background image

NIST NCSTAR 1-1 (Draft)

 

Federal Building and Fire Safety Investigation of the 
World Trade Center Disaster 

 

Design, Construction, and 
Maintenance of Structural and Life 
Safety Systems (Draft) 

 

 

 

H. S. Lew 

Richard W. Bukowski 

Nicholas J. Carino 

 

 

 

 

 

 

For Public Comment

 

 

 

 

 

 

background image
background image

NIST NCSTAR 1-1 (Draft) 

For Public Comment 

Federal Building and Fire Safety Investigation of the 
World Trade Center Disaster 

 

Design, Construction, and 
Maintenance of Structural and Life 
Safety Systems (Draft) 

 

 

 

H. S. Lew 

Richard W. Bukowski 

Nicholas J. Carino, retired 

Building and Fire Research Laboratory 

National Institute of Standards and Technology 

 
 
 
 
September 2005 

 

 

 

 

 

 

 
 
U.S. Department of Commerce 

Carlos M. Gutierrez, Secretary 

 

Technology Administration 

Phillip J. Bond, Under Secretary for Technology

 

 

National Institute of Standards and Technology 

Hratch G. Semerjian, Acting Director

 

background image

 

 

Disclaimer No. 1 

Certain commercial entities, equipment, products, or materials are identified in this document in order to describe a 
procedure or concept adequately or to trace the history of the procedures and practices used.  Such identification is 
not intended to imply recommendation, endorsement, or implication that the entities, products, materials, or 
equipment are necessarily the best available for the purpose.  Nor does such identification imply a finding of fault or 
negligence by the National Institute of Standards and Technology. 

 

Disclaimer No. 2 

The policy of NIST is to use the International System of Units (metric units) in all publications.  In this document, 
however, units are presented in metric units or the inch-pound system, whichever is prevalent in the discipline.   

 

Disclaimer No. 3 

Pursuant to section 7 of the National Construction Safety Team Act, the NIST Director has determined that certain 
evidence received by NIST in the course of this Investigation is “voluntarily provided safety-related information” that is 
“not directly related to the building failure being investigated” and that “disclosure of that information would inhibit the 
voluntary provision of that type of information” (15 USC 7306c). 

In addition, a substantial portion of the evidence collected by NIST in the course of the Investigation has been 
provided to NIST under nondisclosure agreements. 

 

Disclaimer No. 4 

NIST takes no position as to whether the design or construction of a WTC building was compliant with any code 
since, due to the destruction of the WTC buildings, NIST could not verify the actual (or as-built) construction, the 
properties and condition of the materials used, or changes to the original construction made over the life of the 
buildings.  In addition, NIST could not verify the interpretations of codes used by applicable authorities in determining 
compliance when implementing building codes.  Where an Investigation report states whether a system was 
designed or installed as required by a code 

provision

, NIST has documentary or anecdotal evidence indicating 

whether the requirement was met, or NIST has independently conducted tests or analyses indicating whether the 
requirement was met. 

 

Use in Legal Proceedings 

No part of any report resulting from a NIST investigation into a structural failure or from an investigation under the 
National Construction Safety Team Act may be used in any suit or action for damages arising out of any matter 
mentioned in such report (15 USC 281a; as amended by P.L. 107-231). 

 

 

 

National Institute of Standards and Technology National Construction Safety Team Act Report 1-1 (Draft) 
Natl. Inst. Stand. Technol. Natl. Constr. Sfty. Tm. Act Rpt. 1-1 (Draft), 275 pages (September 2005) 
CODEN: NSPUE2 

 
 
 
 
 
 

U.S. GOVERNMENT PRINTING OFFICE 
WASHINGTON: 2005

 

_________________________________________ 
 

For sale by the Superintendent of Documents, U.S. Government Printing Office 
Internet: bookstore.gpo.gov — Phone: (202) 512-1800 — Fax: (202) 512-2250 
Mail: Stop SSOP, Washington, DC 20402-0001

background image

 

NIST NCSTAR 1-1, WTC Investigation

 iii

 

A

BSTRACT

 

