10 years) .................................................. 32
Figure 17: The strategic position of Group 2 countries for the development
of CSP technology (example of the Mediterranean area) ......................................... 66
Figure 18: Global GHG concentration stabilization profi les (left) and emission
profi les for stabilizing greenhouse gas concentrations at 550 ppmv
(S550e) and 650 ppmv (S650e) versus baseline emissions ..................................... 75
Figure 19: Implementation of geothermal power plants worldwide ........................................... 77
Figure 20: Four stages in the development of CSP ................................................................ 79
Figure 21: Market environment for the introduction of CSP technology ...................................... 80
Figure 22: Various fi nancing mechanisms to cross the bridge toward competitiveness
and the role of carbon fi nancing in such a fi nancing strategy ................................... 88
Figure 23: Relative part load losses of the steam turbine for the daytimes when
solar fi eld is not providing solar steam for different ISCCS plant sizes ........................ 104
Figure 24: Daily load curve of the Moroccan electricity system ................................................ 125
Figure 25: Growth in electricity demand ............................................................................. 125
Boxes
Box 1:
What is Technology Transfer? .............................................................................
Box 2:
OP 7 Objectives .............................................................................................
Tables
Table 1:
Overview and status of CSP projects worldwide (excluding WB/GEF projects) ...........
9
Table 2:
ECOSTAR study – cost reduction potentials due to technical improvements .................. 14
Table 3:
Sargent and Lundy—technical improvements for the trough
and the tower technology .................................................................................. 15
Table 4:
Overall risk evaluation for the WB/GEF solar thermal portfolio ................................. 49
viii
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Table 5:
The critical points in the project development tree ................................................... 51
Table 6:
Summary of GEF project status ........................................................................... 53
Table 7:
Main success criteria for CSP strategy .................................................................. 84
Table 8:
Possible role of CSP in different countries/regions with suitable solar resources ............ 85
Table 9:
Example of CDM fi nancing for CSP .................................................................... 89
Table 10: Questions addressed to the short- and long-term CSP strategy by the WB/GEF ........... 90
Table 11: Evaluation of the current WB/GEF portfolio against the set
of success criteria for a long-term strategy for CSP .................................................. 91
Table 12: Overview of power plants owned by ONE in Morocco (2004) ............................... 181
ix
ADB
African Development Bank
AU
Australia
BMU
Bundesumweltministerium fuer Umwelt, Naturschutz und
Reaktorsicherheit (Federal Ministry for the Environment,
Nature Conservation and Nuclear Safety)
c/kWh
cents per kilowatt-hour
CC
combined
cycle
CCGT
combined cycle gas turbine
CEA
Central Electricity Authority
CER
certifi ed emissions reductions
CFE
Comisión Federal de Electricidad
(Federal Commision of Electricity)
CSP
Concentrating Solar Thermal Power
DNI
direct normal irradiance
DoE
U.S. Department of Energy
EEHC
Egyptian Electricity Holding Company
EPC
engineering, procurement & construction contract
ESCOM
South Africa Electricity Supply Commission
FERC
U.S. Federal Energy Regulatory Commission
GAIL
Gas Authority of India Limited
GDP
gross domestic product
GEF
Global Environment Facility
GHG
greenhouse
gases
GMI
Global Market Initiative (for Concentrating Solar Power)
GoI
Government of India
GoR
Government of Rajasthan
GT
gas
turbine
GW
gigawatts
GWh
gigawatt-hours
GWh
e
gigawatt-hours
electric
HRSG
heat recovery steam generator
HTF
high temperature fl uid
IEA
International Energy Agency
INR
Indian
rupee
IPP
independent power producer
IREDA
Indian Renewable Energy Development Agency
IRR
internal rate of return
ISCC
Integrated Solar Combined Cycle
ISCCS
Integrated Solar Combined Cycle System
JBIC
Japan Bank for International Cooperation
KfW
Kreditanstalt für Wiederaufbau (German Development Bank)
kWh
kilowatt-hour
kWh
th
kilowatt-hour
thermal
KSC
Key success criteria
LEC
levelized electricity costs
LNG
liquefi ed natural gas
MMBTU
million British thermal units
MNES
Ministry of Non-Conventional Energy Sources
MSP
medium-sized
project
MT
million
tons
MToe
million tons oil equivalent
MW
megawatt
MWe
megawatt
electric
MW
th
megawatt
thermal
NEAL
New Energy Algeria
L
I S T
O F
A
B B R E V I A T I O N S
x
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
NREA
New and Renewable Energy Authority
OECD
Organisation for Economic Co-operation and
Development
O&M
operation and maintenance
ONE
Offi ce National de l‘Electricité/National Offi ce of
Electricity
OP
Operational
Program
ORC
organic Rankine cycle
PCAST
U.S. President’s Committee of Advisors on Science
and Technology
PEF
Programa de Egresos de la Federación (Planning of
Expenses of the Federal State [of Mexico])
PIU
project implementation unit
PPA
power purchasing agreement
ppmv
parts per million by volume
PR
progress ratio (of learning curves)
PV
photovoltaics
R&D
research and development
RECs
renewable energy certifi cates
RES
renewable energy sources
RfP
request for proposals
RPS
Renewable Portfolio Standard
RREC
Rajasthan Renewable Energy Corporation
RVPN
Rajasthan Rajya Vidyut Prasaran Nigam Limited
SEGS
solar electricity generating systems
SF
solar
fi
eld
SolarPACES
International Energy Agency Implementing Agreement
for Solar Power and Chemical Energy Systems
ST
steam
turbine
STAP
GEF’s Scientifi c and Technical Advisory Panel
STEG
solar thermal electricity generation
STPP
solar thermal power plant
TCF
trillion cubic feet
TEC
techno-economic
clearance
TWh
terawatt-hours
UNFCCC
United Nations Convention on Climate Change
WB
The World Bank
xi
A
C K N O W L E D G M E N T S
Omar Benlamlih, Anna Bjerde, Georg Brakmann, Nourredine
Bouzaher, Anil Cabraal, Ralf Christmann, Gilbert Cohen, Jürgen
Dersch, Salah El Desouky, Gabriela Elizondo Azuela, Thomas
Engelmann, Ayman Fayek, Charles Feinstein, Khaled Fekry, Todd
Johnson, Michael Geyer, Juan Granados, Andreas Haeberle,
Volker Haeussermann, Tewfi k Hasni, David Kearney, Lizmara
Kirchner, Ludger Lorych, Thomas Mancini, Alex Marker, Abdellah
Mdarhri, Rene Mendonca, Paul Nava, Joachim Nick-Leptin, Hani
El Nokrashy, Robert Pitz-Paal, Klaus-Peter Pischke, Hank Price,
Jürgen Ratzinger, Thomas Rueckert, Pedro Sanchez Gamarra,
David Saul, Andre Szechowycz, Franz Trieb, Shri Rakesh Verma,
and Christine Woerlen.
Esther Monier-Illouz and Bob Livermarsh assisted in processing and
editing the fi nal report.
Note:
Most of the work underlying this study was carried out in
2005. Although the authors made their best efforts to refl ect the
changes that have occurred since then in this report it is possible
that some changes might have been left out.
T
his report was was funded by the World Bank Global Envi-
ronment Facility program (WB/GEF) and commissioned by
the World Bank‘s Global Environment Facility Coordination
Team, led by Steve Gorman.
At the World Bank, the project was supervised by Chandrasekar
Govindarajalu, senior environmental specialist, and Rohit Khanna,
senior operations offi cer. The report was written by a core team
of Wolfgang Eichhammer and Mario Ragwitz from the Fraunhofer
Institute for Systems and Innovation Research (ISI) in Germany, Ga-
briel Morin and Hansjörg Lerchenmüller from the Fraunhofer Institute
for Solar Energy Systems (ISE) in Germany, Wesley Stein from the
Commonwealth Scientifi c and Industrial Research Organisation
(CSIRO) in Australia, and Stefan Szewczuk from the Council for
Scientifi c and Industrial Research (CSIR) in South Africa.
The authors would like to thank everyone who contributed their
fruitful thoughts and inputs to this report through comments dur-
ing phone interviews or active workshop participation, includ-
ing Rajeev Agarwal, Shri Salauddin Ahmed, Miguel Angel,
xii
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
xiii
E
X E C U T I V E
S
U M M A R Y
G
lobal warming is now widely considered a very
signifi cant poverty and security issue. The associated
detrimental effects are likely to particularly manifest
themselves in many developing countries. Though
most of the anthropogenic emissions thought to be contributing to the
effect have historically come from the countries of the Organisation
for Economic Co-operation and Development (OECD), modeling
shows that in the future the bulk of emissions will come from coun-
tries such as India and China. It is therefore in the World Bank’s
interest to contribute to the identifi cation and support of solutions
to GHG emission reduction.
The GEF’s Operational Program 7 (OP 7) supports the develop-
ment of technologies with low greenhouse gas emissions that are
not yet commercial, but which show promise of becoming so in
the future. In 1996, the GEF’s Scientifi c and Technical Advisory
Panel (STAP) recommended high-temperature solar thermal power
technology as one of the renewable energy technologies that had
very signifi cant cost reduction potential and potentially a high
demand from countries in the world’s solar belt. Concentrating
solar power (CSP) was viewed as the most cost-effective option
to convert solar radiation into electricity, and has been operation-
ally proven in California since the mid-1980s. Successively, four
solar thermal projects entered the GEF CSP portfolio with a grant
volume of $194.2 million in total managed by the World Bank:
(1) the Egypt Solar Thermal Hybrid Project in Kuraymat, Egypt; (2)
the India Solar Thermal Project in Mathania, India; (3) the Mexico
Hybrid Solar Thermal Power Plant Project in Agua Prieta, Mexico;
and (4) the Morocco Integrated Solar Combined Cycle Power
Project in Ain Beni Matar, Morocco.
Each project has encountered signifi cant delays. Apart from an
unsuccessful attempt on behalf of the Indian project in 2003, no
requests for proposals (RfPs) have yet been issued from any of the
four projects until very recently. This suggests the diffi culties en-
countered have been predominantly associated with non-technical
issues, which are examined in this study.
Solar thermal electricity plants were introduced in California in the
1980s, but no new commercial-scale solar thermal electricity plant
has been commissioned in the last 12 years. This was primarily
due to insuffi cient fi nancial incentives. Research and development
(R&D) has since led to improved solar fi eld components and new
thermal storage concepts. In addition, operation and maintenance
experience has continued to emerge through the existing California
plants. However, past construction experience has been lost, and
there is a feeling outside the solar thermal industry that this is still
a relatively new technology with associated risk.
Over the last 12 months, the industry has been reinvigorated.
Several projects are presently under construction around the world.
Nonetheless, these projects have not reached the kind of critical
mass to suggest that the industry is now self-sustaining. In fact, the
industry is presently nascent, and as a result fragile. “Firm” projects
presently total less than 300 megawatts (MW), whereas several
thousand megawatts would be required for the industry to approach
commercial competitiveness. By comparison, wind energy—the
most successful renewable technology in recent times—is now
exceeding 60,000 MW of global installed capacity.
Solar thermal electricity offers a number of advantages when con-
sidered as part of a country or region’s energy generation options
mix. Solar energy is the world’s most abundant sustainable resource.
It represents an even larger resource because of the favorable
geography of many of the world’s developing countries. Solar
thermal, based on a hot fl uid, can integrate well with conventional
xiv
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
thermodynamic cycles and power generation equipment, as well as
with advanced, emerging technology. It offers dispatchable power
when integrated with thermal storage, and thus good load matching
between solar insolation (exposure to sunlight) and the strong growth
(in many countries) in electrical demand during summer. The collec-
tor technology itself is constructed of predominantly conventional
materials—glass, steel, and concrete, and no fundamental scientifi c
breakthroughs are required for the cost to continue to drop. There
is also the advantage that at a time when deep cuts to greenhouse
gas emissions are being called for, solar thermal can be installed in
large capacities, yet constructed of modular, repeated, well-known
components. However, this also raises perhaps the major barrier
for the technology at present. Depending on solar radiation levels,
the cost of electricity for a one-off plant is presently around 16 to
20 cents per kilowatt-hour (c/kWh), which might be acceptable
for some small applications (kilowatts or a few megawatts), but
diffi cult to justify for larger multi-MW installations.
This report determines that solar thermal electricity technology is
worthy of continued support. The benefi ts of a successful industry,
particularly for developing countries, are signifi cant. The technol-
ogy is not new, but stalled in its development path. All required
technology elements are essentially already in place. The major
outstanding issue is the need for cost reduction, and this study
concludes that there is no fundamental reason why the technology
could not follow a similar cost reduction curve to wind energy and
eventually be cost-competitive. However robust, long-term support
mechanisms will be required.
The major studies associated with cost reduction potential of
solar thermal electricity technology were reviewed in this study,
with some inconsistencies noted in a couple of them. The most
detailed and conservative of the recent studies predicts that com-
mercial competitiveness could be achieved with installations of
around 42 gigawatts (GW) (similar to wind capacity today), not
including allowance for any cost of carbon. This would represent
approximately 1 percent of the global installed power generation
capacity and require subsidies of about
€
12 billion. An allowance
for a carbon cost beginning at
€
7.50 per ton of carbon dioxide
(/t CO
2
) would decrease this capacity to 22 GW, and reduce
required subsidies to
€
2.5 billion. Cost reductions are expected to
come from a combination of plant scale-up (larger plants), increased
production volume, and technological innovation.
The fi gure below plots the required CSP installation rate required
to achieve cost-effectiveness by 2020. It shows that the required
growth rates for solar thermal electricity to achieve cost-competitive-
ness are quite moderate compared to what wind, the fastest grow-
ing energy technology in the world, has achieved. The “probable
to fi rm” represents a prediction based on an analysis of the status of
global CSP projects at present. The Global Market Initiative (GMI)
is a proposed industry target to reach 5,000 MW of installed CSP
by 2015. The growth from 2005 until 2009 is a prediction based
on those projects beyond the stage of formed consortia, and with
fi nancial closure either in hand or imminent.
The table below lists known projects in progress (excluding WB/
GEF projects).
The major success factors required to create a sustainable solar
thermal electricity market are:
Targets
, initially specifi c to CSP
Appropriate fi nancial support
, again initially specifi c to CSP,
including a mix of both investment and production credits
Supporting legislation and regulation
In all the above, it is important that two things are maintained within
the support framework:
0
5,000
10,000
15,000
20,000
25,000
30,000
Cumulative installed MW
35,000
40,000
45,000
50,000
GMI target to reach 5,000MW
by 2015
Probable to firm based on
present statu
1980
1985
1990
1995
2000
2005
2010
2015
2020
Global wind installed capacity
C
UMULATIVE
INSTALLED
CSP & W
IND
C
APACITY
xv
E
XECUTIVE
S
UMMARY
Concept
formally
Consortia
fl oated and pre-
formed—ready
Country and plant details
liminary assess-
to bid or RfP
Financial
Construction
Fully commissioned
(not including GEF projects)
ment conducted
ready to release
closure
commenced
and operating
Algeria 25 MW trough, ISCCS
Ö
Ö
Ö
2006/7 (Original
Possibly 2009
expectation
Sep
2005)
Arizona 1 MW trough ORC
Ö
Ö
Ö
Ö
Ö
(since April 2006)
Australia/Solar Heat and Power Pty Ltd,
Ö
Ö
Ö
Ö
(of fi rst stage)
First stage under
38 MW Fresnel into coal-fi red power station
commissioning
Australia/Solar Heat and Power Pty Ltd, 250
Ö
MW Fresnel, stand-alone with thermal storage
Australia 120 kW tower providing
Ö
Ö
Ö
Ö
2006
solar-reformed natural gas to a heat engine
China/Ordos 50 MW trough
Ö
India/Solar Heat and Power Pty Ltd,
Ö
Ö
5 MW, Fresnel
Iran 67 MW trough, ISCCS
Ö
Israel 100 MW trough
Ö
Ö
Italy/Empoli (2x 80 kW solar gas turbine
Ö
Ö
Ö
Ö
with waste-heat usage for air-conditioning)
Jordan 135 MW trough
Ö
Ö
(RfP 2001)
Nevada 64 MW trough
Ö
Ö
Ö
Ö
(February 2006)
Estimate March 2007
Portugal/Solar Heat and Power Pty Ltd, 5 MW
Ö
Ö
with potential to upgrade to 50 MW, linear Fresnel
Spain/ACS + SMAG, Andasol-1 50 MW trough
Ö
Ö
Ö
(June 2006)
Expected July 2006
Around late 2007
Spain/ACS + SMAG, Andasol-2
Ö
Ö
2006
Expected 2006
Around early 2008
50 MW trough
Spain/Abengoa, PS10 11 MW tower
Ö
Ö
Ö
Ö
Estimate
July
2006
(saturated steam)
Spain/SENER, Solar Tres 15 MW tower
Ö
Ö
(molten salt)
Spain/EHN+SolarGenix, 15 MW trough (HTF)
Ö
Ö
Spain/Iberdrola, 7x50 MW Trough (HTF)
Ö
Ö
Spain/HC, 2x50 MW Trough (HTF)
Ö
Ö
Spain/Abengoa, 2x 20 MW Tower, 1x 50 MW Trough
Ö
Ö
Spain/SMAG,50 MW ExtremaSol 1
Ö
Ö
Spain/5 MW trough with direct steam generation
Ö
Ö
(INDITEP)
Spain/Solar Heat and Power Pty Ltd, 5 MW, Fresnel
Ö
Ö
South Africa/100 MW Molten salt tower
Ö
K
NOWN
PROJECTS
IN
PROGRESS
xvi
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Encouraging competition
. As costs drop over time, the level of
mandated support should be correspondingly reduced.
Providing certainty for investors. This technology requires not only
long-term price security, but also an assurance that rollout can
continue through subsequent plants if stated targets are met.
The following table shows the present status of the existing GEF
portfolio.
CSP technology does not currently contend with signifi cant threats
from other zero emission technologies. In the case of other renew-
ables, their present contribution to global electricity supply is small,
and there is room for new technologies to emerge. In particular,
renewable resources are, by their very nature, geographically
diverse. This tends to support rather than diminish the principle of
encouraging a mix of energy options. Even in a particular region,
different technologies tend to fi t different parts of the electricity
market. For example, photovoltaics can act ideally as distributed
generation, whereas CSP fi ts centralized generation. Of the dis-
patchable non-hydro renewables, geothermal and bioenergy are
quite site-specifi c, and thus resource-constrained, in the same way
that CSP is resource-constrained in some climates.
We can see three options for the World Bank at this point. They
are:
1. Pull out of CSP altogether and perhaps support a different, zero
GHG technology path under OP 7. Given the delays to date,
and quite likely some more hurdles to come, this would appear
an attractive option. However, the goals of OP 7 are worthy,
and it is important that a visible organization such as the World
Bank takes the lead in such issues. Of the zero GHG technolo-
gies that are technically feasible yet not yet commercial, CSP
Country/project
Status of project
Project structure
Expected schedule
India, 140 MW ISCCS incl. 35 MW
WB waited on letter of commitment from
Single EPC with O&M (5yrs). PPA with RVPN. Eventually, the project could not be timely
solar trough, site approximately
GOI, after which the already drafted RfP
Project owner RREC.
implemented due to inappropriate design
2,240 kWh/m
2
/year DNI.
(revised) could be released.
and location.
Egypt/Kuraymat, 151 MW ISCCS incl.
Financial closure agreed. Solar thermal part
Two EPC contracts. The solar island will be
Delays due to the splitting of the packages to
25 MW solar.
and CC at bidding stage.
an EPC with O&M contract; the CC island
be funded by GEF, NREA, and JBIC. Contract
will be an EPC contract with local O&M to
signature expected for early 2007.
be bid separately fi nanced by NREA.
Construction might begin late 2007.
Possible begin of operation late 2009.
Mexico/El Fresnal near Agua Prieta,
November/December 2005: Approval by
The fi nal owner of the plant will be CFE.
At this stage, bidding is expected for 2006,
Sonora State (site decision in March
the Treasury Ministry. The hybrid plant
They will undertake to provide the O&M.
construction to begin 2007, operation 2009.
2005, plant Agua Prieta II), originally
has been included in the PEF (Programa
(Previously, unsuccessful project
285 MW ISCCS but fi nally increase CC to
de Egresos de la Federación) and
development under IPP scheme.)
560 MWe; Solar trough fi eld 25–40 MW; approved by Congress.
Excellent solar site conditions (exact solar
Acceptance of the doubling of fossil capacity
data not available).
by the WB task team after technical
economic assessment by Sargent and Lundy
(May 2006) and a consultancy by
Spencer
Management.
Morocco/Ain Beni Mathar 240 MW ISCCS, EPC with O&M (5 years). Option exists to
Owner of plant will be ONE. Total cost
EPC with O&M contract for the project
including 30 MW trough. Expected
renew O&M contract after 5 years. Bids
expected approx
€
213M, including connection expected to be signed by the end of 2006,
production from ISCCS 1,590 GWh/year, received May 2006. Ongoing evaluation
to infrastructure.
€
43M from GEF, and
€
34M and at the latest in January 2007.
of which approx 55 GWh/year solar (3.5
process.
from ONE. Balance of
€
136.45M from
Expected start of operation of the plant is
percent solar contribution).
African Development Bank as soft loan.
mid 2009 (construction time 30 months).
P
RESENT STATUS OF THE EXISTING
GEF
PORTFOLIO
xvii
E
XECUTIVE
S
UMMARY
is a lead candidate. If the goals of OP 7 are to be pursued, as
they should, other technology paths may prove more frustrating,
and ultimately less rewarding, than CSP.
2. Provide minimalist support to the present portfolio and “wait and
see.” The CSP industry, beginning again in earnest, is presently
fragile. Against the thousands of megawatts needed for CSP
to reach cost-effectiveness, the 120 MW of WB/GEF projects
will not, of themselves, lead to any signifi cant reduction in the
underlying cost of the technology. Wind technology grew in the
OECD countries before it was cheap enough to be used on a
large scale in the developing countries. The same could be done
for CSP. This would be an easy solution, but with the industry
on a cusp, such a decision could be responsible for tipping the
industry toward a demise. Though 120 MW is small against
thousands of megawatts, it is quite large against the present
300 MW or so of possible-to-fi rm projects in OECD countries.
These four projects are instrumental for the following reasons:
They are important to the global CSP industry as they
constitute a signifi cant percentage of planned projects at
present, especially if three or four proceed. Inevitably, some
will not proceed, so the more that are planned, the more
robust will be the early implementation phase. They provide
momentum and continuum to the global industry, which in
turn will provide benefi ts to the developing countries when
future projects are developed.
The developing countries with good exposure to sunlight
(insolation) could play a more signifi cant role in CSP than in
wind. We have not conducted a quantitative analysis, but
there is at least anecdotal evidence to suggest that direct
beam solar radiation is a larger ratio than wind when com-
pared to the resources of the OECD countries.
They will reveal at an early stage any major impediments to
successive plants. Some of these have already been revealed
and are discussed in this report.
3. Provide strong support to the present portfolio, embark on parallel
paths toward supporting more projects, and work pro-actively
to promote the technology globally, with the idea that global
progress benefi ts the World Bank portfolio.
This study suggests a combination of 2 and 3 above as the rec-
ommended path. This essentially allows a prudent, active support
of the technology, but with appropriate exit strategies if various
milestones are not met. We do not advocate that the developing
countries take a lead share of the risk in developing the CSP market.
But the strong solar resource in many of the developing countries,
and the relative simplicity of CSP technology, suggests developing
countries should take a more proactive role than other emerging
energy technologies. However, we do advocate a role in parallel
with present global developments.
A strategy fi rst requires a vision. The following is proposed—
“CSP
should be supported to encourage a rapid growth phase to the point
that it plays a key role in the electricity supply mix of developing
countries where there is a good solar resource.”
The table below recommends a phased strategy for the World Bank
to pursue, with inherent exit paths. The four phases are explained
in the CSP cost reduction curve below.
The key issues and recommendations are:
Make the request for proposal (RfP) specifi cations concerning the
solar fi eld more fl exible. They should allow bids from alternative
collector types and encourage storage.
We would strongly recommend that the bid not specify a
particular solar fi eld capacity, but rather a minimum threshold,
with the capacity offered an assessment criteria. The resulting
competition will ensure the maximum capacity possible is offered
for the fi nance available.
The issue of integrated solar combined cycle systems (ISCCS)
versus stand-alone solar is not critical from a technical basis.
Ultimately, larger solar contributions are desirable, but in these
early days, it is important for operation & maintenance (O&M)
experience to be gained in these countries, and a 200,000
m
2
fi eld will yield similar levels of O&M expertise whether it is
attached to a stand-alone Rankine cycle or to a Rankine cycle
as part of a combined cycle plant. There are likely to be some
early “teething’ problems with ISCCS, simply because it hasn’t
been done before, but should present no problem with good
engineering.
xviii
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
The single engineer, procure, construct (EPC) approach pre-
sented some issues when these projects were fi rst mooted, but
with strong consortia now in place as a result of activities in
other countries such as Spain, the handling of liabilities within
the consortium should be possible.
The two-EPC approach in Egypt—that is, a solar fi eld EPC
contract and a combined-cycle EPC contract—is not new in
the power industry. Many power stations are constructed with
multiple parallel contracts. However, it will tend to limit the fl ex-
ibility of the technologies that can be offered. The liability for
Key Success
Criteria (KSC)
Comment
Importance
Response to RfPs
Critical that a good number of bids are received from robust consortia.
Crucial
Contracts signed for at least two projects Having less than two projects proceed to contract signature would represent a relative failure
of the portfolio. More than two would indicate a healthy CSP portfolio and a good reason to continue.
High
Continuing CSP project activity in other
Though the WB has no control over projects in other countries, it would be prudent to maintain
Medium to high (unless global
countries and fi rst plant installations
a watching brief to ensure the WB/GEF portfolio is not advancing in isolation. This is not so crucial to
CSP activity ceases)
the existing portfolio, but failure of this criteria would prevent movement to Phase 2.
Reallocation of balance of GEF funds
If one or two of the four projects are not successful (based on missing key deadlines without due
Medium
cause), and the above three KSCs have been met, it is recommended that the balance of funds be
reallocated by a competitive call for proposals. It is likely that bidding countries—such as Algeria,
Iran, Jordan, and China—would already have signifi cant progress on their projects.
Continuing emergence of CSP
CSP market development is a long-term process. It will be on the order of 1 year before construction
High
projects in other countries
commences on the fi rst WB/GEF project, a further 2 years until operation commences—realistically
a minimum of 4 years from now until there is a good level of operational data. This affords a good
opportunity for the WB to assess CSP progress internationally.
Successful operational performance
By this time, some good operational data will be emerging from the GEF portfolio, as well as a
High
of Phase 1 WB/GEF projects
number of plants in other countries.
Evidence of legislated fi nancial
Many countries have renewable energy policies and targets, but only fi nancial incentives that have
Medium to high
support mechanisms for CSP
the backing of legislation are useful for bankable documentation. Given that in Phase 2 there is still
a considerable fi nancial gap to be fi lled, it is desirable that target countries are showing commitment
to a domestic CSP industry.
New portfolio of WB projects
If the above KSCs have been satisfactorily met, a new competitive call for proposals should be
High
successfully commenced
launched. The timing will be dependent on the above KSCs.
Emergence of key countries/regions
By this time, key countries or regions will have begun to emerge. It is important that countries are
High
taking the initiative to the World Bank rather than what has to this point tended to be the other
way round. If this interest is not shown, it would be a moot point as to whether the WB should
be pursuing them.
Contribute to development of local
As more plants are destined for developing countries, local solar component manufacturing expertise
Medium to high
manufacturing and operating experience should emerge. It is not, for example, a very expensive matter to set up a tube manufacturing facility.
In addition, if a region such as the Mediterranean emerges, a Mediterranean team (cross-country) of
expertise in construction could make sense.
WB/GEF part of a global CSP fund
If the CSP market has reached this stage, a huge mobilization of funds will be in progress. A global
Medium to high
CSP fund would be an attractive means of helping to leverage WB/GEF funds. The GEF contributions
could be partitioned within the fund to remain with developing countries.
Contribute to the sustainable
Economic (employment, manufacturing) and environmental (international recognition for spurring a
Medium to high
development of a country/region
new renewable technology) benefi ts should have begun to emerge.
Phase 1
Phases 3 & 4
Phase 2
P
HASED STRATEGY FOR THE
W
ORLD
B
ANK TO PURSUE
xix
E
XECUTIVE
S
UMMARY
any engineering design problems occurring between the solar
fi eld and the heat recovery steam generator (HRSG) will rest
with the owner and designer.
WB/GEF funds could be leveraged most usefully through
participation in a global CSP fund. Project proposals would
be bid on a competitive basis for funds. Awarded proposals
could combine a mix of up-front grant monies, and a longer-
term power purchasing agreement (PPA) through the fund.
The WB/GEF funds could be partitioned such that they were
only available to developing country projects. By that time,
particular regions may be emerging as the most attractive op-
portunities.
0
2
4
6
8
10
12
14
16
18
20
CSP
Fossil alternatives
2005 2007 2009 2011 2013 2015 2017 2019 2021 2023 2025
Creation of technical
and institutional experience
1
2
3
4
Generation of
a CSP market
Early CSP
mass market
Near competitive and
competitive market
LEC (cUS/kWh)
CSP
COST REDUCTION CURVE
xx
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
1
1.1 O
PERATIONAL
P
ROGRAMS
OF
THE
G
LOBAL
E
NVIRONMENT
F
ACILITY
Mitigating climate change and achieving stabilization of atmo-
spheric concentrations of greenhouse gases—the objective of the
United Nations Convention on Climate Change (UNFCCC)—will
require deep reductions in global emissions of energy-related
carbon dioxide emissions. Developing and deploying new, low-
carbon energy technologies will thus be needed, in particular
in developing countries where the largest growth in emissions is
expected to occur.
The Global Environment Facility (GEF) has operational programs
that promote the deployment of renewable energy (Operational
Program 6, or OP 6) and energy effi ciency (Operational Program
5, or OP 5) by assisting in the removal of barriers to the use of
energy effi cient technologies and commercial or near-commercial
renewable energy technologies. The objective of these programs is
to lay the foundation for increased public and private investments in
renewable energy and energy effi cient technologies (STAP, 2003;
Mariyappan and Anderson, 2001). An operational program is a
“conceptual planning framework for the design, implementation,
and coordination of a set of projects to achieve a global environ-
ment (that) organizes the development of country-driven projects
and ensures systematic coordination between the implementing
agencies and other actors.”
Operational Program 7 (OP 7) is devoted to “reducing the long-
term costs of low greenhouse gas-emitting energy technologies.”
Its objective is to reduce greenhouse gas emissions by accelerat-
ing technological development and increasing the market share
of low greenhouse gas-emitting technologies that have not yet
become commercial, but which show promise of becoming so in
the future. To achieve this objective, GEF promotes technologies
through fi nancing demonstration projects with a view to bringing
down energy costs to commercially competitive levels, through
technological learning and economies of scale.
Under Operational Programs 5 and 6, the GEF funds the incre-
mental cost of barrier removal; under Operational Program 7, it
funds the incremental cost of the technology.
1.2 CSP
FUNDING
WITHIN
O
PERATIONAL
P
ROGRAM
7
The GEF’s Scientifi c and Technical Advisory Panel (STAP) believes
that OP 7 should be an important element in GEF operations. In
particular, two technologies—grid-connected photovoltaics and
solar thermal technologies—are thought to have comparative
cost advantages because of high solar insolation in developing
countries.
Solar thermal technology has been demonstrated in the state of
California over the past 15 to 20 years. However, the integration
of solar thermal technology with a combined cycle gas turbine
(ISCCS)—the choice to date for a hybrid system in the WB/GEF
solar thermal portfolio—has not been demonstrated. Such integra-
tion has advantages and disadvantages, which are discussed more
fully in Chapters 2 and 3.
In 1996, GEF’s Scientifi c and Technical Advisory Panel (STAP)
recommended high temperature solar thermal power technology
as one of the renewable energy technologies that had very sig-
nifi cant cost reduction potential and potentially a high demand
from countries in the world’s solar belt. Concentrating solar power
1
S
E T T I N G
T H E
C
O N T E X T
2
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
(CSP) was considered the most cost-effective option of converting
solar radiation into electricity; it had been operationally proven
in California since the mid-1980s. However, no follow-up invest-
ments were made when California terminated a favorable tax
policy, and the industrial development slowed down consider-
ably. Any activity that did continue consisted mostly of research
and development programs in Europe and the United States and
considerable efforts to revive the technology on the part of the
solar industry.
The Mathania solar thermal power plant in India was the fi rst to
enter GEF’s Operational Program 7 in 1996 as part of a larger
strategy. In this larger strategy, the proposed project in India was
expected to be the fi rst in a series of multi-country investments that
together would facilitate the commercialization of solar thermal
technology. Similar projects in Mexico, Morocco, and the United
States were in advanced stages of preparation. Additional solar
thermal projects were under consideration in Egypt, Tunisia, Israel,
Jordan, Spain, Italy, and Greece (Crete). Other countries in the high
insolation regions of Africa had also shown interest. While not all
of these projects were expected to materialize in the near term, up
to four projects, including the initiative in India, were anticipated to
be developed by 2001. The combined effects of these projects, it
had been concluded, would be to accelerate the process of cost
reduction, demonstrate the technical performance of the technology
in a wider range of climate and market conditions, and create a
sustainable market for parabolic trough solar thermal technology.
Subsequently, the GEF approved two more projects for OP 7,
namely those under development in Mexico and Morocco, with a
fourth project in Egypt. Presently, the WB/GEF solar thermal portfo-
lio consists of projects in four countries—Egypt, Morocco, India, and
Mexico—with a total solar capacity of approximately 120 MW
and a total WB/GEF commitment of around $200 million. It is
expected that these projects would help benchmark the costs of
technology and contribute to an understanding of the institutional
and regulatory requirements for this and other advanced renewable
energy technologies in developing countries.
Apart from these four projects, GEF-supported project preparations
exist in Brazil and South Africa. South Africa’s utility ESCOM has
undertaken a feasibility study for a 100 MW solar tower. Other
countries have shown interest in receiving GEF support for similar
plants, including Algeria, Iran, Jordan, and China.
To date, the number of OP 7 projects supported has been small
(not just CSP) and the achievements limited. OP 7 has proven to
be a diffi cult portfolio to develop.
1.3 L
ESSONS
FROM
PAST
STUDIES
ON
THE
GEF
SOLAR
THERMAL
PORTFOLIO
All four solar thermal projects in Mexico, Morocco, Egypt, and India
have experienced implementation problems. These four projects
were reviewed in 2001 by Mariyappan and Andersen. Apart from
highlighting common implementation problems (power sector restruc-
turing, general diffi culties of IPP projects in emerging markets) as a
reason for delay, the report alluded to three OP 7 specifi c issues:
i. The contradiction between the drivers of economic develop-
ment in developing countries, i.e. poverty alleviation, and
those of the developed world, i.e. environmental concerns,
generates a mismatch of global expectations and local willing-
ness-to-support these projects.
ii. There has been insuffi cient dialogue between GEF and the CSP
industry during project design, adoption of the CSP strategy,
and project implementation.
iii. GEF has remained the only signifi cant funding source
1
for these
CSP plants.
These issues continue to be at the center of the strategic discussion
on CSP.
In May 2004, GEF published a status report on the solar thermal
portfolio (World Bank, 2004) and argued that the portfolio offers
a variety of lessons related to project preparation, co-fi nancing,
procurement, and progress toward cost reduction.
Project preparation:
Initially the four projects were prepared
as independent power projects (IPPs), but have since been
1
We note that international funding organizations such as KfW, JBIC, and
ADB have offered soft loans, and that national bodies such as the Govern-
ment of India or ONE in Morocco have offered smaller grants.
3
C
HAPTER
1 – S
ETTING
THE
C
ONTEXT
changed and are now being developed as public sector power
projects. This lack of success of the IPP approach appears to
be not only the result of risk aversion to integrated solar thermal
and combined cycle technology in the private sector, but also a
general global decline in IPP interest in developing countries.
Co-fi nancing:
Securing full co-fi nancing is a key feature, as the
four projects are now being developed as public sector power
plants.
Procurement:
There are a limited number of global consulting
fi rms and suppliers in the solar thermal industry. In the WB/GEF
projects, the solar contribution of the integrated solar combined
cycle technology is in the 5 percent range, and consequently
the lead for these hybrid projects would be taken by mainstream
power generation fi rms. Risk perception by the bidders and risk
reduction strategies would be a major barrier to overcome.
Progress toward cost reduction: Experience to date has certainly
helped identify the issues in preparing and structuring solar
thermal projects in developing countries, but progress toward
cost-reduction can only be evaluated with a fair degree of
confi dence after contracts have been negotiated and awarded
to selected bidders, and particularly after operation has com-
menced.
Further lessons learned have been put forward by Cédric Philibert
(2004) of the International Energy Agency:
Lesson 1:
International collaboration may help, but domestic
policy decisions remain decisive.
Lessons 2&3:
In technology transfer, non-fi nancial barriers must
not be underestimated; developing new, large-scale technolo-
gies in developing countries only may not work.
Lesson 4: Sharing the necessary “learning investments” might
be a good idea.
An interpretation of these four lessons, as well as those lessons
presented earlier in this section, is that technology transfer in devel-
oped countries has its own set of challenges. However, technology
transfer into developing countries is very likely to face even further
challenges, including a lack of appropriate policy, legislation,
institutional structures, human resources, (venture) capital resources,
and industrial partners willing to consider new technologies. In
general, economic and institutional barriers rather than technol-
ogy availability are more apt to be the cause of failure to transfer
technology (see the brief review of defi nitions related to technology
transfer in Box 1).
1.4 A
IMS
OF
THE
S
TUDY
The main objective of this assignment was to assess the strategy
being followed by the Bank/GEF for solar thermal power technol-
ogy in light of:
1. The current state of technology, costs, and market develop-
ment;
2. The diffi culties experienced by the GEF co-fi nanced projects, as-
sessing the three primary risks facing the Bank/GEF portfolio:
a. Limited industry response,
b. Uncertainty of meeting the cost and performance targets,
and
c. Uncertainty of sustainability and replicability arising from the
absence of long-term country or international commitments;
3. The original objectives of the portfolio.
1.5 S
COPE
OF
W
ORK
According to the aims of the investigation, the following three tasks
were carried out and are presented in the following chapters:
Task 1—Summary of Solar Thermal Technology Growth:
Brief
summary of the development of the CSP technology thus far (in-
cluding the current international experience in the implementation
of solar thermal power projects), the technological improvements
and cost forecast scenarios (results described in Chapter 2 and
Annexes 1–3).
4
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
B
OX
1: W
HAT
IS
TECHNOLOGY
TRANSFER
?
The term “technology transfer” tends to mean different things to different entities, generally giving fl exibility to individuals and organiza-
tions within their practices. However, most broad defi nitions include (Lawrence-Pfl eeger et al, 2003):
technology—as an idea, practice or object resulting from research, as well as an embodiment of the technology;
the movement of technology into a setting where it can improve a product or process in some way; and
an entire process involving facilitators at different steps, including those who create the technology, those who incorporate the technol-
ogy into a useful product, service, tool or practice, and those who further develop the technology for commercialization and use.
In the context of the above defi nition, the WB/GEF can be viewed as a facilitator in the transfer of technology.
The United Nations Environmental Programme’s (UNEP) Intergovernmental Panel on Climate Change (IPCC, 2000) defi nes the term “tech-
nology transfer” as a broad set of processes covering the fl ows of know-how, experience, and equipment for mitigating and adapting to
climate change among different stakeholders such as governments, private sector entities, fi nancial institutions, and NGOs. The broad
and inclusive term “transfer” encompasses diffusion of technologies and technological cooperation across and within countries. It covers
technology transfer processes among developed countries, developing countries, and countries with economies in transition. It comprises
the process of learning to understand, utilize, and replicate the technology, including the capacity to choose and adapt to local conditions
and integrate it with indigenous technologies.
The transfer of technology may be limited because of existing barriers, barriers that may arise at each and any stage of the process of
technology transfer. These barriers vary according to the specifi c context, for example from sector to sector, and can manifest themselves
differently in developed countries, developing countries, and countries with economies in transition.
The U.S. President’s Committee of Advisors on Science and Technology (PCAST, 2003) investigated the processes associated with the
transfer of technologies. Based on their investigations, a diagram describing this process of technology transfer via a value chain has
been developed (Figure 1).
The PCAST depiction of the technology
transfer process highlights the gaps or bar-
riers that need to be overcome before a
technology is deployed successfully on a
widespread scale. Included in the PCAST
value chain technology transfer process are
the potential sources of funding that can be
accessed to cover the various stages of the
value chain. It should be noted that GEF fund-
ing is viewed as a possible source of funds
from demonstration, through buy-down, and
into the widespread deployment of a technol-
ogy. The value chain process as depicted in
Figure 1 can readily be broadened to include
the developing countries and countries with
economies in transition. Also worthy of note
is PCAST’s view of the role that GEF could
play in technology transfer.
Value Chain
Proposals for “filling the gaps”
Lab/Bench scale
DOE/EPA
DSF (GEF or in country)
CETO (via GEF)
USAID/DOE/EPA
Trade Agencie
GEF
MDBs
Pilots
Small
# of units deployed
Medium
Commercial scale
MW/plan
$/units
Source:
PCAST (2003).
Figure 1: “Gap” identifi cation in technology transfer
5
C
HAPTER
1 – S
ETTING
THE
C
ONTEXT
Task 2—Risk Assessment and Mitigation:
Assessment of risks and
the adequacy of risk mitigation measures provided in project
design in the WB/GEF portfolio. This assessment included
technological performance risk, fi nancial/commercial risks,
regulatory/institutional risks, and strategy risks (results described
in Chapter 3).
Task 3—Market Development Strategy: Following on Tasks 1
and 2, the report considers the chances of realization and the
bottlenecks of each of the four projects in the WB/GEF port-
folio (results described in Chapter 4 and Annex 4). Chapter 5
discusses the importance of the WB/GEF portfolio in the future
development of CSP technology and strategies beyond the cur-
rent portfolio, including projected market impacts of partial or
full implementation of the current portfolio; the extent to which
WB/GEF projects will contribute to the development of this
technology; conditions necessary for further technology develop-
ment; and commercialization following the implementation of
the projects in the WB/GEF portfolio.
This report integrates lessons from previous reports (see references)
and personal surveys/interviews with key stockholders in the four
GEF projects: the World Bank, GEF, target country decision mak-
ers on the WB/GEF CSP projects, fi nancing institutions, industry
(combined cycle & solar fi eld) and consultants. A list of interviewed
organizations/persons is provided in Annex 5.
6
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
7
T
his chapter describes ongoing CSP developments world-
wide; the technological paths of concentrating solar
thermal power plants; and projected cost reductions for
CSP technology due to recent technology improvements,
scale effects (larger plant size), and volume effects (accumulated
capacity). This provides the necessary background for the evalu-
ation of the WB/GEF CSP portfolio and the future development
of CSP.
2.1 O
NGOING
CSP
MARKET
DEVELOPMENT
WORLDWIDE
The solar electricity generation systems (SEGS) plants of Southern
California are well-known for their many successes, not the least of
which was their ability to be constructed relatively quickly and to
meet the constraints associated with various fi nancial incentives. It
is also well-known that no signifi cant commercial plants have been
built since the last SEGS plant in 1990.
Since that time, developers and researchers have been busy im-
proving the various components of the technology, not only in solar
research institutions but also importantly in the fi eld, making use
of the SEGS plants themselves. In fact, the SEGS V fi eld was used
for the purpose of testing an improved collector for the Andasol
project in Spain (SKALET loop) under real conditions. Operation
and maintenance costs have dropped through improved compo-
nents and practices. Importantly, these improvements have been
measured in the fi eld, not just in desktop studies. The nine SEGS
plants were constructed with an investment cost of $1.2 billion,
all private capital. More than 13 TWh of solar electricity were
produced from these plants by 2005, with electricity sales of over
$2 billion. These projects were successful as a result of favorable
Federal Energy Regulatory Commission (FERC) regulations, tax
credits, and attractive time-of-use tariffs (14 c/kWh on average
and up to 36 c/kWh during summer peak).
The sudden loss of all of the favorable conditions in the early 1990s
left no incentives in either the OECD or developing countries. A
shortcoming of that period is that no legacy or supporting framework
was left behind despite all the investment activity. This meant that
the only CSP players left to further the CSP technology after the
SEGS plants had been built were the component manufacturers
themselves. The SEGS operating companies were mainly concerned
with operating what was there, not expansion.
The power manufacturing industry was facing stiff competition at
the time, so margins were very tight, with no room to support the
development of CSP, especially when there were no incentives in
place. Deregulation was occurring in the power industry all over
the world, and the resulting competition, along with only a fl edg-
ling green power market at the time, meant that utilities could no
longer afford to support projects that promised long-term strategic
value but uncompetitive short-term returns. Wind power began to
grow at this time, as units could be installed in small manageable
capacities with a limited fi nancial risk.
Up until a couple of years ago—as interest in Spain, Arizona, and
the GEF projects emerged—there were about two to three times
more CSP researchers than industry personnel. This strong R&D inter-
est has kept the technology progressing during the hiatus period;
however, the industry is likely to stagnate unless the technological
advances that have emerged since 1990 are put into practice.