The collapse of World Trade Center (WTC) 1, 2, and 7 resulted from structural damage from direct and 
indirect effects of aircraft impact and the ensuing fires.  Thus, for collapse analyses of these buildings, 
knowledge of the physical state of the structural and fire safety systems prior to the aircraft impact is 
essential.  To obtain information for the collapse analysis of the buildings, National Institute of Standards 
and Technology reviewed design and construction documents, correspondence, and memoranda related to 
the building projects; interviewed individuals involved in the design, construction, and maintenance of the 
buildings; obtained information from regulatory and emergency services agencies of New York City; and 
reviewed books and published journal and magazine articles related to the WTC building projects.  
Information obtained from various sources are synthesized and summarized in this report. Specifically, 
this report presents (1) provisions used to design and construct the structural, fire protection and egress 
systems of the buildings; (2) tests performed to support the design of these systems; (3) criteria that 
governed the design of the structural and fire protection systems; (4) methods used to proportion 
structural members and other components of the buildings; (5) innovative features, technologies and 
materials that are incorporated in design and construction of the structural and fire protection systems; 
(6) details of variances to the contract documents granted by Port Authority of New York and 
New Jersey; (7) fabrication and inspection requirements at the fabrication yard; and (8) inspection 
protocols during construction.  

This report also documents the fuel system for the diesel generators that supplied emergency power to 
many of the tenants in WTC 7. 

Findings from the synthesis of the information collected and resulting issues are presented. 

Keywords: Buildings, codes, construction, design, egress, elevators, fire, loads, maintenance, regulations, 
standards, World Trade Center. 

 

background image

Abstract 

 

Draft for Public Comment 

iv 

NIST NCSTAR 1-1, WTC Investigation

 

 

This page intentionally left blank. 

 

background image

 

WTC Investigation, NIST NCSTAR 1-1

 

v

 

T

ABLE OF 

C

ONTENTS

 

Abstract ........................................................................................................................................................iii

 

Table of Contents .......................................................................................................................................... v

 

List of Figures .............................................................................................................................................. xi

 

List of Tables .............................................................................................................................................xiii

 

List of Acronyms and Abbreviations .......................................................................................................... xv

 

Metric Conversion Table ........................................................................................................................... xix

 

Preface .....................................................................................................................................................xxiii

 

Acknowledgments..................................................................................................................................xxxiii

 

Executive Summary ................................................................................................................................ xxxv

 

Chapter 1 
Introduction ................................................................................................................................. 1

 

1.1

 

Background ...................................................................................................................................... 1

 

1.2

 

Scope of Report ............................................................................................................................... 1

 

1.3

 

Design and Construction Requirements for WTC 1, 2, and 7 ......................................................... 4

 

1.4

 

Organization of Report .................................................................................................................... 5

 

Chapter 2 
Description of WTC 1, 2, and 7 .................................................................................................. 7

 

2.1

 

Site Plan of WTC Complex ............................................................................................................. 7

 

2.2

 

Description of WTC 1 and WTC 2 .................................................................................................. 7

 

2.2.1

 

Building Description ............................................................................................................ 7

 

2.2.2

 

Structural Description........................................................................................................... 9

 

2.3

 

Description of WTC 7.................................................................................................................... 13

 

2.3.1

 

Building Description .......................................................................................................... 13

 

2.3.2

 

Structural Description......................................................................................................... 14

 

Chapter 3 
Development of Building Codes.............................................................................................. 37

 

3.1

 

Building Code Development in the United States ......................................................................... 37

 

3.2

 

New York City Building Code ...................................................................................................... 38

 

3.3

 

Port Authority Policies for Design and Modifications to Buildings .............................................. 40

 

3.3.1

 

Procedures for PANYNJ Owned Projects .......................................................................... 40

 

background image

Table of Contents 

 

Draft for Public Comment 

vi

 

NIST NCSTAR 1-1, WTC Investigation

 

3.3.2

 

Review of Tower Plans by New York City Department of Buildings ............................... 41

 

3.3.3

 

Procedures for Tenant Alteration Projects.......................................................................... 42

 

Chapter 4 
Code Provisions for Structural Design ................................................................................... 43

 

4.1

 

Contemporaneous Codes ............................................................................................................... 43

 

4.2

 

Loads 44

 

4.2.1

 

Dead Loads......................................................................................................................... 44

 