The industry also has developed a much better understanding of
real-world project fi nance, as well as other project factors such as
2
C
O N C E N T R A T I N G
S
O L A R
T
H E R M A L
P
O W E R
(CSP) D
E V E L O P M E N T
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
8
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Concept
formally
Consortia
fl oated and pre-
formed—ready
Country and plant details
liminary assess-
to bid or RfP
Financial
Construction
Fully commissioned
(not including GEF projects)
ment conducted
ready to release
closure
commenced
and operating
Algeria 25 MW trough, ISCCS
Ö
Ö
Ö
2006/7 (Original
Possibly 2009
expectation
Sep
2005)
Arizona 1 MW trough ORC
Ö
Ö
Ö
Ö
Ö
(since April 2006)
Australia/Solar Heat and Power Pty Ltd,
Ö
Ö
Ö
Ö
(of fi rst stage)
First stage under
38 MW Fresnel into coal-fi red power station
commissioning
Australia/Solar Heat and Power Pty Ltd, 250
Ö
MW Fresnel, stand-alone with thermal storage
Australia 120 kW tower providing
Ö
Ö
Ö
Ö
2006
solar-reformed natural gas to a heat engine
China/Ordos 50 MW trough
Ö
India/Solar Heat and Power Pty Ltd,
Ö
Ö
5 MW, Fresnel
Iran 67 MW trough, ISCCS
Ö
Israel 100 MW trough
Ö
Ö
Italy/Empoli (2x 80 kW solar gas turbine
Ö
Ö
Ö
Ö
with waste-heat usage for air-conditioning)
Jordan 135 MW trough
Ö
Ö
(RfP 2001)
Nevada 64 MW trough
Ö
Ö
Ö
Ö
(February 2006)
Estimate March 2007
Portugal/Solar Heat and Power Pty Ltd, 5 MW
Ö
Ö
with potential to upgrade to 50 MW, linear Fresnel
Spain/ACS + SMAG, Andasol-1 50 MW trough
Ö
Ö
Ö
(June 2006)
Expected July 2006
Around late 2007
Spain/ACS + SMAG, Andasol-2
Ö
Ö
2006
Expected 2006
Around early 2008
50 MW trough
Spain/Abengoa, PS10 11 MW tower
Ö
Ö
Ö
Ö
Estimate
July
2006
(saturated steam)
Spain/SENER, Solar Tres 15 MW tower
Ö
Ö
(molten salt)
Spain/EHN+SolarGenix, 15 MW trough (HTF)
Ö
Ö
Spain/Iberdrola, 7x50 MW Trough (HTF)
Ö
Ö
Spain/HC, 2x50 MW Trough (HTF)
Ö
Ö
Spain/Abengoa, 2x 20 MW Tower, 1x 50 MW Trough
Ö
Ö
Spain/SMAG,50 MW ExtremaSol 1
Ö
Ö
Spain/5 MW trough with direct steam generation
Ö
Ö
(INDITEP)
Spain/Solar Heat and Power Pty Ltd, 5 MW, Fresnel
Ö
Ö
South Africa/100 MW Molten salt tower
Ö
T
ABLE
1. O
VERVIEW
AND
STATUS
OF
CSP
PROJECTS
WORLDWIDE
(
EXCLUDING
WB/GEF
PROJECTS
)
9
C
HAPTER
2 – C
ON CE N TRA TI N G
S
OLA R
T
H E RM A L
P
OW E R
(CSP) D
E V E LOP M E N T
regulatory regimes, permitting requirements, performance warran-
ties, risk factors, liabilities, and tender documentation.
There are today signifi cant bankable projects emerging around the
world (see Table 1).
The following plots can be established from Table 1. The projects
considered „possible to fi rm“ are those projects that are beyond
the „consortia formed, ready to bid“ stage, plus the GEF projects.
Beyond those known projects, the best that can be done is predic-
tive. Perhaps the most advanced long-term program presently in
place that aims to progress CSP technology is the Global Market
Initiative (GMI) (see Chapter 6, section 6.3).
The objective of the GMI is to facilitate and expedite the building
of 5,000 MWe of CSP worldwide over the next 10 years. This
initiative represents the world’s largest, coordinated action in his-
tory for the deployment of solar electricity. It aims to do this by,
among other things, promoting the introduction of incentives and
schemes in participating countries to provide the necessary frame-
work for projects to proceed. This projection was also integrated
into the plots, assuming linear growth in installed capacities up
to 2015.
Table 1 shows that over 700 MW of solar thermal projects are
under differing degrees of development in Spain. This is a direct
result of the new Royal Decree 436/2004, which provides the
following:
Grants same tariffs for PV and CSP from 100 kW to
50 MW.
A premium on top of the electricity pool price of
€
0.18/kWh,
which roughly equates to a total price of
€
0.21/kWh.
Bankable with 25 year guarantee.
Annual adaptation to electricity price escalation.
12 to 15 percent natural gas backup allowed to grant dispatch-
ability and fi rm capacity.
After implementation of fi rst 200 MW, tariff will be revised for
subsequent plants to achieve cost reduction.
Algeria has implemented a feed-in tariff that provides a premium of
up to 200 percent (based on a scale linked to solar contribution)
for CSP plants backed by natural gas. For example, if the solar
F
IGURE
3: S
HORT
-
TERM
AND
POSSIBLE
MEDIUM
-
TO
LONG
-
TERM
DEVELOPMENT
OF
CSP
TECHNOLOGY
WORLDWIDE
(
CUMULATIVE
INSTALLED
MW
E
)
Source:
Authors.
Cumulative installed MW
GMI prediction to reach 5,000 MW by 2015
Probable to firm based on present status
1980
1985
1990
1995
2000
2005
2010
2015
2020
Cumulative Installed CSP
0
2,000
4,000
6,000
8,000
10,000
12,000
F
IGURE
2: S
HORT
-
TERM
AND
POSSIBLE
MEDIUM
-
TO
LONG
-
TERM
DEVELOPMENT
OF
CSP
TECHNOLOGY
WORLDWIDE
(
YEARLY
INSTALLED
MW
E
)
Source:
Authors.
MW installed each year
MW installed annually
Probable to firm based on present status
GMI prediction to reach 5,000 MW by 2015
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
2010
2012
2014
2016
2018
2020
GEF projects
0
200
400
600
800
1,000
1,200
1,400
1,600
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
10
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
share is greater than 25 percent, the price that would be received
for all electricity generated by the plant would be three times the
market price (see Algeria country sheet in Annex 1 for more detail).
The introduction of this feed-in law has led to the development of
the Algeria CSP project.
In the United States, the DoE has a goal to deploy signifi cant CSP
plants in the Southwest. This is known as the 1,000 MW CSP
Southwest Initiative. In June 2004, the Western Governors’ As-
sociation at their annual meeting in Santa Fe resolved to diversify
their energy resources by developing 30 GW of clean energy in
the West, including a declaration to “establish a stakeholder work-
ing group to develop options for consideration by the governors
in furtherance of the 1,000 MW Initiative. The 64 MW Nevada
plant is already under construction and the 1 MW Arizona ORC
is producing electricity since April 2006.
The main conclusion from this project activity is that the WB/GEF
portfolio is not evolving in isolation, but is part of increasingly inter-
connected developments in both OECD and developing countries
that might trigger the take-off of the solar thermal technology. This
nascent global solar thermal power market is evolving through
programs and legal frameworks. The quick response of project
developers to these market signals makes it clear the technology
is ready to proceed.
2.2 T
ECHNOLOGICAL
PATHS
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
PLANTS
Like conventional power plants, a solar thermal power plant consists
of a heat generating unit and a unit that converts heat into electricity.
Whereas in conventional power plants the heat is being provided
by burning fossil fuels or by nuclear decomposition processes, a
solar thermal power plant uses large mirror fi elds to concentrate
the sunlight onto a focal line (e.g. parabolic trough collectors) or
a focal point (e.g. solar tower). Annex 2 provides an overview of
solar collector technologies.
In this section, the technological developments and improvements
will be described for the different collector technologies, and
different power cycle integration variants will be presented and
discussed.
2.2.1 S
OLAR
COLLECTOR
IMPROVEMENTS
A number of important studies have been carried out recently that de-
scribe and evaluate the technical improvements of collector concepts
and components, including Sargent and Lundy (2003), DLR and
others (ECOSTAR, 2005), and Kearney and Price (forthcoming).
These studies have examined the cost reduction potential for solar
thermal power plants that will result from technical innovations.
Improvements of component and system effi ciencies of CSP tech-
nologies and their potential cost reduction effect have been taken
into consideration. Whereas the ECOSTAR study was carried out
by European R&D institutions with the objective to set guidelines
for public R&D funding for CSP technology and to streamline R&D
efforts in the European countries, the Sargent and Lundy study has
a more U.S.-like perspective and is primarily aimed at predicting
future cost reduction of solar thermal power technology based on an
engineering approach (as opposed to learning curve approaches;
see Chapter 2, section 2.3.1). Kearney and Price have conducted
a more detailed and specifi c analysis of the particular components
contributing to a solar fi eld.
The Sargent and Lundy study analyzes the parabolic trough and
solar tower technologies, and bases its cost reduction forecasts on
the existing cost and performance experience from the nine Cali-
fornia trough plants (SEGS) and the two pilot tower plants (Solar
One, Solar Two). In a long-term perspective, the study predicts
lower costs for the tower technology.
The ECOSTAR study analyzes trough, tower, Fresnel, and dish tech-
nologies in different confi gurations. The objective of the ECOSTAR
study is not to compare different technologies. It believes that market
forces will decide if one technology will rule out other technolo-
gies. The objective of the study was to elaborate which technical
improvements (materials, components, system integration) will lead
to which cost reduction effect for each technological path.
The Sargent and Lundy study distinguishes the development goals
according to technical improvements that have already been
realized over the last decade due to continuous R&D in CSP,
and future technical development forecasts until 2020. The main
technical improvements as seen by Sargent and Lundy are given
in Table 3.
11
C
HAPTER
2 – C
ON CE N TRA TI N G
S
OLA R
T
H E RM A L
P
OW E R
(CSP) D
E V E LOP M E N T
T
ABLE
2: ECOSTAR
STUDY
–
COST
REDUCTION
POTENTIALS
DUE
TO
TECHNICAL
IMPROVEMENTS
Parabolic Trough
1
Tower
Linear
Fresnel
2
Dish
3
Innovative structures
Larger heliostats above 200 m
2
Linear Fresnel collector fi eld
Mass production for 50 MW
(up to 28 percent)
(up to 12 percent)
(up to 3 percent)
(38 percent)
Front surface mirrors
Larger module size
Thermal storage
Brayton instead of Stirling cycle
(up to 19 percent)
(up to 15 percent)
(up to 15 percent)
(up to 12 percent)
Advanced storage
Ganged heliostats
Reduced pressure losses
Improved availability and O&M
(up to 18 percent)
(up to 8 percent)
(up to 7 percent)
(up to 11 percent)
Reduced pressure losses
Advanced storage
Dust repellent mirrors
Increased unit size
(up to 16 percent)
(up to 10 percent)
(up to 7 percent)
(up to 9 percent)
Dust repellent mirrors
Increased fl uid temperature
Reduced engine costs
(up to 16 percent)
(up to 6 percent)
(up to 6 percent)
Increased solar fi eld outlet temperature
Increased engine effi ciency
(up to 15 percent)
(up to 6 percent)
1
with thermal oil as heat transfer fl uid and direct steam generation (DSG)
2
reference: Trough with DSG
3
parabolic dish concentrators in combination with a Stirling engine today realize the highest LEC compared to the other collector concepts.
Source:
Authors based on DLR and others (2005).
T
ABLE
3: S
ARGENT
AND
L
UNDY
—
TECHNICAL
IMPROVEMENTS
FOR
THE
TROUGH
AND
THE
TOWER
TECHNOLOGY
Parabolic Trough
1
Tower
2
Receiver coating (solar absorptance, infrared/heat irradiance)
Increasing heliostat size (up to 148 m
2
)
Receiver glass envelope transmittance
New primary mirror technology with thin glass or thin fi lms
New front surface refl ectors
Cost-effective support structure
Receiver reliability
Self-cleaning glass
Reduced parasitics (SF pumping etc.)
Drives for mirror tracking
Heat storage (up to 12 hrs)
Solar fl ux monitoring in the receiver
Solar fi eld support structure (main solar fi eld cost driver)
Improved receiver design
Higher operating temperature (up to 500°C)
Reduced start-up time and improved operation strategies
Self-cleaning glass
Improved heat transfer fl uid and storage
Larger plant sizes
Larger plant sizes
Reduced operation and maintenance costs
Reduced operation and maintenance costs
1
with thermal oil as heat transfer fl uid. No direct steam generation (DSG) considered
2
only molten salt technology considered.
Source:
Authors based on Sargent and Lundy (2003).
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
12
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
The drawback of cost forecasts based on the assessment of future
technological innovations and improvements is the fact that only
today’s technological know-how can be considered. New tech-
nological trends may come up and replace a current technology.
In this context, Fresnel collectors as a technological simplifi cation
of parabolic trough plants are not considered in the S&L study, nor
are other receiver technologies in the tower technology like the
pressurized air receiver, which in the future might produce lower
LEC due to very high solar effi ciencies (thus smaller solar fi elds) by
feeding the solar heat directly into a gas turbine.
Besides the diffi culty of predicting long-term technological paths,
it is not clear which technologies will be accepted by the market;
that is, whether investors will progressively implement technical
innovations or be more prudent and use proven technology. In
Chapter 2 (section 2.3.2), the CSP cost reduction potential will
be analyzed applying the learning curve concept.
2.2.2 Power Cycle integration concepts
The heat generated in the solar absorbers is subsequently used for
electric power generation. In this section, different concepts for
the integration of solar collectors into conventional power cycles
are presented. On the technical side, the difference between
these concepts is the collector integration within the thermody-
namic cycle and the degree of hybridization with fossil power
generation (the solar share). From a strategic point of view, each
concept is suitable for different goals, such as market introduction
of solar collector technologies or long-term options. The different
concepts for collector usage can be subdivided into the follow-
ing categories:
Solar Live Steam in hybrid Rankine plants (Option 1)
In this arrangement, the solar fi eld provides superheated steam for
use in a Rankine cycle. These plants can be operated in hybrid
mode with any type of steam plant for fuel saving. Depending on
plant operation mode and solar fi eld size, the solar share of such
hybrid systems can vary over a wide range. The SEGS plants in
California are examples of this confi guration (they are able to
use up to 25 percent natural gas). Coupling a solar fi eld with
a conventional coal-fi red power plant can lead to even higher
environmental benefi ts, because a carbon-intensive fuel being
converted at relatively low effi ciencies (compared to a CC plant)
can be saved whenever solar steam is available.
“Solar-Only” Rankine plant (Option 2)
A “solar-only” Rankine plant has the same underlying power-block
concept as the hybrid Rankine plant, but without a fossil-fuel steam
generator. It is noted that there may be an argument for small levels
of fossil back-up used only for keeping the turbines available for a
“hot start” following short insolation reductions and for pre-heating
prior to start-up. Preferably, such plants would be equipped with
heat storage of a few to several hours in order to increase the full
load operating hours of the plant. Storage can not only lead to
lower electricity generation costs, but improved dispatchability,
which provides benefi ts to the grid. Although this concept is envi-
ronmentally the most desirable plant confi guration, storage costs
need to be reduced further.
Solar Gas turbine combined cycle (Option 3)
Due to the high concentration factors, solar towers (central receivers)
and dishes can produce very high temperatures (above 1,000°C)
for use directly in gas turbines or to complement the gas turbine
combustion chamber. This offers the possibility of a solar-driven
combined-cycle with correspondingly high effi ciencies. In the me-
dium to long term, this technology has very promising prospects
because of the high effi ciencies and the related savings in solar
fi eld investment.
Combined Heat and Power solar plant (Option 4)
Similar to conventional combined heat and power, in this option a
solar thermal electricity plant is combined with a lower temperature
thermal application such as sea water desalination or air condition-
ing. Co-fi ring is also possible. Due to the double use of the solar heat
for power and heat generation, total effi ciencies of up to 80 percent
can be achieved. Generally, any kind of thermal power plant (also
CC, ISCCS, or fossil steam plants) can in general be designed such
that subsequent heat-driven processes can benefi t from the plant’s
waste heat. In order to supply reasonable temperatures to these
processes, a certain power drop on the electric power side has to
be accepted. In the long run, this concept will be a very attractive
solution where cooling applications are benefi cial (e.g. in hotels)
13
C
HAPTER
2 – C
ON CE N TRA TI N G
S
OLA R
T
H E RM A L
P
OW E R
(CSP) D
E V E LOP M E N T
and especially for locations where drinking water is scarce—a
problem many hot countries are suffering from, and which in many
cases will be further exacerbated by global warming.
Integrated solar combined cycle (ISCC) (Option 5)
The Integrated Solar Combined Cycle System (ISCC) was initially
proposed as a way of integrating a parabolic trough solar plant
with modern combined-cycle power plants. The basis of this plant
type is a combined cycle plant consisting of a high-temperature
gas turbine and a bottoming steam turbine. The steam for the steam
turbine in an ISCCS plant is provided by two heat sources: the heat
recovery steam generator using the exhaust gas of the gas turbine
and the solar fi eld. It is important to note that in this confi guration
the solar is used at the steam turbine cycle effi ciency, not the higher
combined cycle effi ciency as with Option 3. The size of the steam
turbine in an ISCCS is larger than it would be in a conventional
combined cycle.
The three main advantages of this concept are:
higher solar shares than in solar feed water preheating
no solar energy losses due to daily plant start-up and shut-
down
the incremental costs for a larger steam turbine are less than the
overall unit cost in a solar-only plant.
The main drawback of the technology is the part load losses during
operating hours when there is no solar energy input (see Figure 4).
Therefore the interdependencies of steam turbine oversizing, steam
turbine part-load behavior, solar fi eld size, solar irradiance, plant
site, plant operation mode, and possibly solar heat storage or duct
burner have to be carefully considered in a project-specifi c overall
system analysis in order to ensure that the solar fi eld will provide
its full economic and environmental benefi ts.
Solar Feed Water Preheating (Option 6)
In this option, solar thermal heat is used for preheating feed-water
in large-scale conventional Rankine plants, substituting steam that
would otherwise be bled from the turbine. Additional electricity can
be generated, or fossil fuel saved, depending on the operation
mode. This concept is well-suited for market introduction of new
collector types, since it reduces the risk by lowering the investment
costs that would otherwise be needed for a new steam cycle
(approximately $10 million for a 5–10 MWe solar fi eld). Further
advantages are the possibility of using existing plant infrastructure
and good solar heat conversion effi ciencies from solar irradiation
to net solar electricity (Morin and others, 2004). The solar fi eld
can also be installed in phases. The drawbacks include its small
solar share (around 1 percent), which is why this concept is only
attractive for market introduction.
Solar Process Heat Applications (Option 7)
The slow pace of CSP market introduction is mainly related to the
very large investments related to this type of renewable energy
technology. Solar process heat applications are one way to lower
this hurdle, since the initial investment will decrease by a factor
of 10 to100. Typical process heat applications are in the range
of 200–1,000 kWth for the cooling of buildings or refrigerators.
CHP applications are a wise market introduction strategy for new
collector types and suppliers, since such applications can be con-
sidered as the fi rst step toward large-scale solar thermal power
applications. This concept might be attractive to the GEF and the
F
IGURE
4: E
XAMPLE
OF
PART
LOAD
BEHAVIOR
OF
A
STEAM
TURBINE
Source:
E.ON Engineering (modifi ed original data).
Relative part load efficiency
0
20
40
60
80
100
40%
50%
60%
70%
80%
90%
100%
Thermal load of the Steam Turbine (%)
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
14
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
World Bank if future CSP funding sources signifi cantly decrease.
By promoting such projects, WB/GEF could spur the competition
in the CSP sector, because under current conditions (e.g. in Spain)
it is very diffi cult for any new players to enter the CSP market.
These concepts will be further discussed and compared in section
2.2.4.
2.2.3 ISCCS—evaluation of performance, cost, and
CO
2
benefi ts
The ISCCS concept has been of interest to the solar community
for some time, and has been the subject of a number of studies
(Stein, 2000; Dersch, 2002). In 2002, the International Energy
Agency’s SolarPACES implementing agreement carried out a study
(Dersch et al., 2002) on thermodynamic modeling of ISCCS plants
in comparison with combined cycle as well as SEGS-type (hybrid)
plants in order to evaluate the performance, cost, and CO
2
effects
of the ISCCS concept. Its main results are presented here.
Assumptions
A base solar fi eld size corresponding to a 50 MW SEGS plant in
Barstow, California, was used for the calculations (270,000 m
2
).
F
IGURE
5: L
OAD
CURVES
USED
FOR
THE
ANNUAL
PERFORMANCE
CALCULATION
2
Source:
Dersch et al. (2002).
Load (%)
Hour of day (h)
ISCCS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
21
20
22 23 24
0
10
20
30
40
50
60
70
80
90
100
solar dispatching
scheduled load profile
Gas turbine
Steam turbine (fossil fired)
Steam turbine fired
by Solar Field
Load (%)
Hour of day (h)
SEGS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
21
20
22 23 24
0
10
20
30
40
50
60
70
80
90
100
solar dispatching
scheduled load profile
(burning of fossil fuel
during night time)
Load (%)
Hour of day (h)
CC
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
21
20
22 23 24
0
10
20
30
40
50
60
70
80
90
100
free load (solar dispatching)
scheduled load profile
2
For the scheduled load: if no solar energy is available the fossil back-
up-burner is used (ISCCS and SEGS plant). In the solar dispatching mode
no fossil back-up is used.
F
IGURE
6:
R
ESULTS
OF
ANNUAL
PERFORMANCE
CALCULATION
FOR
ISCCS
AND
CC
Source:
Dersch et al. (2002).
annual electricity production
(Gwh/a)
solar share
Cal.
Spain
Cal.
Spain
Cal.
Spain
3,000
2,500
2,000
1,500
1,000
500
0
20%
18%
16%
14%
12%
10%
8%
6%
4%
2%
0%
ISCCS
ISCCS
with storage
CC
Output, Solar Dispatching
Solar Share, Solar Dispatching
Output, Scheduled Load
Solar Share, Scheduled Load
5.6%
4.1%
3.4%
2.0%
9.4%
9.0%
6.4%
5.4%
0.0%
0.0%
0.0%
0.0%
15
C
HAPTER
2 – C
ON CE N TRA TI N G
S
OLA R
T
H E RM A L
P
OW E R
(CSP) D
E V E LOP M E N T
The load curves of all plants were assumed to be identical in the
fi rst scenario. The second scenario considered solar dispatching
load (see Figure 5). All three investigated plant concepts are
sized such that the annual electricity output remains the same for
the scheduled operation. As a consequence, the sizing of the gas
and steam turbine capacities are different for the pure CC and the
ISCCS plant (CC: GT has 201 MW, ST has 109 MW; ISCCS:
GT has 162 MW, ST has 148 MW). The calculations have been
carried out for a site in Spain (DNI: 2,023 kWh/(m
2
a)) and the
Californian site in Barstow (DNI: 2,717 kWh/(m
2
a).
Results
The main results of the annual electricity calculations were that
without solar heat storage the solar share ranges between two
and six percent depending on plant site and operation mode (solar
dispatching or scheduled load). With storage, the solar share can
be increased up to almost 10 percent.
Figure 7 shows CO
2
emissions of all analyzed plant concepts.
All analyzed ISCCS concepts (regardless of sites, storage, duct
F
IGURE
7: S
PECIFIC
CO
2
EMISSIONS
FOR
DIFFERENT
SITES
,
PLANT
CONFIGURATIONS
,
OPERATION
MODES
AND
SOLAR
FIELD
SIZES
Source:
Dersch et al. (2002).
kg CO
2
/ kWh
solar field area in m
a) Solar dispatching without thermal storage
270,320
305,200
340,080
374,960
0
0.5
0.4
0.3
0.2
0.1
ISCCS, California
ISCCS, Spain
SEGS, California
SEGS, Spain
Reference CC
kg CO
2
/ kWh
solar field area in m
b) Solar dispatching with thermal storage
427,280
462,160
497,040
531,920
0
0.5
0.4
0.3
0.2
0.1
ISCCS, California
ISCCS, Spain
SEGS, California
SEGS, Spain
Reference CC
kg CO
2
/ kWh
solar field area in m
c) Scheduled load without thermal storage
270,320
305,200
340,080
374,960
0
0.5
0.4
0.3
0.2
0.1
ISCCS, California
ISCCS, Spain
SEGS, California
SEGS, Spain
Reference CC
kg CO
2
/ kWh
solar field area in m
d) Scheduled load with thermal storage
427,280
462,160
497,040
531,920
0
0.5
0.4
0.3
0.2
0.1
ISCCS, California
ISCCS, Spain
SEGS, California
SEGS, Spain
Reference CC
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
16
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
burning, load scheduling) show lower CO
2
emissions than the
reference CC plant. However, the CO
2
emission difference of an
ISCCS plant compared to a CC plant is small due to the relatively
small contribution of the solar fi eld. The calculations were carried
out under the same constraints, including the use of a reference
plant site. Different ambient conditions can have a considerable
impact on the total plant performance.
Lower ambient humidity, higher ambient temperature, and the use
of dry cooling instead of wet cooling (if suffi cient cooling water
was unavailable) lead to a decrease of the total plant effi ciency
such that the benefi cial solar impact can be outweighed by the
less favorable plant site conditions. A poor site or poorly designed
plant can result in higher CO
2
emissions from the ISCCS plant
than from a pure CC plant. Lower ambient pressure (due to higher
altitude) also has a negative effect on the total plant output, but
the plant effi ciency and thereby the CO
2
emissions will not be
negatively affected.
In this study, the calculated performance of the SEGS plants show
that when operated under load scheduling mode, the specifi c
CO
2
emissions rise because of the use of gas in a lower effi ciency
steam cycle. However this modeling was carried out merely for
the purposes of illustrating a point in the study concerning opera-
tional modes under similar constraints. In practice, a SEGS plant
with gas co-fi ring would under real conditions not be used for 24
hour-operation. Intermediate load operation or solar dispatching
mode would considerably improve the CO
2
.balance of the SEGS
concept. When operated in solar dispatching mode, the SEGS
plants of course show zero CO
2
emissions.
In most cases, the ISCCS confi gurations showed lower LEC than
the SEGS plants (under comparable economic constraints
3
, see
Figure 8). The reason for this is that the incremental cost of a larger
steam turbine is much lower than building a stand-alone power
block for a SEGS plant.
2.2.4 Summary—technological paths
The description of collector innovations (in section 2.2.1) is intended
to provide an insight into CSP technology developments and to pro-
vide a basis for the technology-related cost reduction forecasts that
contribute signifi cantly to overall cost reduction. According to Sargent
and Lundy (2003), 54 percent of the future CSP cost reduction is
attributable to technological innovations, with the balance attribut-
able to plant scale-up and increasing production volume. It is not the
intention to pick the winning technology or development path.
Looking at the potential of the different power cycle integration
concepts (sections 2.2.2 and 2.2.3), in the mid- to long term,
higher solar shares are obtained via the options where solar heat
directly drives a turbine (options 1, 2, 3, and 4). Even if the plants
are designed for hybrid operation, the solar share can be increased
later during the plant’s lifetime, e.g. when collector costs will have
decreased or fuel prices increase.
From a longer-term perspective, the solar contribution of the ISCC
(and solar feed water preheating) cannot be extended beyond
a certain level. However, as long as countries build fossil CC or
Rankine plants anyway, equipping these plants with a solar fi eld
is a signifi cant contribution to GHG emission reduction. On the
one hand ISCCS and solar feed-water preheating are well-suited
for market introduction of new solar collectors because the addi-
tional marginal investment for the conventional plant components is
relatively low (or zero). There are also areas of overlap, and thus
cost reduction potential, with the plant infrastructure and project
implementation costs. For developing countries especially, where
the primary need is electricity (not necessarily green electricity),
the combination of solar energy together with a large-scale fossil
power plant can, in the technology introduction stages, be much
more attractive than stand-alone solar plants. ISCCS is a good
confi guration for creating experience with the CSP technology under
the same operating conditions as in solar-only plants.
2.3 C
OST
REDUCTION
COMPARISON
OF
CSP
TECHNOLOGY
The aim of any electricity producing technology must be to realize
competitive electricity generation costs. Several studies have ex-
3
Constant real discount rate: 6.5 percent, plant lifetime: 25 years, fuel price
1.26 USc/kWh, annual fuel price escalation: 2 percent, annual infl ation
2.5 percent, SF + heat exchanger $220/m
2
, CC specifi c investment cost:
$550/kW, additional power block costs due to SF: $600/kW.
17
C
HAPTER
2 – C
ON CE N TRA TI N G
S
OLA R
T
H E RM A L
P
OW E R
(CSP) D
E V E LOP M E N T
amined the future cost reduction potentials for solar thermal power
generation technology. The most important studies in this context
are Enermodal (1999), DLR (2004), Sargent and Lundy (2003),
DLR and others (2005), and Kearney and Price.
Whereas section 2.2.1 the studies using engineering approaches
were discussed, this section evaluates the studies applying the
learning curve concept.
The experience curve approach developed by T.P. Wright (1936)
and the Boston Consulting Group (1960) assumes that each dou-
bling of the cumulated production of any kind of product results in
a specifi c cost reduction by a so-called learning factor (typically
20 to 30 percent).
The progress ratios
4
of a large variety of products from the electron-
ics, mechanical engineering, paper, steel, aviation, and automotive
sectors were analyzed in a study by the IEA (2000):
F
IGURE
8: S
OLAR
LEC
FOR
DIFFERENT
SIZES
,
PLANT
CONFIGURATIONS
,
OPERATION
MODES
AND
SOLAR
FIELD
AREAS
Source:
Dersch et al. (2002).
Solar LEC in cEuro/kWh
solar field area in m
a) Solar dispatching without thermal storage
270,320
305,200
340,080
374,960
0
35
30
25
20
15
10
5
ISCCS, California
ISCCS, Spain
SEGS, California
SEGS, Spain
Solar LEC in cEuro/kWh
solar field area in m
b) Solar dispatching with thermal storage
0
35
30
25
20
15
10
5
ISCCS, California
ISCCS, Spain
SEGS, California
SEGS, Spain
427,280
462,160
497,040
531,920
Solar LEC in cEuro/kWh
solar field area in m
c) Scheduled load without thermal storage
270,320
305,200
340,080
374,960
0
35
30
25
20
15
10
5
ISCCS, California
ISCCS, Spain
SEGS, California
SEGS, Spain
Solar LEC in cEuro/kWh
solar field area in m
d) Scheduled load with thermal storage
0
35
30
25
20
15
10
5
ISCCS, California
ISCCS, Spain
SEGS, California
SEGS, Spain
427,280
462,160
497,040
531,920
4
The progress ratio r is defi ned as the complementary to the learning factor
l, that is: r=100 percent-l
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
18
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
2.3.1 Cost reduction and growth rates of other
renewable energy technologies
In order to narrow down the perspective from general technology
cost reduction to renewable energy technologies, wind energy
and photovoltaics are analyzed with respect to two main implicit
assumptions of learning curves: (1) the specifi c cost reduction; and
(2) market development.
The next two graphs show the specifi c cost reduction curves expe-
rienced by wind energy converters and photovoltaics.
The next two graphs show the experienced market growth for wind
energy converters and photovoltaics:
2.3.2 Experience curve concept applied to Solar
Thermal Power Generation
Of the above-mentioned studies, the Enermodal study and the
Athene model use experience curve approaches to assess the future
costs of solar thermal power generation.
F
IGURE
9: P
ROGRESS
RATIO
FOR
DIFFERENT
PRODUCING
BRANCHES
. T
HE
HEIGHT
OF
THE
COLUMNS
REFLECTS
THE
NUMBER
OF
OCCURRENCES
(
DISTRIBUTION
)
Source:
OECD/IEA, 2000, Experience Curves for Energy Technology Policy, Figure 1.3, p.
14.
Frequency
Progress ratio (%)
55–56
59–60
63–64
67–68
71–72
75–76
79–80
83–84
87–88
91–92
95–96
99–100
103–104
107–108
0
14
12
10
8
6
4
2
F
IGURE
10: S
PECIFIC
INVESTMENT
COSTS
OF
WIND
ENERGY
CONVERTERS
OVER
TIME
Source:
Ragwitz (2005).
Specific investment costs (DM/kW)
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2002
2000
2004
2006
2008
2010
0
25
20
15
10
5
Onshore
Offshore
F
IGURE
11: S
PECIFIC
INVESTMENT
COSTS
OF
PHOTO
-
VOLTAICS
(
IN
D
OLLAR
PER
WATT
PEAK
POWER
)
AS
A
FUNCTION
OF
CUMULATIVE
PRODUCTION
VOLUME
(
IN
GIGAWATT
PEAK
POWER
GW
P
)
Source:
Duke (2002).
Price (2000$/Wp)
1.E –04
1.E –03
1.E –02
1.E –01
1.E +00
1.E +01
$0.1
$100.0
$10.0
$1.0
cumulative PV production (GWp)
1976
2000
transition to thin-
film experience
curve
Al-PV Experience Curve
R
2
=0.99
PR=0.80
19
C
HAPTER
2 – C
ON CE N TRA TI N G
S
OLA R
T
H E RM A L
P
OW E R
(CSP) D
E V E LOP M E N T
Enermodal (1999): Cost Reduction Study for Solar Thermal
Power Plants
The Enermodal study uses the specifi c investment costs per installed
capacity ($/kW) as a reference measure. This reference number
does not seem appropriate to forecast cost reduction for solar ther-
mal power plants because larger solar fi elds in combination with
heat storage can lead to lower levelized electricity costs due to a
higher plant capacity factor, even though the specifi c investment
costs increase. The second point of note in the approach used by
the Enermodal study is the fact that it uses the cost of the fi rst plant
out of the nine existing parabolic trough plants as the starting point
of the learning curve instead of using a linear regression function
of all reference plants (see Figure 14). Therefore the cost of the
fi rst plant determines strongly the cost forecast for future technology
deployment. The third point of note in the methodology is the fact
that the numbers used for the experience curve differ strongly from
the numbers given in the text, which correspond exactly to the
values given in the Pilkington study (1996).
F
IGURE
12: D
EVELOPMENT
OF
INSTALLED
WIND
CAPACITY
IN
G
ERMANY
Source:
BMU (2004).
MW
1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 200
2
2003 2004
2,000
0
8,000
6,000
10,000
12,000
14,000
16,000
18,000
4,000
310
6112
F
IGURE
13: D
EVELOPMENT
OF
THE
WORLDWIDE
INSTALLED
PV
CAPACITY
AND
ANNUAL
GROWTH
RATE
Source:
Quaschning (2004).
Cumulated power (MW)
Annual growth rate
1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003
500
0%
5%
10%
15%
20%
25%
30%
40%
35%
0
2,000
1,500
2,500
3,000
1,000
Annual growth rate
Others
IEA w/o Germany
Germany
F
IGURE
14: E
NERMODAL
S
TUDY
—E
XPERIENCE
CURVES
FOR
DIFFERENT
ASSUMPTIONS
ON
THE
PROGRESS
RATIO
(
RED
CROSSES
REPRESENT
VALUES
GIVEN
IN
THE
TEXT
OF
THE
STUDIES
FOR
THE
NINE
C
ALIFORNIAN
SEGS
PLANTS
)
Source:
Enermodal (1999): Cost Reduction Study for Solar Thermal Power Plants.
Plant Capital Cost (1,998$/kW)
Cumulative Power Plant Capacity Installed (MW
e
)
10
100
1,000
10,000
100,000
1,000
10,000
Medium-term
Case 10
SEGS IX
Long-term
Case 10
New 200 MW
Ranking (Case 4)
0.92
SEGS
0.88
0.85
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
20
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
DLR (2004): Scenario model “Athene”
This study assumes as a starting point the empirical values from the
existing parabolic trough plants. But for the future cost reductions,
it is explicitly mentioned that all solar thermal power technologies
are included. Technological variants and improvements as well as
competition are essential preconditions of the experience curve
model.
Cost reduction in this study is split into four categories:
Improving effi ciency (from 13.2 percent today to 17.0 percent
in 2025)
Learning effects due to volume production
collector costs, surface-specifi c progress ration (PR) is 0.9
thermal energy storage (up to 12 hrs), capacity-specifi c
PR=0.88
steam cycle components from 850
€
/kW down to today’s
conventional plant costs of 740
€
/kW, PR=0.94
Economies of scale due to larger units (up to 200 MWe):
doubling capacity leads to 15 percent cost reduction
The annual operation and maintenance costs will decrease
proportionally to the reduction of investment costs (2.5 percent
of investment).
Further assumptions of this model are:
No CO
2
-allowances considered, respectively carbon price
increasing from initially 7.5
€
/t CO
2
to 30
€
/t CO
2
in 2050
Plant life time: 25 years
Internal plant project interest rate: 8 percent (in real terms)
Solar Resource DNI=2350 kWh/(m
2
a) (favorable sites for
solar thermal power generation range between 1,800 and
2,900 kWh/(m
2
a).
Market growth of 23 percent p.a. (IEA references: wind
(1971–2000) 52 percent p.a., PV 32 percent), (implementation
of 5,000 MW till 2015 corresponds to GMI goal).
Fossil Reference LEC (IEA) with same number of annual operating
hours as STPPs
Fuel prices increasing by 0.52 percent p.a. (IEA)
As a result of the assumptions given above, the cost reduction
forecasts of the Athene study are given in the following graph:
According to the Athene study, the cost competitiveness of solar
thermal power generation will be reached in 2025. The total
necessary subsidies account to 12 billion
€
, which corresponds
to a total installed capacity of 42 GW
e
, not taking into account
CO
2
trading. If the above-mentioned carbon prices are included,
cost competitiveness will be reached in 2023. The total necessary
F
IGURE
15: D
EVELOPMENT
OF
LEVELIZED
ELECTRICITY
COSTS
AND
REVENUES
FROM
THE
POWER
EXCHANGE
MARKET
REFERRED
TO
BY
LEC
OF
FOSSIL
POWER
PLANTS
(
PLANT
PROJECT
INTEREST
RATE
8
PERCENT
)
Source:
Economic model from DLR (2004), authors’assumptions.
Note:
The continuous line includes Emission Reduction Credits (ERC) of initially 7.5
€
/t CO
2
increasing
to 30
€
/t CO
2
in 2050.
2000
2005
2010
2015
2025
2020
0.02
0.03
0.04
0.05
0.06
0.07
0.08
0.09
0.10
0.11
0.12
Revenue and LEC [Eu/kWh]
Revenues incl. ERC
LEC d=8%
Revenues
21
C
HAPTER
2 – C
ON CE N TRA TI N G
S
OLA R
T
H E RM A L
P
OW E R
(CSP) D
E V E LOP M E N T
investment will thereby be signifi cantly reduced to
€
2.5 billion,
respectively 22 GW
e
.
The implicit assumption is that the number of full-load hours is
constantly increased due to larger thermal energy storages (see
also the “steps” in fossil reference price) up to 6,500 hours per
annum (12 hours thermal storage). However, in some cases it
may be more economical to aim at producing only peaking to
mid-load-power for the period when power tariffs on the electricity
market are highest (smaller energy storage), which in turn could
justify lower thermal storage.
The Athene model is a very thorough assessment using many
validation points from experienced facts and developments. The
assumptions used are generally conservative. In this context, the
Athene scenario may be considered as a very conservative scenario
for CSP cost and market development.
2.3.3 Cost Reduction—Summary
All studies referenced, including the GMI-based market develop-
ment in Chapter 2 (section 2.1), assumed a conservative global
CSP market development compared to the actual deployment of
wind energy, even in a single country (Germany).
5
It has to be
stated as well that many of the countries in the world’s sunbelts
lack the fi nancial resources to fi nance solar energy. With present
global CSP market movements re-emerging, there is no funda-
mental reason why technology growth similar to wind energy is
not feasible.
6
The main messages from the comparison of cost projection studies
are:
The technology has the potential to be cost-competitive within
10 to 25 years, and has the potential to be a signifi cant
electrical power option for developing countries, which often
have abundant solar resources. With hybridization and thermal
energy storage, solar thermal power is dispatchable power that
helps to support grid stability.
Should GEF promote CSP investments now in developing coun-
tries and not once the technology has moved further down the
learning curve?
The GEF projects will contribute to OP 7’s goal of “reducing
the long-term costs of low greenhouse gas-emitting energy tech-
nologies” if at least two or three are successfully deployed and
operated. However, the projects in the current portfolio will not
have a signifi cant cost-reduction impact on the underlying cost of
the technology. It is diffi cult to quantify the cost reduction effect
of the four projects: In the beginning of the portfolio’s history, it
seemed that it would be one of the GEF plants that would be the
fi rst to be built after the California SEGS plants. However today,
with other commercial CSP activities evolving, other projects
5
Another comparison basis of the necessary effort would be the required
subsidies on the basis of the reference LEC by correcting the GW-num-
bers by the specifi c investment ($/kW), equivalent full-load hours (h/a),
and O&M costs ($/a). The result would remain in the same order of
magnitude.
6
In this context it has to be mentioned that the global wind market cor-
responds to approximately three times the German installations.
F
IGURE
16: C
OMPARISON
OF
THE
DIFFERENT
MARKET
DEVELOPMENT
ASSUMPTIONS
OF
THE
CSP
STUDIES
IN
COMPARISON
WITH
THE
G
ERMAN
WIND
MARKET
DEVELOPMENT
AND
THE
GMI-
GOAL
(
TARGET
OF
CU
-
MULATIVE
INSTALLED
POWER
OF
5 GW
IN
10
YEARS
TO
ACHIEVE
COST
-
COMPETITIVENESS
)
Source:
Authors.
0
5
15
10
0
5
10
15
20
Cumulated installed power in GW
year
S&L opt.
S&L pess
Enermodal
Pilkington
Athene
Wind Germany
GMI - based (see above)
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
22
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
will come in fi rst. Therefore the question is, which part of the
cost reduction curve will the GEF projects infl uence? In theory,
the cost reduction effect will be largest for the fi rst plants built.
In practice, much of the early cost reduction will result from a
reduction of the risk premium as design, construction, and O&M
experience is gained. The developing countries in particular
experience an additional premium due to the perceived added
diffi culties of carrying out large projects using new technology.
This is another cost reduction area that the GEF projects can
impact in a positive manner.
Affordable technology and climate protection are goals offi -
cially supported by many developing countries with good solar
resources. In order to meet these goals, GEF and the World
Bank should support the implementation of climate-protecting
renewable energy in developing countries. Whereas the OECD
countries can afford subsidizing power technologies on a large
scale, developing countries usually are not able to do so. By
supporting the implementation of the fi rst CSP pilot plants,
WB/GEF will help create technology trust and institutional
learning and thereby reduce the hurdle for subsequent market
entry. The solar fi elds of solar thermal power plants contain many
components that can be locally manufactured, such as concrete
foundations or standard steel components or, depending on
the solar technology and the project country, mirrors. Last, but
not least, the erection of the plants—as well as operation and
maintenance—represent sustainable development aid through
job creation. These macroeconomic aspects of value creation
in the countries of destination are not considered in the above
cost studies.
23
his chapter assesses risks in the project design of the
WB/GEF portfolio and discusses adequate risk mitigation
measures. This assessment includes:
Technological performance risk
Financial/commercial risks
Regulatory/institutional risks
Strategy risks
The different risks relate either directly to the different projects
in the four GEF countries or more indirectly via the technology
choices, the business model, and the institutional settings made
for the portfolio.
The last group of risks concern the medium- and long-term con-
sequences of the choices made for the current portfolio, such
as the choice of the ISCCS concept for all four projects in the
portfolio.
The risks are evaluated in a qualitative way by presenting their
main impacts. In addition, they are also evaluated in a semi-
quantitative way by categorizing them according to the following
characteristics:
: low risk
: medium risk
: high risk
In the fi nal section of this chapter, an aggregate assessment of
the risks is provided for the four risk groups mentioned above.
This table also shows the main level at which the risk operates:
project success, WB/GEF program success, and global technol-
ogy evolution.
3
CSP R
I S K
A
N A L Y S I S
T
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
24
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
3.1: T
ECHNOLOGICAL
RISKS
RELATED
TO
THE
WB/GEF
PORTFOLIO
Risk
Valuation
Mitigation
1.
Non-optimal choice of location
If the hybrid plant site is to be adapted for a solar fi eld, risk results
This risk can be mitigated by careful plant and site evaluation.
from additional costs (e.g. constructing gas pipeline) or a drop in total
To a certain degree additional costs can be justifi ed by the market
plant electricity due to poorer plant cooling, reduced air density at
introduction of a technology (gaining experience in technology,
higher locations, or hotter sites (lower gas turbine output). As a
institutions, industry, O&M are considered to be superior goals).
consequence, these electricity losses may outweigh the energy yield
of the solar fi eld.
Morocco: good insolation levels. Losses in power plant output due to
India: examine other revenue streams for potential use of the gas
height of location (900 m). Infrastructure for water/natural gas
pipeline. Investigate nearby recent oil discovery for gas. Investigate
available.
alternative
nearby
locations.
Egypt: good insolation levels. Infrastructure for water/natural gas and
transmission is available
Mexico: the two currently discussed plant sites in Sonora offer ideal
conditions for the solar fi eld.
India: fl at site and transmission available. Some infra-structural work
needed to provide water. Current non-availability of gas infrastructure
(gas pipeline). Reasonable insolation levels.
2.
Environmental benefi t low or
The CO
2
emission reduction actually achieved is rather low compared
Not very important issue at the current stage of early market
non-existing due to the ISCCS
to a combined cycle reference: 5 to 10 percent solar share in the
introduction. However, once detailed project design is known, detailed
concept
overall production; decreased effi ciency of the steam generator.
environmental calculations should evaluate weaknesses (including
sensitivity calculations for non-optimized plant operation).
3.
Insuffi cient experience with
Key technologies most likely to be used for the WB/GEF portfolio
Analyzing on-fi eld effi ciency etc. in order to convince investors of the
CSP technology
(solar trough technology, combined cycle, no thermal storage) are
technical feasibility (e.g. 4,360 m
2
test loop SKAL-ET at Kramer
very well known and have a long track record (only concerning
Junction in California to convince the Spanish company ACS to invest
operation, however, not new construction and development).
in the AndaSol 1 and 2 plants in Spain).
Parabolic refl ectors have been tracing the sun for 20 years at the
Secure valid warranties from manufacturers and EPC (in practice one
Californian SEGS plants (from 1986 to 2005 they have generated
of the most critical points in real project development).
nearly 13 TWh).
Steam cycle is conventional Rankine cycle.
Heat exchanger is the interface between solar fi eld and combined
cycle –> proven technology).
4.
Thermal storage new and
Most likely no storage in any of the WB/GEF plants, although for the
Thermal storage can improve the effi ciency and the solar share of
non-experienced technology in
Indian project a bonus was to be awarded for a thermal storage proposal.
the ISCCS. Storage technology based on molten salt (7.5 hours) is
the required size
part of the new Andasol 1 and 2 plants ((2x50 MW) starting operation
in Spain in 2006/2007.
Thermal storage known in chemistry and in smaller dimensions from
Another layout with an extra steam turbine or buffer heat storage
the “Solar Two” project (power tower in the U.S.).
may be worth analyzing.
25
C
HAPTER
3 – CSP R
ISK
A
NALYSIS
5.
Problems arising at the technical
The WB/GEF plants would be the fi rst ISCCS plants; the Spanish plants
Interface occurs at the steam generator in a standard confi guration
interface between the solar
(maximum 15 percent solar) as well as possible plants in the US are
through a heat exchanger. Major complications are unlikely.
component and the fossil component
not ISCCS plants.
In the ISCCS, determining the exact electrical contribution (gas or solar)
One method is to determine the actual (rather than design)
is quite complex. Especially in the shared responsibility model (solar
performance during commissioning tests, so that an accurate set of
fi eld – CC), responsibility questions might arise if the plant does not
offset curves can be generated for each off-design parameter (such as
meet its forecasted output.
ambient temp., relative humidity, steam inlet conditions, condenser
pressure, etc). Any additional MW generated above the calculated
output at a given set of conditions is attributable to the solar fi eld.
Power plants degrade over time, heat exchanger fouling coeffi cients
There are probably enough periods of time when the solar fi eld is not
increase over time, operational parameters change over time, such as
contributing (night, clouds), to be able to periodically reconfi rm the
feed water heaters going out of service.
CC performance.
6.
Non-optimized operation of
Possible in the case of Egypt given the fact that there will be no turnkey
The solar portion will be done through one stage bidding while the
the ISCCS plant
supplier but two separate suppliers for the solar and the fossil parts.
CC portion will be done in two stages. The selected bidder and its
design for the solar portion will feed into the second stage of bidding
for the CC portion as a way to ensure that the interface is optimized.
In addition, a consultant will be hired to ensure that the design and
implementation of the project as a whole will run smoothly, especially
when it comes to the interface.
7.
Complete failure of the solar plant
Complete failure of the solar fi eld might occur at several points during
In order to cope with non-compliance in power purchasing agreements,
construction (e.g. due to bankruptcy of the solar supplier) or during
the gap must be made up by fi ring a duct burner to avoid penalties.
operation (e.g. due to damage to the mirrors by hail etc., but this
The duct burner (also called supplementary fi ring) is a well-known
is
unlikely).
addition to combined cycles, enabling a boost during periods of high
electricity prices. Given the fact that the solar share is small, the loss
is limited. Without a power purchasing agreement, there would only
be a commercial loss. If there is a single plant owner, the attributable
loss would be calculated for accounting purposes more than penalty
purposes.
3.2: F
INANCIAL
/
COMMERCIAL
RISKS
RELATED
TO
THE
WB/GEF
PORTFOLIO
Risk
Valuation
Mitigation
8.
Low interest in bidding by industry
In case bidding conditions are too restrictive and unattractive to
Greater integration of industry in the bidding process, both CC
companies, the industry response to the call for bids might be very
and solar suppliers.
limited (e.g. India, Mexico in the fi rst round).
9.
Insuffi cient fi nancing secured for
Morocco: preferential loan from the ADB, the GEF grant and equity
Downward adjustment of the required solar capacity in case of cost
the WB/GEF projects
from ONE should fully cover the fi nancing required. An unresolved issue
over-runs during the bidding procedure.
is how to compensate the power loss due to a sub-optimal plant site,
possibly by smaller dimensioning of the solar fi eld so that the excess
costs due to the solar fi eld are fully covered by the GEF grant.
(continued on next page)
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
26
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Egypt: Financing settled so far by JBIC, NREA to fi nance local costs,
with a potential for IBRD funding for any gaps that may arise.
Mexico: fi nancing (besides the GEF grant) is to be provided by CFE or
the Mexican Treasury ministry. The rated power will be fi xed. The
company offering least-cost-LEC will win the bid. This leaves the
question of exact investment costs open.
India: preferential loan from KfW and the GEF grant is not suffi cient to
For India, gap in capital cost could be minimized by allowing solar
cover the required capital cost, nor the local LEC to cover the gas and
component of ISCCS to receive same tariff as wind Indian
O&M price. Additional fi nancing required.
Rupee (INR3.3). A cost gap would still remain, which would have to
be fi lled by, e.g. government subsidization. This could be justifi ed by
the other benefi ts gas supply could bring to the region.
10.
Exposure to fossil fuel price
If a combined cycle plant is to be installed, the ISCCS approach helps
Storage technology can signifi cantly increase the solar share.
increases (in particular gas price
to reduce exposure to gas price fl uctuations on a per MWh produced
Storage (based on molten salt; 7.5 hours) will be part of the new
increases)
basis. Compared to a solar-only plant, disadvantage of the ISCCS
Andasol 1 and 2 plants (2x50 MW) starting operation in Spain in
approach.
2006/2007.
Morocco: risk low due to long-term nature of contracts (“droit de
passage”). However, the Moroccan government could levy part of
the fi nancial advantage on ONE.
Mexico has strong gas-CC expansion strategy. ISCCS helps to mitigate risk.
India: gas use for electricity generation is expected to increase here;
however indigenous gas resources are not strong. In addition, India has
a strong commitment to hydro. Solar can help reduce the exposure to
high gas prices and low water fl ows during drought.
11.
Non-guaranteed power purchase
Increasingly, due to the electricity market liberalization, no long-term
Frame for preferential feed-in of renewable electricity (for hybrid
(relevant for IPP approach)
power purchasing agreements are granted to the company that runs
electricity from ISCCS above a certain share).
the ISCCS plant in concession, increasing the risk to companies.
Risk comparatively small in markets with growing electricity demand.
Longer periods of bankable tariff support for CSP so that, as in Spain,
the upfront capital is underwritten by the revenue stream.
12.
Weak fi nancial position of off-taker
Higher fi nancial risks for banks (e.g. case of Nevada – now overcome;
In the Nevada case, recent legislation changes made it possible for
case of Algeria where the off-taker is Sonatrach, the strong national
the renewable contracts signed by the utility to be protected. This
hydrocarbon company, who will sell on to the fi nancially weaker
solution is diffi cult to provide on a wider basis.
electricity supply company).
Back-to-back guarantees from state/WB
13.
Additional fi nancial risk for the solar
The reason for combining the O&M contract with the EPC contract is
It is considered prudent that the fi nal owner of the plant receives some
supplier (but also the main EPC
to instill the fi nal owners with confi dence that the fi eld will perform
assurance as to performance over a period of time. There may be an
contractor) due to combined EPC
as desired prior to them taking ownership.
opportunity to minimize the risk for the solar supplier by having the
and O&M contracts
owner (if a utility) carry out the O&M, if the owner is prepared to
bear the associated risk.
Risk
Valuation
Mitigation
27
C
HAPTER
3 – CSP R
ISK
A
NALYSIS
(continued on next page)
The EPC contractor will generally have built in a factor for technical risk.
(Consider separate O&M contracts if confi dence in the performance
There is also a factor built in for O&M risk, which increases the overall
of the plants allows it.)
price.
Generally, the O&M contract is smaller in volume than the EPC contract.
Often the O&M and EPC contractors are different companies. In the case
of combined EPC + O&M, the liability of the O&M contractor is then for
the overall project volume.
14.
Unusually high level of guarantees
In the case of India, up to 20 percent of the investment was required
Discuss the required amount of security at an early stage.
required from the national side
as a guarantee until the end of the O&M contract because the
technology involved was new. This forces companies either to raise their
Risk sharing among turnkey contractor, fi nancing organizations, and at
margins or to wait fi ve years before they can expect the return.
national level.
15.
Full liability for the contractor of the
Despite the fact that the technical risk of the solar plant not performing
Careful study of limited liability requirements of the turnkey provider
solar thermal component for the
is limited (see above), the fi nancial risk is high for the smaller solar
and the solar provider.
whole ISCC
supplier but also for the turnkey provider if the failure of the solar plant
is considered a reason to reject the combined cycle plant. Civil work and
Investigation of replacement solutions and cost.
the combined cycle by far the largest share in the investment.
Demonstration of critical components.
16.
Risk pricing by bidders
Risk pricing by bidders might occur at an early stage of CSP
Reduction in the size of the solar component.
development when there are a lot of uncertainties.
Ensure competition (possibly including solar tower).
17.
Insuffi cient protection of
Concern has been raised that in a single EPC arrangement, there would
This will need to be dealt with using conventional legal mechanisms—
intellectual property
have to be signifi cant sharing of know-how and experience both from
this situation is commonplace in collaborative relationships.
the CC supplier to the solar fi eld supplier, and vice versa to enable the
overall plant to run optimally. There was a concern that either party could
deal with other partners in future projects and share the information
acquired. This brings up the issue of the contractual relationship
(confi dentiality agreements) and clauses on future freedom to operate.
It is important that the overall plant run optimally and reliably to benefi t
the reputation of both the CC supplier and the solar fi eld supplier.
3.3: R
EGULATORY
/
INSTITUTIONAL
RISKS
RELATED
TO
THE
WB/GEF
PORTFOLIO
Risk
Valuation
Mitigation
18.
Lack of incentives to maximize
Since the plant operator gets an initial grant; from his short-term
Ensure incentives/obligations to operate the solar fi eld in the form of
operation of the solar fi eld
perspective, the operation of the solar fi eld only makes sense if O&M
penalties on a kWh-basis (below design operation).
costs are below the selling price of the electricity. If the solar fi eld causes
(unexpected) problems with respect to the CC operation, non-usage of
the solar fi eld might be the consequence.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
28
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
19.
Loss of confi dence in potential
In principle, diffi culties with the WB/GEF portfolio and delays were
The WB/GEF portfolio needs one rapid success in order to restore
project developers due to lengthy
to be expected as a new technology is combined here with the more
confi dence of investors and companies who have participated in bids
bidding procedures
diffi cult environment of developing countries. Therefore, the time frame
in the past.
is not really a surprise. Several years were lost with the unsuccessful
IPP
approach.
Frame conditions have changed (higher general energy prices, ongoing
The portfolio requires higher priority and shorter decision lines in the
projects in Spain and the U.S.), which advocates pushing through the
WB/GEF hierarchies. It represents one third of GEF’s climate
current
portfolio.
change
budget.
Concentrate efforts to convince investors and fi nancial institutions.
20.
Loss of confi dence in project
Pushing a new technology is a hurdle companies only take if the related
Rapid implementation of at least the fi rst of the WB/GEF projects.
developers due to missing long-term
risks are adequately compensated and/or long-term perspectives of
assurance of CSP market growth
the market are attractive.
Due to today’s favorable conditions in other parts of the world
Common discussion and development of a long-term view of CSP
(e.g. Spain, U.S., Algeria), this problem seems less dramatic than it
(including information, dissemination, and public discussions in strategy
did a few years ago.
workshops).
21.
Lack of supportive-framework for
All of the WB/GEF countries have a certain frame for renewables with
Investigate suitable mixes of fi nancing and support structures for future
renewables, in particular CSP
ambitious targets, R&D etc. However , in general, national fi nancial
promotion of CSP technology such as soft loans + renewable portfolios,
support is limited to the provision of own funds for the main electricity,
(low-level) feed-in tariffs adapted to the fi nancial context of developing
which limits the further expansion of the renewables technology until it
countries, Clean Development Mechanisms.
is competitive with the main market technology.
For future projects, national RES goals and frameworks should be a
primary criterion for choosing a country to support in order to increase
the likelihood of a multiplication effect of the fi rst plant.
Consider market barriers (“OP6 –type barriers”) also in technology
simulation projects such as under OP 7.
22.
Lack of competitive electricity
Opening electricity markets can have negative and positive impacts on
This is a bigger issue than that just facing CSP. The issue for CSP is to
market
structures
the development of new technologies such as CSP: on one hand, it
create a framework in which it can compete against fossil fuels and
might squeeze out the surplus of the main market operators that is
other renewable technologies.
needed to embark on such a technology. It might also lead to higher
uncertainties (e.g. during market transitions or when PPAs are no
Create security in tariffs and allow for attractive returns.
longer available). On the other hand, within the framework of
interlinked markets, CSP might have a better chance (e.g. electricity
exports from Algeria, or the whole of Northern Africa to Europe).
Risk
Valuation
Mitigation
29
C
HAPTER
3 – CSP R
ISK
A
NALYSIS
3.4: S
TRATEGIC
RISKS
RELATED
TO
THE
WB/GEF
PORTFOLIO
Risk
Valuation
Mitigation
23.
Risk in mandating a particular
Opportunities
integration confi guration such as
In the short run, it is more important to get the fi rst WB/GEF plants
Accurate and comprehensive instrumentation is required to measure the
ISCCS and its future impact
running than to achieve a maximum CO
2
reduction.
contribution to electricity generation in an ISCC, which may not be
Even though ISCCS may only have around 5 percent or less of solar
available in all plants.
contribution, this is still 30 MW (around 200,000 m
2
), and the same
amount of solar fi eld O&M experience and know-how will be gained
either
way.
A prime requirement for developing countries is the additional capacity,
ISCCS is, in the medium to long-term, not the fi rst choice, but for
rather than a specifi c need for peak power as in many developed
further developments in the short term, it mightt be the only acceptable
countries. Most of the developing countries are suffering from low
option for solar thermal power from a developing country’s perspective.
reserve margins in available power (e.g. 6 percent in Mexico). The
However, thermal and fi nancial calculations should carefully consider
advantage of ISCCS is that a one-off project results in both signifi cant
whether the ISCCS option really has the lowest cost, or whether the
additional capacity plus the solar contribution, whereas STR + CC
compromises to be made between the solar and the fossil parts
requires the planning complexity of two projects with the chance that
increase costs to a point where options with larger solar fractions
one will fail.
become comparable in costs. Environmental benefi ts are to be
checked ex-post for the fi rst plants.
Constraints
Limited overall GHG benefi ts compared to a solution involving stand-
alone solar thermal Rankine (STR) + conventional combined cycle (CC),
especially if the ISCC’s design is not optimized for low CO
2
emissions.
Limited public acceptance in developed countries and international
funding
organizations.
ISCCS might require compromises between the solar and the fossil parts,
which hamper the performance of one or the other and result in a sub-
optimal overall performance (e.g. dry and sunny location versus lower
performance of the CC due to high outside temperatures and lack of
cooling water; location constraints due to the availability of natural gas,
power losses etc.).
Upgrading the low solar share in an ISCCS plant later during the plant’s
lifetime is not possible from today’s technological perspective.
Moving from the ISCCS technology route with a low share of solar to a
solar thermal technology with a larger share of solar or a solar-only
technology route is not a gradual process but represents a technology
change (otherwise the steam generator has an increasingly degraded
performance).
24.
Risk in mandating the trough
According to the Sargent and Lundy study (2003), tower technology
As much freedom as possible should be left to the bidders. Competition
technology compared to tower,
has the larger potential for cost reduction in the longer term. On the
speeds up cost reduction. Therefore the bidding should not be focused
dishes, or Fresnel collectors for
other hand, there may be a limit to the size of the plant due to the
on the trough technology but be technology-independent (CSP). A
future developments
diffi culties of focalizing the light on the tower over large distances.
security criterion might be bidding companies/consortia fi nancially
strong enough to bear the risk of non-operation.
(continued on next page)
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
30
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
25.
CSP might take up market shares
Other renewable energy sources allow an incremental growth in
Storage technology should be introduced, perhaps only in future project
more slowly than other renewables
contrast to CSP with generally large steps of several tens of MW so
developments. In the current round of WB/GEF, introducing project
options (incl. PV and wind)
they can be more easily adapted to fi nancing constraints and small
storage might cause additional delays in the realization of the projects.
investments. This reduces the overall risk exposure of an investor.
Compared to PV and wind, CSP has a storage possibility.
Levelized electricity costs for most CSP technology routes are (still)
Solar dish technology is similar to other renewables as it allows
very much below those of PV.
incremental add-ons in the kW range compared to the main CSP
technologies of trough and tower. Although levelized electricity costs are
highest with this technology (dishes are hardly competitive today with
PV
7
), it could be worthwhile investigating its potential in smaller
projects in developing countries given the incremental nature of this
technology.
26.
Concepts chosen not fl exible
If fi nancing constraints are an issue, one solution might be to construct
Investigate modular concepts that allow additional capacities to be
enough with respect to future
a solar power plant over a number of years. With the ISCCS concept
added once additional fi nancing is available without increasing costs
plant extensions
this is more diffi cult to implement and more costly: with an ISCCS,
considerably. This is not possible with ISCCS given the fact that the
any delays in the solar fi eld do not have to delay the combined cycle,
steam turbine needs to be designed to an optimal point of use.
even though the combined cycle will operate less effi ciently using duct
burning or a partly loaded steam turbine until the solar fi eld is fully
installed. The solar contribution could be extended over time by adding
mirrors with corresponding storage.
27.
Dependency on single supplier of
Currently only Flabeg manufactures such mirrors.
Evaluate bottlenecks that might occur if construction of a number of
key elements
plants coincides. However, Flagsol believes two 50 MW plants of the
Andasol type with 500,000 m
2
can be fabricated in a year, with a
third being possible with a new furnace within six months.
With fi nancial support by the German Ministry for the Environment,
Bending is the time consuming process rather than the glass production
Solar Millenium and Schott have successfully developed improved
(glass production takes only 9 days for the Andasol plant). In principle,
receiver tubes (now there are globally two commercial tube suppliers).
mirror bending could be offered by other companies too and is a
question of CSP market development (motivation for competitors to
enter
the
market).
All other elements are more or less standard.
Guarantee access to fabrication train for mirrors.
Risk
Valuation
Mitigation
7
On the other hand the Ecostar study (DLR, 2005) shows that this technology has a considerable future cost reduction potential (see Table 2).
31
C
HAPTER
3 – CSP R
ISK
A
NALYSIS
3.5 O
VERALL
RISK
EVALUATION
The following table presents the compilation of the different risks
and their evaluation across the four risk categories (technological
risks, fi nancial/commercial risks, regulatory/institutional risks, and
strategic risks), the main level of impact (project success; WB/GEF
program success; global technology evolution) and the main actors
for risk mitigation.
T
ABLE
4: O
VERALL
RISK
EVALUATION
FOR
THE
WB/GEF
SOLAR
THERMAL
PORTFOLIO
Main level
Main body for
Risk
Risk Level
of impact
risk mitigation
Technological risks related to the WB/GEF portfolio
/
❶
1.
Non-optimal choice of location
/
/
❶
National
level
2.
Environmental benefi t low or non-existing due to the ISCCS concept
❷
/
❸
Plant
designer/operator
3.
Insuffi cient experience with CSP technology
❶
/
❷
Equipment
suppliers
4.
Thermal storage in the required size new and non-experienced technology
❶
/
❸
Equipment
suppliers
5.
Problems at the technical interface between the solar component and the fossil component
/
❶
Plant
designer/operator
6.
Non-optimized operation of the ISCCS plant
❶
Plant
designer/operator
7.
Complete failure of the solar plant
❶
Plant
designer/operator
Financial/commercial risks related to the WB/GEF portfolio
❶
/
❷
8.
Low interest in bidding by industry
❷
National level – WB/GEF
9.
Insuffi cient fi nancing secured for the WB/GEF projects
/
❶
National level – WB/GEF
10.
Exposure to fossil fuel price increases (in particular gas price increases)
❷
National
level
11.
Non-guaranteed power purchase
❸
National
level
12.
Weak fi nancial position of off-taker
❶
National
level
13.
Additional fi nancial risk for the solar supplier (but also the main EPC contractor)
due to combined EPC and O&M contracts
❷
National level – WB/GEF
14.
Unusually high level of guarantees required from the national side
❶
National
level
15.
Full liability for the contractor of the solar thermal component for the whole ISCC
❷
National level – WB/GEF
16.
Risk pricing by bidders
❷
Bidders – National level
17.
Insuffi cient protection of intellectual property
❶
Bidders
Reglatory/institutional risks related to the WB/GEF portfolio
/
❷
/
❸
18.
Lack of incentives to maximize operation of the solar fi eld
❶
National level – WB/GEF
19.
Loss of confi dence in potential project developers due to lengthy bidding procedures
❷
National level – WB/GEF
20.
Loss of confi dence in project developers due to missing long-term assurance of CSP market growth
❷
/
❸
National level – WB/GEF
21.
Lack of supportive-framework for renewables, in particular CSP
❷
/
❸
National level – WB/GEF
22.
Lack of competitive electricity market structures
❷
/
❸
National
level
Strategic risks related to the WB/GEF portfolio
/
❸
23.
Risk in mandating a particular integration confi guration such as ISCCS and its future impact
❸
National level – WB/GEF
24.
Risk in mandating the trough technology compared to tower, dishes, or Fresnel c
ollectors for future developments
❸
National level – WB/GEF
25.
CSP might take up market shares more slowly than. other renewables (incl. PV and wind)
❷
/
❸
National level – WB/GEF
26.
Concepts chosen not fl exible enough with respect to future plant extensions
❸
27.
Dependence on single supplier of key elements
❷
/
❸
Equipment
suppliers
Legend:
Importance of risk:
: low risk;
: medium risk;
: high risk
Main level of impact:
❶
project success;
❷
WB/GEF programme success;
❸
global technology evolution
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
32
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
An overall impression of the risk is provided for each of the four risk
categories. It appears that the regulatory/institutional risks present
the highest risk level for the portfolio as a whole. Technological risks
are less relevant for the overall portfolio (but might have an impact
at the level of individual projects), while fi nancial/commercial risks
might be relevant both at the level of the individual projects and
to some degree for the WB/GEF portfolio as a whole. Strategic
risks are equally high but only relevant in the longer term, and may
be mitigated by a more diverse development of the general CSP
market compared to the WB/GEF portfolio, which relies solely on
the ISCCS technology route. Strategy risks, by defi nition, mainly
affect the global technology evolution.
Table 5 shows where the most critical points are in the project de-
velopment trees. While project delay is the general consequence
in the pre-bidding stages, the bidding process itself accumulates the
most critical short-term risks. These result either in further substantial
project delays if the whole process has to be redesigned (shift from
the IPP approach to a public EPC/O&M fi nancing), or in project
abortion in the worst case.
T
ABLE
5: T
HE
CRITICAL
POINTS
IN
THE
PROJECT
DEVELOPMENT
TREE
Step in project development tree
Risk
Damage in case of risk event
Project idea and fi rst evaluation
19
project delay
Feasibility study
19
project delay
Prequalifi cation of bidders
19
project delay
Development of detailed bidding procedure (EPC, O&M)
19
donors/national bodies damaged in credibility
Financial close
9, 19
project delay
Bidding process
8, 11 (IPP), 12, 13, 14, 15, 16
project abort/project delay
19
donors/national bodies damaged in credibility
Contract 17
project delay
Construction 27
project delay
Operation
1, 2, 3, 4, 5, 6, 7
technology line (e.g. ISCC) and possibly whole CSP
line damaged in credibility
18
De facto project abort; technology line (e.g. ISCC) and
possibly whole CSP line damaged in credibility
Technology replication
10, 20, 21, 22, 23, 24, 25, 26
Replication endangered
33
his chapter briefl y describes the status of the WB/GEF
portfolio and its possible development. For more details,
see Annex 4.
4.1 S
TATUS
OF
THE
WB/GEF
PORTFOLIO
AND
POSSIBLE
DEVELOPMENT
The team made personal visits to each of the GEF project countries,
interviewing key players and decision makers, as well as conduct-
ing follow-up interviews and discussions by phone/email to clarify
the points and issues raised. The interviewed people are listed in
Annex 5. A detailed assessment of each project—status, key is-
sues and recommendations, energy infrastructure, and institutional
framework—is contained in Annex 4. This section summarizes some
of the key fi ndings and issues relating to the projects.
Each project is at a different stage of delivery, and all have encoun-
tered various obstacles along the way (see Table 6). The Indian
Mathania project was the fi rst to receive approval in principle from
GEF. The Mexican, Moroccan, and Egyptian projects benefi ted
perhaps from the prior experience of India in terms of the bid docu-
ments and bidding procedure, and the dealings with the World
Bank and GEF. However, each country has its own institutionalized
routes through government. Specifi c issues and diffi culties are dealt
with in Annex 4. Overall though, each country shows a high level
of enthusiasm and desire to progress with their projects. The fol-
lowing views are pertinent to the overall portfolio.
A certain amount of confusion has arisen from the wealth of LEC
fi gures that appear around the world in papers, at conferences, and
independent evaluations. Quite often, the LEC fi gure is discussed
with little regard to the assumptions and robustness of the underly-
ing calculation. For example, fi gures of 12–14 c/kWh are often
purported to be the benchmark LEC set by the SEGS plants, when
in reality the agreed energy price for those SEGS plants depended
on maximizing return with due regard to time-of-use tariffs, the
various incentive schemes in place at the time, and the specifi c
requirements of the investors. They do not necessarily equate with
the conventional method of calculating LEC—put simply, cost of
capital + O&M (with or without tax, depreciation, etc. included).
The other signifi cant factors are the level of insolation under which
they were calculated, and the currency upon which they were
based. It is not appropriate, for example, to apply the exchange
rate between the euro and the Indian rupee to the whole of the
LEC and expect to have an accurate idea of LEC in India. Different
parts of the capital are sourced at different rates, and some of the
labor will be at local rates.
Individual techno-economic feasibility studies are needed and have
been conducted for these four projects (including a very recent one
for Mexico). These ensure that all factors are considered. They also
take local factors into account. For example, the Indian RfP set
specifi c limits on the levels of euro and dollar that could be used
toward the EPC fi nancing.
It is possible that an element of over-optimism surrounded the projects
of this portfolio at an early stage. When the detailed feasibility
assessments were carried out, including all the local factors plus
risk factors of performance, fi nance and insurance, the fi nal price
went up instead of down, which made things more diffi cult for the
decision makers at the political level. However, this is not a unique
scenario for a new, or relatively new, technology.
In addition, the projects were initially predicated on the basis of
an IPP structure, where all the diffi culties and risks of raising fi nance
4
T
H E
S
T A T U S
O F
T H E
WB/GEF
CSP P
O R T F O L I O
T
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
34
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
and ensuring performance were to be borne by large organiza-
tions. When this had to be revised for EPC with O&M contracts,
many more institutional and governmental factors came into play,
which has resulted in delays.
It would be naive to believe that additional delays of some form
or other affecting one or more projects will no longer occur. We
believe fi rm dates now need to be set for each project after con-
sultation with each country.
4.2 S
TATUS
OF
THE
WB/GEF
PORTFOLIO
BY
COUNTRY
4.2.1 WB/GEF project in Egypt (Kuraymat)
Project history
The chronology of the Egypt/Kuraymat project is as follows:
April 2004
Pre-qualifi cation and bidding documents com-
pleted. In parallel, NREA was investigating
potential sources of fi nancing, including JBIC.
June 2004
Government of Egypt makes offi cial request to
JBIC to fi nance the project.
T
ABLE
6: S
UMMARY
OF
GEF
PROJECT
STATUS
Country/project
Status of project
Project structure
Expected schedule
India, 140 MW ISCCS incl. 35 MW
WB waited on letter of commitment from
Single EPC with O&M (5 years). PPA with
Eventually, the project could not be timely
solar trough, site approx
Govt of India, after which the already-
RVPN. Project owner RREC.
implemented due to inappropriate design and
2,240 kWh/m
2
/year DNI.
drafted RfP (revised) could be released.
location.
Egypt/Kuraymat, 151 MW ISCCS incl.
Financial closure agreed. Solar thermal
Two EPC contracts. The solar island will be
Delays due to the splitting of the packages to
25 MW solar.
part and CC at bidding stage.
an EPC with O&M contract; the CC island
be funded by GEF, NREA and JBIC. Contract
will be an EPC contract with local O&M to
signature expected for early 2007. Construction
be bid separately fi nanced by NREA.
might begin late 2007. Possible begin of
operation
late
2009.
Mexico/El Fresnal near Agua Prieta,
November/December 2005: Approval by
The fi nal owner of the plant will be CFE.
At this stage, bidding is expected for 2006,
Sonora State (site decision in March
the Treasury Ministry. The hybrid plant has
They will undertake to provide the O&M.
construction to begin 2007, operation 2009.
2005, plant Agua Prieta II), originally
been included in the PEF (Programa de
(Previously, unsuccessful project
285 MW ISCCS but fi nally increase
Egresos de la Federación) and approved
development under IPP scheme.)
CC to 560 MWe; Solar trough fi eld
by Congress.
25–40 MW; Excellent solar site
Acceptance of the doubling of fossil
conditions (exact solar data not available). capacity by the WB task team after
technical economic assessment by Sargent
and Lundy (May 2006) and a consultancy
by Spencer Management.
Morocco/Ain Beni Mathar
EPC with O&M (5 years). Option exists to
Owner of plant will be ONE. Total cost
EPC with O&M contract for the project expected
240 MW ISCCS, including 30 MW trough. renew O&M contract after 5 years. Bids
expected approx
€
213M, including
to be signed by the end of 2006, and at the
Expected production from ISCCS 1,590
received May 2006. Ongoing evaluation
connection to infrastructure.
€
43M from
latest in January 2007.
GWh/year, of which approx 55 GWh/year process.
GEF, and
€
34M from ONE. Balance of
Expected start of operation of the plant is
solar (3.5 percent solar contribution).
€
136.45M from African Development
mid 2009 (construction time 30 months).
Bank as soft loan.
35
C
HAPTER
4 – T
HE
S
TATUS
OF
THE
WB/GEF CSP P
ORTFOLIO
August 2004
JBIC sends fact-fi nding mission, shows interest,
but requests the splitting of the CC and solar
packages as well as a halt of 5 months on the
procurement process to allow for JBIC’s pro-
cessing and approval of the fi nancing. World
Bank team expresses its reservations on the
two-package approach, given the signifi cant
additional risks (integration, management and
accountability) it poses to the client.
March 2005
Government of Egypt decides to split the CC
and solar packages in order to obtain JBIC
fi nancing.
March 2006
The prequalifi cation process for the solar thermal
part (March 2006) resulted in four prequalifi ed
bidders.
Future development according to current planning:
The project experienced delays due to the splitting of the packages
to be funded by GEF and JBIC, which required a certain change
in scope.
February 2007 Contract signature expected.
Late 2007
Construction might begin.
Late 2009
Possible beginning of operation (assuming 30
months construction time).
4.2.2 WB/GEF project in Mexico (Sonora)
Project history
The chronology of the Mexico/Sonora (previously Mexicali) project
is as follows:
1986
8
The Mexican electricity sector was opened
to competition in a limited way. New types
of projects emerged: financed built-transfer
projects OPF corresponding to EPC, CAT and
Independent Power Producers (PIE Productores
Independientes de Electricidad).
1995–96
Spencer Management Associates (SMA) under-
took an evaluation of ISCCS plants under IPP
fi nancing scheme in cooperation with CFE.
Oct. 1998
Meeting on “solar thermal dissemination mission”
sponsored by IEA SolarPACES, CFE and others.
Interest was shown by all sides for a possible
solar thermal project as part of CFE’s expansion
plan.
Aug.–Nov. Technical and economical feasibility study
1999
9
carried out by SMA for integrating parabolic
trough solar fi eld into a gas turbine combined
cycle plant at Cerro Prieto near Mexicali, Baja
California Norte.
Dec. 1999
Mexico solar thermal hybrid project entered the
GEF program (with GEF grant of $49.3 million)
as an IPP project at a specifi c site in Mexicali,
Baja California Norte, to be procured in con-
junction with the planned Mexicali II Combined
Cycle Gas Turbine (CCGT) Project IPP.
10
March 2002
“Call for Bids” on an IPP basis was published.
The solar fi eld was an option for the combination
with a CC plant.
April–March
After several postponements of the deadline
2003
for the “call for bids,” the bidding process was
halted after the visit of Laris Alanís (CFE director)
to the World Bank. It became clear that there was
an irresolvable “the hen or the egg” problem: the
8
http://gaceta.diputados.gob.mx/Gaceta/58/2002/feb/20020213.
html
9
Thematic Review of GEF-fi nanced solar thermal projects, October
2001.
10
World Bank to GEF Council, April 2004.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
36
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
World Bank could not commit its grant funding
before knowing the identity of the winning bidder,
while CFE could not fi nalize the bidding process
before the fi nancing was secured. It also has to
be stated that there were not only problems on
the fi nancing side, but also the industry response
to the published bidding was very limited.
For the further ISCCS project development, it was
decided that an EPC scheme with CFE as WB
grant recipient should be pursued. The solar fi eld
would no longer be an option but compulsory.
Oct. 2004
Finalizing of a feasibility study for Mexicali II
(Baja California Norte) including Sargent and
Lundy as the World Bank’s consultants and social
and environmental specialists.
Nov. 2004
The plant location was changed to Sonora state
(Agua Prieta Site). CFE’s explanation was that the
power sector expansion plan would not allow
further delays related to the implementation of
the solar fi eld.
March 2005
Inquiry from CFE to the World Bank if the Bank
would still support an ISCCS plant with a solar
fi eld integrated into a 500 MW instead of a
250 MW plant.
May 2006
A technical economic study by Sargent and
Lundy and a consultancy by Spencer Manage-
ment, of the 500 MW CCGT concluded that
“the bigger the host of CCGT is, the greater the
conversion effi ciency and the solar energy col-
lected” and explained that “the reasons for the
outstanding output is due to two factors i) higher
effi ciency of the thermal 2x2x1 arrangement and
ii) the 500 MW thermal plant results in a lower
drop in effi ciency during night hours, when the
solar fi eld is not operating.”
By June 2005
Completion of technical and economical evalu-
ation by CFE.
June 2005
Presentation to the Treasury Ministry.
Nov.–Dec.
Approval by Treasury ministry.
2005
Jan. 2006
The hybrid plant has been included in the PEF
(Programa de Egresos de la Federación) and
approved by Congress.
Future development according to current planning:
June 2006
Invitation for tenders (published).
Sept. 2006–
Start construction.
Jan. 2007
April 2009
Grid connection of the plant.
4.2.3 World Bank/GEF/KfW project in India
(Mathania)
Project history
The chronology of the India/Mathania project is as follows:
1988
Project report to the Government of India (GoI)
on a 30 MW solar thermal power plant. GoI
approved India for a demonstration project.
1989 Land
allocated.
1990
Working group fi nalized the parabolic trough
preference for design.
1991
Revised feasibility study report in view of cost es-
calations and tariff revision to Central Electricity
Authority (CEA) for techno-economic clearance
(TEC).
1992
CEA dropped project, fi nding it techno-economi-
cally non-viable.
37
C
HAPTER
4 – T
HE
S
TATUS
OF
THE
WB/GEF CSP P
ORTFOLIO
1993
Prime Minister’s Offi ce intervened, steering com-
mittee was constituted.
1994
BHEL and Solel prepare detailed project report
for 35 MW solar.
1995
Proposed to GEF and KfW for funding; compre-
hensive feasibility report prepared by Engineers
of India and Fichtner; found 140 MW CC with
35 MW solar most viable.
1996
Possibility of implementation by IPP with private
equity explored; GEF grant of $49 million
agreed to in principle.
1997
Rajasthan State Power Corporation Ltd formed
especially for the Mathania ISCCS project.
1998
Detailed project report (with naphtha as fuel)
submitted to CEA for TEC.
1999
CEA approved, KfW appraised, EPC with O&M
approach decided on.
2000
GoI decision facilitates grant funding; Fichtner
Solar appointed as consultant.
2001
Pre-qualifi cation process completed; high price
volatility of naphtha results in changeover to R-
LNG; revised pre-qualifi cation process initiated.
2002
Pre-qualifi cation fi nalized with LNG as fuel;
RfP document fi nalized; project agreement and
separate agreement signed; heads of agreement
for gas supply signed with GAIL; RfP issued.
2003
Protracted negotiation with potential bidders fails
to secure a bid.
2004
Fichtner redrafts RfP ready for release mid-2004,
but prior to release World Bank requests a letter
of commitment to the project from Government
of India.
Letter from GAIL (India Ltd) to Rajasthan Renew-
able Energy Corporation (RREC) (March 16
2004) stating that the agreed gas price would
be INR270.47/MMbtu, including transmission,
and escalating at 5 percent per year (note RREC
modeling assumes 5 percent per year for fi rst 5
years, then fi xed).
Principles and terms and conditions for PPA
agreed upon by Discoms and RREC on 16th
August 2004.
Letter from CEA to Government of Rajasthan con-
fi rming LEC of INR2.62/kWh (current modeling
shows 2.82) and suggesting that it would be
“desirable that the concerted efforts be made to
implement the project at its earliest” (September
3, 2004).
2005
MNES informed of new large gas/oil fi nd near
Mathania.
Future development according to current planning:
At the time of the study, the consultants had recommended that (i)
the GoI needed to reply to the World Bank letter of 2004 stat-
ing the government’s commitment to the project proceeding and
to meeting the requirements stated therein, and that (ii) there be
a resolution of the balance of funding from KfW. Eventually, the
project could not be implemented in a timely manner due to inap-
propriate design and location.
Additional information/discussion of the Indian project
In March 2003, the STAP Brainstorming Session on OP 7 (STAP
2003) reported that the likelihood of success for the Indian project
was 30 percent, due partly to the complicated process to that
date, and the risk to industry players. In the intervening period, we
believe the chance of success has risen.
gas and PPA agreement principles, terms and conditions have
been agreed to;
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
38
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
a modifi ed bid document has been prepared in draft form (we
have been unable to view this document);
all clearances are now in place;
the CEA, which dropped the project on the grounds it was
“techno-economically nonviable” in 1992, has recently (Sep-
tember 3, 2004) written to the Government of Rajasthan stating
that it would be “desirable that the concerted efforts be made
to implement the project at its earliest”.
The document “principles of PPA” dated September 16, 2004,
has been modifi ed from that agreed to in June 2001. It includes
the following:
The determination that there will be “no fi nancial burden on the
Discoms (distribution companies) because the tariff is well below
the cost of generation compared to new coal-based power
plants and within the price-band of procurement of power by
the utilities.”
States that the risk involved with a “take or pay” gas contract
will be covered by a back-to-back arrangement under the PPA.
Furthermore, if the plant load needs to be reduced on request
from Discoms, there will be compensation paid for fi xed charges
and take or pay obligations of the gas supply contract. The
problem was exacerbated when the GoR directed in 2001 that
the ISCCS plant would be outside the purview of merit order
dispatch.
Notwithstanding occasions when there will be no choice but to
ask the plant to shut down, every effort will be made to keep
the solar part going when radiation is available by ensuring the
part load of the CC remains high enough to enable the solar
fi eld to operate (albeit at part-load conditions).
The latest costing spreadsheet (June 2004) shows a fi rst year energy
cost of INR 2.49/kWh, and 20 year average LEC of INR 2.82/
kWh (taking into account: $45 million GEF grant, INR 500 million
GoI grant, and INR 500 million GoR grant). The total project cost,
including IDC, is INR 8,226.87 million. This is based on a gas
price of INR 270.47/Mmbtu, a water price of INR 20/1,000
Cuft, and O&M at 1 percent of total project cost for fi rst 2 years,
then 2.5 percent in year 3 with 4 percent escalation following.
These costs have been worked out on the basis of a total plant
output of 155 MW, with 30 MW solar block. The annual electrical
output of the plant is 916 GWh, including 63 GWh estimated
from the solar block.
Note that it was conveyed to us that the present pool price is
INR2.1–2.2/kWh, depending on the hydro situation, but imported
electricity to the State of Rajasthan is around INR4–5/kWh. Cur-
rently, Rajasthan imports much more electricity from other states
than would be generated by the Mathania plant. The electricity
generated by Mathania will essentially be a cheaper substitute for
currently imported electricity.
Based on these fi gures, the solar electrical capacity factor is 24 per-
cent. This seems high for an insolation regime of 2,240 kWh/m
2
/
yr DNI, even allowing for the advantages of ISCCS in terms of start-
up and transients. However, even if a 20 percent capacity factor
were assumed to allow for fi eld availability, the LEC only goes from
2.82 to 2.85. This is another of the effects of ISCCS—it desensitizes
the overall LEC to solar performance (in both directions).
With regard to gas supply, RREC has informed MNES about the
biggest inland gas and oil reserve found in Jaisalmere and Barmer,
which is about 150–170 km from the Mathania site. Cairns
Energy, UK, will operate oil and gas rigs. This is closer than the
present 425 km, and if supplies are confi rmed, should result in a
cheaper gas price. However, it is understood that the “GoR has
entered into a gas cooperation agreement with GAIL for assess-
ment of potential demand in the industrial sector, transport sector
and domestic sector on the pipeline route, which will further bring
down the transport charges to Mathania project on progressive
development of demand potential.” There is also potential for the
possibility of further extension of the pipeline from Kota-Mathania
to Ramgarh (Ramgarh Gas and Power) due to the potential for
industrial towns along the way.
Though these gas options provide the possibility for cheaper gas,
they also give rise to further project delay while the optimum op-
tion is being sought. A preferred route needs to be established as
soon as possible. The study could be conducted while bids were
being assessed. Then construction of the new pipeline needs to
be started so that gas fl ows will have been established prior to
39
C
HAPTER
4 – T
HE
S
TATUS
OF
THE
WB/GEF CSP P
ORTFOLIO
construction completion of the ISCCS. This completion date will
need to be enforced by penalties for late delivery.
There seems to have been a differing view over time as to the
capacity of the solar portion. Figures up to 35–40 MW of solar
have been circulated, but the latest cost spreadsheet was based
on 30 MW. This seems a sensible choice if the reluctance of the
GoI to sign off is due to cost. It makes the technical integration
easier, with less manipulation of an otherwise optimized combined
cycle required. It also improves the overall GHG performance of
the ISCCS as off-design operation is closer to the ideal (the steam
turbine is better dimensioned so duct-fi ring or the level of part-load
operation is reduced). The arguments by RREC appear to make
this capacity quite competitive in terms of LEC versus the imported
price of electricity. However, we would recommend consideration
of the following option for the next RfP.
The next RfP should include additional assessment criteria with a
signifi cant weighting that considers the size of the fi eld (or solar
GWh
e
) offered. There should still be a minimum required fi eld size
(in the original RfP this cut-off was 50 GWh
e
below which the bid
would not be considered). But this should be a lower fi gure, to be
determined through consultation. This would mean that bids could
be differentiated on the basis of the solar fi eld size, prompting
competition on both the quality and quantity of solar offered.
Paradoxically perhaps, the ultimate outcome for GEF is likely to
improve if the solar expectation is reduced. The solar fi eld, which
is modular in design, will generate as much experience and know-
how as a larger one. And though the solar capacity would be less,
the number of solar MW is to some extent arbitrary. In the broad
scheme of things, which is ultimately what OP 7 is concerned
with, the technology and the industry would be better served by
a successful project. There is more chance of a successful industry
being spawned by a successful 25 MW than by a risky 30 MW,
or even by a proposed 35 MW that never proceeds because it is
too expensive. By 2015, no one will be concerned that the very
fi rst project was a few MW less than originally intended.
One of the delays in 2003 when no bids were received was due to
the fact that there was no clear defi nition of who would bear the risk
liability. We were informed the risk issues have since been resolved
and tender documents revised. Currently risk is being shared by
the whole consortium of contractors. The second issue raised by
MNES was involvement of very few contractors in the project and
the revised proposal has a consortium of contractors/participants
to address this issue. The Department of Economic Affairs fully
supports this project and will ultimately approve it. Currently, the
decision for this project rests with MNES.
The original project was approved by the central government,
but there was a change of government after the last election in
late 2004. The new central government revised the whole project
again and approved it in principle, but the formal decision is still
outstanding. The fi nal decision is to be made by MNES (Ministry of
Non-conventional Energy Sources). Offi cials from the MNES have
personally visited the Mathania site and approved the project in
principle. The chief minister of Rajasthan wrote to the prime minister
(around February 2005) to speed up the process, but no reply
has been received as yet. RREC believe formal approval could
be gained any day.
Offi cials from the Rajstahan Vidyut Vitran Nigam stated that they
fully support the project and will purchase electricity subject to the
Rajasthan Regulatory Commission setting the price.
4.2.4 World Bank/GEF project in Morocco
(Ain Beni Mathar)
Project history
The chronology of the Morocco/Ain Beni Mathar project is as
follows:
1999
Idea for the Moroccan project started in 1999.
The Morocco project entered the GEF work
program in May 1999.
2000
Assistance by Fichtner Solar for the design of
bidding documents under an IPP scheme.
Feasibility study report (while IPP scheme in-
tended).
2002
The Moroccan electricity sector started to open
to competition in a limited way (smaller con-
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
40
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
sumers remain captive). Process still ongoing in
2005.
2003
Publication of the IPP call in 2003; organization
of a workshop with interested companies. But
not enough consortia interested in the bid (pos-
sible reasons: technology uncertainties, market
uncertainties, lack of long-term PPA).
2003
Change to public fi nancing as public EPC with
O&M the same year.
Revised feasibility study report according the
public EPC scheme.
2004
Prequalifi cation procedure in 2004, bidding
and evaluation in 2005.
2005
Fichtner Solar redrafts RfP ready for release mid-
2005.
May 2006
Two out of four pre-qualifi ed bidders submitted
a technical and a commercial proposal and
the bids were open on May 10, 2006. Faced
by a shortage of capacity, ONE is considering
asking the bidders for an increase in the size of
the combined cycle power plant. No decision
has been reached yet.
Future development according to current planning:
Dec. 2006
Bidding and evaluation of the bids.
Jan. 2007
Contract signature.
Feb. 2007
Construction is to begin
Dec. 2008–
Plant starts operation.