4.2.2

 

Live Loads.......................................................................................................................... 45

 

4.2.3

 

Wind Load.......................................................................................................................... 47

 

4.2.4

 

Earthquake Load................................................................................................................. 49

 

4.2.5

 

Other Loads ........................................................................................................................ 50

 

4.2.6

 

Distribution of Loads.......................................................................................................... 51

 

4.3

 

Design standards ............................................................................................................................ 52

 

4.3.1

 

Design Standards ................................................................................................................ 52

 

4.3.2

 

Load Combinations ............................................................................................................ 53

 

4.4

 

Alteration of Existing Buildings .................................................................................................... 55

 

4.5

 

Materials and Methods of Construction......................................................................................... 56

 

4.6

 

Stability, Bracing, and Secondary Stresses.................................................................................... 58

 

4.7

 

Deflection Limitations ................................................................................................................... 59

 

4.8

 

Load Tests...................................................................................................................................... 59

 

Chapter 5 
Structural Design of WTC 1, 2, and 7 ...................................................................................... 63

 

5.1

 

Design Criteria ............................................................................................................................... 63

 

5.1.1

 

Loads .................................................................................................................................. 63

 

5.1.2

 

Live Load Reduction .......................................................................................................... 66

 

5.1.3

 

Wind Load.......................................................................................................................... 68

 

5.1.4

 

Aircraft Impact ................................................................................................................... 70

 

5.2

 

Structural Design Requirements .................................................................................................... 71

 

5.2.1

 

Concrete Requirements ...................................................................................................... 72

 

5.2.2

 

Steel Requirements............................................................................................................. 72

 

5.2.3

 

Methods Used to Proportion Structural Members .............................................................. 73

 

Chapter 6 
Innovative Features Incorporated in Structural Design ........................................................ 87

 

6.1

 

Innovative features......................................................................................................................... 87

 

background image

Draft for Public Comment 

Table of Contents 

NIST NCSTAR 1-1, WTC Investigation

 vii

 

6.2

 

Lateral-Load-Resisting System...................................................................................................... 87

 

6.3

 

Composite Floor System................................................................................................................ 88

 

6.4

 

Viscoelastic Damping Units .......................................................................................................... 89

 

6.5

 

Wind Tunnel Tests......................................................................................................................... 90

 

6.5.1

 

Tests Conducted at CSU..................................................................................................... 91

 

6.5.2

 

Tests Conducted at NPL..................................................................................................... 93

 

Chapter 7 
Fabrication and Construction Inspections and  Variances................................................... 97

 

7.1

 

Introduction.................................................................................................................................... 97

 

7.2

 

Fabrication Inspection Requirements for WTC 1 and WTC 2 ...................................................... 97

 

7.2.1

 

Floor Trusses ...................................................................................................................... 98

 

7.2.2

 

Box Core Columns and Built-Up Beams ........................................................................... 98

 

7.2.3

 

Exterior Columns from Elevation 363 ft to the 9th Floor Splice ..................................... 100

 

7.2.4

 

Exterior Columns Above the 9th floor Splice .................................................................. 100

 

7.2.5

 

Rolled Columns and Beams ............................................................................................. 101

 

7.2.6

 

Other Requirements.......................................................................................................... 101

 

7.3

 

Fabrication Inspection Requirements for WTC 7 ........................................................................ 102

 

7.4

 

Inspection During Construction ................................................................................................... 102

 

7.4.1

 

Erection Marks and Marking System WTC 1 and WTC 2............................................... 103

 

7.4.2

 

Quality Control and Inspection Program for WTC 1 and WTC 2.................................... 104

 

7.5

 

Variances Granted........................................................................................................................ 104

 

7.5.1

 

Variances Relating to Fabrication and Erection Tolerances............................................. 105

 

7.5.2

 

Variances Relating to Defective Components.................................................................. 105

 

7.5.3

 

Variances Relating to Alternate Fabrication and Erection Procedures ............................ 106

 

7.5.4

 

Variances Relating to Product Substitutions .................................................................... 106

 

7.5.5

 

Variances Relating to Inspection Practice ........................................................................ 107

 

Chapter 8 
Structural Maintenance and Modifications During Occupancy.......................................... 109

 