Jan. 2009
41
T
he original interest of the World Bank and the Global
Environment Facility in CSP technology was due to the
signifi cant contribution that CSP could potentially make
toward meeting the rapidly increasing energy demands of
the developing world. It is evident that the WB/GEF portfolio in
itself—with at best around 120 MW solar thermal power capac-
ity at the end—is not able to signifi cantly reduce the costs of CSP
technology, and was never intended to do so, although this issue
is mentioned as an aim for the WB/GEF portfolio. The institutional
learning aspects, which cannot be so easily measured quantitatively
as levelized electricity costs (LEC), have by far been more important
than the possible cost reduction. It is also important to underline that
the commitment of the GEF on the CSP technology was important
in fi nancial terms given that the GEF funds for the project portfolio
represent roughly one-third of its annual budget for climate change
issues in recent years.
Given this important engagement and the stated objectives of the
WB/GEF portfolio, it is legitimate to consider the long-term con-
tribution of the CSP portfolio and possible evolution of a long-term
strategy by the WB/GEF, independent of any shorter-term focus
of large organizations. Short-term focus may yield premature re-
sponses, driven by failures, pressure from alternative development
routes, or up-coming issues “à la mode.” Nevertheless, it is clear
also that a complex issue
11
such as the introduction of CSP tech-
nology in developing countries needs more time than just the time
of the realization of a portfolio of four projects. It is therefore not
surprising that the portfolio encountered the diffi culties and delays
that have been observed so far.
The main question for the WB/GEF today is whether the effort
necessary to continue the support for the joint development of technol-
ogy and structures is worthwhile, or whether the exceedingly slow
progress of the portfolio thus far makes it diffi cult for the WB/GEF to
further pursue CSP technology, quite apart from the short-term aspect
of bringing the currently existing portfolio to a successful end.
With such heterogeneous interests, it is valuable to consider the
implications of different scenarios, both in the short and the long
term, before providing recommendations on a market strategy within
and beyond the currently existing portfolio in Chapter 6.
5.1 “S
CENARIO
”
DISCUSSION
OF
STRATEGIC
ASPECTS
FOR
WB/GEF
IN
THE
DEVELOPMENT
OF
CSP
This section explores, in the form of different scenarios, the possible
consequences and impacts of decisions made at the WB/GEF for
CSP technology. It is not the intention to provide a judgment on one
or the other option, but to simply depart from the present situation
and explore the likely impact of other choices.
5
L
O N G
-
T E R M
CSP
D E V E L O P M E N T
S C E N A R I O S
F O R
T H E
W
O R L D
B
A N K
/GEF
11
Not so much complex from the technological side, given the fact that
the components for CSP technology are already well-proven, including in
large projects, but from the fact that one combines the development of a
new technology of a certain scale with the inadequacy of existing structures
in the developing world to try to bring the technology to a more mature
stage. The scale of the CSP technology is an important aspect in this, and
proper to CSP, as is the aspect that CSP development in industrialized
countries has so far not contributed to introduce suffi cient amounts of power
capacity to reduce costs and to establish an industry. With smaller scale
technologies such as PV or wind, similar problems exist for the combined
development of technology and structures in the developing world, but the
two aspects previously mentioned have greatly reduced the importance
of these technologies.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
42
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
For the purpose of representing short- and long-term aspects, the
scenarios are divided into two groups:
The “First Round.” This group of scenarios treats short-term aspects
and in particular the current WB/GEF portfolio and the impact
of decisions on the portfolio on the ongoing CSP developments
around the world. Within the fi rst round, the following two
scenarios are considered:
“Falling Dominos.”
This scenario assumes that the WB/GEF
portfolio would be canceled as a whole due to the delays
accumulated so far, as well as the recognition that WB/GEF
might have underestimated the time it takes to get the technol-
ogy to the market in the developing world with inadequate
structures to promote renewables and without parallel efforts
in industrialized countries.
“Getting to the harbor.”
This scenario assumes that the
WB/GEF portfolio would be partially or totally realized
during the next two years.
The “Second Round” assumes a (more or less) successful termi-
nation of the fi rst round and considers options for WB/GEF for
further activities. This is inscribed in a longer term vision of CSP
development, including both the development of the technology
and of suitable structures.
“Wait and See.”
This scenario is based on the recognition
by WB/GEF that as long as the costs for CSP have not
come down to levels close to being competitive with fossil
power generation, and as long as the political frame for re-
newables and CSP in developing countries is not advanced
enough, further support to CSP is not likely to have much
impact.
“2-Track approach” (CSP in industrialized + developing
countries).
This scenario is based on the recognition by
WB/GEF that CSP will not develop simply in regions other
than industrialized Southern countries, at least not on the
short term, but requires further support and development at
the international level in order to open up rapidly the second
track.
“Specialising.”
This scenario is based fi rst on the recognition
by WB/GEF that the large scale promotion of CSP might
exceed its fi nancial and institutional capacities, and second
on the recognition of the fact that CSP is to play an important
role in the power mix of developing countries. This requires
specialization of the WB/GEF support on particularly
sensitive issues for the future development of CSP in those
countries.
It is also suitable for such scenario development to classify the
countries according to their possible interests in CSP technology
into three groups:
12
Group 1 countries.
Industrialized countries with suitable climatic
resources for CSP technology and highly developed economies
that have already set up a comprehensive framework to promote
renewables or that could potentially do so (southern Europe,
southwestern United States, Israel)
Group 2 countries.
Countries that are or will sooner or later be
connected to Group 1 countries, and among themselves, for
power exchange (Northern Africa and Mexico
13
). Figure 17
clearly illustrates the importance of this issue with the example
of the Mediterranean rim. There are a variety of developments
going on that make this „ring“ more likely to happen in the
future than in previous times. Such aspects concern the open-
ing of electricity markets, although to various degrees in North
African countries, the establishment of physical links for power
exchange among North African countries themselves as well
as toward Spain and Italy. CSP can potentially play an im-
portant role in this power exchange. However, the implication
12
This grouping is derived from a similar classifi cation proposed in the
Global Market Initiative (GMI). There was an intensive debate at one of
the workshops organized in the course of this project regarding whether the
distinction between Group 2 and Group 3 is not too artifi cial. However,
looking at the map presented on the interlinkage of the Mediterranean
area and its potential large impact, it appears useful to consider these
two groups separately.
13
Mexico is an OECD country, but still has some characteristics of a
developing country caused in part by the large split in wealth within the
population.
43
C
HAPTER
5 – L
O N G
-
T E R M
CSP
D E V E L O P M E N T
S C E N A R I O S
F O R
T H E
W
O R L D
B
A N K
/GEF
of such a power ring goes well beyond the mere importance
of electricity exchange: it contains elements of political
14
and
societal development around a project of common interest, as
well as economic development by setting up local production
structures for important components of technologies and prod-
ucts, such as for CSP technologies. Structures of this type exist
with the so-called “maquiladoras,” manufacturing companies
of small to large size along the Mexico-United States border,
cooperating intensively with companies in the United States.
15
Depending on the success or failure of the fi rst round of CSP
development, this group of countries appears as strategic in
the future development of CSP. For the moment, given the
somewhat more hesitant development of CSP in the Southwest
United States as compared to the development in Spain; the
impression that the North African WB/GEF CSP projects
have the highest chance of being realized; and the stage of
the ISCCS project proposed outside the WB/GEF portfolio in
Algeria, as well as the CSP activities in Jordan, Iran, and Israel
suggest that the Mediterranean area is a key region for future
CSP development, given the institutional learning accumulated
so far for CSP in these countries as well as in the international
funding organizations.
Group 3 countries.
These developing countries are not close
to the electricity grids of Group 1 countries. This comprises
important countries like India, China, Brazil, and South Africa,
where the driving force is essentially the tremendous need for
new electricity generation capacity. The motivation to invest
in CSP might be different and focused on the national context
rather than on the interaction with other countries.
5.2 T
HE
F
IRST
R
OUND
: “F
ALLING
D
OMINOS
“
This scenario, dealing with shorter term aspects, assumes that
the WB/GEF portfolio would be canceled as a whole in a short
frame of time due to the delays accumulated so far as well as the
recognition that WB/GEF might have underestimated the time it
takes to get the technology to the market in the developing world
with inadequate structures to promote renewables and without
parallel efforts in industrialized countries. As a consequence,
there could be negative impacts on all three groups of countries,
though with different degrees. In some countries, such as Spain,
which has a solid policy framework for CSP in place, it appears
less likely that there would be an impact of a WB/GEF decision
to phase out the portfolio, although in the longer term (Spain has
a decision point concerning the continuation of its favorable sup-
port frame for CSP once 500 WM are reached), some impact
cannot be excluded.
F
IGURE
17: T
HE
STRATEGIC
POSITION
OF
G
ROUP
2
COUNTRIES
FOR
THE
DEVELOPMENT
OF
CSP
TECHNOLOGY
(
EXAMPLE
OF
THE
M
EDITERRANEAN
AREA
)
14
Political relationships among countries in North Africa, for example
among Morocco and Algeria, continue to be diffi cult for a variety of
historic reasons. However, there are encouraging efforts and symbols to
overcome these divisions. Potentially, in the longer term North Africa can
parallel the European Union.
15
The development of such structures is not without problems for the Group
1 countries, given the high levels of unemployment in some of them and
the pressure from the population to protect national employment; see for
example the recent discussion in Europe after the opening of the EU toward
the Eastern countries and the subsequent transfer of production plants to
these regions and the social consequences in the old EU. On the other
hand, it is unlikely that the development of a North African Union would
not present in some stage of its development such features.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
44
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
5.3 T
HE
F
IRST
R
OUND
: ”G
ETTING
TO
THE
HARBOR
“
This scenario, also dealing with shorter term aspects, assumes that
the WB/GEF portfolio would be partially or totally realized
16
during
the next two years. The timeframe of two years appears reasonable
in order to provide enough time for the projects to progress. It is
diffi cult to conceive that the WB/GEF portfolio should exceed this
time frame up to contract signature given the fact that the catalyser
Comments:
Critical moment in time for CSP: a
variety of projects are in a phase of
consolidation Other projects in a phase
of stabilization.
The WB/GEF portfolio represents a
relatively small installed solar capacity of
around 120 MW; nevertheless important
amount of solar technology, given the
early stage of the industry and the few
plants under construction.
The WB/GEF projects represent with
Algeria, the only ISCCS plants currently
in some advanced stage.
Possible Impacts:
Strong impact on Group 1 countries
partially unlikely: solid policy frame
in Spain; Arizona quite advanced. But
further developments, e.g. in Nevada,
California, Israel slowed down. The
CSP market loses the chance to get a
broader base to be less dependent on
promising but early-stage market devel-
opments in Spain and other countries.
Impact in Group 2 countries (Algeria)
and Group 3 countries larger: “If
even the countries supported by
WB/GEF cannot do it, we can’t do
it either”. CSP technology—being
a very important technology for GHG
reduction in the countries of the world‘s
sunbelts—might not at all or only
after 20 years be applied in de-veloping
countries. ISCCS technology particularly
threatened.
No realization of important learning
effects with the solar suppliers, and
in particular the consortia (compris-
ing solar suppliers and suppliers of
conventional CC technology) that
propose ISCCS technology. This could
have negative consequences for the
future cooperation of such consortia on
plants with larger share of solar thermal
generated electricity.
Credibility/reliability of GEF and World
Bank at stake, at least within the CSP
community.
By 2010 at best 500 MW installed CSP
All WB/GEF CSP
Negative Impacts on all groups of
projects canceled
countries (delay; projects canceled)
16
The expression “has been realized” means in this context that the sig-
nature of the EPC contract with the successfully bidding consortium has
occurred, not the fact that the plants have been built. This takes typically
another 2−3 years.
All 4 WB/GEF CSP passing
in next 2 years
2–3 WB/GEF CSP passing
in next 2 years
Comments:
The frame for CSP technology take-off
is currently the most favorable in years
(development in Spain; international
energy price environment).
“Psychological” impact of 4 or only
2–3 WB/GEF projects realized probably
quite similar on the different groups of
countries. Realizing only one project
out of four would not be suffi cient to
characterize the portfolio as a success;
it would at best be perceived as “saving
face”.
Revision/cancellation of 1–2 projects:
Question of alternatives? Alternative
technology lines to ISCCS concept, see
next page (time delay?) Support to
more motivated countries (preferentially
in Group 2) with good projects and the
willingness to set up suitable support
structures.
Environmental impact (CO
2
) of the
WB/GEF portfolio small (ISCCS plants).
Success aspect more important than
environmental expectations.
Projects passing in Group 1 and
2 countries, and some projects in
Group 3 countries by 2010
Possible Impacts:
In total about 1,000 MWe CSP installed
or in construction by around 2010
(Spain 500 MW, Nevada 50 MW,
California, Israel 100 MW, Algeria 25
MW in ISCC, South-Africa: 100 MW,
Iran, Jordan,…, WB/GEF 120 MW in
ISCC).
Progress on cost curve not yet enough
but noticeable
Successful examples of projects in Group
2 and possibly Group 3 countries.
Different technology lines in the phase
of realization (including the ISCCS
technology line in the WB/GEF portfolio
and in Algeria), opening up options for
future choices.
T
HE
F
IRST
R
OUND
: F
ALLLING
D
OMINOS
T
HE
F
IRST
R
OUND
: G
ETTING
TO
THE
H
ARBOR
45
C
HAPTER
5 – L
O N G
-
T E R M
CSP
D E V E L O P M E N T
S C E N A R I O S
F O R
T H E
W
O R L D
B
A N K
/GEF
function in a now more favorable environment for CSP might have
passed, either due to suffi cient progress in Group 1 or due to a
slowing down of CSP activities worldwide once again. One pos-
sibility to speed up the operations could be a transfer of the CSP
portfolio to the IFC.
It is important to underline that the environment for CSP develop-
ment is currently indeed different from the one a few years ago:
sometimes, while reading statements made a few years ago by
supporters of the CSP technology, some critics of the engagement
on CSP have the impression of “déjà vu,” when it comes to current
statements on development of CSP in industrialized countries as
well as the imminence of the WB/GEF portfolio and other projects
in developing countries being realized.
Although it is clear that even today it is not unlikely that there is
a part of “principle hope” with respect to the speed with which
changes occur, it is undeniable that two important frame elements
for CSP have changed in the last two years: (1) the general en-
ergy price environment is one of strong tensions on prices; and
(2) the development and the policy frame in Spain is a hard fact,
although even for these two elements reverses or delays are not
fully excluded (short-term collapses of energy prices due to reces-
sion in important countries or speculation; delays in the realization
of current projects and the starting of new projects in Spain). As a
consequence there could be positive impacts on all three groups
of countries, with most impact on Group 2 countries. The basic
requirement for the realization of this scenario is that the WB/GEF
promotes very actively at the conclusion of the contracts for the next
months. Otherwise, keeping contract signature within a delay of
two years will not be possible.
In the case of the revision/cancellation of one or two projects,
and the wish of the WB/GEF to support further this important
technology, the following alternative technology lines to the ISCCS
concept might be considered:
Market introduction for industrial process heat applications based
on concentrator solar
Small-scale solar combined heat & power plants (heat for absorp-
tion chillers (e.g. air conditioning), process heat or sea water
desalination (the latter one becoming an increasingly important
in some cases dramatic issue in many countries with good solar
resource).
Feed-water preheating in fossil steam plants: promoting also
other than parabolic trough collector types (e.g. tower, dish,
Fresnel) by a technology-unspecifi c bidding procedure, feed-
water preheating leads to good solar effi ciencies, good ratio
of funding and solar-MWh because of reduced investment.
Existing plant (infrastructure) might be used.
5.4 T
HE
S
ECOND
R
OUND
: ”W
AIT
AND
S
EE
“
This scenario, dealing with longer term aspects, is based on the
recognition by WB/GEF that as long as the costs for CSP have not
come down to levels close to being competitive with fossil power
generation,
17
and as long as the political frame for renewables
No WB/GEF activities in Group 2
or Group 3 countries until costs
for CSP are lowered
Comments:
CSP electricity cost reduction continues
toward break-even with fossil generation
by 2015–20.
Competition from other renewables in
Group 2 and 3 countries (wind, PV,
concentrating PV, geothermal). But CSP
has some advantages: 1) dispatchability
(due to storage and/or hybrid fi ring) 2)
local industry promotion/job creation 3)
sea water desalination.
WB/GEF working on improvement
of the policy frame for CSP in some
countries.
Group 1 countries going ahead;
realization of projects in Group 2
and 3 countries left to the market
and possibly other international
funding organizations
Possible Impacts:
Little impact in Group 1 countries
Delays in the replication of projects in
Group 2 and 3 countries from the fi rst
round.
CSP will loose market shares to other
renewables in Group 2 and 3 countries,
perhaps even to more expensive
renewables such as PV.
ISCCS technology line abandoned
except for Algeria.
By 2015 not more than 2,000 MW
installed.
17
Considering nevertheless that gas prices are on the rise for power
generation even if contracts for gas delivery tend to have very long run-
ning times.
T
HE
S
ECOND
R
OUND
: W
AIT
AND
S
EE
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
46
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
and CSP in developing countries is not advanced enough, further
support to CSP is not likely to have much impact. This means es-
sentially taking a break on the technology for the next fi ve years
and reconsider activities in the light of the development occurred
by then. This attitude raises a variety of questions:
with respect to the long-term requirements as well as the con-
stancy needed from the side of a funding organisation like the
GEF to promote such a large scale technology as CSP in the
developing world;
the relevance of this technology in the future power generation
mix of the developing world in general, and in comparison to
other renewable energy sources in particular
the necessary preparation of the policy frame in developing
countries before such a large-scale technology can be taken
up
WB/GEF supports further
motivated Group 2 and 3
countries
Comments:
Question of the technology choice,
if any choice to be made „...(ISCCS
plants may be excluded because of low
and unexpendable solar shares (<20
percent)”.
More critical on environmental perfor-
mance? (ISCCS technology).
Revision of the bidding procedures
(complexity, liability issues: e.g. what
is an adequate liability for the solar
component in the case of ISCCS technol-
ogy).
Question of the most successful business
model (public EPC versus private IPP
investments).
Type of fi nancing instrument (GEF
grants, soft loans, Clean Development
Mechanism)?
Requests on the policy frame for renew-
ables/CSP of the hosting country?
Requests on the structure of the electric-
ity sector in the hosting country?
Question of the focus on Group 2 coun-
tries given the prominent role of these
countries for CSP at an intermediate
stage of technology take-off.
Linking up with the Global Market Initia-
tive.
Group 1 countries going ahead,
Group 2 and 3 countries taking
up in parallel
Possible Impacts:
Realistically ~4 projects (perhaps ~8
if continued cost reduction from fi rst
round).
Strong CSP development in Group 1
countries as a basic requirement for
the justifi cation of such an important
commitment. Possibly stronger signs
of development from countries such as
Italy, Israel, and the U.S. where devel-
opment is still slower or nonexistent
compared to Spain.
Concentration on Group 2 countries as
a key group at the intermediate stage
of development of the CSP technology
(previously successful WB/GEF group
2 countries and new countries such as
Algeria, Jordan, Iran).
Mitigation of the risk that the few CSP
market nations might fail to successfully
make the CSP market run (see above).
Concentrate on technologies that allow
a fl exible extension of solar capacities
as fi nancial means become available.
ISCCS continues depending on the
interest of the host country, but more
technology options realized in develop-
ing countries.
By 2015, more than 2,000 MW
installed, in case of a very favorable
development up to 5,000 MW.
WB/GEF supports further moti-
vated Group 2 and 3 countries
but only in a specialized way
Comments:
Support technologies particularly
well adapted to some of the Group 3
countries.
Enhancing the application of smaller
scale CSP (dishes?) to alleviate the
problem of the large initial steps to
enter CSP, even if specifi c costs higher.
Small direct impact on the overall
installed MW.
Concentrating on other technology
routes such as a larger market introduc-
tion of CSP technology for small-scale
CHP in industrial and other ap-plications.
Concentrating on countries with
problematic water supply (not all CSP
technologies equally suitable).
Concentrating on regions with weaker
grids.
Activities to improve the frame for CSP
(non-technical) and to reduce liability
problems in particular cases by suitable
guarantees.
Linking CDM activities and CSP support
(carbon pricing alone cannot bring suf-
fi cient support unless costs of CSP have
fallen further).
Group 1 countries going ahead,
Group 2 and 3 countries taking
up in parallel
Possible Impacts:
Longer-term “preparation of grounds”
for the faster take-off of the CSP
technology thereafter.
No large-scale CSP projects with
WB/GEF involvement. Projects in Group
2 and Group 3 countries mainly market
driven or driven from the national level
/ other in-ternational fi nancing sources.
ISCCS technology line abandoned ex-
cept for countries with specifi c interests
such as Algeria.
Impact on installed MW com-paratively
small.
By 2015, not more than 2,000 MW
installed.
T
HE
S
ECOND
R
OUND
: 2-T
RACK
A
PPROACH
T
HE
S
ECOND
R
OUND
: S
PECIALIZING
47
C
HAPTER
5 – L
O N G
-
T E R M
CSP
D E V E L O P M E N T
S C E N A R I O S
F O R
T H E
W
O R L D
B
A N K
/GEF
5.5 T
HE
S
ECOND
R
OUND
: ”2-T
RACK
A
PPROACH
“
This scenario, also dealing with longer term aspects, is based on
the recognition by WB/GEF that CSP will not develop simply in
regions other than industrialized Southern countries, at least not on
the short term, but requires further support and development at the
international level in order to open up rapidly “the second track.”
Such a second track raises inevitably the question whether the GEF
can raise again a substantial fraction of its climate change budget
and justify this internally as well as to the GEF donors. In turn, this
question can only be answered once the GEF has refl ected on the
importance of the development of CSP for the power supply of
developing countries. It also raises the question of lessons learned
from the fi rst round with respect to the institutional settings and the
long-term interest in the countries taking up the technology, questions
of technology choices, etc.
5.6 T
HE
S
ECOND
R
OUND
: ”S
PECIALIZING
”
This scenario, dealing with longer term aspects, is based on one
hand on the same assumptions as the “wait-and-see” scenario
described previously (that is, the recognition by WB/GEF that
the large-scale promotion of CSP might exceed its fi nancial and
institutional capacities), and on the other hand on the recogni-
tion of the facts described in the “2-Track Scenario;” that is, the
important role that CSP is to play in the power mix of developing
countries. This requires specialization of the WB/GEF support on
particularly sensitive issues for the future development of CSP in
developing countries.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
48
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
49
T
his chapter tries to narrow the different scenarios considered
in the previous chapter. It starts with the statement of the cen-
tral objective of a long-term vision for solar thermal power
and develops a set of success criteria for the establishment
of such a long-term vision. This vision does not imply a unique
strategy and a unique actor to realize it, but (possibly harmonized)
efforts from different actors, including WB/GEF, in both developed
and developing countries. The chapter then provides answers for a
variety of questions aiming et the role and consistency of WB/GEF
actions on CSP departing from the present portfolio up to long-term
aspects of WB/GEF involvement in CSP.
6.1 L
ONG
-
TERM
VISION
FOR
CSP
Proposed long-term vision for solar thermal power in developing
countries:
CSP should be supported to encourage a rapid growth phase to
the point that it plays a key role in the electricity supply mix of
developing countries where there is a good solar resource.
This vision is based on the following observations. A more detailed
rationale for these reasons is provided below in the form of hypoth-
eses. The corresponding hypotheses are mentioned in brackets.
1. In order to maintain climate change within acceptable limits, CSP
power plants must, in combination with other renewable power
options, increasingly replace fossil infrastructure in developing
countries that would build up in those countries and create a
lock-in for at least three decades (
Hypothesis 1
). Promoting CSP
fi rst through small-scale applications in order to lower cost and
then return to the bulk power market with a more competitive
CSP technology cannot fulfi l this target given the time frame
involved (
Hypothesis 2).
2. Due to promising cost-reduction prospects (Hypothesis 3
), dis-
patchability and local industry benefi ts, CSP is considered one of
the most promising technologies for deep cuts in GHG emissions
in countries of the world’s sunbelt. Other renewables except geo-
thermal, which appears complementary to CSP, and potentially
wind energy, cannot fi ll in the gap rapidly enough (however, wind
suffers from the problem of dispatchability) (
Hypothesis 4).
3. Although today the economic perspective is prevailing in many
developing countries, and although the way will certainly be
long toward general acceptance of the fact that, despite the
historic emissions of the developed world, a large contribution
to the GHG problem will growingly come from the developing
world, developing countries start to realize that climate change
will threaten their development before they can reach the level
of the developed world. Correspondingly, many of them take
fi rst steps toward renewable targets and frameworks, which will
help to promote CSP in suitable countries and in a suitable mix
with other renewables (Hypothesis 5).
4. Exporting electricity from renewables from the sunbelt may con-
stitute an important incentive for some developing countries to
introduce CSP plants. This is, however, not to be promoted without
precaution: Given the strong growth in electricity demand in devel-
oping countries mentioned under (1), renewable power must fi rst
be directed toward reducing GHG emissions from power genera-
tion in their own country. Two regions, the Mediterranean/Near
East area and Mexico have—in the longer term—the potential
to export additional solar electricity to the Northern industrialized
countries (United States and Europe) in order to replace fossil
6
S
H O R T
-
A N D
L O N G
-
T E R M
R E C O M M E N D A T I O N S
F O R
T H E
WB/GEF
S T R A T E G Y
F O R
CSP
I N
T H E
C O N T E X T
O F
A
L O N G
-
T E R M
V I S I O N
F O R
CSP
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
50
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
fuel generated electricity there, to lower GHG emissions, and
to develop a common project narrowing the development gap
between both the participating parties (Hypothesis 6).
The central objective is underpinned by the following accompany-
ing hypotheses:
Hypothesis 1: Now is the right time for CSP to increasingly replace
new installations of large centralized fossil power stations
Electricity demand is currently growing in many countries of
the sunbelt at a rate of 6 to 7 percent annually, especially in
developing countries. Even considering the strong necessity for
electricity saving measures in these countries, which are often
not considered, large new electric capacities are required
(IEA, 2003 and 2004). These capacities will be built in the
next 20 years and will remain for at least 30 years—until the
middle of this century—which will create a technology lock-in
in the developing world. What is problematic about such a
technology lock-in? According to current science, it is important
to stabilize GHG concentrations in the atmosphere at levels
of 550 parts per million by volume (ppmv) in order to not ex-
ceed a 2° C global temperature increase. This level requires
a peaking of world GHG emissions in the middle of the next
decade (Figure 18). Other emission paths allow an increase
of concentration levels to 650 ppmv. Even if there are doubts
whether this concentration level is not already far too high, this
is still a considerable distance from the baseline development
with levels close to 1,000 ppmv, increasing well into the next
century. Also in the 650 ppmv scenario world emissions need
to peak in 2030, requiring considerable efforts up to then. It
follows from this reasoning that if the occasion is not used to
replace at least part of the fossil power plants to be built in the
next 25 years with CSP power, they will still be an important
source of greenhouse gases up to the middle of this century.
18
2000
2020
2040
2060
2100
2080
0
100
200
300
400
500
600
700
800
900
1,000
ppmv
year
S650e
baseline
S550e
GHG Emissions (GtCo2-eq)
1970
1990
2010
2030
2050
2070
2090
0
10
20
30
40
50
60
70
80
S550e
S650e
Baseline
F
IGURE
18: G
LOBAL
GHG
CONCENTRATION
STABILIZATION
PROFILES
(
LEFT
)
AND
EMISSION
PROFILES
FOR
STABILIZING
GREENHOUSE
GAS
CONCENTRATIONS
AT
550
PPMV
AND
650
PPMV
VERSUS
BASELINE
EMISSIONS
(
CURVES
LABELLED
S550
E
AND
S650
E
IN
THE
GRAPH
)
Source:
Criqui
et al.
, 2003.
18
See the Policy Recommendations for Renewable Energies of the Bonn Inter-
national Conference for Renewables (2004): “As developing countries work
to expand and modernize their energy systems, and industrialized countries
work to replace their ageing systems and meet rising demand, societies face
a unique opportunity over the next few decades to increase investments in
renewable energies. Over the next 30 years, global investments in energy-
supply infrastructure are projected to be $16 trillion. The opportunity is to
orient a large and increasing share of these investments toward renewable
energy, in order to advance the transition to a global energy system for
sustainable development. On the other hand, if these investments continue
as business as usual, mostly in conventional energy, societies will be further
locked into an energy system that is incompatible with sustainable develop-
ment and that further increases the risks of climate change.”
51
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
In this case, even the 650 ppmv level is very unlikely to be
reached. The importance of developing countries in climate
change stems from the fact that their share in energy-related
carbon dioxide emissions will increase from 37 percent in 1995
to 45 percent in 2025 and 66 percent in 2050 (Criqui
et al.
,
2003). In addition, a delay of institutional and technology learn-
ing for the implementation of solar thermal power plants in the
coming years in developing countries could hamper a stronger
growth of solar capacities even in the second generation of
power plants beyond 2030.
Hypothesis 2: Small-scale CSP applications do not correspond
to strongly growing electricity needs in developing countries
Niche or small-scale applications for solar thermal power will
certainly contribute to develop the market in the longer term and
are also necessary to contribute to the diversifi cation of technolo-
gies (e.g. development of solar dishes or Fresnel collectors), but
would not develop fast enough to introduce solar thermal power
on the market in a time when the electricity infrastructures in the
developing countries are essentially built up. In addition, they
would rather satisfy different target groups as compared to the
bulk power generators, in particular industrial CHP applications
or solar thermal applications in remote areas.
Hypothesis 3: After many years of technology improvement
through R&D, now CSP markets are needed
Electricity generation costs from CSP have been at a level compa-
rable to wind energy in the late 1980s. This is one of the reasons
why the technology was considered interesting for developing
countries, as it was expected that costs could be brought down
quite soon to competitive levels. The costs of CSP have poten-
tially been brought down in the last decade since the fi rst plants
in California by further R&D, but now steady and sustainable
implementation is needed to establish optimized fabrication
infrastructure as well as institutional and business procedures.
Hypothesis 4: CSP is the most promising renewable energy
source for developing countries in the world’s sunbelt
There are no serious renewables alternatives to solar thermal
power in the developing countries in the sunbelt. Wind energy
is in principle a competitor for solar thermal power, due to
its advanced maturity among the renewable energy sources
together with hydropower, but needs a “stabilizing partner” in
the power mix in particular as long as countries are not well
interconnected. Technical progress,
19
power network intercon-
nection on a larger scale, improved information/communication
technologies for distributed power generation, improved weather
forecasts and a well-balanced power mix with renewables
that compensate each other’s weaknesses in a given country
constitute important strategies to reduce the non-dispatchability
of wind, but will need considerable time to be implemented. In
addition, hot summers with extended dry periods impact strongly
on the power generation from wind converters, as experienced
for example in Spain in the dry summer months of 2003.
Hydropower often has a similar trend to fail in hot summers,
similar to wind. Increasing temperatures due to the greenhouse
effect will further aggravate this problem. In principle, biomass
generated electricity as well as PV (including hydrogen gener-
ated from PV at the longer term) could be such a partner for
wind. However, in the sunbelt, biomass is not abundant and PV
is, in the short run, still too expensive and mainly an option for
rural electrifi cation, hence a complement to bulk generation of
solar thermal electricity. Like wind energy, PV also suffers from
a lack of dispatchability. This might be strongly reduced in the
combination of both technologies, but PV still has a way down
the cost curve before it can fulfi l the role of complementing wind
in the power mix. Geothermal energy is an already well-proven
technology with comparatively low electricity generation costs.
Geothermal energy is mainly available at economic levels in the
“ring of fi re,” which includes most countries of the Pacifi c Rim
(Figure 19). Given this occurrence, geothermal energy is in many
19
This statement should not shadow the tremendous progress going on in
the dispatchability of wind. Wind energy has made considerable progress
with respect to availability in the past ten years: even in sites with wind
speeds of 22 km/h, the charge factor (number of full operation hours per
year) has passed from 1,600 (18 percent) to 2,400 hours (27 percent)
per year. On average, in the European Union, the wind converters produce
during 3,000 h/year (34 percent) as compared to 20 percent in 1995,
and the newest 5 MW machines approach 40 percent. Wind speeds to
be used extend now from 9 to 100–120 km/h as compared to 14-–79
km/h a decade ago (Science and Vie, 2005).
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
52
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
respects, on a worldwide level, complementary to CSP, although
in some countries the technologies could be in competition (in
particular for example in Mexico, which has already installed
several geothermal power plants). Tidal and wave energy is in
a more early stage of development as compared to CSP.
Hypothesis 5: Developing countries are increasingly favoring
RES due to increasing fossil fuel prices and climate change
Power plants that are built in the coming years and decades
will face a changing environment as compared to the last 20
years, such as growing fossil fuel prices in particular for natural
gas. Partly this will be compensated for by increased exploration
efforts for fossil fuels and better exploitation of existing resources,
but access to cheap gas will be a central element of competition
among all countries. There will also be an increasing attitude
of developing countries to consider climate change seriously
because it constitutes a threat to their existence, at least their
development, and in particular for regions in the sunbelt that are
close to desert areas with a tendency to expand due to climate
change (see the declarations of a variety of developing countries
at the Bonn International Conference for Renewables, 2004).
Hypothesis 6: CSP electricity export represents an important
long-term option for some developing countries
Industrialized countries have also important resources for solar
thermal power, however, less than the developing countries in the
solar belt. This varies between the countries. While the United
States and Australia have in principle enough of their own solar
thermal resources to cover larger needs for electricity in their
own country (see for example Price, 2005), Europe might only
cover a few percentage points of its own electricity needs with
solar thermal power. Japan has even more limited domestic solar
thermal power potential. In such cases, importing clean electricity
from the sunbelt region can be an important reduction option for
industrialized countries. Hence the need to develop electricity
exchange based on CSP. However, this should not occur at the
expense of covering a country’s own needs and/or should con-
tribute to regional development and cooperation. As long as a
country’s own needs are not covered by clean electricity, tradable
solutions
20
could constitute a suitable approach also. This sup-
poses, however, the installation of an international trading system,
which currently is only the case with CDM. Physical exchange of
electricity between adjacent developed and developing regions
can also generate additional benefi ts as compared to tradable
F
IGURE
19: I
MPLEMENTATION
OF
GEOTHERMAL
POWER
PLANTS
WORLDWIDE
Source:
World Bank (http://www.worldbank.org/html/fpd/energy/geothermal/markets.htm)
20
Tradable solutions constitute an alternative to physical export of green
electricity by unbundling the environmental attributes of a unit of renewable
energy from the underlying electricity. Possible trading solutions are in par-
ticular renewable energy certifi cates (RECs) and certifi ed emission reductions
(CERs) (under the CDM). The development of tradable certifi cate programs
is driven by the implementation of legislation known as renewable portfolio
standards (RPS). RPS typically mandate that each retail power supplier obtain
a certain percentage of its total annual energy sales from renewable sources.
An important issue in developing a robust international market for renewable
certifi cates is the ability to track both the certifi cates and greenhouse gas
emission reduction credits. For RECs, electronic issuing and tracking systems
have been developed in parts of North America, the European Union, and
Australia to support the development of RECs as a compliance and market
tool. A pilot project has also been carried out to develop RECs to fi nance
renewable energy projects in Brazil, China, and South Africa (http://www.
reeep.org/groups/TRECS). In the European Union, there is currently a dis-
cussion to link Mediterranean countries to the EU Renewables Directive from
2001 which could imply a trading solution but also a feed-in tariff for those
countries. RPS have so far shown much less impact on the development of
renewables as they make investments in renewable electricity plants more
risky. Therefore, the emergence of additional investments in the renewable
market may take more time with this system than with other systems that
guarantee a fi xed premium price for the renewable electricity.
53
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
solutions, such as increased network stability (allowing larger
amounts of renewable electricity in the respective countries) or the
contribution to interregional stability, which can be an important
element in the Mediterranean/Near East area.
Several global visions for CSP have been formulated quantitatively
in recent years, in particular (see also the discussion in Chapter
2, section 2.1):
The Global Market Initiative, with the objective “to facilitate and
expedite the building of 5,000 MWe of CSP worldwide over
the next ten years” (GMI, 2003).
The Greenpeace/ESTIA study (2003) that projects “that by
2040 the proportion of global electricity demand which could
be satisfi ed by solar thermal power will have reached a share
of 5 percent. This is on the assumption that global electricity
demand doubles by that time, as projected by the Interna-
tional Energy Agency.” For 2015 the study projects around
6,000 MW (of which 25 percent in developing countries), for
2020 around 21,500 MW (of which 30 percent in developing
countries).
The ATHENE scenarios in the SOKRATES project (DLR, 2004),
which envisage the installation of around 5,000 MW by 2015,
15,000 MW by 2020, and 42,000 MW by 2025. The
share of developing countries is higher in this study (at around
50 percent already in 2025) due to a lower installed capacity
in the United States as compared to Greenpeace/ESTIA.
6.2 C
RITERIA
DESCRIBING
THE
SUCCESS
OF
A
LONG
-
TERM
CSP
STRATEGY
Any successful strategy aimed at the realization of the above-de-
scribed vision should accompany the various stages of the develop-
ment of CSP along the cost reduction curve (see Figure 20) with
different elements of support adapted to the advancement of the
market for the technology.
The four parts in the cost reduction curve are briefl y described as
follows. The curve assumes cost competitiveness around 20 years
from now in 2025, which appears a realistic target.
Part 1 of the cost reduction curve
: Creation of technical and
institutional experience. Small number of new units (in addition
to the Californian SEGS plants), a few hundred MW. Creation
of confi dence, lowering of risk factors applied to fi rst plants, fi rst
“pilots” in developing countries. Corresponds to the realization of
a few plants in Spain, the United States, and some of the WB/
GEF projects as well as of the fi rst Algerian plant by 2010.
Part 2 of the cost reduction curve
: Generation of a market
(total installations of 500–2,000 MW). Diversifi cation in tech-
nologies, certain degree of cost reduction, but still far away
from economic margins. Target of perhaps 15–20 percent of
capacities installed in developing countries. Financing driven in
industrialized countries by feed-in tariffs and renewable portfo-
lios, in developing countries by a mixture of grants, preferential
loans and national fi nancing as well as a dedicated CSP fund
(see below).
Part 3 of the cost reduction curve
: Early phase of a growing
mass market (total installations of 2,000−7,000 MW). Sub-
stantial decrease in costs due to scale and volume effects, costs
approaching competitive ranges but not yet generally cost-effec-
tive. Target of perhaps 20 to 25 percent of capacity installed
F
IGURE
20: F
OUR
STAGES
IN
THE
DEVELOPMENT
OF
CSP
Source: Authors.
CSP
Fossil alternatives
LEC (cUS/kWh)
2005 2007 2009 2011 2013 2015 2017 2019 2021 2023 2025
0
6
8
10
12
14
16
18
20
4
2
Generation of
a CSP market
Early CSP
mass market
Near competitive and
competitive market
1
2
3
4
Creation of techinical
and institutional
experience
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
54
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
in developing countries. In some applications, however, even
without subsidies, fi nancing in developing countries through
carbon pricing and (premiums from exports), national fi nancing,
private investors.
Part 4 of the cost reduction curve
: Development of a mass
market (near competitive and competitive market). Installed
capacities: 7,000–25,000 MW. Further decrease in costs
due to volume effects and R&D. Target of 30 to 40 percent of
capacity installed in developing countries. This is a stage that
is currently reached by wind, but with a still comparatively low
share of the developing world (by the end of 2004 around
47 GW of wind were installed worldwide, of which around
8.5 percent in the developing world).
A successful strategy must further take into account that the main
purpose is not to realize individual projects but to secure the
development of a market. For this, the strategy must integrate the
expectations of important market players that constitute the market
environment for the CSP technology (Figure 21).
The third major issue is that a market introduction strategy must
cope with the main barriers to the technology. For CSP, barriers in
the developing countries are relevant, such as:
Lacking fi nancial means to support more expensive renewables
in an early phase in order to cover the rapidly growing electricity
demand;
Lacking institutional frames for renewable energy sources and
lacking competition on electricity markets;
Suspicion toward a technology “that is even not used in the
developed world.”
Table 7 translates these general requirements in a list of success
criteria for a suitable CSP strategy that may realize the vision de-
scribed in section 6.1. The criteria are further described according
to the phase of the cost reduction curve where they mainly act,
possible OP 7 objective to which they are linked (see the following
box), the scenarios of the second round described in Chapter 3 to
which they are relevant, as well as the importance of the criteria
in an early stage of market development.
Table 8 describes the different roles that CSP could take in the
power system of the different countries/regions (where solar ther-
mal energy is most promising) according to criteria 3 described
above. This role is important for the economics of CSP in the shorter
term and for the acceptance of the whole technology line in the
longer term. It also might determine the choice of the technology.
Solar-only technologies might be preferred in principle, but there
are various functions that might favour ISCCS as the preferred
technology in a country.
6.3 N
EW
MARKET
INITIATIVES
AND
THEIR
RELEVANCE
IN
A
LONG
-
TERM
STRATEGY
FOR
CSP
The following briefl y describes two important new market initia-
tives, which have in common that they try to integrate the different
stakeholders relevant for the development of a technology and take
into account the regulatory/institutional framework, thus meeting
F
IGURE
21: M
ARKET
ENVIRONMENT
FOR
THE
INTRODUCTION
OF
CSP
TECHNOLOGY
Source:
Haeussermann (2005).
Big projects
need big money
It is about markets, not
projects
Markets need
perspectives and fantasy
for the future
Smaller solar-only plant
designs could attract
more players
Regulatory
Authority
Equity
Investors
Lead Investor
Utility
Technology &
Knowhow
Gas
Supply
Construction
Oversight
Loans from
Financing Bank
PPA / Secured
Feed-in
O&M
Power
Plant
Market Environment
55
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
B
OX
2: OP 7
OBJECTIVES
The main OP 7 objective is “to reduce greenhouse gas emissions from anthropogenic sources by increasing the market share of low
greenhouse gas emitting technologies that have not yet become widespread least-cost alternatives in recipient countries for specifi ed
applications.” Underlying this objective is the basic aim of the GEF, which is to promote technologies directed to non-Annex I countries.
The GEF document describing OP 7 objectives assumes that “the objective will be achieved by GEF’s promotion of such technologies so
that, through learning and economies of scale, the levelized energy costs will decline to commercially competitive levels.” However, it
also admits that “programmatic benefi ts also can result from structured learning from projects implemented.” This major objective is ac-
companied by a variety of other requirements laid on the GEF by the Conference of the Parties of the UNFCCC. For example, projects:
a) are country driven and in conformity with, and supportive of, national development priori ties;
b) are consistent with and supportive of internationally agreed programs of action for sustainable development;
c) transfer technology that is environmentally sound and adapted to suit local conditions;
d) are sustainable and lead to wider application;
e) are cost-effective (not relevant for OP 7 technologies at the beginning);
f) strive to leverage other funds; and
g) mitigate climate change.
With respect to CSP, OP 7 emphasizes “the proven parabolic trough variant for electric power generation” but leaves open the choice
of other technologies for support in the future.
With respect to resources, the GEF concludes that “given the long lead times for the development and deployment of highly capital in-
tensive backstop technologies, as well as the time required to move down learning curves, time horizons for the achievement of program
objectives will typically be on the order of decades. The technologies identifi ed under this program will require the security of funding
and long-term commitment of GEF support. Analysis of indicative project pipelines and estimates of minimum “critical mass” of support
for the various technologies under this program suggest an initial requirement of $100 million per year in GEF grant resources, gradually
rising to $200 million per year over fi ve to ten years as investment demand and absorptive capacity grow. One analysis of the median
amount of resources required to induce cost reductions in just one of the technology applications listed in the operational program (for
large-scale electricity production using PV cells) is around $3.3 billion,
21
about half of which would be for applications in developing
countries. It is therefore clear that the GEF should choose technologies for this operational program where it can leverage resources of
other players as well.
21
This is in good compliance with the Athene cost reduction forecast (see
chapter 2.3.2): 2.5 million
€
(under the assumptions of an internal project
revenue rate of 8 percent and CO
2
-trading)
22
Section based on “ The Concentrating Solar Power Global Market
Initiative”
some of the most important criteria for successful market creation
mentioned previously. The fi rst, the Global Market Initiative (GMI)
is specifi cally directed toward CSP; the second, EM Power, ad-
dresses renewable electricity (RE) more broadly.
6.3.1 Global Market Initiative (GMI)
22
The goal of this coordinated action, called the CSP Global Mar-
ket Initiative (GMI), is to facilitate and expedite the building of
5,000 MWe of CSP power worldwide over the next ten years
up to 2015. Furthermore, the GMI claims that by then full com-
petitiveness with conventional power generation will be reached.
For this purpose, a visible, reliable, and growing market for solar
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
56
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
T
ABLE
7:
M
AIN
SUCCESS
CRITERIA
FOR
CSP
STRATEGY
Criteria
most
important for
Ranking of
position
1–4
4
OP 7 objective
Criteria relevant
criteria from an
in cost
linked to
for Chapter 5
early market
Main success criteria for CSP strategy
reduction curve
criteria
scenario
perspective
1
Ensure increasing participation of developing countries in CSP development
1-3
Main objective
“Two-Tracks”
very important
2
Spur CSP market deployment in industrialized countries
1,2
“Two-Tracks”
Wait
and
See”
3
Make sense for the country‘s power market (see Table 8)
1,2
a)
“Two-Tracks”
“Wait
and
See”
4
Include successful market creation policy measures
2,3
Main objective
all
5
Serve economic development of countries/region
1-4
a)
all
6
Contribute to building up of local institutional experience
1
Main objective
all
7
Create renewables frame in developing countries
2,3
a)
“Two-Tracks”
8
Mobilize suffi ciently large funds
2
f)
“Two-Tracks”
9
Promote CSP electricity production instead of CSP investments
1-4
a) b) e) f) g)
all
10
Mobilize private investment
2-4
f)
“Two-Tracks”
11
Promote technology diversity
2
-
“Two-Tracks”
12
Enhance previous country experience with CSP
2,3
-
“Two-Tracks”
13
Contribute to building of local manufacturing experience
3,4
c)
all
14
Contribute to the sustainable development of a country/region
1
(note see below)
3,4
c) d)
all
15
Reduce environmental impact
2
2-4
g)
“Two-Tracks”
16
Assure acceptability of technology in regions to which CSP electricity is exported
3,4
d) g)
“Two-Tracks”
17
Promote small- and large-scale applications of the technology
3
3,4
-
“Specializing”
less
important
Notes:
1
including social and economic dimensions in addition to the environmental dimension. Enhance capacity of the country/region to integrate different aspects
2
In developing countries only relevant for phases 2-4 in the cost reduction curve, in industrialized countries also for 1
3
Small-scale development alone is not suffi cient to achieve the goal in a suffi ciently short time to lower costs for CSP. Targeted rather at specifi c applications. Volume is needed.
4
See Figure 20
57
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
thermal power with normal risk levels must be established in order
for project developers and CSP equipment suppliers to make the
needed long-term investments to achieve acceptable investment
costs, and hence competitive rates. The following policy areas will
have the greatest impact on the use of concentrating solar power.
Each country or state participating in the CSP GMI will contribute
with the following policy measures:
Targets
: As the overall goal of the CSP GMI is 5,000 MWe to
reach cost competitiveness by 2015, national and/or regional
targets will be set for CSP capacity. These targets may be a
specifi c number of MW over a certain period of time, or may
be a percentage of CSP within the new capacity to be built over
a certain period of time, as in Renewable Portfolio Standards.
Tariffs
: The level of revenue for CSP projects needs to be
adequate to encourage private sector investment and provide
a stable investment climate. This can be achieved by feed-in
tariffs, production tax credits, or public benefi t charges specifi c
for CSP. These supports will be designed to reduce over time
as the CSP technology becomes competitive in the power
market after 5,000 MWe of CSP has been built by 2015.
Coordination with participating neighboring countries, states,
or regions with preferential tariff schemes will allow CSP-based
electricity imports from high solar radiation areas (and therefore
lower electricity costs). The use of long-term power purchase
agreements or similar long-term contracts with creditworthy off-
takers, or equity ownership by public organizations will build
the confi dence of investors and fi nancial institutions.
Financing
: Cooperating bilateral and/or multilateral fi nan-
cial institutions will ensure that project-related fl exible Kyoto
instruments such as Clean Development Mechanisms and
Joint Implementation Actions become applicable to CSP and
ensure that the mechanisms are bankable. The establishment
of national or regional loan guarantee programs via existing
T
ABLE
8: P
OSSIBLE
ROLE
OF
CSP
IN
DIFFERENT
COUNTRIES
/
REGIONS
WITH
SUITABLE
SOLAR
RESOURCES
Function
Country/Region
Technology selection criteria
Technology implications
Local industry promotion
Spain, Italy, Greece, Egypt
Share of local manufacturing
CSP in general, espe-cially Fresnel collectors
(foundations, steel, glass industry)
because of high local value creation (due to
larger share of simple collector components)
Environmental protection
Spain, Italy, U.S.
Environmental impact
Solar only or SEGS
Noon peaker
Israel, Egypt, Jordan
Local daily power load characteristics
Solar only or SEGS
Evening peaker
North Africa, South Africa
Local daily power load characteristics
Storage technology or ISCC
Summer noon peaker
Spain, U.S.
Local yearly power load characteristics;
Solar-only options (including storage)
power mix (wind; hydro)
or SEGS
Diversifi cation of power mix
Morocco, China, Mexico
Fit to power generation mix
Solar only or SEGS; ISCCS technology
(if own gas resources or large amount of
MW
needed)
Fuel Saver
Mexico (to prolong national gas resources
Combination with natural gas or coal
Feed-water preheating but also ISCC
or to reduce ineffi cient coal use),
South
Africa
Exporter of Gas/Green Electricity
Algeria, Iran
Combination with natural gas
ISCCS technology
Remote Power Producer
Remote regions with larger electricity
Quality of energy service
Small-scale CSP
demand that cannot be satisfi ed by PV
Transmission Stabilizer
Crete
Quality of energy service
Storage technology
Source:
Geyer (2005); authors’ own additions.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
58
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
windows at multilateral banks, national lending programs,
and global environmental programs (such as GEF, UNEP, and
UNDP) will further reduce the inherent risk of introducing new
technology for private sector banking institutions. Investment tax
credits, which stimulated the fi rst 354 MWe of CSP plants in
the United States, should be maintained, and production tax
credits similar to those that have stimulated the growth of wind
power in the United States should be made available to CSP
plants. Cost-shared development of transmission lines between
regions with excellent solar resources and urban load centers,
even across borders of participating countries and regions,
will optimize the development and exploitation of all regional
resources.
Regulation: Limitations on CSP plant capacity or operating strat-
egies that make the technology introduction more costly need
to be avoided. Legal restrictions and barriers to allow more
cost-effective connections of CSP plants to the electric grid at
the end user (customer), distribution, and/or transmission points
shall be identifi ed and eliminated.
6.3.2 EM Power: A new approach to OP 7?
23
An initiative is under development, involving UNEP and KfW, that
could be a new model for support to near-commercial energy
technologies. The proposal is technology neutral, and looks at how
markets function. It started with PV-hydro applications, and now also
includes distributed PV and CSP. The aim is to facilitate collabora-
tive market development and transformation on a regional level. It
is a partnership project that will explore market aggregation tools
and identify investment opportunities. The idea is to work with the
industry and OECD countries and try to bring partners together,
and build regional capacity (in fi nancing, contracting etc.). GEF
could facilitate market aggregation for a specifi c RE (renewable
electricity) or technology application. The problem, though, is not
being able to spend money in developed countries and to get the
motivation of OECD countries. Information is being collected on
market aggregation tools, such as forward procurement and dual
betting (bundling of fi nancing for RE and conventional, which lowers
the transaction costs). Firstly, a market has to be created before it
can be aggregated. The proposal is that GEF sponsors a few pilot
medium-sized projects (MSPs), and links them up with investment,
scaling up the effects.
6.4 T
HE
POSSIBLE
ROLE
OF
THE
C
LEAN
D
EVELOPMENT
M
ECHANISM
IN
PROJECT
FINANCING
: H
OW
TO
CROSS
THE
BRIDGE
TOWARD
COMPETITIVENESS
As mentioned in the previous section, the Clean Development
Mechanism can play an important role in the further development
of CSP (although currently there is no easy way to combine GEF
and CDM), in particular once costs have come to a level where
F
IGURE
22: V
ARIOUS
FINANCING
MECHANISMS
TO
CROSS
THE
BRIDGE
TOWARD
COMPETITIVENESS
AND
THE
ROLE
OF
CARBON
FINANCING
IN
SUCH
A
FINANCING
STRATEGY
Source
: Authors.
today
2015/2020
Soft loans?
GEF?
IPP?
CDM (CDM financing could help
to cover some fractions of the over-
costs once those have reached
lower levels)
National financing through
promotion mechanisms
for renewables?
Combination of various
financing sources in a CSP
fund, initially dedicated to a region
GEF Funds. No
cumulation possible
with CDM financing
CDM financing could
help to cover substantial
fractions of the overcosts
once those have reached
lower levels
?
Turnkey
Contract EPC
23
Section based on the Report of the STAP Brainstorming Session on Op-
erational Program 7, Washington, D.C., March 10–11, 2003. Information
from a presentation by Peter Hilliges, GEF Secretariat.
59
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
the additional fi nancing expected from CDM projects could con-
tribute substantial fractions to the project fi nancing. Currently, the
contribution would be typically several million dollars with a need
for additional fi nancing of around $50 million, corresponding to
the amount of the grants in the current GEF portfolio.
6.5 C
ENTRAL
QUESTIONS
FOR
DETERMINING
THE
ROLE
OF
THE
WB/GEF
IN
THE
REALIZATION
OF
THE
CSP
VISION
In view of the vision formulated previously and the criteria describing
a successful strategy for the realization of such a vision, the World
Bank has to answer a variety of questions addressing its implica-
tions for CSP and technology choices at different time horizons.
The long-term questions concern both strategic questions as well
as operational questions.
6.6 A
NSWERS
TO
THE
QUESTIONS
ADDRESSING
THE
SHORT
-
TERM
DEVELOPMENT
OF
THE
WB/GEF CSP
PORTFOLIO
After having reviewed the current WB/GEF portfolio in the frame
of the long-term vision and the corresponding success criteria de-
veloped in Chapter 6 (sections 6.1 and 6.2), the current chapter
provides answers to the questions addressing the short-term develop-
ment of the WB/GEF CSP portfolio raised in section 6.5. A third
T
ABLE
9: E
XAMPLE
OF
CDM
FINANCING
FOR
CSP
Project
Investment: $250
million
Installed capacity:
100 MW solar only power station
Generation
430 GWh electricity/year
CDM component
Baseline:
Coal-fi red power plant (1.1 t CO
2
/MWh)
CER generation
475,000 t CO
2
/year
Additional revenues
$4.7 million/year (over crediting life of 20 years, $10
24
/t CO
2
)
Split up of revenues
Conventional electricity sale 6 cents/kWh
CER sale
Source
: Authors, based on Sutter (2002)
24
The value of $10 used by this author appears as high. Typical CER
prices are on average rather $5 than $10, although it must be empha-
sized that present CDM projects might be the most profi table ones. On the
other hand, there is also scope for system learning, which would mitigate
increasing CER prices.
section then addresses in detail the chances/risks of each of the
four WB/GEF projects to reach realization (question (9)).
6.6.1 The current WB/GEF portfolio in the frame of
the long-term vision
This section investigates the extent to which the current WB/GEF
portfolio is “in line” with the long-term vision and the criteria for a
successful overall long-term strategy developed in sections 6.1 and
6.2, or whether there are individual characteristics of the current
portfolio that contradict the development of a long-term strategy.
For this purpose, the current portfolio is evaluated below against
the list of criteria set up previously.
From the comparison with the list of success criteria it follows
that:
The present portfolio is to a satisfactory degree in line with the
requirements for the further development of a successful promo-
tion strategy for CSP along the cost reduction curve. The strategy
has certainly helped to keep the CSP technology up during the
past years; it has contributed considerable funding to the initial
stage of the cost reduction curve (however, conclusion of this
stage is necessary with at least a partial success of the portfo-
lio), and it has generated considerable institutional learning. As
such, it can be considered a partial success (under condition of
fi nalization).
The weakest point seems to be the fact that currently no incen-
tives are given to actually operate the installed solar fi elds in the
ISCCS plants. In case the solar fi eld causes unexpected trouble
or the O&M costs of the solar fi eld exceed the remuneration from
the solar electricity sales, it seems quite possible that the solar
fi eld will not be operated. Penalties on a kWh
th
-basis for the
solar fi eld might be a possibility to mitigate that weak point.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
60
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
T
ABLE
10: Q
UESTIONS
ADDRESSED
TO
THE
SHORT
-
AND
LONG
-
TERM
CSP
STRATEGY
BY
THE
WB/GEF
Questions addressing the short-term development of the WB/GEF CSP portfolio
1. Can the rationale to include CSP in the OP 7 objectives be confi rmed?
2. Should the WB/GEF portfolio of CSP plants be continued as a whole, in parts, or should it be stopped?
3. Are there particular conditions for the continuation of the portfolio?
4. Are there alternative possibilities for disbursement of the WB/GEF grants to promote CSP in one or two of the four selected countries, in particular in case of project failure?
5. Was the ISCC/solar trough technology the right selection for the WB/GEF portfolio?
6. Should there rather be a single or a two-EPC approach (combined or separate EPC for the fossil combined cycle and the solar part of the plant)?
7. Should the pending bidding procedures show fl exibility with respect to the size of the solar fi eld in order to be fl exible with respect to cost uncertainties?
8. What are the opportunities for successive plants?
9. What are the chances/risks of each of the four WB/GEF projects to reach realization?
Questions addressing the long-term development of the WB/GEF CSP portfolio
Strategic questions
10. Which strategy choice as discussed in Chapter 5 (sections 5.4 to 5.6) (“Wait and See”, “2-Track-Approach”, “Specialization”) should be adopted in case of successful/unsuccessful
termination of the current portfolio? What would be the outcome of such an engagement?
11. Should a future WB/GEF strategy concentrate on regions with the best chance to create volume markets ?
12. What are the requirements on the composition of any future portfolio for CSP in order to fi t the development toward the realization of the CSP vision described in Chapter 6 (section 6.1)?
Operational questions
13. Should a future engagement continue to promote ISCC? Should it promote a broader range of technologies; if yes, which?
14. Which funding mechanisms appear as most suitable to promote CSP in the future? Should WB/GEF bundle forces with more actors to reach a critical mass? In particular, how can the
technology best be promoted in developing countries?
15. What amount of support is necessary for any following step?
16. What could be the potential GEF engagement in case of reduced available CSP funding?
Another weak point is to generate a stronger link between the
development of a frame for renewables in the countries and
the evolution of CSP technology. Both are largely disconnected
in the WB/GEF portfolio countries, whereas in Algeria, for
example, the connection is explicitly made. This point is linked
to the previous one.
One other weak point in the comparison appears to be the
interface from the currently ongoing activities in the phase
of institutional and technical learning to a full-fl edged market
development strategy as necessary for the next phase where a
market has to be generated.
Private sector investment was not present in the fi rst phase of
market development, although a suitable replacement was found
with the public EPC approach. However, the next phase must
involve more private investment.
6.6.2 Short-term recommendations for the WB/GEF
Portfolio
This section provides answers to the questions raised in section 6.5
addressing the short-term development of the WB/GEF CSP port-
folio. It gives general and project-specifi c recommendations for the
WB/GEF portfolio and looks at implications for the CSP strategy.
61
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
T
ABLE
11: E
VALUATION
OF
THE
CURRENT
WB/GEF
PORTFOLIO
AGAINST
THE
SET
OF
SUCCESS
CRITERIA
FOR
A
LONG
-
TERM
STRATEGY
FOR
CSP
Strong/weak/medium
Criteria
Relevance in the current WB/GEF portfolio
point in portfolio
1. Ensure increasing participation of developing countries
Important issue in current portfolio. However, weak point in so far as
Medium
in CSP development
no mechanism in place that generates further interest. Successful
termination of the larger part of the WB/GEF portfolio will generate
confi dence for other developing countries to enter at part 2 of the cost
reduction curve or to continue the experience from part 1.
2. Spur CSP Market Deployment in industrialized countries
Not taken into account. Only indirectly accessible to WB/GEF; can
Medium
be infl uenced through a parallel development of the market in
developing
countries.
3. Better understand the country’s power market
Given to a certain degree, but limited.
Medium
4. Include successful market creation policy measures
Only partially taken into account through grants and preferential loan. Weak
Lack of a strategy extending in particular from part 1 to part 2 of the
cost reduction curve. Originally this strategy was there in the form of
larger amounts of grants, but it is questionable whether grants would
be the best means to move on to the next phase. For the future, it
will be more effective to fund MWh instead of MW (see also
description of a CSP fund in section 6.3).
5. Serve economic development of countries/region
In the frame of the size of the WB/GEF projects, once realized they
Medium
will certainly have an economic impact on the region concerned
(even considering the solar part alone).
6. Contribute to building up of local institutional experience
Important issue of the current WB/GEF portfolio.
Strong
7. Create renewables frame in developing countries
The current strategy provides for little incentives for the current to
Weak
consider a wider frame for CSP. The frame for renewables is also
developing in parallel, but there is no straight link between the
renewables frame and the CSP strategy in the countries, as for
example established in Algeria.
8. Mobilize suffi ciently large funds
GEF funds provided are considerable. However, no strategy discussed so
Strong
far how to move from part of 1 of the cost curve to part 2 (Figure 20)
9. Mobilize private investment
Not successful so far (failure of the IPP approach). However, so far a
Weak
fairly successful replacement solution was found with the public
EPC
approach.
10. Promote technology diversity
Not considered so far. The main focus was right from the beginning on
Medium
troughs as the most experienced technology by the time. The selection
of four ISCCS plants might have been determined by the country choice
for large capacity increase. Important issue for part 2 of the cost
reduction
curve.
11. Enhance previous country experience with CSP
Not an issue in Part 1 of the cost reduction curve.
—
12. Contribute to building of local manufacturing experience
Larger fractions of the plants will be built by local companies, in
Medium
particular all construction work. Concerning solar components, given
the small volumes involved so far, the presence of suppliers in
industrialized countries, no local manufacturer has arisen so far
(continued on next page)
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
62
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
1. Can the rationale to include CSP in the OP 7 objectives be
confi rmed?
The context for the recommendations in this section is the original
objective of OP 7—to increase the market share of low greenhouse
gas-emitting technologies that are not yet commercial, but which
show promise of becoming so in the future. In view of strongly grow-
ing energy demand in the developing world, increasing global envi-
ronmental concerns regarding energy provision, fuel security issues
including domestic supply constraints, and an increasing likelihood
of some form of global trade on carbon emissions (including targets
in all countries also in the developing world), we strongly believe
the OP 7 objectives are responsible, timely, and necessary.
There are numerous avenues for manifesting these objectives, some
of which have already been pursued under OP 7 such as biomass
and fuel cells. From an overall perspective, we believe CSP is a
technology worth pursuing under the objectives of OP 7 as it meets
all important criteria:
Solar energy is the world’s largest sustainable energy re-
source
Solar energy is abundant in many developing countries
Solar thermal is positioned favorably in terms of technology
development—no exotic material breakthroughs are required,
and it comprises thermal processes that are well-understood
Solar thermal integrates well with other thermal processes,
thermodynamic cycles, and conventional power generation
equipment
There remains room to “stretch” the technology
Operation and maintenance issues can be undertaken relatively
easily and without too much dependence on an incumbent sup-
plier
Solar thermal electricity plants can be installed in large “chunks,”
which means it is one of relatively few renewable technologies
that can make the necessary deep cuts in GHG emissions.
Solar plants can be designed to be dispatchable
We see that solar thermal electricity offers prospects that have much
strategic value for the countries that take up the technology, and
thus forms an important part of the technology mix to be pursued
under OP 7, which itself is a critical element toward the worldwide
deployment of low GHG-emitting technologies. The rationale is
discussed below.
2.Should the WB/GEF portfolio of CSP plants be continued as a
whole, in parts, or should it be stopped?
We would encourage the World Bank and GEF to proceed with
each of the present projects. First, we believe they are crucial
Strong/weak/medium
Criteria
Relevance in the current WB/GEF portfolio
point in portfolio
13. Contribute to the sustainable development of a country/region
The contribution to the overall sustainable development of the current
Medium
portfolio is limited to the direct economic and environmental impact
(see below). Criteria less important in Part 1 of the cost reduction curve.
14.
Reduce environmental impact
Is in principle the case but depends on the quality of the plants realized
Unclear at present
(issue of the larger steam boiler with larger partial load losses in ISCC).
Criteria of less importance in Part 1 of the cost reduction curve.
15.
Ensure acceptability of technology in regions to which
So far no export of electricity is foreseen for any of the 4 WB/GEF projects
—
CSP electricity is exported
given that this is essentially an interesting option for gas suppliers such as
Algeria who want to sell electricity from combined cycles in combination
with solar thermal power. Criteria of less importance in Part 1 of the cost
reduction
curve.
16.
Promote small and large-scale applications of the technology
3
Criteria of less importance in Part 1 of the cost reduction curve given that
—
the technological diversifi cation is more an issue of part 2 of the cost curve
63
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
to building momentum in the solar thermal industry. Second, by
proceeding, future projects in those countries are likely to benefi t
from the leverage applied now. It is likely that by the time these
GEF projects begin operation, and any subsequent projects are
formulated, new projects will have commenced around the world,
leading to cost reductions. These cost reductions won’t be enough
to avoid the need for gap funding (whether in OECD or developing
countries), but the gap will be less, and perhaps acceptable.
We would liken the process to falling dominoes. It only takes one
domino to “miss the mark” and halt the fl ow. Multiple, well-designed
projects with gaps that are not stretched to their limits are more
likely to give rise to a continuous stream of new projects.
At the very least, each project should be given the opportunity to
proceed the release of the RfP, as the cost to get to this point will
be relatively small against the opportunity it affords to discern the
level of interest.
In the course of writing this report, the question has been raised
whether the present portfolio context is not similar to a few years
ago, when hopes were high for an immediate realization of WB/
GEF projects that have not materialized so far. However, there are
substantial differences in the context now, such as a considerably
higher energy price context, concrete CSP projects coming up in
the developed world, and stabilization of the business model (move
from the IPP approach to public EPC).
3. Are there particular conditions for the continuation
of the portfolio?
Given the time elapsed for the project portfolio, the countries with
pending projects must commit to fi rm timelines that it must meet
in order to keep the GEF grant available. The key dates for the
countries to adhere to are (a) release of RfP (i.e. must have passed
“non-objection”); (b) assessment of bids and presentation of pre-
ferred bidders to WB; and (c) signing of contracts.
Such timelines need to be discussed and fi xed with each of the
four countries individually. From the current perspective, it appears
realistic that by the end of 2007 the Moroccan project—as well
as the projects in Egypt and Mexico—could have reached the
contract signature stage.
4. Are there alternative possibilities for disbursement of the WB/
GEF grants to promote CSP in one of the four selected countries,
in particular in case of project failure?
The team has considered alternative possibilities for disbursement
of the GEF grants, in particular providing a smaller contribution
toward the capital cost of the project and maintaining some for
“other activities to promote CSP in the country.” Other activities
could help to improve the chances of subsequent projects in those
countries, and might include setting up in-country fabrication facili-
ties for mirrors or tubes and the establishment of “expert teams”
of local skilled labor. However, we don’t believe this money will
be well-spent given the tenuous chance of immediate subsequent
projects in those countries.
There was also the possibility of splitting the grant into two smaller
grants to fund two smaller projects, but, as discussed above,
there are fi xed costs that are relatively independent of capacity
associated with such power projects, and it would be likely that
instead of one 25 MW solar fi eld one would end up with two
10 MW solar fi elds (or two 12.5 MW solar fi elds with higher
LEC’s) without the benefi t of contributing to a cost reduction in the
technology. There would also be the risk that one of them would
not proceed.
In the case of the revision/cancellation of one to two projects, and
the wish of the WB/GEF to support further this important technol-
ogy in the given country without looking for alternative sites, the
following alternative technology lines to the ISCCS concept might
be considered:
Market introduction for industrial process heat applications based
on concentrator solar.
Small-scale solar combined heat & power plants (heat for ab-
sorption chillers (e.g. air conditioning), or process heat or sea
water desalination (the latter becoming increasingly important
in many countries with good solar resources).
Feed-water preheating in fossil steam plants: promoting tech-
nologies other than parabolic trough collector types (e.g. tower,
dish, Fresnel) by a technology unspecifi c bidding procedure.
Feed-water preheating leads to good solar effi ciencies, good
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
64
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
ratio of funding and solar-MWh because of reduced investment.
Existing plant (infrastructure) might be used.
5. Was the ISCC/solar trough technology the right selection for
the WB/GEF portfolio?
The question has arisen as to which is the better confi guration—
SEGS or ISCCS? Our contention is that it is a matter of “horses for
courses.” Technically, both options are feasible, as is the option
of integration into a coal-fi red Rankine cycle. One of the major
issues that arise is one of perception—that in an ISCCS plant there
may only be a solar contribution of some 6 percent. In reality, a
30 MW solar fi eld in either confi guration will still generate ap-
proximately the same GWh/yr of solar electricity, and bequeath
the same level of O&M experience, through having to maintain
some 200,000 m
2
of solar array.
There is a more pressing need for MW than for solar plants in the
developing countries of this portfolio. There is also a signifi cant
non-technical lead time associated with any new project—permits,
authorities, contract administration, etc.—regardless of the project
capacity. Given that there is less than a 100 percent chance that
all proposed power generation projects will proceed, the hybrid-
ization of solar with combined cycle both helps to meet the power
needs of that country while simultaneously deploying a solar fi eld,
a fi eld that may just have been deemed “too hard” if for the sake
of only a 25–30 MW plant.
The ISCCS confi guration has not been tried before, and thus it is
probably inevitable that some teething troubles will emerge. If sound
engineering is applied, we believe that enough is known about
solar fi eld operation, and enough about combined cycle operation,
that any problems that may arise are not likely to be fundamental in
nature, but rather to do with optimizing energy fl ows, particularly
under transient solar conditions.
ISCCS makes particularly good sense in the following context:
if the country aims at exporting gas through the combination
with clean solar energy (e.g. Algeria);
if the country wants to build fossil plants in areas suitable for solar
thermal plants (e.g. Morocco); however, one should carefully
consider hampering the performance of the combined cycle plant
in the case of a non-optimal location due to the solar plant;
if the country can save on old ineffi cient coal-fi red power plants
by the combination with solar thermal (e.g. Mexico);
if the country has a strong need for increasing the installed MW
due to strongly increasing demand and combination of solar and
combined cycle does not create additional delay (in principle
Egypt, but delays were caused by the contractual separation
of the two plants while technically they are combined).
So the answer to the question posed on the ISCCS technology is
not a frank yes, but there are some arguments that point to ISCCS
as a suitable solution for the current phase of market introduction.
Nevertheless, the ISCCS choice has introduced a variety of ad-
ditional problems that have delayed project realization (e.g. the
question of a single or two EPC contracts for the fossil and the
solar part, see below; the question of mutual liability between the
two project parts etc.)
The other technology issue is that of the solar fi eld—trough, tower,
Fresnel, dish? The trough using a heat transfer fl uid is certainly the
most advanced, and for the most advanced projects in the portfolio,
particularly Morocco, we would advocate staying with the existing
project as formulated. However given that these projects are early
in the cycle for the technology, it is important that the best options
be given the opportunity to emerge.
We would strongly suggest that consideration be given to not
specifying troughs for the remaining projects (presently it is not
specifi ed for Egypt), but rather leaving the technology selection
up to the bidders. We believe this will lead to a greater number
of bids, improving the competition. Though the tower technology
providers would probably balk at installations greater than 50 MW,
25–30 MW should be within their capacity.
6. Should there rather be a single or a 2-EPC approach (combined
or separate EPC for the fossil combined cycle and the solar part
of the plant)?
In the absence of IPP approaches to this portfolio, the issue of
single EPC (to cover the whole ISCCS turnkey project) versus two
65
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
EPC (one contract to cover the combined cycle, and the other to
cover the solar fi eld) has arisen. In power projects, single turnkey
projects (made up of multiple sub-contracts) are common, but power
projects comprising multiple EPC contracts (boiler, turbine, cooling,
etc) are not uncommon either. An ISCCS project combines a well-
known technology (combined cycle) with the less well-known solar
fi eld. There are a number of large well-established combined cycle
suppliers, but few solar suppliers. The resulting imbalance led, in
the past, to some confl icts over the balance of risk. However, with
larger consortia now emerging (as a result of the Spanish activi-
ties) that are willing to take on the whole project, the single EPC
approach appears favored.
There is no fundamental reason why the two-EPC approach is
unworkable, however it does raise some diffi culties. In particular,
the design of the cycle, particularly the interface between the
solar and the heat recovery steam generator (HRSG), needs to be
well defi ned in the specifi cations, requiring a detailed design and
optimization study. In the single EPC, the consortium carries out the
optimization as part of the bid. The issue that arises, however, is if
the project is built as specifi ed and does not perform, the liability
must rest with the designer of the specifi cations.
This approach also limits the fl exibility of the solar fi eld offers.
This is because the specifi cations for the HRSG (steam generator)
will need to know the thermal contributions and the temperatures
that will come from the external heat source (solar fi eld). These
will need to be specifi ed so the various heat exchangers in the
HRSG can be sized appropriately. For example, the superheater
will need to be oversized to accommodate the additional super-
heating required (given that troughs using heat transfer fl uid are
limited to around 370°C steam temperature, yet the steam turbine
requires perhaps 500°C). However, when the solar fi eld is not
operating, the superheater area is too great, and thus signifi cant
desuperheating is needed (an effi ciency loss). Superheater area
is a fi xed parameter defi ned by the operating temperature of the
solar fi eld. For example, if the superheater area was designed
for 370°C to enable troughs using htf to comply, it would be
an excessive area for a tower that could supply the full 500°C.
The end result is that the HRSG ends up being designed to suit a
particular solar temperature, and thus is optimized for a particular
collector.
7. Should the pending bidding procedures show fl exibility with
respect to the size of the solar fi eld in order to be fl exible with
respect to cost uncertainties?
The team has only been able to view one set of RfP documents—the
original ones from the aborted bid process for India. Those docu-
ments specifi ed a fi xed solar fi eld aperture size (220,000 m
2
±
3 percent) for the troughs. Given that the grant from GEF is also
a fi xed amount, there is no fl exibility should costs come in higher
than originally anticipated when these projects were originally de-
veloped. Given these are fi rst-off projects in developing countries,
the risk margin is likely to be high, resulting in the possible situation
where all the bids come in either too expensive for the fi nance
available, or non-conforming (reduced fi eld size).
The capacity of these fi rst projects is to some extent arbitrary. It is
unlikely that in ten years time the issue of whether the fi rst ISCCS
project comprised 25 or 28 MW of solar will be an issue. What
will be an issue, however, is whether the GEF projects failed to
get past the RfP process as a result of overly restrictive bidding
requirements, and, if they did proceed, whether they operated
successfully.
We suggest the bid documents allow for a minimum threshold
capacity requirement for the solar fi eld, but make the offered solar
capacity one of the assessment criteria. The resulting competition
will help ensure the maximum capacity possible is offered for the
fi nance available. Most importantly, it would allow the bidders to
develop, and feel comfortable with, their own risk profi le.
It does raise additional complications as to how the bids are assessed.
The documents would need to provide clear guidance as to the
weightings given to different assessment criteria—overall LEC, peak
solar capacity, solar $/MWh
th
, etc., in much the same way as the
2002 Indian bid documents gave priority to thermal storage, etc.
In single EPC contracts where one turnkey price is offered, the
break-out cost of the solar fi eld itself will not be known, and even
were it requested, there would be the tendency to offl oad some of
the solar fi eld cost against the combined cycle power block cost to
make the solar fi eld appear more attractive on a $/MWh
th
basis.
The dual-EPC approach has the advantage that each component
is bid separately and competitively.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
66
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
8. How are the opportunities for successive plants?
The World Bank has asked “what is the likelihood of these four
plants contributing to the development of a momentum that sees
subsequent plants being installed?” And as a corollary, why pursue
this GEF portfolio of 4 x $50 million
25
projects if the chance of fol-
low-up plants is slim? There are a number of factors impacting on
this issue, but perhaps the key one is the expected cost reduction
curve. Depending on the particular model and assumptions used
(see section 2.2) some thousands of MWs are required before the
technology is competitive with conventional fuels. This means that
subsequent plants are only likely to be built if some other form of
fi nancial incentive is available—grants, renewable portfolio stan-
dards, renewable feed-in laws, etc. The other possibility is that the
necessary cost reductions occur as a result of a signifi cant rollout in
the OECD countries, the benefi ts eventually feeding through to the
World Bank countries. The latter is quite possible, but could take
on the order of ten to twenty years. Perhaps the most reasonable
chance of subsequent plants is some combination of the above in
a suitable CSP fund starting in a given region such as the Mediter-
ranean/Middle East region (see discussion below).
The rollout in the OECD countries is still in its infancy, although
there are in particular robust incentives in Spain, and emerging
activity in the United States, to help underwrite signifi cant deploy-
ment activity. Nonetheless, at this point in time, there are less than
300 megawatts of what we would regard as relatively fi rm project
prospects. Arguably, technology and industry maturity could be
said to have been reached before commercial competitiveness
was achieved—perhaps after a couple of thousand MW—and
there would be a greater degree of certainty that competition and
corresponding momentum would help to roll the industry forward to
commercial competitiveness. Once 2–3,000 MW was installed,
much as for wind, there would be much more data available to
plot the cost reduction curve and provide a degree of certainty
for investors. At this point, the industry is totally reliant on external
fi nancial incentives; if existing ones were to be removed for any
reason, the industry would stop, just as the removal of incentives in
California halted the continued progression of the SEGS plants.
The most attractive fi nancial incentives are in Spain. However,
these presently only apply to the fi rst 200 MW. Beyond that, there
is an expectation they would reduce in line with a (to-be-speci-
fi ed) cost reduction target. However, given that the Royal Decree
was essentially put in place to support Spanish industry, and at
this point Spanish industry has taken the lead role in the projects
proposed, there would appear to be a good chance of continued
support. The only other strong support in OECD countries for solar
technology is via a small number of Renewable Portfolio Standards
(RPS)’s in the United States, although we feel that something like
the Southwest United States CSP Initiative needs to be confi rmed
with strong fi nancial incentives attached for a robust CSP market
to develop there.
At this point, the industry still appears fragile. However, once
construction is well under way for a few projects in Spain and
the Nevada project, a cusp will have been reached. It is more
the number of projects than the total MW under construction that
will help to move the industry beyond the cusp (part 1 of the
cost reduction curve, see Figure 20) and into the beginnings of
a more robust rollout (part 2 of the cost reduction curve). In other
words, six 30 MW projects are deemed to be of more value
than a single 360 MW project. More projects spread over more
countries will ameliorate the risk associated with reliance on one
country’s incentive, and also the risk of one or more projects not
proceeding. It will also help build the profi le and the perception
of widespread activity.
From this point of view, an announcement of at least 1 or 2 GEF
projects in the next 12 months becomes quite crucial. We do not
feel that the existing portfolio would benefi t from any signifi cant
change to the way the funding is made available to the projects.
The best chance of success is to make the funding available as
an upfront grant, as is presently the case. Holding a retainer until
certain performance milestones are met would not be necessary,
as performance penalties are covered in the bid documents.
From the overview of the mid-term expansion plans for the electric-
ity sector, it appears that with the exception of Egypt none of the
other countries in the portfolio have concretely integrated further
CSP plants into their expansion plan. Morocco has established a
certain number of sites that are suitable for further CSP plants. This
25
the exact amount is $194.2 million
67
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
is understandable to a certain degree given the awaiting for the
fi rst plant. Most likely, with the experience of the fi rst plant, and the
experiences in countries like Spain, further CSP plants would be
considered in a few years as options. However, by then economic
conditions will dominate the decisions.
6.6.3 Specifi c recommendations on the four WB/
GEF projects
9. What are the chances/risks of each of the four WB/GEF
projects to reach realization?
Egypt
Egypt is currently a net exporter of energy through its reserves of oil
and natural gas, which provides valuable foreign income. However,
the Egyptian Government does recognize that these reserves of
oil and gas do have a fi nite life. The Egyptian Government further
recognizes that it has good renewable energy resources such as
wind and solar insolation that can be exploited. Additionally, the
Egyptian Government has as one its primary objectives the expan-
sion of its manufacturing industry, which includes the manufacture
of components for its energy sector. The government recognizes
that expansion of the manufacturing sector is dependent on the
development of local know-how and intellectual capital. Finally,
the Egyptian demand for electricity is growing and new generation
capacity has to be continuously installed.
Importantly, the government recognizes that the GEF grant has
provided the catalyst to explore the application of solar thermal
technologies.
Two issues that had introduced delays in the project course over
the last year were:
An agreement had to be reached between NREA and the World
Bank with regard to incremental costs not only covering capital
costs but also operation and maintenance costs (agreement was
reached mid-May 2005 that the GEF fi nancing will cover the
incremental O&M costs).
Resolution of concerns regarding the JBIC request to split the
existing bid documents into two, one for the solar island and
the other for the combined cycle island. This issue was fi nally
accepted by the World Bank and Fichtner Solar prepared the
two bid documents.
It is within this context that the following is recommended for
Egypt:
1. The RfP does allow bids for a broad range of collector technolo-
gies (trough, dish, tower, Fresnel). This will stimulate the level
of interest in the Egyptian project and reduce the probability of
no successful bidders being found.
2. Flexibility must be allowed to explore the consequences of
JBIC’s request for two bid documents; careful management of
timelines to execute the project must be maintained. Although
this approach has many unknowns (see the discussion in section
6.6.2), it is an occasion to learn about a different institutional
arrangement for the contract.
3. To stimulate Egyptian interest in implementing further solar thermal
power projects, we recommend that the World Bank seriously
consider a role in facilitating:
Egypt’s establishing a renewable energy fund to fi nance
future solar thermal project. Such a renewable energy fund
could be fi nanced through a small levy on oil and gas that
is exported, similar to the procedure in Algeria.
Surveying local equipment suppliers/contractors to establish
what components may be provided locally and to inform
such suppliers and contractors of the opportunity of further
projects.
Establishing how best to develop local know-know and
intellectual capital. Local know-how enables wider choices
to be made and increases the probability of new technolo-
gies being accepted by all stakeholders, in particular local
stakeholders.
How best to integrate any Egyptian solar thermal project into
a Mediterranean basin power pool. Such a power pool has
the potential to provide Egypt with foreign income and allows
Egypt to retain its position of being a net energy exporter.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
68
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
How best Egypt can secure any benefi ts from mechanisms
such as the Clean Development Mechanism.
(4) It was specifi cally requested by those interviewed in Egypt that
the World Bank keep the ISCCS stakeholders in Egypt, Morocco,
Mexico, and India informed of developments in the various countries
through regular newsletters, and seriously consider facilitating an
international meeting at a convenient venue where the four coun-
tries and other interested countries can compare experiences and
developments. Such an international meeting will facilitate future
dialogue among the four countries and reduce the communications
load off of the WB.
India
At the time of the study, the consultants had recommended that (i) the
GoI needed to reply to the World Bank letter of 2004 stating the
government’s commitment to the project proceeding and to meeting
the requirements stated therein, and that (ii) there be a resolution of
the balance of funding from KfW. Eventually, the project could not
be implemented in a timely fashion due to inappropriate design
and location. In case the project is brought forward again, the
following remarks might be considered:
The RfP should be modifi ed to allow a broad range of collector
technologies to be bid (trough, dish, tower, Fresnel) to supply
steam to the steam cycle. This will help improve the level of
interest in the Indian project, and make less likely the situation
where no successful bidders can be found.
The RfP should be modifi ed such that there is a minimum threshold
of required solar capacity (perhaps around 23 MW), but which
encourages bidders to compete to offer the most solar MW (or
better still GWh) for the available grant. This will help reduce
the possible situation where no bids are received because the
fi xed grant is not enough to cover the mandated fi eld size.
A timeline with specifi c dates will depend on the above issues
being resolved. However it is suggested that the Moroccan
project be given time to release RfP’s fi rst to at least get one
project successfully under way. Given the signifi cant time
gap in this project, a new call to pre-qualify bidders will be
needed.
The gas supply issue has plagued this Mathania project from the
outset. Discussions in India suggested an alternative supply point
requiring a much shorter pipeline; this is now the new preferred
option. In addition, some preparatory work has been carried
out to investigate alternative uses for the gas and revenue pos-
sibilities along the pipeline. This situation needs to be clarifi ed
and confi rmed in a letter to the World Bank.
We have seen little technical evidence to support Mathania’s
selection as the preferred site for this fi rst Indian project. How-
ever, various stakeholders suggested it might be unwise to open
up this issue to any signifi cant degree as it could lead to further
procrastination, and thus quash any project altogether. In any
case, it was pointed out, the permits are in place and most of
the infrastructural and resource requirements are now starting to
come together for Mathania. However, other stakeholders con-
sidered there were better sites available and that these should
be explored. Integration with the Jaiselmer 110 MW combined
cycle was mentioned, but the existing steam turbine would need
resizing to accommodate a 30 MW solar fi eld, or a smaller solar
fi eld. The Mathania solar resource of 2,240 kWh/m
2
/yr is only
an average site by world standards. We would be reluctant to
recommend a detailed investigation of alternative sites, however
there could be value in ensuring that in the last decade—since
Mathania was selected—a better site has not emerged. We
would suggest a short assessment with very tight deadlines of no
more than two or three other sites that might host such a plant.
The onus would need to be on the other sites to prove themselves
more attractive than Mathania’s present status, and also that
they could make up the lost time. This could perhaps form part
of the required response to the World Bank. One advantage
this would have is to effectively lay the groundwork for a more
fl exible technology response, as recommended above.
Mexico
Long-term prospects of CSP in Mexico
Mexico has excellent solar insolation conditions, a growing electric-
ity demand, and a growing dependence on natural gas imports.
Solar thermal power plants can help mitigate the country’s risk
related to volatile fuel prices. Further arguments to introduce CSP
in Mexico are the fact that CSP can be used to substitute Mexico’s
69
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
expensive peaking power plants, which would justify higher solar
LEC. Furthermore, the local industry will profi t from the CSP mar-
ket. A Mexican company has already provided structures for the
Californian SEGS collectors. In the future, over 50 percent of the
solar fi eld investment and O&M can be provided by the Mexican
national economy (Spencer Management Associates, 2000).
Near-term prospects of CSP in Mexico
The country has in place legislation mandating a least-cost obliga-
tion for electricity generation technologies. The arguments as to
why Mexico would profi t from CSP technology would have to be
recognized by Mexican political authorities with the consequence
of developing a legal framework that fosters CSP deployment in
the country (ideally in the form of feed-in-tariffs). Currently, a new
law for the promotion of renewable energies in the country is in
preparation. According to CFE, it might take one to two years
before this law is approved. This law will foster solar and wind
projects in the future. It is not yet clear how this law will comply
with the least-cost requirement, which is also fi xed by law. As a
consequence the question of whether, in the near term, Mexico will
be able to invest domestic capital into further multiple solar thermal
power projects is not yet known.
Recommendations on the Mexican project
Given the fact that in the long run, the country will profi t from CSP
technology and that CFE shows strong interest in the current ISCCS
project, it is recommended to maintain the WB/GEF support of
the project. CFE will gain valuable construction and especially op-
erational experience with such a plant. With this CSP experience,
the country would be much more likely to invest in this technology
at a later point.
Mexico’s new plan to equip a 560 MW CC instead of a 250 MW
plant with a solar fi eld, thereby diluting the solar share to approxi-
mately 50 percent of its original contribution, should not be grounds
(from an energy, ecological, or economic point of view) to cancel
project support. The 560 MW CC would be built anyway and,
with the same solar fi eld size, more solar electricity is actually gener-
ated (Figure 23). This is because during the hours when the solar
fi eld is not operating, there are thermodynamic advantages due
to the solar fi eld now representing less of an off-design imposition.
Recent further developments for this plant and the recent Sargent
and Lundy study (2006) have shown that the doubling in size of the
fossil component is not a decisive argument against this plant.
We are unsure if the same methodology has been used to model
annual output in both the Sargent and Lundy (2003) feasibility
study and the earlier Spencer (2000) study, and for clarifi cation
suggest this be reviewed.
The dilution of the solar share of the plant does not appear to be
a decisive argument against the 500 MW plant because high
solar shares are not among the advantages of the ISCCS concept
anyway. ISCCS is a good concept to boost a CC that would
anyway be built with a comparatively huge amount of renewable
energy (compared to other forms of solar energy usage).
One critical point with respect to the ISCCS concept in general, but
especially in combination with a larger combined cycle, is the fact
that suffi cient incentives will be in place in order to ensure that the
solar fi eld will actually be operated. Such motivation is especially
strong when the remuneration of the solar electricity occurs on a
kWh basis. However, in this case, an upfront grant covers the ex-
F
IGURE
23: R
ELATIVE
PART
LOAD
LOSSES
OF
THE
STEAM
TURBINE
FOR
THE
DAYTIMES
WHEN
SOLAR
FIELD
IS
NOT
PROVIDING
SOLAR
STEAM
FOR
DIFFERENT
ISCCS
PLANT
SIZES
Source:
part load characteristics: E.ON Engineering (see fi gure 4); interpretation and transfer to ISCCS:
Gabriel Morin.
500 MW: ST operation when no
solar energy available
250 MW: ST operation when no
solar energy available
40%
50%
60%
70%
80%
90%
100%
Relative part load efficiency
Thermal load of the Steam Turbine (%)
0
20
40
60
80
100
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
70
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
cess solar costs. Possibly such incentives might be provided in the
form of penalties if the solar fi eld is not working according to the
design conditions (penalties on kWh
th
basis for the solar fi eld).
A different plant concept was discussed at the World Bank CSP
Workshop (April 20, 2005)—the integration of a solar fi eld into an
existing coal-fi red Rankine plant owned by CFE. Such a combination
will have a much higher CO
2
-emission benefi t by displacing coal
rather than natural gas, when the solar fi eld is used as a fuel saver.
Technically/thermodynamically, the solar fi eld would fi t well into
the Rankine cycle. If the GEF, the World Bank, and CFE are fl exible
enough to change to this non-ISCC concept, further examination
of this hybrid concept is strongly recommended.
In any case, we recommend that CFE, the World Bank, and GEF
agree upon a common project plan for further project implementa-
tion, including meetings and/or reporting after each milestone to
avoid institutional problems encountered in the past (delays due to
low project priority, unclear procurement guidelines).
Morocco
The Morocco project appears from the current perspective the most
advanced of the four WB/GEF projects, although the Moroccan
request to increase the CC capacity due to power shortage could
introduce further delay. It is therefore a key project in the portfo-
lio and important for the whole GEF program that this project is
strongly promoted and supported, even in the most diffi cult phase
still ahead, the bidding process. The World Bank should therefore
pay particular attention to the Morocco project so that delays are
kept to a minimum and the deadlines as proposed currently, with
contract signature by January 2007, are respected. This could set
a sign for the other projects in the portfolio (lead function). Internally,
this requires for the World Bank a tough follow-up of procedures.
Problems arising in the bidding procedure might arise from the
fact that bidding companies, not yet trusting the establishment of
a market, might add risk factors to the price that could bring the
price beyond the currently foreseen fi nancing. From the current
perspective, this risk appears limited (larger share of well-known
conventional components with known costs due to the ISCCS ap-
proach, fi nancial calculations taking into account such a risk to
some degree, the development in Spain that might share the “risk
of the fi rst plant”), but not fully excluded. In case of substantial
cost overdraw, a rapid compromise should be discussed with the
participating companies.