8.1

 

Introduction.................................................................................................................................. 109

 

8.2

 

Tenant Construction Review Manuals......................................................................................... 109

 

8.2.1

 

1971 Edition ..................................................................................................................... 110

 

8.2.2

 

1979 Edition ..................................................................................................................... 110

 

8.2.3

 

1984 Edition, Revised 1990 ............................................................................................. 111

 

8.2.4

 

1997 Edition ..................................................................................................................... 112

 

background image

Table of Contents 

 

Draft for Public Comment 

viii

 

NIST NCSTAR 1-1, WTC Investigation

 

8.3

 

Standards for Structural Integrity Inspection of the WTC Towers .............................................. 112

 

8.3.1

 

Visual Inspections ............................................................................................................ 113

 

8.3.2

 

Review of Reports ............................................................................................................ 114

 

8.3.3

 

Periodic Measurements .................................................................................................... 115

 

8.3.4

 

Recordkeeping.................................................................................................................. 116

 

8.4

 

Standards for Architectural and Structural design ....................................................................... 117

 

8.5

 

Structural Inspection Programs.................................................................................................... 117

 

8.5.1

 

Facility Condition Survey of WTC 2 ............................................................................... 118

 

8.5.2

 

Facility Condition Survey of WTC 1 ............................................................................... 121

 

8.5.3

 

Facility Condition Survey of WTC 7 ............................................................................... 124

 

8.5.4

 

Due Diligence Condition Survey of WTC 1 and WTC 2................................................. 124

 

8.5.5

 

Structural Integrity Inspection Program ........................................................................... 125

 

8.5.6

 

Summary of Structural Integrity Inspection Programs..................................................... 133

 

8.5.7

 

Modifications and Repairs to Structural Framing Systems of WTC 1, 2, and 7 .............. 133

 

Chapter 9 
Comparison of Fire Safety Codes and Practices ................................................................. 141

 

9.1

 

Comparison of Fire Provisions in Building Codes ...................................................................... 141

 

9.1.1

 

Introduction ...................................................................................................................... 141

 

9.1.2

 

Interrelation of Codes, Standards, and Practices .............................................................. 142

 

9.1.3

 

Comparison of New York City and Contemporary Building Codes................................ 142

 

9.1.4

 

Occupancy Group............................................................................................................. 147

 

9.1.5

 

Egress Systems ................................................................................................................. 148

 

9.2

 

Summary of Differences between Codes..................................................................................... 149

 

Chapter 10 
Influence of Codes and Standards on the Design and Construction of  
WTC 1 and WTC 2 ................................................................................................................... 151

 

10.1

 

Egress SYSTEM DESIGN .......................................................................................................... 151

 

10.1.1

 

Egress Provisions from Windows on the World .............................................................. 152

 

10.1.2

 

Egress Provisions from Top of the World ........................................................................ 156

 

10.2

 

Elevators ...................................................................................................................................... 157

 

10.3

 

Active Fire Protection Systems.................................................................................................... 158

 

10.3.1

 

Fire Alarm Systems .......................................................................................................... 158

 

10.3.2

 

Fire Sprinklers .................................................................................................................. 158

 

10.3.3

 

Smoke Management ......................................................................................................... 160

 

background image

Draft for Public Comment 

Table of Contents 

NIST NCSTAR 1-1, WTC Investigation

 ix

 

10.4

 

Design and Construction of Fire Safety and Egress Systems ...................................................... 161

 

10.4.1

 

Construction Classification .............................................................................................. 161

 

10.4.2

 

Occupancy Group............................................................................................................. 161

 

10.4.3

 

Compartmentation of WTC 1 and WTC 2 ....................................................................... 161

 

10.4.4

 

Construction of Partitions and Shaft Enclosures .............................................................. 162

 

10.4.5

 

Tenant Separation Walls................................................................................................... 164

 

10.4.6

 

Egress Systems ................................................................................................................. 165

 

10.4.7

 

Elevators........................................................................................................................... 165

 

10.4.8

 

Active Systems ................................................................................................................. 165

 

Chapter 11 
Maintenance and Modifications to Fire Safety Systems ..................................................... 167

 

11.1

 

Local Laws 5 (1973) and 16 (1984)............................................................................................. 167