6.7 A
NSWERS
TO
THE
QUESTIONS
ADDRESSING
THE
LONG
-
TERM
DEVELOPMENT
OF
THE
WB/GEF CSP
PORTFOLIO
This section provides answers to the questions addressing the long-
term development of the WB/GEF CSP portfolio raised in section
6.5 (both questions related to strategy and operational questions).
From the previous description of a long-term vision for CSP and of
the success criteria for a strategy to introduce CSP in developing
countries in particular, one can deduce several recommendations
that are important for the future development of the WB/GEF CSP
portfolio in order to fi t such a successful strategy:
6.7.1 Strategy recommendation
The options discussed here for part 2 of the cost reduction curve
assume that the current portfolio has some reasonable implementa-
tion success (at least 2 projects).
10. Which strategy choice as discussed in Chapter 5 (sections 5.4 to
5.6) (“Wait and See”, “2-Track-Approach”, Specialization”) should be
adopted in case of successful/unsuccessful termination of the current
portfolio ? What would be the outcome of such an engagement?
The “Wait and See” strategy (see Chapter 5, section 5.4) is
incompatible with the success criteria and OP 7 main objective:
The “Wait and See” strategy described in section 5.4 does not
fulfi l Criteria 1 in that it delays the introduction of solar thermal
technology beyond the point when a lot of the power generation
infrastructure of developing countries will be in place. It is also in
contradiction to the main objective of the OP 7 to promote GHG
technologies that will make a major contribution to the reduction of
greenhouse gas emissions in developing countries. This objective
remains entirely valid in the light of the arguments provided at the
beginning of this chapter.
Pursuing the “Specialization” strategy now will for some decades
only lead to a limited contribution to a path toward reduced CO
2
emissions
: It is unlikely that a strategy based on small-scale promotion
71
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
of CSP technology would be able to lower the cost suffi ciently rapidly
in order to allow for a stronger penetration of the bulk electricity mar-
ket. Hence the “Specialization” strategy considered in the previous
chapter cannot replace the “2-Track-Aproach” in order to promote
quickly enough the penetration of CSP power before fossil alterna-
tives lock down the path toward reduced CO
2
emissions for some
decades. However, in the absence of a more ambitious strategy, it
can constitute a suitable means to keep interest in CSP at a minimum
level or to complement possible more comprehensive strategies from
other actors (for more details see answer to Question (16)).
Future GEF Strategies must rely on a 2-Track-Approach:
It follows
that the main strategy must rely on a 2-Track-Approach promoting
the technology in both the developing and the developed countries
and to accompany it along the cost reduction curve with different
strategies.
11. Should a future WB/GEF strategy concentrate on regions with
the best chances to create volume markets?
For the
fi rst phase
of the cost reduction curve (in which we are cur-
rently and which establishes technical and institutional experience),
it appears as adequate that there was a broad consideration of
countries/regions, as the main aspect was the creation of technical
and institutional experience. The second phase of the cost reduc-
tion curve should concentrate on regions with the best chance to
create volume markets (Criteria 4) in the shortest time and should
not disperse efforts. However, technology promotion might mean,
at a given point of the cost curve, to focus on a given region. Such
countries/regions are from the current perspective:
The
Mediterranean area and the Middle East.
26
The main reason
for this conclusion is this region fulfi ls partially or fully a variety
of the above-mentioned criteria such as Criteria 1 (if the current
WB/GEF portfolio and the ISCCS project in Algeria are success-
ful), Criteria 2 (recent development in Spain and partially Italy
and Israel; to be enhanced in Greece), Criteria 3 (in particular
for example in Algeria but for the whole of the North African
region up to Iran due to the nascent power interconnection of
those countries with Europe and among themselves as well as
the growing electricity demand at noon and power technology
diversifi cation issues), Criteria 7 (currently only in Algeria), and
Criteria 12 (if the current WB/GEF portfolio is successful).
A successful strategy in this area must enhance the partially
fulfi lled criteria in other countries and in particular (1) stabilize
and increase the participation of the European Mediterranean
countries and Israel; (2) replicate the current WB/GEF portfolio
in Morocco and Egypt; (3) support the current efforts in Algeria;
(4) activate stronger support for the CSP efforts in Jordan and
Iran; and (5) investigate for other countries in the region without
current CSP strategy but suitable solar resources the possibil-
ity to develop a CSP strategy (e.g. Libya or possibly African
countries further to the South, see Trieb, 2005). According to
Criteria 3, the technology chosen must best fi t the requirements
of power sector development. In some or all cases, this might
be ISCCS technology, either because it best fi ts the needs of
the economy (Algeria) or because it ensures the largest solar
capacity installed at the lowest price combined with an overall
large fossil capacity covering the rapidly growing demand in
the region. Diversifi cation of technologies (Criteria 11) appears,
nevertheless, also relevant for the developing countries in the
region, although initially it can be assured by the developed
countries such as Spain, which have a different weighting of
the criteria in the early stage of the cost reduction curve, in
particular Criteria 15 (environmental impact).
China. Due to the sheer volume of demand including for renew-
able energy sources, the exemplary recent approach to create
an institutional frame for renewables, and the nascent efforts
to create its own manufacturing base for the technology. This
region appears interesting despite not having the most optimal
solar resources and a larger distance between consumers and
suitable areas in the country (Huang, 2005).
Other countries/regions as compared to the previous two markets
(Mediterranean/Middle East and China) might have also their logic
to develop CSP, but they require additional arguments to concentrate
on in the second phase: Mexico
27
could gain interest from a strong
26
A detailed scenario analysis of the renewables needs and CSP needs,
in particular for the Mediterranean area and the Middle East, is carried
out by Trieb (2004).
27
Mexico’s long-term-prospects of solar electricity export (to the U.S.) are
less promising compared to North Africa and Middle East (to Europe)—be-
cause the U.S. itself has huge solar resources (irradiation and land) in
contrast to Europe.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
72
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
uptake of CSP in the Southwest United States or from a strong national
strategy for CSP. India, like China, is a market of its own, but is ham-
pered by the complexity of the decision levels that are manifested in
the current WB/GEF portfolio. A minimum requirement for this market
to be considered is a successful implementation of the corresponding
current WB/GEF project. South Africa is for the moment an isolated
market and has little real interest to develop CSP given the strong
role of coal. Possibly feed-water preheating in combination with coal
could be a viable strategy for this country, as well as combination
of existing low-effi ciency coal plants with solar.
12. What are the requirements on the composition of any future
portfolio for CSP in order to fi t the development towards the realisa-
tion of the CSP vision described in Chapter 6 (section 6.1)?
At a minimum four CSP plants should be promoted by the GEF
within the second phase of the cost reduction curve:
For the second
phase of the cost curve, it can be estimated from the above that for
the developing countries about 200 to 300 MW of solar thermal
power are to be installed by about 2015. Of this, about 90 MW
might be provided in phase 1 (at least two WB/GEF projects
and Algeria succeeding). The second phase should consist of—at
a minimum—another four projects in the Mediterranean/Middle
East region. Out of these projects, each one in the range of 30 to
50 MW, two might concentrate on the countries of phase 1, which
have most advanced in the development of the frame for renewables
and developed further their power sector expansion strategy to
include CSP. Another two projects might be built in Jordan and Iran,
which are to some degree advanced with their strategy, although
the interest of CSP for their power sector must be demonstrated in
detail. Additional small amounts of fi nancing would be required to
investigate CSP and prepare the grounds for further implementation
in other countries in the region. The total funding required for the
second phase of the cost reduction curve (developing countries
only) might be around
€
200 to
€
300 million.
6.7.2 Operational recommendations
13. Should a future engagement continue to promote ISCC? Should
it promote a broader range of technologies; if yes, which?
Promote a broader range of technologies (power cycle integration
and solar thermal collectors):
The ISCCS concept is an attractive
option for developing countries to include solar energy into the
existing power market expansion plans. On the other hand, it is
also reasonable to focus on parabolic trough technology, being
the most experienced CSP technology so far. However, in the
long run,
28
the promoted technology options should be wider
(see power cycle integration options in section 2.2.2 and solar
collector types in Annex 3), in order to spur further competition
and to adapt to individual needs/inquiries of the countries of
destination.
14. Which funding mechanisms appear as most suitable to promote
CSP in future? Should WB/GEF bundle forces with more actors to
reach a critical mass. In particular, how can the technology best
be promoted in developing countries?
Provide future grants for production (MWh) instead of investments
(MW):
It is also questioned whether an investment grant strategy
might provide the right frame for the market (see also fi nancing
mechanisms below). In particular, it must be emphasized that in
the current portfolio grants are given for investments and not for
production. It is therefore not assured that the solar plants effectively
produce over a larger number of years. Therefore feed-in-tariffs
with MWh instead of MW as funding basis should be considered
(criteria 12). In this context, we favor a discussion about operating
future CSP plants under the IPP scheme in suffi ciently liberalized
markets. The commitment of the plant operator would also be lever-
aged by the fact that the total plant fi nancing has to be provided.
The plant operator would get its electricity remuneration in a strong
currency (e.g. $/MWh), potentially with a GEF implementing
agency (e.g. the World Bank) as the electricity buyer. The GEF
implementing agency would in turn place a contract with the local
electricity supplier, reducing its fi nancing risk by paying a premium
on top of the local market price. This again would motivate the IPP
contractor to produce electricity in accordance with the electricity
price/demand.
In particular for the Mediterranean region funding mechanisms
based on electricity production are discussed:
28
And partially even for the short term (current portfolio) by including solar
tower or potentially a solar hybrid steam plant in the case of Mexico.
73
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
Global Market Initiative for Concentrating Solar Power (GMI):
GMI (2003)
29
describes an initiative to formulate a fair scheme
that accounts for both improved tariffs for clean energy gener-
ated in the developing countries and to allow a benefi t from
enhanced feed-in tariffs for energy that is imported into close-by
industrialized countries. According to GMI (2003), the fi nan-
cial cost gap can be further reduced through a blend of clean
development mechanisms (CDM such as carbon tax credits, if
bankable), and preferential fi nancing, such as the European
Union’s infrastructural support program, the Mediterranean
Development Aid (MEDA) Programme.
Financing Instruments for the Market Introduction of Solar Thermal
Power Plants—the Scenario Model Athene (DLR 2004):
DLR
(2004) describes with their ATHENE model a comprehensive ap-
proach regarding how project fi nancing can be assured through
the development of a fund for the market introduction of CSP.
Such a fund could be developed further later on to accompany
the introduction of phase 3 and 4 of the cost reduction curve.
This approach can provide guidance on how to develop, for
example, a Mediterranean/Middle East-centered fund. The aim
of the vision developed by DLR (2004) is, as described above, to
implement 5,000 MW CSP worldwide by 2015 and more than
40 GW by 2025. Several funding mechanisms are combined
in order to lower considerably the additional costs of initially
€
145 billion (required with a 15 percent internal rate of return).
Such a fund could provide, in analogy to feed-in tariffs such as
in Spain (for CSP) or Germany (for other types of renewables),
long-term power purchasing agreements in hard currency in such
a way that the risk perception due to the reliable PPA could be
signifi cantly reduced. As a consequence, the investors’ expected
internal rate of return of the projects will be reduced from 15
percent down to 8 percent.
30
Through such a mechanism alone,
the additional costs of the market introduction are calculated to
be lowered to about
€
12 billion. Comprehensive risk reduction
is provided in the form of government export and credit guaran-
tees as well as machine insurance and insurance against natural
disasters through the re-insurance branch. According to the fund
idea developed with the ATHENE model, the additional market
introduction costs are lowered to about
€
2.5 billion if the carbon
pricing is added, with a carbon price increasing from initially
7.5
€
/t CO
2
to 30
€
/t CO
2
in 2050. If every project receiving
fi nancing from the fund revolves a unique fee of
€
21 million
to the fund, the market introduction cost is lowered to
€
1.75
million. Under these conditions by 2015 and with 5,000 MW
installed power a price can be achieved that can be covered
from the electricity sales and carbon fi nancing. Starting in 2023
with an installed power of 20 GW, a cost level is reached that
covers cost also with conventional project fi nancing and carbon
fi nancing. Starting in 2030, solar power plants would also be,
according to the calculations, cost-competitive without carbon
fi nancing. It must be emphasized that the ATHENE approach is
a rather conservative approach to estimate cost competitiveness
(see also Chapter 2, section 2.1.2). If the market introduction
is realized according to the calculations of the ATHENE model,
the
€
1.75 billion in initial market fi nancing fl ows back to the
fund with an internal rate of return of 4 percent and will achieve
a surplus between 2020 and 2050 of about
€
8 billion. Such
revenues could be used to pay the initial market fi nancing
back or to increase, as an ex-post dividend, the internal rate
of return of the individual projects. If the carbon price would
be only 30 percent of the model estimates, the fund would still
revolve but without interest. For the implementation of the CSP
strategic goals, it is recommended that the GEF in the future
organize its CSP funding according to the above-mentioned
fund in order to reduce risk and thereby signifi cantly reduce
the technology’s market introduction costs. On the other hand,
the environmental and economic benefi t of the funding will be
signifi cantly enhanced by motivating the power producers to
produce MWh instead of MW.
29
GMI (2003) emphasizes that to some extent, the large tariff differences
between ostensibly cheap fossil-based bulk power and solar-generated
power are due to subsidies granted implicitly or explicitly for fossil fuel in
some countries. This infl ates the subsidies needed to cover the apparently
higher cost of CSP power. Therefore, access to favorable tariffs from solar
thermal electricity importers could be offered while reducing subsidies on
fossil power production in solar thermal electricity exporters to minimize
net funding.
30
Given the fact that this is not equity interest but project IRR with mixed
fi nancing (debt and equity), the used interest rate of 15 percent appears
rather high. Nevertheless, the fi nanciers’ expectations on the IRR directly
depends on risk perception. All mentioned fi nancing risks can signifi cantly
be reduced by such a fund in a way that 8 percent (in real terms) appears
as a realistic if not conservative assumption.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
74
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
15. What amount of support is necessary for any following
step?
Necessary GEF (and other donor) CSP engagement accounts to
$44 million on an annual average up to around 2025:
Under the
assumption that 35 percent of the CSP installations by 2025 will
be installed and operated in developing countries, the cumulative
subsidies would account to
€
875 million
31
, or $1.12 billion.
32
If
it is further assumed that 30 percent of this amount will be borne
by countries like Algeria from its own national means, an amount
of
€
610 million ($786 million) has to be fi nanced by international
funding. If the GEF is supposed to fi nance this part, on an aver-
age $44 million of annual CSP funding would be necessary. This
includes CO
2
emission trading (through CDM). In case the CO
2
emission trade is not taken into account, the necessary annual
average CSP funding amounts to $189 million.
16. What could be the potential GEF engagement in case of
reduced available CSP funding means?
Potential GEF engagement in case of reduced available CSP
funding means:
Although the original OP 7 objectives consider as
likely decades for the promotion of the target technologies with a
considerable annual funding, all-in-all the grants really available
from the GEF fund for future CSP development stay behind initial
expectations and the estimated requirements. In case the required
large-scale funding (Criteria 8) exceeds the fi nancial perspectives
of the GEF, we suggest the following two alternatives:
The GEF should try to join forces in the fi eld of renewable en-
ergy deployment in developing countries in order to establish
such an above-mentioned fund with the participation of differ-
ent stakeholders. Potential co-funding organizations are export
and development banks like KfW, JBIC, African Development
Bank, Asian Development Bank, and national development aid
programs, especially if allowing for the promotion of RES.
33
In the case of signifi cantly reduced fi nancial means for future
CSP projects in combination with the wish of the WB/GEF to
support further this important technology, the following technol-
ogy lines (alternative to the ISCC) concept might be considered
(see also Chapter 2, section 2.2):
o Feed-water preheating in fossil steam plants (approximate
invest: $10 million for 10 MWe): also promoting other than
parabolic trough collector types (e.g. tower, dish, Fresnel)
by a technology-unspecifi c bidding procedure. Feed-water
preheating leads to good solar effi ciencies, good ratio of
funding and solar-MWh because of reduced investment.
Existing plant (infrastructure) might be used.
o Small-scale solar combined heat and power plants (heat
for absorption chillers (e.g. air conditioning), process heat
or sea water desalination (the latter becoming increasingly
important in many countries with good solar resources).
o Industrial process heat applications of 200–1,000 kW
th
(based solar concentrators).
For the implementation of such small-scale CSP projects, the
following tendering strategy might be interesting. Preliminarily, a
set of criteria (compare also criteria in Table 7) to be met by the
projects have to be defi ned by the WB/GEF. For example:
o Multiplication effect (the project suggestion should make clear
that it is a pilot project that will induce several successors of
its kind)
o Environmental benefi t
o Cost-effective use of GEF-funding (possibly based on a cri-
terion like solar MWh per $)
o Social benefi t (the project should prove that it will have a
positive impact on social and economic aspects)
31
Under the assumption of a project IRR of 8 percent without revolving
fee of 21 million
€
.
32
Exchange rate (May 10, 2005)
€
1 = $1.2835.
33
German Federal Ministry for Economic Cooperation and Development
(BMZ)/KfW Entwicklungsbank
Special Facility for Renewable Energies and
Energy Effi ciency
(budget of
€
500 million over fi ve years for soft loans for
RES projects in developing countries.)
75
C
HAPTER
6 – S
HORT
-
AND
LONG
-
TERM
RECOMMENDATIONS
FOR
THE
WB/GEF
STRATEGY
FOR
CSP
IN
THE
CONTEXT
OF
A
LONG
-
TERM
VISION
FOR
CSP
Based on such criteria, bidders are invited to present their project
ideas, without limitations concerning the collector technology or
the heat usage (power, heat, cooling etc.), without limitations
concerning countries, and possibly even without limitations
concerning the budget.
34
Possible technology options are
given in Chapter 2 (section 2.2) and with respect to collector
technologies in Annex 2. Possible candidate countries might be
any country with a long-term interest in CSP technology, e.g.
Mediterranean countries or China.
This type of business concept could also be applied based on
the currently available funding if one or two projects of the current
ISCCS portfolio might not come to successful implementation.
34
Depending on the available budget, more capital-intensive power op-
tions like SEGS plants could be favored.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
76
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
77
BMU (German Ministry for the Environment, Nature Conservation
and Nuclear Safety). 2004. “International Action Programme
of the “Renewables 2004.” International Conference for Renew-
able Energies, Bonn, Germany, August 30, 2004.
BMU (German Ministry for the Environment, Nature Conservation
and Nuclear Safety). Personal communication from Ludger
Lorych.
Bonn International Conference for Renewables. 2004.
Con-
ference Report. Outcomes & Documentation – Political
Declaration / International Action Programme/Policy Rec-
ommendations for Renewable Energies
, Conference Sec-
retariat, Deutsche Gesellschaft für Technische Zusam-
menarbeit (GTZ), Bonn, Germany, June 1–4, 2004.
www.renewables2004.de
Criqui, P., and others. 2003.
Greenhouse Gas Reduction Pathways
in the UNFCCC Process up to 2025—Technical Report
. Study
Contract: B4-3040/2001/325703/MAR/E.1 for the DG
Environment.
Dersch, J., and others. 2002. “Trough integration into power
plants—a study on the performance and economy of in-
tegrated solar combined cycle systems.” Proceedings of
11th SolarPACES International Symposium on Solar Thermal
Concentrating Technologies, Zürich, Switzerland, September
4–6, 2002.
DLR (German Aerospace Center). 2004. “Financing Instruments for
the Market Introduction of STTPs—Scenario Model ‘Athene.’”
BMU-funded study SOKRATES, December 2001–December
2003, Final Report 2004.
DLR and others. 2005.
European Concentrated Solar Thermal
Road-Mapping (ECOSTAR)
. Pitz-Paal, R.; Jürgen Dersch, J. and
Milow, B. (eds). EU-funded study SES6-CT-2003-502578,
December 2003–February 2005. Stuttgart: Deutsches Zentrum
für Luft- und Raumfahrt e.V. DLR.
Enermodal. 1999.
Cost Reduction Study for Solar Thermal Power
Plants
. Kitchener, Ontario: Enermodal Engineering Limited.
Gelil, I.A. 2002. “Energy Situation in Egypt, Effi ciency Perspec-
tives.” Paper presented at the Egypt Energy Day. World Energy
Council WEC Executive Assembly, Cairo, 24 Oct. 2002.
(http://www.worldenergy.org/wec-geis/global/downloads/
eacairo/prsn001024Gelil.pdf)
Häussermann, V. 2005. “General risks involved with CSP Invest-
ments – View from Investors Perspective.” Paper presented at
the World bank/GEF Seminar on CSP Projects, Washington,
D.C., April 20, 2005.
IEA (International Energy Agency). 2000.
Experience Curves for
Energy Technology Policy.
(http://www.iea.org/textbase/
nppdf/free/2000/curve2000.pdf)
IEA (International Energy Agency): 2003.
World Energy Investment
Outlook.
Paris: IEA.
IEA (International Energy Agency). 2004.
World Energy Outlook
2004
. Paris: IEA.
IPCC (Intergovernmental Panel on Climate Change). 2000.
Meth-
odological and Technological Issues in Technology Transfer.
Cambridge: Cambridge University Press.
R
E F E R E N C E S
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
78
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Duke, R. 2002.
Clean Energy Technologies Buydowns: Eco-
nomic Theory, Analytic Tools and the Photovoltaics Case
. Ph.
D. dissertation presented to the Faculty of Princeton University,
November 2002.
GEF. “Operational Program number 7—Reducing the long-term
costs of low greenhouse gas-emitting energy technologies.”
(www.gefweb.org)
Geyer, M. 2005. “Role of CSP Market Deployment in Developing
Countries for the Future CSP Development.” Paper presented at
the World Bank/GEF Seminar on CSP Projects, Washington,
D.C., April 20, 2005.
Global Market Initiative (GMI). (http://www.solarpaces.org/GMI.
HTM)
Greenpeace/ESTIA. 2003.
Solar Thermal Power 2020—Ex-
ploiting the Heat from the Sun to Combat Climate Change
.
Amsterdam/Birmingham: Greenpeace/European Solar Thermal
Power Industry Association (ESTIA).
Huang, Ming. 2005. “China and CSP activities.” Paper presented
at the Worldbank/GEF Seminar on CSP Projects, Washington,
D.C., April 20, 2005.
Kearney, D., and H. Price. Forthcoming. “Recent Advances in
Parabolic Trough Solar Power Plant Technology.”
Lawrence-Pfl eeger, S. and others. 2003. “Facilitating technology
transfer of federally funded R&D.” Arlington, VA: RAND Science
and Technology Policy Institute.
Mariyappan, J., and D. Anderson. 2001. “Thematic Review of GEF-Fi-
nanced Solar Thermal Projects.” Monitoring and Evaluation Working
Paper 7. Washington, DC: Global Environment Facility GEF.
http://thegef.org/ResultsandImpact/Monitoring___Evalua-
tion/Evaluationstudies/WP_7.pdf
Ming, H. 2005. “China and CSP activities.” Paper presented at
the Workshop on CSP promotion strategy of the GEF and the
World Bank, Washington D.C., April 20, 2005.
Morin, G., and others. 2004. “Plug-in Strategy for Market Intro-
duction of Fresnel-Collectors.” Proceedings of 12th SolarPACES
International Symposium on Solar Thermal Concentrating Tech-
nologies, Oaxaca, Mexico, October 6–8, 2004.
Pacudan, R., and M.K. Lee. 2003. “Overview of the CDM
market and CER prices.” Roskilde: UNEP RISØ Cen-
tre on Energy, Climate and Sustainable Development.
http://www.rtcc.org/html/articles/cdm/unep-cdm.htm
PCAST (The President’s Council of Advisors on Science and
Technology). 2003.
Report on Technology Transfer of Federally
Funded R&D – Findings and Proposed Actions
. Washington,
DC: Executive Offi ce of The President’s Council of Advisors on
Science and Technology
Philibert, C. 2004.
International Energy Technology Collaboration
and Climate Change Mitigation, Case Study 1: Concentrating
Solar Power Technologies
. Paris: International Energy Agency.
Pilkington Solar International GmbH. 1996.
Status Report on Solar
Trough Plants—Experience, prospects and recommendations to
overcome market barriers of parabolic trough collector power
plant technology
, Koeln: Pilkington Solar International GmbH.
Price, H. 2005. “Status of CSP Technology and CSP Projects in the
US.”. Presentation at the WB/GEF Workshop on Solar Thermal
Power Generation, Washington D.C., March 18, 2005.
Quaschning, V.:
Projektion der Kosten und Anteile von Solarstrom
zur Stromversorgung im Jahr 2025
, Tagungsband des 20.
Symposiums Photovoltaische Solarenergie—Kloster Banz, Bad
Staffelstein 9.–11. März 2005. Regensburg: Ostbayerisches
Technologie-Transfer-Institut e.V. (OTTI), Page 448–453.
Ragwitz, M. Fraunhofer. 2005. Personal communication.
Sargent and Lundy. 2003.
Assessment of Parabolic Trough and
Power Tower Solar Technology Cost and Performance Forecasts.
Chicago: Sargent and Lundy LLC Consulting Group.
Sargent and Lundy. 2004. Feasibility Study of Integrated Solar
Combined Cycle System (ISCCS) Mexico
. Report prepared for
79
R
EFERENCES
the World Bank. Chicago: Sargent and Lundy LLC Consulting
Group.
Sargent and Lundy. 2006.
Evaluatgion Study of the Integrated Solar
Combined Cycle System (ISCCS) Mexico
. Report prepared for
the World Bank. Chicago: Sargent and Lundy LLC Consulting
Group.
Science&Vie. 2005. “Eoliennes—le grand vent de la maturité.”
N°1053, p. 94–98, Juin 2005.
Spencer Management Associates. 2000.
Final Report—Mexico
Feasibility Study for an Integrated Solar Combined Cycle System
(ISCCS)
. Report prepared for the World Bank. Diablo, CA:
Spencer Management Associates.
STAP (Scientifi c and Technical Advisory Panel of the GEF). 2003.
Report of the STAP Brainstorming Session on Operational Pro-
gram 7
. Global Environment Facility, Washington D.C.
,
March
10–11, 2003.
STAP. 2004.
“Reducing the long term costs of low greenhouse
gas-emitting energy
.” Global Environment Facility, Washington,
DC: GEF.
Stein, W. 2000.
The Integration and Optimisation of Solar Energy
into Conventional Power Plants.
Masters Thesis, Sydney: Uni-
versity of New South Wales.
Trieb, F. 2005.
Concentrating Solar Power for the Mediter-
ranean Region. Study commissioned by Federal Ministry
for the Environment, Nature Conservation and Nucle-
ar Safety. Stuttgart: German Aerospace Center (DLR).
http://www.dlr.de/tt/med-csp
World Bank. 2004. Global Environment Facility, Solar Thermal
Portfolio: A Status Report
. Prepared for the GEF Council May
19–21, 2004.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
80
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
81
Algeria (Hassi R’mel)
Australia(Liddell)
Iran(Yazd)
Israel (Asharim)
South Africa (Upington)
Spain (Andasol 1 & 2)
Spain (PS10)
USA (Nevada)
USA (Arizona)
A
N N E X
1
C
H A R A C T E R I Z A T I O N
O F
T H E
S
T A T U S
O F
I
M P O R T A N T
O
N G O I N G
CSP P
R O J E C T S
W
O R L D W I D E
(D
ESCRIPTION
OF
EACH
PROJECT
ACCORDING
TO
A
SET
OF
CRITERIA
)
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
82
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Country/Location Algeria/Hassi
R’mel
Type of technology
Parabolic trough integrated with a combined cycle plant
Technical parameters
130 MW combined cycle, with a gas turbine power on the order of 80 MW and a 75 MW steam turbine. 25 MW solar fi eld, requiring a surface of around 180,000 m
2
of
parabolic mirrors. Addition of a desalination plant fore-seen. Originally the following confi gurations were considered: Size 150 MW (combined cycle 107 MW net, solar fi eld
43.6 MW net).
Business model
BEA-NEAL partnership guaranteeing one-third of the capital, beyond which the remainder would be guaranteed by a foreign investor at a minimum of 51 percent and the
EIB with a profi t-sharing loan (QUASI EQUITY). BUILD OWN OPERATE contract or BOO/BOT, “non-recourse.” Sonatrach will buy the electricity (NEAL: a company set up by
SONATRACH, SONELGAZ and SIM to carry out projects that make use of renewable en-ergy. Sonatrach: National company for the production, transport and commercializa
tion of hydrocarbons. Sonel-gaz: Electricity and Gas Company of Algeria. BEA: Banque Extérieure d’Algérie).
Liability provisions
Status of plant
Invitation for expressions of interest launched on June 8, 2004. The publication of the bidding was originally planned for September 2004, with contract award December
2004 and project start by September 2005. A Request for Proposals was issued in May 2005 by the New Energy Algeria (NEAL) to construct, fi nance, exploit, and
maintain a hybrid solar/gas power plant of 150 MW at the site of Hassi R’mel. A visit to the site and the data room took place on July 4, 2005. The interested consortia
have (until October 5, 2005) been invited to submit a technical proposal. An investor has been retained for construction, exploitation, and commercialization.
Expected project time schedule
Expected start of construction 2006/2007.
Project developer/Prequalifi ed devel-opers
NEAL is the project developer. Following the invitation for expressions of interest, the following companies declared their interest: CME and General Electric (USA), ACS
COBRA (Spain), LAVALLIN (Canada), SIEMENS and Solar Millennium (Germany), MITSUI-JGC (Japan), ALSTOM (France), BLACK & VEATCH (Great Britain) and BRC
(Algeria).
Financing structure
Aggregate investment: $177 million (of which EPC $143.9M, intercalary interests $12M, preliminary costs $0.5M, contingency $4.3M, customs taxes $5.3M).
Investments of nearly $140 million will be contributed by the German investment bank KFW in preferential rate loans and the European Investment Bank (EIB). The BEA
will syndicate with the EIB the portion in Dinars.
Final owner of plant
Foreign investor or consortium
Institutional frame for renewables in host
Algeria has set up a national program for the promotion of renewable energy sources in the frame of a sus-tainable development up to 2020 (5-years program) (Law
N° country 04-09 of 14 August 2004 relative to the Promo-tion of Renewable Energy Sources in the frame of Sustainable Development).
Quota system for renewable energy sources with a tender procedure (The promotion shall occur “in coherence with the principle of competitiveness”). Later on, green
certifi cates for renewable energy sources are envisaged but no structure for Green certifi cates is in place so far.
The decree N° 04-92 of 25 March 2004 “on the costs of diversifi cation” aims at bringing the share of electricity produced by the renewable energies to 5 percent of
the total electricity to be produced by 2010, by introducing incentive measures for all the branches of energy used to produce electricity. Premiums for each kWh from
renew ables and cogeneration (see below), including an obligation to the network operator to connect renewable energy sources to the grid within economic acceptable
limits. In accordance with the law N° 02- 01 of February 5, 2002 (art. 98), the costs of diversifi cation are integrated in the tariffs. In addition: creation of a “national
observatory for the promotion of renewable energy sources.”
83
A
NNEX
1
–
C
HARACTERIZATION
OF
THE
S
TATUS
OF
I
MPORTANT
O
NGOING
CSP P
ROJECTS
W
ORLDWIDE
Type of renewables
Premiums
(expressed as a percentage of the electricity price per kWh defi ned by the market operator)
Electricity from solar thermal – natural 200 percent if the contribution of solar energy represents a minimum of 25 percent of the total primary energy,180 percent
gas hybrid plants
if the solar share is 20 to 25 percent, 160 percent if the solar share is 15 to 20 percent, 140 percent if the solar
share is 10 to 15 percent,100 percent if the solar share is 5 to percent, no premium below 5 percent.
Electricity from solar only
300 percent
(PV or solar thermal)
Electricity from wastes
200 percent
Hydropower
100
percent
Wind power
300 percent
CHP
160 percent (the production capacities should not exceed 50 MW).
Source: Executive Decree N° 04-92 of 25 March 2004 relative to the diversifi cation costs of electricity production (Articles 12–17).
In the case of the presently planned plant at Hassi R’mel, the solar output is expected to be 11 percent of the total plant output: This would lead to a production premium
of 140 percent on the conventional price estimated at 2.2 c/kWh.
Institutional frame in host country
Electricity is currently growing at around 4 percent a year. The additional requirements in production capacity are estimated at 6,000 MW for the period mentioned. The law
for the electricity market
02-01 on electricity and distribution of gas from February 2002 has liberalized the electricity sector by opening production and distribution to competition. This law is in the
perspective of an interconnected and liberalized Euro-Maghreb market comprising the neighbors of Algeria and the closest European countries (signature of the Rome agree
ment in December 2003 by three Maghreb countries and the European Commission in view of a common electricity market starting 2006). This
law also foresees the integration of renewable energy sources in the energy mix of the country.
In this perspective, Algeria is following up a “Project 2000 MW” comprised of three elements:
a fi rst set of power plants destined to the internal market with a capacity of 800 MW;
a second set of power plants destined to the export market with a capacity of 1,200 MW;
under-sea connection cables with a minimum capacity of 2,000 MW linking Algeria to Spain to reach the European markets.
IIn addition, Algeria investigates the possibility of a second project of 500 to 1,000 MW destined also to electricity export via an under-sea cable that links Algeria to Italy
(Sardinia).
Key governmental institutions and
The contribution of revenues from oil and natural gas was 55 percent of the state budget, 97 percent of foreign currency infl ow, and about 40 percent of GDP. Algeria has
their interests
an interest to export gas, but also a need to diversify the economy. Ninety-fi ve percent of Algeria’s exports go to Europe.
One main objective for Algeria, being a producer for gas, is to export this energy carrier, in particular to Europe (Algeria envisages increasing gas exports to 100 billion m
3
in 2010 and to 120 billion m
3
in 2020. As Europe, for diversifi cation reasons has set limits on gas imports from Algeria, exporting gas through the generation of electricity
constitutes a second road to exporting gas. Combining with solar helps to make the electricity exports more acceptable to Europe in the view of Algeria.
During the last two decades, Algeria has been suffering from droughts and a lack in water due to both the droughts and the increase in the Northern population, living
standards, and its industrialization. For this reason, water desalination becomes an important issue to which solar thermal power plants could provide solutions.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
84
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Tariff structure in country
The tariffs are administered in the expectation of the electricity market liberalization.
Near-term strategy for CSP in the country
Algeria has considered, in addition to the presently planned ISCCS plant, the following two options, but no con-crete plans exist for the moment: (1) Size 306 MW (com
bined cycle 258.8 MW net, solar fi eld 54.1 MW net. (2) Size 400 MW (combined cycle 363.4 MW net, solar fi eld 71 MW net).
Otherwise, since the launch of the electricity market reform in 2002, the following two IPP projects are in the phase of realization:
Project Kahrama at Arzew 321 MW: combined cycle unit coupled to a seawater desalination unit of 90,000 m
3
/day. Total project cost is $400 million. Financing is
assured to 80 percent by the company Black & Veatch and to 20 percent by the Algerian Energy Company (AEC), a mixed Algerian company between Sonatrach and
Sonelgaz.
Project Sharikat Kahraba Skikda (SKS) 824 MW: combined cycle unit. Total project cost is $460 million. Financing is assured to 20 percent by the company SNC
Lavallin and to 80 percent by the Algerian Energy Company (AEC).
The operation for the two projects is expected for 2005. In addition, for the following project a call for a joint venture has been launched:
Project de Hadjerat Nouss – bidding call – 1,400 MW: interest was manifested from two main international groups, the Canadian group SNS Lavallin and the German
company Siemens, which have been prequalifi ed on a technical level. Financing shall be assured through a minimum foreign investment of 51 percent and the remain
der from public Algerian companies (SONELGAZ, SONATRACH and AEC).
Project Sharikat Kahraba Berrouaghia 400–500 MW (EPC won by Siemens).
View of the country on a mid-term
Algeria envisages 500 MW generating power from renewables for local use in 2010 and further strongly in-creasing power generation both for local use and for export
strategy for CSP with possible future
from 2010 to 2020. The fi rst electric cables linking Algeria and Europe are currently investigated or in the starting phase.
options (5–10 years)
Year
Renewable Energy Capacities (MW)
Local
Export
2010
500
200
2015
1,000
400
2020
1,500
6,000
The fi rst 500 MW for local production are supposed to be 400 MW solar thermal capacity (corresponding to 2,200 MW hybrid plants, and to 100 MW wind energy and other renewable energy sources. Investment costs
will be of the order of $2 billion. After 2015, Algeria believes that it will be possible to construct solar-only CSP, as they will be competitive with the combined cycle plants.
85
A
NNEX
1
–
C
HARACTERIZATION
OF
THE
S
TATUS
OF
I
MPORTANT
O
NGOING
CSP P
ROJECTS
W
ORLDWIDE
Country/Location Australia,
Liddell
Type of technology
Linear Fresnel preheating feedwater for large coal-fi red power station
Technical parameters
A staged project with up to 135,000 m
2
to provide 285°C/70 bar steam to the feedwater cycle of a 500 MW steam turbine. Solar Heat and Power Pty Ltd. (SHP)
calculates this is equivalent to 38 MWe.
Business model
EPC for solar fi eld
Liability provisions
Status of plant
First 1 MW
th
completed, and contract for 2
nd
stage in process of being signed
Expected project time schedule
38 MWe operating by 2007
Project developer/Prequalifi ed developers
Solar Heat and Power Pty Ltd. (SHP)
Financing structure
Grants from Australian Govt. where available plus capital raised through semi-public offering
Final owner of plant
Macquarie Generation
Institutional frame in host country
The State of New South Wales (NSW)—where this project is located—has a deregulated electricity structure, with generation supply bid competitively into a pool. Genera
tors are separate organizations to the retailers, distributors, and transmission companies, so power purchase agreements for the generated electricity are required. The coun
try has in place a mandatory renewable energy target (MRET), which requires electricity retailers to purchase renewable energy certifi cates equivalent to a small proportion
of their sales each year. These are purchased competitively; certifi cate prices are presently around the AU3.5c/kWh level. With pool prices around the same level, the
maximum price available to renewables projects from this scheme is around AU7-8c/kWh. In the state of NSW, there is also the opportunity to gain NGACs on top of the
RECs worth approximately AU1c/kWh. An energy white paper was released by the Australian Government in late 2004 that offers support through grants for both renew
ables R&D and large-scale energy projects, which have a signifi cantly reduced GHG signature.
Key governmental institutions and
Australian Greenhouse Offi ce; Offi ce of the Renewable Energy Regulator; NSW Department of Energy, Utilities and Sustainability.
their interests
Tariff structure in country
For most of the country, electricity is sold into a pool with successful bidders receiving the price of the last successful bid. In the main electricity markets, this means pool
prices of around AU3.5c/kWh for most of the year. Most organizations use a combination of pool and contract pricing.
Near-term strategy for CSP in the country
There is no specifi c target or goal for CSP in the country. Renewables are presently bid against each other, so it is the cheapest renewable project that proceeds. Over the
three years of operation so far, the main winners have been wind, solar hot water, and hydro, and to a lesser extent landfi ll biogas.
View of the country on a mid-term
The abundant availability of cheap good quality coal, followed by natural gas, makes it very diffi cult for renewables to compete in Australia without a renewables program
strategy for CSP with possible future
such as MRET. Because MRET essentially means only the cheapest renewable project will proceed, CSP will have a diffi cult time until it can meet the price of wind, which is
options (5-10 years)
presently around AU7-8c/kWh. There still appears to be availability of good wind sites. Good solar sites are abundant, and hybridizing with coal-fi red plants (and to a lesser
extent gas-fi red plants) seems the most attractive proposition in the near term. Long-term thermal storage is being actively investigated, which could then open up many
opportunities as the reliance on nearby fossil fuel would no longer be a limitation.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
86
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Country/Location Iran/Yazd
Type of technology
ISCCS
Technical parameters
Total plant capacity proposed 430 MWe; Peak solar input 67 MWe; air cooled condenser; Annual DNI 2,500kWh/m
2
/yr
Business model (as per 2002 pro-posal
Intended to repower existing gas turbines with extension owned by IPP
when GEF funding had been anticipated)
Status of plant
Feasibility study undertaken; Consultancy Services let to Moshanir Power Engineering Consultants January 2001 for upgrading 2 GT’s to a combined cycle power plant and
adding a solar fi eld with aperture area of 366,240 m
2
. At this stage, tender documents have been prepared.
Expected project time schedule
Would like to progress asap
Project developer
Information not supplied
Financing structure
Total project cost of $322 million (incl existing GT’s $67 million) comprising $150 million Iranian Ministry of Energy, $50 million GEF (note this is not a GEF project),
$55 million balance from soft loans (note $10 million imbalance)
Final owner of plant
Information not supplied
Key governmental institutions
The Islamic Republic of Iran is interested in large-scale exploitation of its solar resource by CSP. The principle rationale is the government’s strategic goal of diversifi cation
and their interests
of its power production base and the promulgation of the country’s oil and gas reserves. The Iranian Power Development Company (IPDC) has and will play a key role in
any CSP plant in Iran.
Tariff structure in country
Information not supplied
Near-term strategy for CSP in the country
The country has indicated its strong interest by initiating preparatory work toward a large CSP plant. Previously Iran has helped sponsor (by the Energy Ministry and the
Electric Power Research Center, now named NIROO Research Institute) and organize the “First German-Iranian Seminar on Solar Thermal Power Plants” (1993), a joint
Iranian-German Expert Group on Solar Thermal Power conducted a concept study for a 100 MW Solar Thermal Power Plant. In 1996. IPDC contacted GEF to investigate the
possibility of support. GEF responded that a more thorough feasibility study was needed as the basis for potential commitment of grant support. This study was carried out
by NIROO, FLABEG Solar, and Fichtner Solar. Of a number of sites, it determined Yazd to be preferred with 2511kWh/m
2
/yr DNI. Approximately 9km
2
of land has already
been purchased by the Yazd utility. Water is limited and thus dry cooling was selected. Three older 64 MW gas turbines (KWU V93.1) and two new Alstom gas turbines
(PG9171E) have already been installed and put into operation in 2000. A consultancy has been awarded to convert 2 GT’s into an ISCCS. The feasibility study showed an
investment of $115 million would result in an additional net electricity generation of 964 GWh/yr and upgrade the plant effi ciency from 32.2 percent to 50.2 percent. The
solar fi eld, costing around $138 million, would further improve annual average effi ciency to 53.1 percent.
View of the country on a mid-term
Iran is one of the world’s largest players in the petroleum market. With global concern over medium-term supplies
strategy for CSP with possible future
of petroleum, prices on the world market are high. It is in the national interest to conserve domestic supplies so more is available for export. CSP offers a large opportunity
options (5–10 years)
to reduce domestic consumption of petroleum products, as well as diversifying the resource base. There is interest in the job creation possibilities resulting from CSP plants
and a local CSP industry.
87
A
NNEX
1
–
C
HARACTERIZATION
OF
THE
S
TATUS
OF
I
MPORTANT
O
NGOING
CSP P
ROJECTS
W
ORLDWIDE
Country/Location Israel,
Asharim
Type of technology
Trough (oil) Rankine cycle
Technical parameters
100 MW initially, up to 500 MW if fi rst successful.
Business model
IPP in a BOO arrangement; PPA with IEC.
Status of plant
Preferred site selected.
Expected project time schedule
Information not supplied.
Project responsibility
Israel Electric Company
Financing structure
$250 million for 100 MW, expected to yield LEC of 9c/kWh
Final owner of plant
IPP
Key governmental institutions and
Public Utilities Authority (Electricity) responsible for setting strategic targets such as the national need for CSP to be developed. Israel Electric their interests Authority (IEA) is
a special commission that has responsibility for approving market price. When a new technology such as CSP is suggested to be integrated for strategic reasons, the cost
of CSP must be included in the total cost mix, and the marginal additional cost spread over the generation mix with only a small price increase to the public. The National
Council for Planning and Construction provides authority for plants such as this to proceed.
Tariff structure in country
The Public Utilities Authority has decided to issue premiums for the production of renewable electricity.
Near-term strategy for CSP in the country
It is reported that the IEC approved in principle the construction of a 100 MW CSP plant with a $250 million investment cost. The IEC approved this on the basis that IEA
approves additional higher cost to the public.
View of the country on a mid-term
Information not supplied
strategy for CSP with possible future
options (5–10 years)
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
88
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Country/Location
South Africa, near Upington in the Northern Cape Province
Type of technology
Solar tower
Technical parameters (installed MW, etc.)
Gross electrical rating: 110 MWe
Net output approximately 100 MWe
Plant design life 35 years
Annual DNI = 2.95 MWh/m
2
Business model (EPC, separate EPC
Not yet determined.
for solar and fossil, IPP)
Liability provisions (in particular for hybrid)
Not yet determined.
Status of plant
ESCOM undertook a prefeasibility study on CSP technologies. In the fi rst task, fourteen CSP technologies and/or variations were to be studied further. Information on the
technologies was compiled from published literature and where possible from demonstration facilities or operational plants. The technologies were screened in terms of a list
of selection criteria. The screening process identifi ed two technologies, solar trough and central receiver technologies, as possible near-term options to be evaluated further.
The second task comprised the compilation of a typical meteorological year (TMY) data fi le for a reference site, as well conducting a strategic environmental assessment
(SEA) for the Northern Cape Province of South Africa as the most suitable location for possible CSP plants.
Using Upington as a reference site for the plant locations, annual simulation models were developed to predict the performance and costs of the two CSP technologies,
identifi ed through the screening process as task 3. Pilot plant designs were developed around 100 MWe systems and optimized to provide the lowest levelized energy cost
(LEC) for the location. Long-term cases were also evaluated to provide an indication of the lowest possible energy costs that could be expected with future development.
ESCOM also investigated what industry, mainly South African and to some extent international, could supply on a cost-effective basis toward the construction of a solar ther
mal plant. One of the major fi ndings that emerged was that SA industry was not geared to manufacture troughs for a one-off plant and with no guarantees of further plants
industry felt it far to risky to invest in production facilities for a one-off plant. However, it emerged that there were less risks associated with the local manufacture of a
central receiver. This infl uenced ESCOM’s decision toward the further investigation into central receiver option.
ESCOM furthermore undertook a full technical engineering study, based on conditions for the Upington region.
Expected project time schedule
To be established.
Project developer/Prequalifi ed developers
Likely to be ESCOM.
Financing structure
To be established.
Final owner of plant
To be established.
Institutional frame in host country
With the adoption of the white paper on energy policy of 1998, the SA government has sought to integrate its broad policy frameworks, with the need to provide policy
stability for investors, suppliers, and consumers in the sector. Recognizing the potential role that the energy sector could play in achieving national growth and development
aims, the following fi ve key objectives are identifi ed in the white paper:
Increasing access to affordable energy services;
Improving energy governance;
Stimulating economic development;
89
A
NNEX
1
–
C
HARACTERIZATION
OF
THE
S
TATUS
OF
I
MPORTANT
O
NGOING
CSP P
ROJECTS
W
ORLDWIDE
Managing energy-related environmental impacts;
Securing supply through diversity.
These objectives refl ect the need for achieving a balance between sustainable development, economic growth, environmental management, and security of supply issues in
the energy sector. Fundamental to achieving these objectives is the creation of a suitable environment for encouraging competition, coupled with focused regulation to
ensure a self-sustaining industry ultimately serving to benefi t the broader economy and energy consumers.
In September 2004, the updated National Integrated Resource Plan (NIRP) was published by the National Electricity Regulator (NER). This is a process of planning that is
revised every year based on the projected demand.
Capacity needs
: South Africa is expected to experience sustained growth in electricity demand under-pinned by growth in industrial, mining, and commercial sectors.
The NIRP has estimated that about 2,640 MW of new peaking generation capacity will be required between 2006 and 2010. These require-ments for new capacity are
over and above the need to return to service the mothballed coal-fi red power plants as currently planned by ESCOM.
The key strategic objectives of the SA government pertaining to meeting the new peaking generating capacity are:
Meeting new generation capacity requirements;
Introducing private sector participation in the generation sector;
Enhancing security of supply through fuel diversity;
Accessing private sector fi nancing and informing policy decisions on public versus private sector procurement;
Enhancing black economic empowerment (BEE) in the energy sector; and
Maintaining low-cost electricity.
The white paper on renewable energy was approved in November 2003 by the SA cabinet. The aim of the policy is to create the conditions for the development and com
mercial implementation of renewable energy. This includes:
Ensuring that economically feasible technologies and applications are implemented through the development and implementation of an appropriate program.
Ensuring that an equitable level of national resources are invested in renewable technologies given their potential and compared to investments in other energy supply
options.
Addressing constraints on the development of the renewable energy industry.
The Department of Minerals and Energy has translated this white paper on renewable energy into a practical strategy with clear implementation plans for 2004–13. Renew
able energy will be used for power generation to the grid and for water heating. Non-grid applications will be integrated in the electrifi cation program and research and
development. Bio-fuel technologies will be initiated as part of the strategy.
It is in this context that the SA government is committed to this renewable energy policy document, which is intended to give much needed thrust to renewable energy. This
policy envisages a range of measures to bring about integration of renewable energies into the mainstream energy economy.
To achieve this aim, the government is setting as its target 10,000 GWh (0.8 Mtoe) renewable energy contribution to fi nal energy consumption by 2013, to be produced
mainly from biomass, wind, solar, and small-scale hydro. The renewable energy is to be utilized for power generation and non-electric technologies such as solar water
heating and bio-fuels. This is approximately 4 percent (1,667 MW) of the projected electricity demand for 2013 (41,539 MW).
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
90
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Some of the main benefi ts of the renewable energy white paper will be renewable energy for rural com-munities, far from the national electricity grid, remote schools and
clinics, energy for rural water supply and desalination, and solar passive-designed housing and solar water heating for households in urban and rural settings and commercial
applications. Large-scale utilization of renewable energy will also reduce the emissions of carbon dioxide, thus contributing to an improved environment both locally and
worldwide.
Key governmental institutions and
The key institutions that infl uence the electricity sector, including ESCOM in adopting new technologies such as solar thermal systems are:
their interests
The Department of Minerals and Energy (DME). The DME establishes energy policy and legislation as well as provides direction, through planning processes, as to what
course of action is needed to meet energy policy objectives.
The Department of Science & Technology (DST). The DST together with DME has formulated an energy research and development strategy for SA. One of the areas identi-
fi ed for R&D is renewable energy.
Department of Public Enterprises. ESCOM, as a public enterprise, reports directly to this department.
The National Electricity Regulator (NER). The NER sets tariff prices as well as granting licenses for electricity production. Any new electricity generation facility will need to
ensure that it complies with regulations as managed by the NER.
Expected LEC (in SA Rands)
In the prefeasability study, full component costs & maintenance cost fi gures were determined for the base case plants. These fi gures were used to calculate the cost of
production over the plants’ lifetimes. A com-parison was done for the trough and tower technologies
Parameter
Trough
Tower
Capacity,
MWe
100
100
Annual capacity factor
0.4
0.51
Winter Peak Capacity Factor
0.87
0.98
Summer peak capacity factor
0.86
0.86
Capital cost (1000 Rand/kW)
22.5
22.2
Annual O&M costs (million Rands)
24.2
19.0
LEC
(Rand/kWh)
0.5
0.39
Near-term strategy for the country
CSP will cost more than ESCOM’s current price of coal-based power for the foreseeable future, but could still represent an attractive power source because of environmental
and economic benefi ts.
Mid-term strategy for the country
See above.
with possi-ble future options
(maybe 10 years)
Suggested approach to improve
Coal Resource/Reserve
chances of CSP success in South Africa
South Africa’s current coal resource/reserve information (of 55 billion tons of reserves and 115 billion tons of resources) is based on the Bredell report of 1987. In the light
of South Africa being a major producer, user, and exporter of coal in the world, and therefore largely reliant on coal for its medium- to long-term economic development,
it is essential that the potential of the remainder of the country’s coal resources and reserves be evaluated. The major question that needs to be answered is: “To what
extent are the current coal resources and reserves suffi cient to supply the future needs of the various coal-consumption sectors, of which the coal export sector is one of the
most important?” In this light it is important to establish a national inventory on coal resources and reserves.
Country/Location
South Africa, near Upington in the Northern Cape Province
(cont.)
91
A
NNEX
1
–
C
HARACTERIZATION
OF
THE
S
TATUS
OF
I
MPORTANT
O
NGOING
CSP P
ROJECTS
W
ORLDWIDE
It is the responsibility of the government (as is the case throughout the world), and particularly that of the Department of Minerals and Energy, not only to reevaluate the
amount of coal available in the national coal resource/reserve base, but also the amount of coal that has already been mined out, as well as the rate at which future
exploitation will take place. For this purpose, the Department of Minerals and Energy has awarded a contract to Miningtek (a division of the Council for Scientifi c and
Industrial Research) to un-dertake the investigation.
Coal is the second largest earner of foreign exchange in South Africa today. Coal energy is used by dif-ferent sectors of the South African economy. Coal composition is a
complex structure of organic and inorganic components, which determine its specifi c characteristics. The effi cient utilization of coal reserves demands the production of differ-
ent but very specifi c saleable products to satisfy market requirements.
The outcome of this study is very likely to infl uence decisions on how the remainder of SA’s coal reserves will be utilized.
Coal Discards
South Africa generates approximately 60 million tons per annum of discard coal, which is estimated to have already accumulated to more than 1 billion tons. These large
amounts of carbonaceous material impact negatively on the environment; in addition, they contain signifi cant amounts of usable coal. Discard coal is therefore a major
concern to the Department of Minerals and Energy regarding potential future environmental impacts. It poses the challenge of being a major resource that provides an
economic op-portunity through its utilization.
In 2001, the Department of Minerals and Energy commissioned a survey to establish an inventory of dis-card and duff coal in South Africa. This resulted in the publishing of
the National Inventory on Discard and Duff Coal.
In the context of this project, the primary stakeholders interviewed were:
Dept of Minerals and Energy - DME
Dept of Science & Technology - DST
ESCOM (South Africa Electricity Supply Commission)
The primary objective of the SA government is to alleviate poverty by creating an enabling environment for socioeconomic development. This is primarily to be achieved
through promoting local manufacturing enterprises and through the expansion of local expertise.
A major barrier to the implementation of new technologies is the lack of knowledge and awareness of the technology in the host country. Here a “critical mass” of know-
ledge and expertise is required.
Key issues to be considered in developing local knowledge and expertise are:
(a) Knowledge transfer precedes technology transfer;
(b) Knowledge enables wider choices to be made and increases the probability of new technologies being accepted by all stakeholders;
(c) Complete technology transfer is sensitive to the sociological dimension and ensures complete “owner-ship;” and
(d) Human pride and dignity need to be taken into account.
Regarding barriers to solar thermal technologies in developing countries, technology transfer is made up of two legs, technology push and market-pull. As far as technology
push is concerned, this is well-established, understood, well-resourced, and well-organized. This issue has been heavily infl uenced by stakeholders, who are mostly from the
developed
world.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
92
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
A shortcoming with the stakeholders from the developing world is that, having a sound technology-push strategy, they do not have a sound market-pull strategy. A market-
pull strategy has to be formulated with stakeholders from the developing world. Without active participation and “champions” from the developing world, the transfer of
solar thermal technology into this environment will be diffi cult.
Critical success factors for SA in the fi eld of solar thermal energy
Establish how solar thermal technologies can contribute toward meeting the objectives of the Millennium Development goals;
Implement SA’s energy policy, taking into account that SA’s coal reserves have a limited life;
Implement the energy effi ciency policy with encouragement on the utilization of clean coal tech-nologies;
Within the context of the renewable energy and energy effi ciency policy, encourage the exploita-tion of SA’s renewable energy resource to meet the targets that have
been established by govern-ment;
Develop local expertise, know-how, and intellectual capital; and
Establish local manufacturing enterprises to take advantage of solar thermal projects.
Country/Location
South Africa, near Upington in the Northern Cape Province
(cont.)
93
A
NNEX
1
–
C
HARACTERIZATION
OF
THE
S
TATUS
OF
I
MPORTANT
O
NGOING
CSP P
ROJECTS
W
ORLDWIDE
Country
Spain/Andasol 1 & 2
Spain/PS10
Type of technology
Solar only trough (oil htf)
Central receiver (tower) with saturated steam receiver
Technical parameters
2 x 50 MWe oil troughs with 7.7 full load hrs molten salt storage;
11 MWe gross; 23 GWh
e
(gross)/yr; 15 MWh sat steam thermal storage
2 x 179.1 GWh/a
(25 min at full load)
Business model
EPC Consortium
EPC
Status of plants
SKAL-ET loop tested in SEGS V; all permitting applica-tions submitted; nearly
Abengoa (Inabensa), CIEMAT, DLR, Fichtner re-ceived
€
5M for preparatory
all land secured (problem with needing to acquire many small allotments;
work; construction under way
tenders called for loans, strong response, fi nal deal being considered
Expected project time schedule
Commence construction mid- to-late 2006, commence operation approximately
Expected to be operational by July 2006
24 months later
Project developer & owner
Milenio Solar S.A., AndaSol-2 S.A. (now held 70 percent by ACS Cobra,
IPP Sanlucar Solar S.A.
30 percent by Solar Millenium)
EPC led by Solucar Energia S.A.
Financing and project structure
EPC price 2 x
€
260 million
Total capital investment cost
€
33 million
Solar 2004, Paul Nava, Flagsol
Country Spain/Solar
Tres
Spain/EuroSEGS
Type of technology
Tower with molten salt
Trough (oil htf)
Technical parameters
15 MWe, approx 240,000 m
2
(heliostats) considering 16hrs full load
15 MWe, 95,880 m
2
, originally proposed to use two different types of solar
thermal storage, 78.8 GWh
e
/yr
collector, solar radiation at this site poor compared to other sites in Spain
Business model
IPP
IPP
Banks
Permitting
Entities
European
Comission
Insurances
Grid
Operator
(REE)
O&M
Company
Solar Field
Engineering
Power Block
BOP
Engineering
HTF System
& Storage
Solar Field
Components
Turbine &
BOP
Milenio Solar S.A.
(AndaSol.S.A)
EPC Consortium
O&M
Costs
Permits
Debt Ser
vice
Cred
it
Equity
Dividends
Su
bventions
Liability
Premium
Tariff
Electricity
O&M
Appl
ications
Investors
Spanish industry
Solar Millennium AG
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
94
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Status of plants
Activity in this project has recommenced with the an-nouncement of the
Prefeasibility study, site assessment, pre-engineering of power block and
new tariffs in Spain
solar fi eld all completed
Expected project time schedule
Operational in 2006
Not known
Project developer & owner
Ghersa, assisted in technical design by Boeing and Nexant (these
EHN
three companies have formed Solar Tres)
Financing and project structure
2002 estimate: $72 million
2002 estimate: $45 million
Key governmental institutions and their interests
Tariff structure in country
Spain has introduced the most attractive tariffs for CSP in the world. The Royal Decree 436-2004 allows for tariffs up to
€
0.21/kWh, allows 12 to 15 percent gas
backup for purposes of dispatchability and fi rm capacity, is secure for 25 years (to provide necessary bankable guarantees), and allows for annual infl ation escalation. The
tariff is in place for the fi rst 200 MW, after which the tariff will be reviewed downward to follow the expected cost-reduction curve.
Near-term strategy for CSP in the country
Spain has set in place a suite of support mechanisms that will help support a range of renewable energy technologies. It is understood that the increase in tariffs from
€
12 to 18cents/kWh and other associated changes has helped to provide the necessary fi nancial cover for the risk premium on these fi rst projects. The specifi c tariffs to
support CSP, including the associated support of bankable timeframes and sensible allowance of gas, sees Spain as one of the leaders in promoting CSP projects.
View of the country on a mid-term strategy
As various capacity points for CSP are achieved, the tariff premium will drop to suit a cost reduction path. This is a sensible approach; however, the technologies that miss
for CSP with possible fu-ture options
out on the fi rst 200 MW installment will have to accept a lower premium.
(5–10 years)
Country
Spain/Andasol 1 & 2
Spain/PS10
(cont.)
95
A
NNEX
1
–
C
HARACTERIZATION
OF
THE
S
TATUS
OF
I
MPORTANT
O
NGOING
CSP P
ROJECTS
W
ORLDWIDE
Country/Location
USA, Nevada
USA, Arizona
Type of technology
trough + Rankine cycle
trough + organic Rankine cycle
Technical parameters
64 MWe (net) (increased from originally 50 MW)
1 MWe, 2,000 MWh annual generation, O&M 2.91c/kWh, 95 percent plant
availability,
10,346m
2
aperture
Business model
EPC
Status of plant
Construction commenced February 2006, start-up expected March 2007
Construction commenced March 2004, start-up April 2006
Project developer/Prequalifi ed developers
Solargenix is project developer; four large compa-nies bidding for EPC contract
Project team is APS as the utility, Ormat for the turbine, and Solargenix for the solar
fi
eld
Financing structure
Final owner of plant
Key governmental institutions
Much of the renewable energy policy drive and framework is being provided by the individual states. There are a variety of incentives available for renewable energy driven
and their interests
by consumer demand and renewable energy portfolio standards (see U.S. map below). In Arizona, the standard goes further to specify that 60 percent of the RPS must be
solar
electric.
Tariff structure in country
The retailing of electricity in the U.S. is increasingly being carried out by companies that stretch across the traditional state boundaries, with signifi cant interstate wheeling of
electricity and gas. The market is highly competitive, with many green energy schemes available on a voluntary basis to consumers.
Near-term strategy for CSP in the country
Continued development of renewables in the U.S. will be infl uenced largely by statutory requirements based on regulation or legislation. The major policy driver at pres
ent for CSP in the U.S. is the “1,000 MW CSP South West Initiative” as part of the Western Governors’ Association resolution to diversify energy resources by developing
30 GW of clean energy in the U.S. West. A comprehensive study of CSP options for New Mexico has just been completed. The Southwest is a rapidly growing area with a
corresponding need for increased power. As this is also the country’s sunbelt, there are good opportunities for CSP if appropriate incentives are available.
View of the country on a mid-term strategy
The U.S. has a long history in CSP development, and since the last SEGS plant was built has continued with R&D and O&M cost reduction programs. The next stage for
for CSP with possible future options
CSP in the U.S. will depend on the technical success of the Nevada and Arizona plants, the continued activity in Spain and elsewhere, the success of the Global Market
(5–10 years)
Initiative for CSP, and the emergence of mandated requirements to specifi cally support solar electric technologies. Under the present RPS of the four states (NM, CA, AR,
NV), there would be a total of 4,926 MW of renewable capacity required by 2008 and 7,297 MW required by 2015. There are 37,099 MW of additional power genera
tion required in these four states over the net three to fi ve years, of which 87.6 percent is natural gas. There is an estimated 7,858,560 MW of solar capacity potential
from these four states based on available land area near to infrastructure. The combination of sun, gas, sites, and power demand, particularly summer demand, ensures
there are strong opportunities available for CSP in the Southwest.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
96
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
97
A
N N E X
2
T
H E
F
R A M E W O R K
F O R
CSP
I N
C
H I N A
Country China
Business model
Feb 28, 2005 – National Congress of China endorsed the Renewable Energy Law in the form of feed-in-tariffs.
Institutional frame in country
Thermoelectric power accounts for 75 percent of China’s electrical energy generation, and coal represents the bulk of the primary raw material.
Growing electricity needs, energy shortage, Kyoto Protocol and air pollution in metropolitan areas have led to electricity strategies based on
nuclear energy and RES.
Near-term strategy for Renewables
At the Renewables2004 Conference in Bonn, Germany, China committed itself to build up renewable energy, aiming for:
in the country
(1) 60 GW
e
by 2010 RES;
(2) 121 GW
e
by 2020 RES; and
(3) RES for heat supply and biofuels.
China’s RES goals are also implemented in national frameworks on a fi ve- and fi fteen-year basis in the “New and renewable energy industry
development.”
As an instrument to implement these ambitious goals, a “Feed-In-Law for Renewables” was endorsed on Feb 28, 2005. The goals of this law
are
to:
(1) Confi rm the important role of renewable energy in China´s national energy strategy;
(2) Remove barriers to the development of the renewable energy market;
(3) Create market space for renewable energy;
(4) Set up a fi nancial guarantee system for renewable energy; and
(5) Create a social atmosphere conducive to renewable energy.
This law is considered as a strategic investment not only in clean energy, but also as a strong future business opportunity for China. The utility
companies will surcharge the extra cost to the end users. The law has not yet come into force. The State Council will set the feed-in-tariffs at
the beginning of 2006 according to different regions and different types of renewable energy resources.
Near- and long-term strategy for CSP
Especially in the Southwest of the country, solar conditions are favorable to CSP.
in the country
The Chinese Academy of Science is developing different types of solar collectors for use in solar thermal power collectors. China already is the
largest producer of low-temperature solar collectors for water heating in the world. and has interested companies to start CSP activities in
China for the local and the export market.
It is not yet clear if and how CSP will be considered in the Renewable Energy Law. A fi rst—possibly GEF-co-fi nanced—commercial pilot
project would increase awareness of CSP technology in China. Under China’s favorable RES conditions, a pilot project could induce a signifi cant
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
98
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
multiplication effect for CSP market development. In the long term, CSP as a dispatchable power source can to some extent be a safe and
clean alternative to nuclear energy.
The Solar Millenium AG, Germany, announced in May 2006 the development of solar thermal power plants for the Chinese market. For this
purpose, a framework agreement for the realisation of solar thermal power plants with a total power of 1,000 MW up to 2020 was signed
with regional companies (total investment $2.5 billion). The fi rst plant (50 MW) will be completed soon in Inner Mongolia (estimated costs
$1,62.5 million). Solar Millenium, with the Inner Mongolia Ruyi Industry Co Ltd, is conducting a feasibility study for the project in Ordos of
the northern Inner Mongolia Autonomous Region. Preparatory work will be completed for construction to begin by the end of the year 2006.
About 20 to 30 per cent of the total spending will be fi nanced by investors, with the remaining coming from bank loans. Chinese experts
estimate that the Ordos solar plant would sell its electricity for 18.8-20c/kWh to the grid companies. During the next four years, 200 MW
solar thermal power plants will be constructed. Prior to the framework agreement, investigations on possible locations were carried out in
three Chinese provinces in cooperation with the Ministry of Energy (autumn 2005). China has also integrated solar thermal power plants in
the new Five-Year-Plan. Since January 2006, a new law will promote the implementation of renewables (10 percent renewables electricity by
2010, or 100,000 MW).
Solar Resources in China (DNI-map, Source):
Country China
(cont.)
99
S
OLAR
COLLECTOR
TECHNOLOGIES
Parabolic Trough Systems
Steam cycle power plants with up to 80 MW capacity using
parabolic trough collectors have been in commercial operation
for more than 15 years. Nine plants with a total of 354 MW of
installed power are feeding the Californian electric grid with 800
million kWh/year at a cost of about 10–12ct/kWh. The plants
have proven a maximum effi ciency of 21 percent for the conver-
sion of direct solar radiation into grid electricity. While the plants in
California use a synthetic oil as heat transfer fl uid in the collectors,
efforts to achieve direct steam generation within the absorber tubes
are under way in order to reduce the costs further.
Linear Fresnel Collectors
Another option under investigation is the approximation of the
parabolic troughs by segmented mirrors according to the principle
of Fresnel. Although this will reduce effi ciency, it shows a consid-
erable potential for cost reduction. The close arrangement of the
mirrors requires less land and provides a partially shaded, useful
space below.
Solar Tower Systems
Concentrating the sunlight by up to 600 times, solar towers are
capable of heating a heat transfer fl uid up to 1,200 °C and higher.
Today, molten salt, air or water is used to absorb the heat in the
receiver. The heat may be used for steam generation or—making
use of the full potential of this high-temperature technology in the
future—to drive gas turbines. The PS10 project in Sanlucar, Spain,
being the fi rst commercial solar tower project currently under con-
struction aims to build a steam cycle pilot plant with 11 MW of
power. For gas turbine operation, the air to be heated must pass
through a pressurized solar receiver with a solar window. Com-
bined cycle power plants using this method will require 30 percent
less collector area than equivalent steam cycles.
Parabolic Dish
Parabolic dish concentrators are typically relatively small units that
have a motor-generator in the focal point of the refl ector. The mo-
tor-generator unit may be based on a Stirling engine or a small
gas turbine. Their size typically ranges from 5 to 15 m of diameter
or 5 to 25 kW of power. Like all concentrating systems, they can
additionally be powered by fossil fuel or biomass, providing fi rm
capacity at any time. Because of their size, they are particularly
well-suited for decentralized power supply and remote, stand-alone
power systems. Dishes up to 400 m
2
have been built, with this size
being used for direct steam generation.
A
N N E X
3
CSP T
E C H N O L O G Y
O
P T I O N S
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
100
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
101
A
NNEX
4
C
HARACTERIZATION
OF
THE
GEF
F
OUR
-C
OUNTRY
P
ORTFOLIO
(D
ESCRIPTION
OF
EACH
OF
THE
FOUR
PROJECTS
ACCORDING
TO
A
SET
OF
CRITERIA
)
Country/Location Egypt/Kuraymat
Type of technology
Conventional combined-cycle plant with solar thermal power collector (not trough-specifi ed)
Technical parameters (installed MW, etc.)
Located about 90 km south of Cairo. The project site is characterized by an uninhabited fl at desert
landscape, high intensity direct solar radiation that reaches 2,400 kWh/m
2
/annum, an extended
unifi ed power grid, and extended natural gas pipeline, and is near a source of water.
The conceptual design of the project is as follows:
Power Block
Typical combined-cycle power plant consists of:
Two gas turbines of about 41.5 MWe, each fi ring natural gas as fuel to generate electricity, in
addition to the capability of using fuel oil distillate No.2 as an alternate fuel for emergency;
Two heat recovery steam generators – (HRSG) will use the exhaust gases from the gas turbine
to produce superheated steam;
One steam turbine of about 68 MW;
Cooling system in which the steam turbine exhaust will be condensed in the condenser and
pumped to the HRSG.
Solar fi eld
The solar fi eld comprises parallel rows of solar collector arrays (SCAs), sets of typical
mirrors—which are curved in only one dimension—forming parabolic troughs. The trough
focuses the sun’s energy on an absorber pipe located along its focal line (Heat Collection
Element
“HCE”).
The total area of the solar collectors is about 220,000 m
2
, connected in series and parallel
to produce the required heat energy by tracking the sun from east to west while rotating on
a north-south axis.
The heat transfer fl uid (HTF), (typically synthetic oil) is circulated through the receiver heated
to a temperature up to 4000C. The fl uid is pumped to a heat exchanger to generate steam that
can be superheated in the HRSGs and integrated with the steam generated from the combined
cycle (CC) before introducing it to the steam turbine (ST) to generate electricity.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
102
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Summary of Technical Parameters of Baseline Design
Capacity of Solar portion (MWe)
30
Capacity of gas turbine (MWe)
2 X 41.5
Capacity of steam turbine (MWe)
68
Net electricity generated (GWh
e
/annum) 985
Exegetic solar generation (GWh
e
/annum) 65
Solar share
6.6 percent
Fuel saving due to solar portion (toe/annum)
14,000
CO
2
reduction (Tonnes/annum)
38,000
Source: Information provided by NREA.
Business model (EPC, separate EPC for
The Government of Egypt put in place regulations that are not attractive to the BOOT approach concept, which resulted in the adoption of the EPC with O&M project by
solar and fossil, IPP)
NREA.
The current structure of the Egyptian electricity sector is vertically integrated where the generation, transmission, and distribution companies form part of the Egyptian
Electricity Holding Company. The holding company is obliged to purchase electricity from the generation companies. This potentially simplifi es the purchasing of electricity
from any new generation facility, including that from any ISCCS plant.
Business models that will be applied will depend to a large extent on future investment policies as presented by the government.
Furthermore, international investment organizations such as the World Bank, JBIC, and KfW should also facilitate investments in the Egyptian manufacturing industry.
Egypt derives much of its foreign exchange through exporting crude oil and natural gas.
Solar thermal, as well as other renewable energy technologies, has the potential to save Egyptian natural gas, which could then be exported at a premium price, with a
small margin (profi t), possibly Piasters 2/kWh, going into a renewable energy fund.
Liability provisions (in particular
NREA will be the owner of the project and the recipient of the GEF grant. The private sector can participate in the O&M through contracts of limited time frame that will not
for hybrid) exceed fi ve years.
Two separate contracts are planned for the combined cycle (CC) island and the solar thermal island. This arrangement is at the request of JBIC. No major problems are
foreseen by NREA with this two-island arrangement. Bidding documents will be designed to be very specifi c as to how to manage this two island approach.
Status of project
At bidding stage (see below)
Country/Location Egypt/Kuraymat
103
A
NNEX
4
–
C
HARACTERIZATION
OF
THE
GEF F
OUR
-C
OUNTRY
P
ORTFOLIO
Expected project time schedule
Solar Island
C.C. Island
Conceptual Design Report
March 11, 2003
Prequalifi cation Document issued for Solar & CC
August 30, 2005
December 26, 2005
WB non-objection of evaluation of PQD
March 14, 2006
June 28, 2006
Financing secured (letter of intent from JBIC)
Issue Bid Documents (two packages)
May 30, 2006
July 17, 2006
Bidding (fi rst stage)
August 5, 2006
Evaluation by Consultant
August 28, 2006
Clarifi cation with bidders (solar + CC)
September 25-28, 2006
September 25-28, 2006
Bidding (second stage)
November 30, 2006
November 15, 2006
Evaluation by Consultant
December 21, 2006
December 25, 2006
Review by NREA
15 days end October 2006
WB/JBIC non-objection
January 10, 2007
January 10, 2007
Negotiation & Draft Contract
January 15, 2007
January 22, 2007
WB/JBIC Approval
January 30, 2007
January 30, 2007
Egyptian Authorities Approval
February 15, 2007
February 15, 2007
Contract Sign
February 20, 2007
February 20, 2007
Completion of Construction
July 2009
July 2009
WB/NREA sign grant agreement
End April 2007
WB non-objection on draft contract
2 weeks mid-May 2007
Egyptian Authority approval & ratifi cation
mid-April 2007
(including
fi
nancing)
Consulting contract for project
End May 2007
management in place
Contract signature
End May 2007
Contract effectiveness
Mid-June 2007
Completion of EPC works
30 months mid-December 2009
Financing structure
JBIC to fi nance the CC island with the GEF grant to cover the incremental cost of the solar power plant. NREA to participate in both the solar part and the CC.
The total project cost is estimated at $199.3 million, including taxes and duties and contingencies, but excluding interest during construction. The total project cost includes
the 5-year O&M estimated at $13.93 million for the solar and combined cycle islands. The total project cost of $199.3 million will be fi nanced as follows: $49.9 million
from the GEF as a grant; $92.3 million from the Japanese International Bank of Japan (JBIC); and the remaining $57.1 million equivalent from NREA. The discount rate is
assumed to be 6 percent.
Final owner of plant
NREA
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
104
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Institutional frame in host country
The Egyptian energy policy depends on three main pillars, namely (1) diversifying energy resources; (2) improving energy effi ciency and enhancing energy conservation
for electricity generation
programs; and (3) maximizing the share of renewable energy (RE) in the energy mix.
Fossil fuels (oil, natural gas, limited deposits of coal) contribute 85.3 percent to the energy mix. Hydro (Nile River), contributes 13.7 percent to the energy mix. Renewable
energy (RE), mainly from wind, contributes nearly 1 percent to the energy mix.
Currently, the growing demand rate for electric energy to satisfy Egypt’s socioeconomic plans ranges from 6.5 to 7.5 percent annually during this decade. The target is to
increase installed capacity from 18,600 MW in 2004 to about 27,000 MW by 2010. Consequently, Egypt is required to add about 2,000 MW/year, as an average, to
secure the needed energy supplies. Such expansion provides room for a considerable share of electricity generation from renewable sources.
Securing energy demand on a continuous basis is a vital element for sustained development plans, in view of the nation’s limited fossil fuel reserves. Egypt has given due
consideration to the promotion of its indigenous renewable energy resources, mainly solar, wind, and biomass.
The evolution and expected increase in generation capacity can be seen in the following graph:
Source: Information provided by NREA.
Institutional framework in host country
In 1982, a renewable energy strategy was formulated as an integral part of national energy planning in Egypt. Currently, the strategy aims to cover 3 percent of Egypt’s
for renewable energy
electric energy demand with renewable energy resources, mainly from solar, wind, and biomass applications by the year 2010, with additional contributions from other
renewable energy applications.
The growing demand of electric energy to satisfy economic and social development plans reaches about 6 percent annually up to 2010. Such expansion plans provide
room for a considerable share of electricity generation from renewable energy resources.
The strategy calls for the development of renewable energy resources, particularly solar, wind, and biomass, through specifi c measures for development activities, including:
Renewable energy resource assessment and planning;
Research, development, demonstration, and testing of the different technologies;
Country/Location Egypt/Kuraymat
0
5,000
10,000
15,000
20,000
25,000
30,000
MW
year
2003
2007
2004
2005
2006
2008
2009
2010
Evolution of electricity installed capacity in Egypt
105
A
NNEX
4
–
C
HARACTERIZATION
OF
THE
GEF F
OUR
-C
OUNTRY
P
ORTFOLIO
Transfer of technology, development of local industry, and application of mature technologies;
Establishment of testing and certifi cation facilities and development of local standards and codes; and
Education, training, and information dissemination programs.
Renewable energy’s environmental benefi ts allow for fi nancial support through various mechanisms such as the Clean Development Mechanism (CDM), fi nancing RE
incremental costs, soft loans, and mixed credits.
Key governmental institutions and
Ministry of Electricity & Energy
their interests
New and Renewable Energy Authority (NREA)
The national power utility, the Egyptian Electricity Holding Company (EEHC).
Tariff structure in country
The average cost of electricity at generation for Egypt is Piasters 15/kWh (approximately 2.63 cents/kWh as of April 2005).
It has been calculated that for the ISCCS the cost of generation will be 4.9 cents/kWh.
It should be noted that Egypt’s installed generation capacity at 2003/2004 was 18,119 MW. With the planned ISCCS capacity of 150 MW, the size of the project is small
in comparison to Egypt’s total generation capacity and the initial high generation costs can easily be absorbed by the total generation capacity.
Expected LEC (c/kWh)
The LEC for kWh price of the ISCCS plant is still uncompetitive compared to other schemes of power generation. (See previous note).
Overall energy situation of Egypt
Energy policies
Egypt’s energy policies are formulated basically in the two main energy sectors; the oil and gas sector, and the electricity sector.
The oil and gas sector has the following objectives:
To achieve national self-suffi ciency of petroleum products and natural gas;
To increase Egypt’s hydrocarbon reserves. The oil reserves had slightly increased from 3.46 billion barrels (1990/91) to 3.68 billion barrels (2000/01). Gas reserves
have increased nearly six times in the same period to reach about 57 trillion cubic feet (TCF);
To maintain oil export revenues as one of the major sources of foreign exchange needed for development;
To undertake oil and gas operations using environmentally sound practices to protect human health and the environment; and
To promote energy utilization effi ciency in all consuming sectors.
The electricity sector aims to achieve the following objectives:
To maximize the exploitation of all feasible hydro resources, including mini-hydro;
To maximize the use of natural gas for existing and new generating facilities;
To develop and promote the use of renewable energy resources, especially wind, solar, and biomass;
To improve energy effi ciency in both sides of supply and demand; and
To develop regional electricity interconnection with the neighboring countries.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
106
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Primary Energy Resources
Egypt’s main energy resources are oil, natural gas, hydropower, and coal, in addition to good potential for renewable energy resources. Oil and gas accounts for 93.5 per
cent of total commercial energy consumption.
Current oil reserves total 3.68 billion barrels, mostly located in the Gulf of Suez. The present annual production level of oil is nearly 32.3 million tons (MT), of which
23.4 MT are consumed domestically (representing 73 percent of that production). The balance is exported.
Current reserves of natural gas are about 57 TCF. Most of the gas resources are located in the north coast, Nile Delta, and western desert. The development of proven
natural gas reserves is a result of the country’s intensive efforts to attract foreign investment in gas exploration and production. The Government of Egypt has allowed
for sharing gas production and more fl exibility in gas pricing; these incentives have attracted more foreign investment in oil and gas exploration. With an annual production
level of 796.4 TCF in 2000/01, natural gas could play an important role in the country’s future energy scene. A gas substitution policy has been adopted and is being
implemented to promote the use of natural gas in electricity generation, industry, transport, and residential and commercial utilizations.
Hydropower is the third major energy resource in Egypt. Most of the Nile’s hydro potential has already been exploited to generate about 13.7 TWh of electricity annually.
Some assessment studies revealed the feasibility of using mini-hydro-generating facilities to make use of some small hydro potential along the river’s main streams.
Currently it is planned to develop four small hydropower stations with total installed capacity of nearly 60 MW. Pumped storage potential has also been assessed in
“Algalala” and “Ataka” sites to be used as peak load pump storage stations.
In addition to oil, natural gas, and hydro, Egypt has limited coal reserves estimated at about 27 MT. The only commercial mining is in Maghara, Sinai, producing about
600,000 tons per year. However, the current production is 58,000 tons per year. About 1.8 million tons of coal are being imported now as feedstock for the steel industry.
Near-term strategy for CSP for the Egypt
NREA expects a successful pilot project in Egypt that leads the CSP technology and may create new industries related to solar fi elds. In the near term, the project schedule as
presented earlier will be followed to implement the pilot project. Additionally, the transfer of know-how and learning into Egypt is expected to take place. As part of the
overall project, additional activities will include:
Training of NREA/EEHC and regulatory staff in solar thermal power plant operations, with particular respect to dispatching and integration into the power system;
Monitoring/evaluation and dissemination of performance results from the project, both domestically and internationally. The purpose of this activity is to support future
replication;
and
Consulting services for project management and support to NREA’s PIU.
NREA also is planning to survey local equipment suppliers/contractors to establish what components may be provided locally and to inform such suppliers and contractors of
the opportunity for future projects.
Mid-term strategy for the country with
NREA developed an ambitious program for large-scale electricity generation using an integrated solar combined cycle ower plant. In this fi eld, NREA has completed a study
possible future options (maybe 10 years)
on “Technical Development of Solar Thermal Electric Power Generation and its Potential Utilization both in Egypt and Mediterranean Countries,” including evaluation of the
application status of the solar thermal generation technologies and systems developed worldwide along with a study specifying predictions of the construction and operation
development
capacities.
The long vision for STEG targets the installation of 750 MW by 2017 producing 7 TWh/year of electricity for local consumption and export through the interconnected
electricity grid to Europe. Such a plan envisages a fuel saving of 64,000 TOE at 2017. In addition, it will create valuable chances for technology transfer and job creation
opportunities in Egypt and the region
Country/Location Egypt/Kuraymat
107
A
NNEX
4
–
C
HARACTERIZATION
OF
THE
GEF F
OUR
-C
OUNTRY
P
ORTFOLIO
Annual
Energy
Generation at the
Power
Total
5 year
end of the period
No. of
Capacity
Capacity
Cumulative
Accessible
development
plans
GWh/year
plants
(MW)
(MW)
Capacity
Potentials
1997–2002
2002–2007
0.95
1
150
150
150
70
2007–2012
3.98
1
300
300
450
74
2012–2017
7
1
300
300
750
80
Source: Information provided by NREA.
Accessible potentials and installation plants for solar thermal electricity generation
1. Accessible potential: Total capacity that can be installed on 50 percent of the lands that are sunny and available at less than 5 km from electric and gas networks.
2. The fi rst plant is anticipated to be ISCCS.
Suggested approach to improve
NREA has gained signifi cant experience in designing and implementing wind energy projects with international loan and grant fi nancing. Important lessons drawn from that
chances of CSP success in Egypt
experience include the importance of a transparent and well-managed competitive bidding process. Another important lesson from the development of the wind projects is
that they have attracted major international suppliers of wind technology, demonstrating the interest and comfort of major suppliers with business transactions in Egypt.
Furthermore, through the development of these projects, NREA has operated under PPAs with the national utility and has gained signifi cant experience in structuring and
negotiating such agreements. This experience will be very useful in the competitive bidding approach adopted for the solar thermal project, in which a power purchase agree
ment will need to be put in place as well as a gas purchase agreement
Egypt has a large oil and gas sector and provides valuable foreign exchange. However, one of the objectives of the oil and gas sector is to promote energy effi ciency in this
sector. A barrel saved is a barrel produced, and considering Egypt’s energy situation, which is characterized by a growing energy requirement and depleting energy
resources, energy conservation becomes of paramount importance. The upward adjustment of oil prices is driving the need for energy conservation. How pressing such a
need may be may differ from one country to another, depending on the impact of imported energy prices on the economy and the balance of payments. Energy-producing
countries, which were lucky enough to attain self-suffi ciency, are least hit by the energy shocks and tended to deal complacently with it.
Egypt was one of the countries that experienced these mixed-blessing events. Egypt has concluded a large number of oil exploration agreements with many international
companies, and consequently, oil production has steadily been on the rise since the mid-1970s. Starting in 1976, Egypt has been able not only to meet its own needs of
energy, but also to export some oil. Consequently, the urge for energy conservation was given a lower profi le in the Egyptian energy policy. The growing production of oil
and gas since 1975 has stimulated a period of fast economic growth. With little or negligible effort at energy conservation, domestic energy consumption went hand in
hand with domestic oil and gas production since the mid-1970s. The availability of domestic oil and gas, which were priced at historically very low prices, encouraged
unrestrained uses of energy. This distorted pricing system was justifi ed, at the time, on the basis of prevailing social and political reasons, but this does not change the fact
that a great deal of precious resources have been wasted over a long period of time. Now, with increased awareness of the limitation of oil and gas reserves, and a valid
expectation of higher future prices of imported energy, the call for energy conservation should take a more serious dimension.
The process of energy conservation usually begins with efforts to change certain behavioral attitudes and practices acquired under a period of low energy costs. At a second
stage, emphasis should shift to investment in retrofi tting activities whose energy savings would be quick and attractive. Finally, in the longer run, the process would aim at
replacing obsolete technologies with new and more effi cient ones. Therefore, energy conservation should not be considered as a one-time process, but rather as an ongoing
process that extends over the short, medium, and long terms. Moreover, the overall target should not be limited to the enhancement of energy effi ciency, as represented by
reduced energy intensity, but it should also aim at attaining a higher level of GNP and a faster rate of economic growth. Generally, energy saved as a result of energy
Installed plant rate
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
108
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
conservation could be redirected either to feed larger and more effi cient domestic production, or exported to generate foreign receipts that support investment plans and the
balance of payments.
A policy recommendation to delay Egypt from becoming a net importer of energy is to retain all or most of the limited oil and gas reserves to meet future domestic energy
requirement.
NREA has indicated that the solar thermal project, as well as other renewable energy projects, can save Egyptian natural gas, which could be exported at a premium price,
with a small margin (profi t), possibly Piasters 2/kWh, going into a renewable energy fund
Such a renewable energy fund can make a major contribution toward the establishment of a solar thermal industry. If an integrated and holistic approach is adopted to
the use of such a fund, it can be argued that such a fund can fi nd strategic application in the development of Egyptian know-how and intellectual capacity. Locally based
knowledge enables wider choices to be made and increases the probability of new technologies being accepted by all stakeholders. Furthermore, locally based knowledge
is sensitive to local issues. One such issue may be poverty alleviation, which would benefi t from an expansion of the manufacturing sector—manufacturing sector that
could be expanded to support an Egyptian solar thermal industry. As indicated by NREA, one of the fi rst sets of activities to be undertaken in this regard is to:
Survey local suppliers/contractors to establish what components can be sourced locally’
Train NREA/EEHC and regulatory staff in solar thermal plant operations, in particular in dispatching and integration into the power system; and
Monitor, evaluate and disseminate performance results both locally and internationally with a view to support future replicability.
Critical success factors for Egypt in the fi eld of solar thermal energy
Implement Egypt’s energy policy, taking into account that Egypt’s oil and gas reserves have a limited life;
Implement energy effi ciency policy to encourage retention of oil & gas reserves for local consumption;
Within the context of the energy effi ciency policy, encourage the exploitation of Egypt’s renewable energy resources;
Develop the renewable energy fund, fi nanced through a levy on exported oil and gas;
Develop local expertise, know-how, and intellectual capital; and
Develop local manufacturing enterprises to take advantage of solar thermal projects.
Country/Location Egypt/Kuraymat
109
A
N N E X
4
–
C
H A R A C T E R I Z A T I O N
O F
T H E
GEF F
O U R
-C
O U N T R Y
P
O R T F O L I O
A
DDITIONAL
I
NFORMATION
FOR
E
GYPT
An overview of the Egyptian energy situation is outlined by Gelil (2002). The following table provides a description and an overview
of the characteristics of Egypt’s electricity sector:
Description
2003/2004 2002/2003 Variance
(%)
Peak
Load
MW
14,735 14,401 2.3
Total power generated
GWh
94,913
88,951
6.7
Hydro
GWh 13,019 12,859 1.2
Thermal
GWh 67,948 68,204 (0.4)
Power purchased from wind
GWh
368
204
80.4
Power purchased from (IPPs)*
GWh
77.4
76.7
0.9
Power gen. from private sector (BOOT)
GWh
13,501
7,607
77.5
Net exported power
GWh
918
827
11
Sent energy from connected power plants
GWh
78,029
78,065
(0.5)
Generated energy from isolated plants
GWh
269.7
239
12.8
Total fuel consumption
ktoe
15,261
15,267
–
H.F.O
ktoe 1,213 1,642 (26.1)
N.G
ktoe
14,006 13,579 3.1
L.F.O
ktoe 42 46 (8.7)
Fuel consumption (private sector BOOT)
ktoe
2,735
1,400
95.4
Fuel consumption rate
gm/kWh gen.
224.6
223.5
(0.5)
Fuel consumption rate
kcal/kWh
2,201
2,190
(0.5)
Thermal
effi
ciency
% 39.1 39.2 (0.3)
N.G ratio to total fuel
%
92
89.2
3.1
N.G ratio from power plants connected to gas grids
%
98.1
97.1
1
Installed
capacity MW
18,119
17,671
2.5
Hydro
2,745 2,745 –
Thermal
13,186.5
13,498
2.3
Wind
140
63
122.2
Private
sector
2,047.5
1,365
50
Transmission
lines km
50
kV
2,263 2,263 –
400
kV 33 33 –
220
kV
13,711 13,711 –
132
kV
2,466 2,466 –
66
kV
15,731 14,855 5.9
33kV
2,749 2,526 8.8
Transforme Capacities
MVA
500
kV
10,155 10,155 –
220
kV
29,208 24,605 18.7
132
kV
3,641 3,591 1.4
66
kV
29,362 27,917 5.2
33
kV
1,851
1,801
Source: Authors based on information provided by NREA.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
110
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
The following fi gure describes the evolution of the Egyptian electric-
ity sector 1971–2003.
Source: Autors based on ENERDATA Database.
Below is the daily load curve for Saturday, June 19, 2004. This
provides a perspective on the daily load curve in the middle of
the Egyptian summer. Prominent is the maximum demand at about
10:00 pm in the evening.
Source: Information provided by NREA.
Below is the daily load curve for Wednesday, December 31,
2003. This provides a perspective of the daily load curve in the
middle of the Egyptian winter. Prominent is the maximum demand at
about 7:00 pm in the evening, as expected for winter, the demand
is higher than for summer.
Source: Information provided by NREA.
The diagram below presents the daily load curve for two days, June
19, 2004, and September 30, 2004. Peak demand is similar,
but with differing times of occurrences.
Source: Information provided by NREA.
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
GMh
year
Daily Load Curve (Maximum Discharge) on Saturday
19/6/2004 (Discharge: 235 Million m
3
)
Grid
Hydro
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
30/9/2004 (14401)
19/6/2004 (14735
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
MW
2003/2004
2002/2004
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
GMh
year
Evolution of electricity installed capacity in Egypt
1971
1972
1973
1974
1975
1976
1977
1978
1979
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
Electricity production from gas
Electricity production from oil
Wind electricity production
Hydro-electricity production
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
MW
year
Daily Load Curve (Minimum Discharge) on Wednesday
31/12/2003 (Discharge: 75 Million m
3
)
Grid
Hydro
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
111
A
NNEX
4
–
C
HARACTERIZATION
OF
THE
GEF F
OUR
-C
OUNTRY
P
ORTFOLIO
Country/Location India/Mathania
Type of technology
Parabolic trough integrated with a combined cycle plant
Technical parameters (based on Sep
Capacity of the plant is 155 MW
e
, of which 30 MW are solar (original was 35 MW using 220,000±3 percent m
2
parabolic trough fi eld). Expected annual net production
2004 RREC spreadsheet)
from the ISCCS of 916 GWh per year. The solar output is estimated at 63 GWh
e
(depending on the level of thermal storage included) representing 6.9 percent of the
annual production. Solar radiation for the region has been quoted as around 2240 kWh/m
2
/yr (DNI).
The inclusion of thermal storage has been encouraged, with the 2002 RfP document stating that 5 percent of the bid assessment weighting criteria would be devoted to
storage (bids with no storage would receive a score of 0 for this parameter).
The site is relatively fl at, with access to water and transmission. The source of fossil fuel for the gas turbine has proved problematic. Supply of cost-effective fuel to the
project has been one of the critical issues to be resolved. There is a letter from GAIL stating gas price of INR 270.47/MMBTU, with possibility of cheaper gas from a new,
nearby oil/gas fi eld.
Business model (based on 2002 RfP)
Pre-qualifi ed bidders submit a proposal for an EPC with O&M contract to build the plant on a turnkey basis and operate it for a period of fi ve years. The plant will be owned
by the Rajasthan Renewable Energy Corporation (merger of REDA and RSPSL). The EPC part of the contract is a fi xed lump sum. The power purchase agreement is intended
to be with Rajasthan Rajya Vidyut Prasaran Nigam Limited (RVPN).
Liability provisions (based on 2002RfP)
Bids with less than 50 GWh
e
of solar production will not be accepted. For the purpose of tests on completion, rejection criteria (i.e. plant not accepted) apply to net electric
power (if 5 percent below performance model), net heat rate (if 2 percent above performance model), and the solar fi eld (if 5 percent below performance model). Penal
ties for performance defi ciencies apply to a number of parameters. In relation to the solar fi eld, a penalty of 100,000 INRs is payable per kW
th
of defi ciency (2002 RfP).
A second acceptance test applies at the end of the fi ve-year O&M period whereby penalties amounting to 80 percent of the fi rst acceptance test penalties apply. An agreed
level of degradation is permitted.
Status of project
The project could not be implemented in a timely fashion because it had serious fl aws in design due to the proposed technology and aggravated by inappropriate location.
The capital cost of the project was about $200 million, and the resulting subsidies were in the range of $112 million to $136 million. After many extensions, an ICB failed
in September 2003 due to lack of bidders. Subsequently, the Bank requested a commitment from the Government of India for additional measures to improve the project’s
economics, including additional subsidies. Finally, the Ministry of Finance sent a letter stating that the Ministry of Environment and Forest had decided to close the project.
Expected project time schedule
The project has been dropped and is no longer part of the WB/GEF pipeline. The Government of India and other donors (such as KfW) might consider other opportunities
for taking the project forward.
Project developer/Prequalifi ed developers
Prequalifi cation was completed in February 2002. Initially three consortia were involved; however, one pulled out, leaving two consortia, both from India, using the same
solar fi eld supplier.
Financing structure
The present funding arrangement (according to RREC) is:
Loan from KfW (revised)
€
92.16 million (this fi gure is from the RREC 2004 fi nancial spreadsheet, however KfW advise their loan at present is
€
125.7 million).
Grant from GEF
$45 million
Grant from GoI
$10.86 million
Grant from GoR
$10.86 million
Total
INR 8,226 million
Capital cost breakdown (including IDC) is solar block (INR 3,557.2) and CC block (INR 4,669.6).
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
112
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Owner of plant
RREC
Institutional framework in host country
Generation and distribution throughout the country is controlled by state-owned bodies, apart from several private sector licensees catering to such cities as Mumbai,
for electricity generation
Ahmedabad, Surat, and Calcutta, and in the state of Orissa where distribution of power has been privatized.
India requires signifi cant power generation installation over the coming years. Its tremendous growth rates make it a power-starved nation, even after 50 years of planning
and the experience of putting up a 90,000 MW generating capacity with associated transmission and distribution systems. Power shortages have resulted from insuffi cient
capital investment in the sector and from a need for improved effi ciency in delivery (the country has high T&D losses and low plant utilization). The national average energy
shortage in FY99 was 5.9 percent, and the peak defi cit was as high as 14 percent. In Rajasthan, the shortages were a little less than average. According to estimates of
Central Electricity Authority (CEA), India needs an additional 100,000 MW at an estimated investment of nearly $100 billion to meet its power requirements in the next
15 years. Participation of private/foreign capital would appear inevitable.
Installed Power Generation Capacity (MW) as on 02/28/2005
Thermal
Sl.
No. Region Hydro Coal Gas DSL Total Wind
Nuclear Total
1
Northern 10,596.6 16,914.5 3,213.2
15.0 20,142.7
178.5 1,180.0 32,097.8
2
Western
5,702.1 20,791.5 5,035.7
17.5 25,844.7
632.5
760.0 32,939.3
3
Southern 10,437.8 13,892.5 2,720.4
939.3 17,552.2 1,671.7
780.0 30,441.7
4
Eastern
2459.5 15737.4
190
17.2 15944.6
5.2
0.0 18409.3
5
N.
Eastern 1,133.9 330.0 750.5 142.7
1,223.2 0.3 0.0
2,357.5
6 Island
5.3 0.0 0.0 70.0 70.0 0.0 0.0 75.3
7
All
India 30,335.2 67,665.9 11,909.8 1,201.8 80,777.5 2,488.1 2,720.0 116,320.8
Source: CEA National Electricity Plan, Appendix 4.3.
Year
Electricity Consumption (GWh)
Annual compounded growth rate (%)
1950
4,157
–
1960–61
13,841 11.6
1970–71
43,724 12.2
1980–81
82,367 6.5
1990–91
190,357 8.7
2000–01
316,600 5.2
Source: General Review, CEA.
Country/Location India/Mathania
113
A
NNEX
4
–
C
HARACTERIZATION
OF
THE
GEF F
OUR
-C
OUNTRY
P
ORTFOLIO
Summary of All-India long-term forecast
Year
Energy Requirement (GWh)
Peal Load (MW)
2006–07
719,097 115,705
2011–12
975,222 157,107
2016–17
1,318.644
212,725
Source: 16th EPS Report.
11th Plan Capacity Addition (Tentative) – Sector Wise
Sector
Hydro
Thermal
Nuclear
Total
Central
15,828
4,328
2,264
22,420
State
11,740
12,523
9,273
33,536
Private
4,940
0
0
4,940
Total
32,508
16,851
11,537
60,896
Source: 16th EPS Report
Institutional frame in host country
India is keen to promote and develop its renewable energy resources. There is apparently a goal (administered by the MNES) to have 10 percent of new power come from
for renewables
renewables by 2012. The technologies pursued are mainly solar PVs, solar thermal, wind, many forms of biomass, and also associated new and emerging technologies.
The Ministry of Non-Conventional Energy Sources (MNES) provides fi nancial incentives, such as interest subsidy and capital subsidy. In addition, soft loans are provided
through the Indian Renewable Energy Development Agency (IREDA), a public sector company of the ministry and also through some of the nationalized banks and other
fi nancial Institutions for identifi ed technologies/systems.
The government also provides various types of fi scal incentives for the renewable energy sector, which include direct taxes (100 percent depreciation in the fi rst year of the
installation of the project), exemption/reduction in excise duty, exemption from central sales tax, and customs duty concessions on the import of material, components,
and equipment used in renewable energy projects.
The ministry has also suggested that states should announce general policies for purchase, wheeling, and banking of electrical energy generated from all renewable energy
sources. Fourteen states have so far announced such policies in respect of various renewable energy sources.1 We heard of a 10 percent target for renewables, but can’t
confi rm its status at this time.
Key governmental institutions
The key institutions for renewables in India are the Government of India itself, the Ministry of Non-Conventional Energy Sources (MNES), the Renewable Energy Develop
and their interests
Agency (IREDA). In the state of Rajasthan, the state government formed a new company—Rajasthan Renewable Energy Corporation (RREC)—on
August 9, 2002 by merging the activities of REDA and RSPCL. RREC is the state nodal agency for promotion of renewable energy programs in the state.
Main Activities of RREC are:
Extending electricity in remote rural areas through solar photovoltaic (SPV) lighting systems;
Execution of 140 MW integrated solar combined cycle power project at Mathania;
Development of wind energy power projects;
Development of biomass power projects;
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
114
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Development of mini-hydropower projects; and
Designated agency under Energy Conservation Act.
The state government announced a wind policy in April 2003, which is valid up to 2009 for additional capacity creation. The following incentives apply to this Wind Policy
Sale of power to RVPN for 2003–04 Rs. 3.3/unit;
Annual escalation at 2 percent;
Wheeling charges fi xed at 10 percent;
Provision for third party sale/captive consumption;
Exemption of electricity duty for fi ve years; and
Allotment of sites at concessional rate.
200 MW commissioned/application for 500–600 MW registered with RREC.
Electricity data for the State of Rajasthan
PARAMETER
JODHPUR
DISCOM
RAJASTHAN
GENERAL
Population
15,317,007 53,523,388
Area
(km
2
) 182,509
242,239
Population
Density(Persons/km
2
) 84
156
District.
10
32
Employees
9,249
40,223
ELECTRICAL
Total connected load (MW)
2,614
9,902
33KV lines (kms)
10,000
25,718
33/11KV S/S (Nos./Capacity in MVA)
581/2,140 MVA
1,650/6,490 MVA
Domestic Connected Load (MW)
725
2,181
Agriculture Connected Load
793
3,110
Ind.Connected Load (MW)
714
3,382
Domestic Electrifi cation
47 percent
42 percent
Villages/Towns Electrifi ed
83 percent
92 percent
T&D Losses (percent)
39 percent
38 percent
Revenue from sale of electricity (Rs.Crores)
785
2948
Energy Sold (MU)
3,463
12,716
Average Tariff (Rs./unit)
2.11
2.18
Country/Location India/Mathania
115
A
NNEX
4
–
C
HARACTERIZATION
OF
THE
GEF F
OUR
-C
OUNTRY
P
ORTFOLIO
CONSUMER
Total
Consumers
1,520,871 5,082,743
Domestic
Consumers
1,174,897 3,703,259
Agricultural
Consumers
104,813
577,443
Industrial
Consumers
35,172
134,084
HT
Consumers
600
2,505
Domestic Consumers as percent of total consumers
77 percent
73 percent
Source:
http://www.rajenergy.com/JodDiscom.htm#
Near-term strategy for CSP in India
India, being the fi rst ISCCS and fi rst GEF project, suffered from a lack of competitive interest. While India has become mired, other projects have benefi ted from the early
diffi culties identifi ed as a result of the Mathania process. India could now stand to benefi t from the renewed interest shown in CSP and ISCCS. Thus it would probably be
premature to drop the Indian project from GEF funding until the near future for Morocco and Egypt in particular are established. There does not appear to be, however, a
stated plan for CSP at the government level beyond the existing project. The Central Electricity Authority’s draft National Electricity Plan [http://www.cea.nic.in/nep/nep.
htm] considers a wide range of energy technologies and potential, but essentially expects most of the contribution over the next 15 years to come from fossil fuel, hydro,
and nuclear. Certainly India is well aware of the technical potential for the technology, and the solar resource is available. It is noted in the draft plan that just 1 percent of
the Raj desert could provide up to 6,000 MW of solar power. In addition, there is interest from Indian private industry to advance CSP technology, whether troughs, Fresnel,
towers, or dishes. The summer demand and supply curve for Delhi shown below indicates a signifi cant power shortage during solar hours in the summer months. This gap
would be well-matched by a solar technology such as CSP, especially as thermal storage could also help supply the demand into the evening.
Source:
http://www.ndplonline.com/index.jsp
India also has a strong R&D base, which could help to provide a good scientifi c resource, not only for technical development of the components but also for performance
monitoring and thermodynamic cycle improvements. The strong knowledge and familiarity that Indian power engineers have with thermal technologies (based on fossil fuel)
provides a good foundation for integration of solar thermal, which essentially uses the same power cycles and power blocks.
0
500
1,000
1,500
2,000
2,500
3,000
MW
HOUR
Reqt
Demand Met
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Own Generation
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
116
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
View of the country on a mid-term
India has huge power capacity additions planned over the next decade. At the end of 2002 (end of the 9th Plan), the country had a peaking shortage of 12.7 percent and
strategy for CSP with possible future
energy shortage of 7.5 percent. The 10th Plan (2002–07) recommended an additional 46,000 MW to be installed by 2007, and the 11th Plan is likely to suggest a fur
options (5–10 years)
ther 60,896 MW required by 2012. The modeled break-up by fuel type is shown below. For the longer term, a further 69,500 MW is expected to be required during the
12th Plan (2012–17). The 12th Plan continues with the same expected trend of hydro, thermal, and nuclear.
The plans also consider various scenarios. In particular, gas is a limited resource in the country, and it is likely that gas will have to be sourced outside of India. Hydro also
is a resource that can produce signifi cant seasonal variability, particularly if climate change becomes more pronounced. Solar thermal fi ts well with other fossil fuels, as it is
based on the same thermodynamic cycles and power generation equipment. Thus it could be a strategic move to incorporate solar thermal into the mix to help offset any
unplanned shortfalls in gas resources. With hydro expecting to contribute approximately ??? of the installed capacity by 2017, solar is likely to be a strategic hedge here
also because, if there is a reduction in water fl ows due to drought, there is a good chance that levels of solar insolation will be high. It has possibly already been carried
out, but with climate models improving it would be interesting to consider the complementarity of solar and hydro under various climate change scenarios.
Suggested approach to improve chances
There seems to have been a differing view over time as to the capacity of the solar portion. Figures up to 35 to 40 MW of solar have been circulated. The latest cost
of CSP success in India
spreadsheet (June 2004) has been based on 30 MW. This seems a sensible choice, in fact, if the reluctance of the GoI to sign off is due to the cost. It makes the technical
integration easier, with less manipulation of an otherwise optimized combined cycle required. It also improves the overall GHG performance of the ISCCS as off-design
operation is less removed from ideal (the steam turbine is less-oversized, thus duct-fi ring or the level of part load operation is reduced). The arguments by RREC appear to
make this capacity quite competitive in terms of LEC versus imported price of electricity. However we would recommend consideration that the next RfP include additional
assessment criteria with a signifi cant weighting that considers the size of the fi eld (or solar GWh
e
) offered. There should still be a minimum required fi eld size (in the
original RfP this cut-off was 50 GWh
e
, below which the bid would not be considered). However, this should now be a lower fi gure, to be determined through consultation
This would mean that bids could be differentiated on the basis of the solar fi eld size, prompting competition on both the quality and quantity of solar offered.
Paradoxically perhaps, the ultimate outcome for GEF is likely to be improved if the solar expectation is reduced. The solar fi eld, being modular, will generate as much experi
ence and know-how as a larger one. And though the solar capacity would be less, the number of solar MW is to some extent arbitrary. In the broad scheme of things, which
is ultimately what OP 7 is concerned with, the technology and the industry would be better served by a successful project. There is more chance of a successful industry
being spawned by a successful 25 MW than by a risky 30 MW, or even by a proposed 35 MW that never proceeds because it is too expensive. By 2015, no one will be
concerned that the very fi rst project was a few MW less than originally intended.
In addition for the India case, we would recommend that the specifi ed CSP technology be broadened to enable alternative collector technologies to be offered. There is
already a study under way for a 5 MW linear Fresnel plant in India, and strong interest in a dish-based solar steam plant.
Country/Location India/Mathania
117
A
NNEX
4
–
C
HARACTERIZATION
OF
THE
GEF F
OUR
-C
OUNTRY
P
ORTFOLIO
Country/Location
Mexico/Sonora State, Aqua Prieta
Type of technology
Parabolic trough integrated with a combined cycle plant
Technical parameters
For the former site Cerro Prieto near Mexicali in Baja California Norte (source: SMA study, June 2000): 285 MWe plant with a 39.6 MW
e
parabolic trough solar fi eld,
14 percent of plant capacity is solar corresponding to 4 percent of annual electricity yield (site has an average DNI of 2,600kWh/(m
2
a)).
Plant site was changed to Sonora state in November 2004, irradiation data there even seems to have slightly higher values. Latest inquiry from CFE to the WB: increase the
ISCCS total plant size from 250 MW to 500 MW. The solar fi eld capacity is not yet determined (in between 25 MW
e
and 40 MW
e
).
A new study by Sargent and Lundy (May 2006) determined that the increase in capacity of the thermal component in fact increases the conversion effi ciency of the solar
energy
collected.
Business model
“Obra Pública Financiada OPF” corresponds to a Finance Build Transfer scheme, similar to an EPC contract (Engineering, Procurement & Construction = Turnkey contract ).
The operation will be performed by CFE (by law). Flexibility about maintenance.
Previously IPP was pursued and a tender was already published in March 2002. But due to the fact that WB/GEF could/would not commit to its funding before the win
ning bidder was chosen, the bidding process had to be stopped. After a visit of Mr. Laris Alanís (one of the 5 CFE directors) at the World Bank in Spring 2003, the business
concept was changed to an EPC contract with CFE getting the WB fund. The former hen-egg-problem (CFE could not put out a conditional bid while the WB could not grant
the funding previous to knowing who would receive it) is resolved now.
Liability provisions
The EPC contractor will be responsible for the construction fi nancing, engineering, procurement, and construction, selling the turnkey hybrid plant to CFE. CFE will operate it,
maybe maintenance contractor.
Status of plant
June 2005: presentation to the Treasury Ministry.
November/December 2005: Approval by the Treasury Ministry.
The hybrid plant has been included in the PEF (Programa de Egresos de la Federación) and approved by Congress. The site for the 500 MW facility has been selected at
Agua Prieta, State of Sonora.
After a technical economic assessment by Sargent and Lundy (May 2006) and a consultancy by Spencer Management, the World Bank task team has concluded that “the
500 MW 2x2x1 CCGT arrangement enhances the contribution and effi ciency of the solar component”. In addition, the larger size of the thermal component does not affect
the contribution of the project to reduce either the long term cost of the technology or the amount of GHG emissions. In fact, the installation of the solar fi eld in Mexico will
build local technical capacity with the potential to trigger replication in the country with either gas or coal based power facilities. The chances for this are particularly high for
Mexico, given the culture of entrepreneurship exhibited by CFE engineers with other technologies such as geothermal.
Expected project time schedule
June 2006: invitation for tenders (published).
September 2006–January 2007: start construction.
April 2009: Grid connection.
Project developer/Prequalifi ed developers
In the IPP bidding procedure in 2002, several companies were submitting bids. However, there was very little interest for offering the solar fi eld because the solar-fi eld-only
was an option for the CC plant. The bidding was stopped by CFE when it became clear that the above-mentioned hen-egg-problem could not be resolved. According to
current planning, the next bidding will occur in 2006. According to Mexican law, no prequalifi cation of bidders occurs.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
118
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Financing structure
CFE is paying for the combined cycle, for the land (CC+SF), and for O&M. WB is paying for the solar fi eld investment and the excess power block investment.
(CFE fi nancing procedure: CFE is applying for the investment fi nancing within its annual investment plan at the Mexican Treasury, which has to approve the investment
in agreement with the Congress.)
The investment for the thermal portion of the Solar Thermal Hybrid Plant Agua Prieta II has been approved by Treasury and Congress.
Final owner of plant
Comisión Federal de Electricidad (CFE)
Institutional frame in host country
The main electricity company in Mexico is CFE, a state-owned utility. CFE is responsible for the whole country, except for the central area of Mexico City, which is served by
for the electricity market
a CFE-owned daughter (Luz y Fuerza del Centro – LFC). CFE has a similar structure and spirit as EDF in France who contributed to set up CFE.
The revenue of CFE is part of the federal budget (same as the oil company Pemex). Subsidies and profi ts must balance (requirement from Ministry of Treasure) but
currently subsidies to CFE are higher (source: Gabriela Elizondo, Feb05). It seems diffi cult to compensate this with the tariffs (subsidized tariffs for the residential and
agricultural sector, the subsidies are planned to be reduced (POISE – Programa de Obras e Inversiones del Sector Eléctrico 2004–13).
CFE has a legally fi xed least-cost expansion plan (law: LSPEE); investments have to be justifi ed in compliance with the objective to provide the least-cost electricity.
The Mexican power sector is open to competition in a limited way. There are three types of projects:
Build-lease-transfer (CAT): the acceptor of the bid provides the fi nancing, the detailed engineering, and the construction. These projects are operated by CFE and use
fi nancial means belonging to a trusteeship until the investment is covered by CFE, when CFE acquires plant ownership.
Financed-built-transfer projects (OPF): same as CAT with the only difference that the fi nancing is provided by CFE.
Independent Power Producers (PIE): the acceptor of the bid provides the fi nancing, builds the plant, operates it, and owns it.
Institutional frame in host country
Currently no green tariffs exist in Mexico, but a new law on renewables is in preparation looking at these issues. It is not yet clear how or if this law will justify excess
for renewables
costs related to current status of CSP technology, especially against the background of the least-cost-obligation. In the past, CFE has been more reluctant to invest in
renewables plants. Mexico has a capacity payment for generation capacities (subsidy for availability); hydroelectric power is considered as intermittent and does not
receive this subsidy.
The current CFE plant portfolio contains the following renewable energy sources:
Hydroelectric power plants
These are considered cost-competitive during the demand peak.
Geothermal power plants
These are cost-effective.
Wind energy
According to CFE calculations, wind energy (LEC 4-7c/kWh) cannot compete with CC technology, however it can compete with coal-fi red power stations. Furthermore,
wind energy is considered useful to help diversifi cation (fuel) and is considered environmentally friendly. (It has not become clear how strictly the least-cost-obligation
is being applied against other criteria (as e.g. fuel diversifi cation). Apparently, wind energy does not fully meet the least-cost requirement. However, approximately
400 MW of wind turbines will be installed over the next 10 years.)
Country/Location
Mexico/Sonora State, Aqua Prieta
119
A
NNEX
4
–
C
HARACTERIZATION
OF
THE
GEF F
OUR
-C
OUNTRY
P
ORTFOLIO
Photovoltaics
In Mexico, 5 percent of the 103 million inhabitants are not connected to the grid. During the last nine years, 42,000 small solar modules have been installed to
serve the same amount of houses. This will be a widely applied technology in the future for populations pending electrifi cation in rural areas.
Key governmental institutions and
CFE: Mexico’s main electricity company
their interests
Mexico’s Ministry or Energy (SENER)
Mexico’s Treasury Ministry, to approve the fi nancing of new plants
Structure of the Mexican energy sector:
Source: Information provided by CFE.
Energy Policy Objectives (SENER):
Increase the quality of life of the Mexican people;
Promote a rational use of resources in the context of sustainable development and intergenerational equity;
Promote investment in productive and feasible projects for Mexico;
Generate an elastic supply of hydrocarbons;
Increase productivity in the sector; and
Achieve a competitive pricing policy.
Ministry of
Energy
CRE
Energy Regulatory
Commission
CNSNS
National Nuclear
Safety
Commission
CONAE
National
Commission for
Energy Savings
PEMEX
Mexican Petroleum
Company
CFE
Federal Electricity
Commission
LyIFC
Light and Power
Company for
the Center
ININ
National Nuclear
Research Institute
IMP
Mexican Petroleum
Institute
IIE
Electric Research
Institute
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
120
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Tariff structure in country
The large-scale industry (high and medium voltage customers), companies and high-level consuming households (low level voltage customers) are paying a price calculated
from the fuel price development and a price component depending on the indices of the producing branches: machinery and equipment, basic metallurgy, and other
manufacturers. The residential and agricultural sectors pay subsidized tariffs.
Description of the electric power system
Concerning gas and oil reserves, Mexico ranks (worldwide):
9th in crude oil proven reserves;
21st in natural gas proven reserves;
7th in crude oil production; and
8th in natural gas production.
Despite these promising numbers, Mexico is a net importer of natural gas; about 30 to 40 percent of total gas consumption is imported.
The country has 45 GW installed capacity (gross capacity in 2003). The power generation system of CFE by produced amount of energy is given in the following graph
(only grid-connected plants).
Source: Information provided by CFE.
Accordingly, the use of fossil energy sources accounts for 82 percent of annual energy production.
Self-producing (autonomous) units account for 9.4 percent of national electricity production. The past and future (forecasted) electricity consumption are given in the
following
graph:
Country/Location
Mexico/Sonora State, Aqua Prieta
Combined Cycle,
27.0%
Turbogas, 3.4%
Internal combustion
engine, 0.4%
Dual-firing,6.8%
Coal-fired power
stations, 8.2%
Geothermal and wind,
3.1%
Nuclear power,
5.2%
Hydroelectric power,
9.7%
Conventional Rankine,
36.2%
121
A
NNEX
4
–
C
HARACTERIZATION
OF
THE
GEF F
OUR
-C
OUNTRY
P
ORTFOLIO
Source: Information provided by CFE.
For the years 2004–13 (being the reporting period of the latest CFE electrifi cation plan POISE), CFE predominantly plans to build combined cycle plants, with a total
capacity of 13.0 GW. The arguments are high effi ciency, and thereby air cleanliness for critical zones. According to POISE, combined cycles offer the fl exibility to use
alternative (future) fuels like gasifi cation of other energy sources (e.g. from PEMEX refi neries, gasifi ed coal, or waste).
The electricity production from heavy fuel oil becomes less attractive because its production in Mexico is decreasing. Nuclear energy is not considered to be practicable
(Mexico already has one nuclear power plant). The utilization of coal is limited due to necessary infrastructure (e.g. port), environmental aspects, and importation of
this
fuel.
In the face of possibly future high natural gas prices or possible future limitations of gas procurement by PEMEX (Petróleos Mexicanos) or limitations from US-American
importations, CFE has taken action such as gas drilling (Altamira and another drilling in the Pacifi c Ocean). For the future, CFE permanently studies other generation
technologies like renewable energies or combined cycles with gasifi cation of coal and waste. Beyond the planned 13.0 GW of CC plants, 3.2 GW hydroelectric, 0.7 GW
coal-fi red Rankine, 1.0 GW gas turbine, 0.1 GW internal combustion (e.g. Diesel), and 0.4 GW wind and 6.7 GW of not yet defi ned plant types are being planned.
CFE has many old plants with low effi ciencies and high costs that are only used for peaking power generation. In the forecasted period (2004–13) 4.2 GW of these plants
will be taken off the grid to improve the competitiveness of CFE’s power plant assembly.
In 2003, Mexico exported 765 GWh
el
to California and 188 GWh
el
to Belize; the cumulative imports amounted to 71 GWh
el
.
Near-term strategy for CSP in the country
Besides one 25 MW
el
solar fi eld (to be integrated into the CC plant “Baja California III”) no other solar thermal power projects are mentioned in Mexico’s electrifi cation
plan for the years 2004–13.
View of the country on a mid-term strategy
Once successful experiences have been completed with a fi rst solar thermal power plant (i.e. the ISCCS plant), a further expansion of CSP technology is likely, esp. in the
for CSP with possible future options
face of rising fossil fuel prices and favorable solar conditions in Mexico (personal communication of Juan Granados, CFE). This has happened with wind energy: After 10
(5–10 years)
years of successful operation of a fi rst wind turbine, several wind parks with a total capacity of several 100 MW are now being projected.
0
50
100
150
200
250
300
TWh
350
Autoabastecimiento
Ventas sector público
1993 1995 1997 1999 2001 2003 2005 2007 2009 2011 2013
Histórico
177.0
160.4
Pronóstico
Consumo total
305.8
279.3
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
122
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Country/Location
Morocco/Ain Beni Mathar
Type of technology
Parabolic Trough integrated with a combined cycle plant
Technical parameters
200–250 MW
el
, of which 20–30 MW solar, 220,000 m
2
parabolic trough fi eld. Expected annual net production of 1,590 GWh per year. The solar output is estimated at
3.5 percent of the annual production representing 55 GWh per year.
Link to the gas pipeline Maghreb-Europe (Algeria to Spain) (12 km connection). Morocco is entitled to about 10 percent from the gas transited through this pipeline. So
far, it has not used all its entitlement.
Business model
EPC (Engineering, Procurement & Construction = Turnkey contract) with O&M. Following an unsatisfactory response to an original competitive bidding of an IPP, Morocco’s
public power utility ONE has decided to fi nance the solar thermal plant itself. Contract common for the solar and the fossil part. 5-year O&M contract. This contract can be
renewed for another 5-year period. The O&M contract will ensure appropriate incentives for the operation of the plant, including to the full capacity utilization of the solar
fi
eld..
Liability provisions
(in particular for hybrid)
Status of plant
The bid document has been completed by Fichtner Solar and reviewed with the client (Offi ce National d’Électricité). Beginning March 2005, the bid document has been
submitted to the World Bank for “Non-Objection.” The two-stage bid documents were issued to the prequalifi ed bidders in July 2005. The technical and fi nancial proposals
were opened May 2006.
Expected project time schedule
Allowing for normal time span for bid evaluation, and contract negotiations, it is expected that the EPC with O&M contract for the project can be signed by the end of
2006, and at the latest in January 2007; expected start of operation of the plant is mid-2009 (construction time 30 months).
Project developer/Prequalifi ed developers
The prequalifi cation of potential contractors had been completed in 2004. There were applications from seven international consortia, out of which four have been
prequalifi
ed.
Financing structure
Total cost of plant is expected be around $243 million. This includes transmission lines and substations, connection to gas pipeline, land acquisition, boreholes, access road
and engineering and supervision.
GEF grant (20 percent): $50 million (incremental cost due to solar thermal component).
O.N.E. will bear about 16 percent of the total cost of the project.
Remaining from African Development Bank as a loan (The Board of the ADB has already approved the co-fi nancing for this project in March 2005): about $156 million.
Final owner of plant
Offi ce National de l’Electricité ONE
Institutional frame in host country for the
The Moroccan electricity market is being structured into a competitive part of the market (for industrial consumers) and a regulated single-buyer market (for residential
electricity market
consumers). Both parts are expected to converge towards a fully open whole sale market for electricity. Morocco is interconnected with Spain and Algeria. ONE will
continue to be solely responsible for transmission .
The program by ONE for the development of its transmission network (3 billion Dirham,
€
270 million) has the objective to enforce the reliability and the security of its
functioning, as well as the exchange with the neighbours in view of the opening of the national electricity market to competition and its integration into a vaster European-
Maghreb market. This programme foresees notably: (1) the doubling of the interconnection with Spain, already done in December 2005 ; (2) the reinforcement of the
interconnection with Algeria; (3) the development of the 400 kV grid towards the centre (Mediouna) and the East (Oujda) with the construction of 3 400 kV/225 kV
stations; (4) The extension of the 225 kV grid; and (5) the modernisation of the national dispatching.
123
A
NNEX
4
–
C
HARACTERIZATION
OF
THE
GEF F
OUR
-C
OUNTRY
P
ORTFOLIO
Institutional frame in host country for
Objective to increase the share of (new) renewables from 0.24 percent in 2003 to 10 percent in 2011 and close to 20 percent in 2020.
renewables
Since June 2004, Morocco has a national plan for the development of renewables and for the improvement of energy effi ciency (EE). This is an indication of the political
will to integrate renewables into the national energy landscape with quantifi ed objectives. The plan shall contribute to the national objectives of supply security at the lowest
cost, general access to energy, the preservation of the environment, and more generally to sustainable development. It foresees the production of electric power of
600 MW from wind parks and thermo-solar hybrid plants; the exploitation of biomass and cogeneration; and a program for the creation of 1,000 micro enterprises for
energy services close to the user, and decentralized electrifi cation of about 150,000 rural households under the rural electrifi cation program.
Key governmental institutions and
ONE: Morocco has a strong need for new capacity: peak power in July was 3,190 MW, which is only 12 percent above the available capacity (available capacity is less
their interests
than installed capacity).
Government of Morocco/Ministry of Energy: enabling Morocco to embark on a path of sustainable development in accordance with its commitments under the 2002 Johan
nesburg World Summit for Sustainable Development and the 1997 Kyoto Protocol to the Climate Change Convention.
Centre de Développement des Energies Renouvelables (CDER)
Tariff structure in country
Electricity tariffs to consumers are high in Morocco due to the taxes: 7–8c/kWh. This is pressure to lower the costs, especially to industry (tariffs have been lowered by 36
percent)
Description of the electric power system
As of September 2004, the power plants owned by ONE are 26 hydropower plants (total installed power 1,265 MW), 5 thermal power plants based on steam generation
(2,574 MW), 7 power plants based on gas turbines and several diesel plants (784 MW), wind turbines (54 MW), or in total an installed power of 4,508 MW). 40
percent of the capacity is working less than 5 hours a day.
The vast majority of Morocco’s electricity is generated in thermal power plants that burn oil and coal. All of the oil is imported, and most of the coal comes from South Africa
(the United States and Columbia are also key suppliers). The country’s two largest electricity power station are located at Mohammedia and Jorf Lasfar. Sixty percent of the
hydropower is concentrated in the fi ve largest hydro plants: Bine el Ouidane in Azilal (capacity 1.38 billion m
3
), Idriss 1er on the Oued Sebou (1.186 billion m
3
), Al
Massira at Settat (2.76 billion m
3
), al Wahda (3.8 billion m
3
) and Ahmed el Hansali in Zaouiyat Echeikh (0.74 billion m
3
).
The year 2004 registered a strong increase in electricity demand of 7 percent and this for the second year in a row; demand has now reached 17,946 GWh. Some
56.4 percent of demand was met by IPPs, 35 percent by the power plants exploited directly by ONE, and 8.6 percent by imports through the interconnection with Spain.
Hydroelectricity production reached 1,591 GWh (a 10.4 percent increase compared to 2003) and represents 8.9 percent of electricity demand.
Near-term strategy for CSP in the country
Power projects near fi nalization:
First gas-fi red combined cycle plant of Tahaddart: Power 385 MW, Owner: E.E.T (Energie Electrique de Tahaddart, created for this purpose. 48 percent of the capital is
owned by ONE, 32 percent by Endesa Europa and 20 percent by Siemens Project Ventures), Operator: Siemens O&M, Cost
€
285 million, Start: April 2005. 20 years
Power Purchasing Agreement E.E.T – ONE. Financing: 25 percent of the investment is fi nanced by the provision of capital, the remainder by two loans raised on the
Moroccan market at the Banque Centrale Populaire BCP and a consortium constituted by the BCP, the BMCE Bank and the CA.
Hydro pumping station of Afourer, Power 463 MW, Owner and operator ONE, Cost 1,700 million Dirham (about
€
155 million), Financing: European Investment Bank
and Arab Fund for Economic and Social Development. Start: 2005.
Wind park of Essaouira, Power 60 MW, mean annual production 210 GWh, Owner and operator ONE, Cost 650 million Dirham (about
€
60 million), Financing: Loan
€
50 million from KfW. Start of operation: end of 2006.
Wind park of Tanger, Power 140 MW, mean annual production 510 GWh, Owner and operator ONE, Cost 1,800 million Dirham (about
€
165 million), Financing:
Loan
€
80 million from the European Investment Bank,
€
50 million from KfW, Agence Française de Développement, ONE. Start of operation: beginning 2007.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
124
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
Hydropower plant Tanafnit-El Borj, Power 2 x 9 MW MW, mean annual production 100 GWh, Owner and operator ONE, Cost
€
61 million, Financing: Loan
€
61
million from KfW. Start of operation: second half of 2007.
Installed Power
Short term projects
MW
Start
Combined cycle plant Tahaddart
385
2005
Pumping station Afourer
463
2005
Transfer of 3 gas turbines from Tan Tan to Laâyoune
100
2005
Wind Park Essaouira
60
2006
Wind Park Tanger
140
2007
Solar thermal plant Ain Beni Mathar
200–250 MW
2009
Hydroelectric complex Tanafnit El Borj
2x9 MW et 2x13 MW
2007
Performance boost for the thermal power plant of Mohammedia
600
2007
Source: Authors based on internet data from ONE.
Rural electrifi cation: The PERG global program for rural electrifi cation was approved in the Government Council in August 1995 and put into practice starting 1996. ONE,
which is responsible for carrying out the program of rural electrifi cation, has accelerated the pace since 2002 to generalize the access to electricity by 2007 rather than
2010 as originally foreseen. At the end of 2007, the PERG will have contributed to electrify 34,400 villages, of which more than 28,000 are linked to the national grid,
thus providing access to electricity for 12 million people for a global budget of around 20 billion Dirham (close to
€
2 billion). This objective will be realized to 91 percent
by linking the consumers to the grid and by 7 percent through decentralized electricity generation with PV installations. At the end of 2003, a budget of about 12.3 billion
Dirham (more than
€
1 billion) was engaged by ONE to electrify 13,235 villages (989,946 homes, 6,434,000 rural inhabitants). The rural electrifi cation level, which
was 18 percent in 1995, reached 62 percent at the end of 2003, and 72 percent at the end of 2004 with the connection of 187,000 homes to the electric grid. ONE
projects to connect 4,000 villages in 2005, with 200,000 homes. The investment will reach
€
420 million, of which part is used for solar energy equipment for
22,000
houses.
Conclusion: The hybrid solar thermal plant of Ain Beni Mathar is a fi rm part of the short to medium strategy for the expansion plans of
the electric sector in Morocco. Together with the recent commitment of the African Development Bank to engage fi nancing, the chances
for the project taking up operation by 2009 appear high.
View of the country on a mid-term strategy
The new 5-years plan (2005–2010) of ONE foresees investments of the order of 30 billion Dirham (
€
2.7 billion).
for CSP with possible future options
Longer-term power projects:
(5–10 years)
Second gas-fi red combined cycle plant of Tahaddart: Power 400 MW. Start of operation: 2008–2009
Combined cycle plant de Al Wahda (Province de Sidi Kacem): 800 MW. Start of operation: 2008–2009. Invitation for the expression of interest launched
March 2005 in view of the prequalifi cation of companies.
Conclusion: New solar thermal plants are so far not part of the mid-term strategy for the expansion of the electricity sector in Morocco
(time horizon 2005–2010). However, ONE plans to consider solar thermal option further in an early stage of realization of the fi rst plan
at Ain Beni Mathar.
Country/Location
Morocco/Ain Beni Mathar
125
A
N N E X
4
–
C
H A R A C T E R I Z A T I O N
O F
T H E
GEF F
O U R
-C
O U N T R Y
P
O R T F O L I O
Additional information for Morocco:
F
IGURE
24: D
AILY
LOAD
CURVE
OF
THE
M
OROCCAN
ELECTRICITY
SYSTEM
(
OVER
THE
YEAR
AND
OVER
THE
WEEK
)
May
June
July
Aug
Sept
Oct
Nov
Dec
Jan 2005
Feb
April
Feb 2004
March
1,000
1,500
2,000
2,500
3,000
3,500
MW
Hour
0
2
4
6
8 10 12 14 16 18 20 22 24
Winter Summer
Charge curve Morocco Feb 2004–Feb 2005
(first Tuesday in each month)
Thu 6
Fri 7
Sat 8
Sun 9
Wed 5
Mon 3
Tue 4
1,000
1,500
2,000
2,500
3,000
3,500
MW
Hour
0
2
4
6
8
10 12
14
16
18 20
22
24
Charge curve Morocco week 3–9 January 2005
Source: Authors, based on ONE.
F
IGURE
25: G
ROWTH
IN
ELECTRICITY
DEMAND
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
GWh
1990
1992
1994
1996
1998
2000
2002
2004
Growth in final electricity demand in Morocco 1990–2002
Source: Authors based on ENERDATA Database.
T
ABLE
12: O
VERVIEW
OF
POWER
PLANTS
OWNED
BY
ONE
IN
M
OROCCO
(2004)
Installed Power in MW
26 hydropower stations
1,265
Pumping station and turbines of Afourer
233
5 thermal power stations (steam)
2,385
Coal-fi red
1,665
Oil-fi red
720
6 gas turbines
615
Diesel
69
Total thermal plants
3,069
Wind (of which 50 MW from the CED*)
54
Total ONE
4,621
Source: Authors based on internet data from ONE.
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
126
A
SSESSMENT
OF
THE
W
ORLD
B
ANK
/GEF S
TRATEGY
FOR
THE
M
ARKET
D
EVELOPMENT
OF
C
ONCENTRATING
S
OLAR
T
HERMAL
P
OWER
T
ABLE
13: E
LECTRICITY
PRODUCED
BY
TYPE
OF
POWER
PLANT
IN
M
OROCCO
(2004)
(GWh)
Part
(%)
Thermal ONE
4,648
25.9
Hydro 1,600
8.9
Wind 13
0.1
Concession
10,122
56.4
JLEC: Jorf Lasfar Energy Compagny JLEC
9,936
55.4
Compagnie Eolienne de Détroit CED (Wind)
186
1.0
Contributions from third
72
0.4
Balance of exchange
1,535
8.6
Morocco – Spain
1,554
8.7
Morocco – Algeria
–19
–0.1
Auxiliary consumption and compensators
–33
–0.2
STEP (Energy absorbed by the pumping)
–10
–0.1
Total electricity called
17,945
100
Source: Authors based on internet data from ONE.
T
ABLE
14: T
HERMAL
POWER
PRODUCTION
IN
M
OROCCO
(2004)
Fuel
Net production in GWh
Part (%) *
Coal 12,520
85.8
Jorf Lasfar
9,936
68.1
Mohammedia
1,571
10.8
Jérada
1,012
6.9
Fuel oil
2,061
14.1
Mohammedia
1,113
7.6
Kénitra
768
5.3
Gas turbines
126
0.9
Laâyoune + Dakhla
53
0.4
Gas oil
4
0.0
Total thermal
14,584
100
* in relation to the total thermal production
Source: Authors based on internet data from ONE.
T
ABLE
15: H
YDROPOWER
PRODUCTION
IN
M
OROCCO
(2004)
Installed Power *
Net production
MW
GWh
Part (%)
Bine El Ouidane
135
130,302
8.1
Afourer 94
304,594
19.0
Step Afourer
233
10,329
0.6
Hassan 1er
67
55,414
3.5
Moulay Youssef
24
43,351
2.7
Al Massira
128
66,784
4.2
Imfout 31
17,735
1.1
Lalla Takerkoust
12
14,544
0.9
M. Eddahbi
10
13,194
0.8
El Kansera
14
17,044
1.1
Oued El Makhazine
36
67,992
4.2
Lau 14
33,155
2.1
Idriss 1er
41
110,417
6.9
Allal El Fassi
240
162,432
10.1
Al Wahda
240
319,948
20.0
Mohammed El Khamis
23
46,477
2.9
Ahmed El Hansali
92
136,661
8.5
Ait Messouad
6
23,338
1.5
Other 58
26,619
1.7
Total hydro
1,498
1,600,330
100.0
* At the maximum slope of the dams
Source: Authors based on internet data from ONE.
127
A
N N E X
5
L
I S T
O F
I N T E R V I E W E D
P E R S O N S
African Development Bank: Nono J.S. Matondo-Fundani
Ajmer Vidyut Vitran Nigam Limited: Rajeev Agarwal
BMU – German Ministry of Environment: Joachim Nick-Leptin,
Ralf Christmann
Comisión Federal de Electricidad CFE (Mexico): Ing. Juan
Granados, Ing. Alberto Ramos
DLR (German Aerospace Center): Robert Pitz-Paal, Jürgen
Dersch, Franz Trieb
Fichtner Solar GmbH: Georg Brakmann
FlagSol GmbH: Paul Nava, Michael Geyer
Global Environment Facility GEF: Christine Woerlen
Imperial College Centre for Energy Policy and Technology:
Dennis Anderson
International Energy Agency SolarPACES: Thomas Mancini,
Michael Geyer
Kearney & Associates: David Kearney
KfW (Kreditanstalt für Wiederaufbau): Klaus-Peter Pischke
New & Renewable Energy Authority NREA (Solar Thermal
Department): Eng. Salah El Desouky, Eng. Ayman M Fayek,
Eng. Khaled M Fekry
National Renewable Energy Laboratory NREL: Henry Price,
Mark Mehos, Tom Wil-liams
Offi ce National de l’Electricité: Omar Benlamlih, Abdallah
Mdarhri, AbdelazizMr. Houachmi, Azzedine Khatami
Rajasthan Renewable Energy Corporation RREC: Shri Rakesh
Verma (Chairman and Managing Director) and S.L. Surana
Rajasthanstahan Vidyut Vitran Nigam: Shri Salauddin
Ahmed
Sandia National Laboratories: Thomas Mancini
Schott-Rohrglas GmbH: Nikolaus Benz
Siemens Financial Services: Jürgen Ratzinger
Siemens Power Generation: Thomas Engelmann
Solargenix: Gilbert Cohen
Solel, Inc.: David Saul
US Department of Energy DoE: Thomas Rueckert
VDI/VDE (Verein Deutscher Ingenieure/Verband der Elektro-
technik Elektronik Informationstechnik e.V.): Ludger Lorych
World Bank: Gabriela Azuela, Anne Bjerde, Chandrasekar
Govindarajalu, Charles Feinstein, Rohit Khanna, Todd Johnson,
Rene Mendonca, Pedro Sanchez
World Bank Global Environment Facility
Coordination Team Environment Department
THE WORLD BANK
1818 H Street, NW
Washington, D.C. 20433, USA
Telephone: 202.473.1816
Fax: 202.522.3256
Email: GEOnline@worldbank.org
Web: www.worldbank.org/gef