 

11.2

 

Code Compliance Summary Following the 1993 Bombing ........................................................ 168

 

11.3

 

WTC Due Diligence Study of November 22, 1996 ..................................................................... 169

 

Chapter 12 
WTC 7 Fuel System................................................................................................................. 171

 

12.1

 

Code Requirements...................................................................................................................... 171

 

12.1.1

 

Tanks (27-828 and 27-829) .............................................................................................. 171

 

12.1.2

 

Piping (27-830)

37

.............................................................................................................. 171

 

12.1.3

 

Power Systems Designs.................................................................................................... 172

 

12.2

 

Base Building System .................................................................................................................. 172

 

12.2.1

 

Modifications to System................................................................................................... 172

 

12.2.2

 

Ambassador Modification ................................................................................................ 175

 

12.2.3

 

American Express Modification....................................................................................... 175

 

12.2.4

 

Mayor’s Office of Emergency Management (OEM) Modification**.............................. 175

 

12.2.5

 

Salomon Brothers Emergency Power System .................................................................. 175

 

12.3

 

Possible Failure Modes ................................................................................................................ 176

 

Chapter 13 
Findings ................................................................................................................................... 179

 

13.1

 

Findings ....................................................................................................................................... 179

 

13.1.1

 

General ............................................................................................................................. 179

 

13.1.2

 

Structural Safety ............................................................................................................... 180

 

13.1.3

 

Fire Safety ........................................................................................................................ 182

 

background image

Table of Contents 

 

Draft for Public Comment 

x

 

NIST NCSTAR 1-1, WTC Investigation

 

Chapter 14 
References............................................................................................................................... 189

 

Appendix A

  

Supporting Documents for Chapter 1 ................................................................................... 193

 

Appendix B

  

Supporting Documents for Chapters 2 and 3 ...................................................................... 203

 

 

background image

 

NIST NCSTAR 1-1, WTC Investigation

 xi

 

L

IST OF 

F

IGURES

 

Figure P–1.  The eight projects in the federal building and fire safety 

investigation of the WTC disaster...................................................................................... xxv

 

 

Figure 2–1. 

WTC site plan. ..................................................................................................................... 17

 

Figure 2–2. 

West elevation of WTC 1..................................................................................................... 18

 

Figure 2–3. 

Elevation of exterior wall from foundation to floor 9.......................................................... 19

 

Figure 2–4. 

Typical WTC tower architectural floor plan........................................................................ 20

 

Figure 2–5. 

Arrangement of express and local elevators. ....................................................................... 21

 

Figure 2–6. 

Framed tube system. ............................................................................................................ 22

 

Figure 2–7. 

Cross section of perimeter columns. .................................................................................... 23

 

Figure 2–8. 

Typical WTC tower exterior wall tree panel........................................................................ 24

 

Figure 2–9. 

Typical WTC tower exterior wall panel............................................................................... 25

 

Figure 2–10.  Elevation of exterior wall frame illustrating staggered panel construction.......................... 26

 

Figure 2–11.  Typical welded box members and rolled shapes between floor 83 and floor 86. ................ 26

 

Figure 2–12.  Core column layout in WTC towers. ................................................................................... 27

 

Figure 2–13.  Typical floor-framing plan................................................................................................... 28

 

Figure 2–14.  Prefabricated floor panel used in WTC 1 and WTC 2. ........................................................ 29

 

Figure 2–15.  Typical WTC floor truss framing zone. ............................................................................... 30

 

Figure 2–16.  Position of viscoelastic damper............................................................................................ 31

 

Figure 2–17.  Perimeter column wall panel and steel truss floor modules................................................. 32

 

Figure 2–18.  Hat truss. .............................................................................................................................. 33

 

Figure 2–19.  Typical floor plan above floor 7. ......................................................................................... 33

 

Figure 2–20.  Perimeter elevations of WTC 7............................................................................................ 34

 

Figure 2–21.  Floor 1 plan of WTC 7......................................................................................................... 34

 

Figure 2–22.  Framing plan for floor 8 through floor 45............................................................................ 35

 

Figure 2–23.  Floor 5 diaphragm plan. ....................................................................................................... 35

 

Figure 2–24.  Typical built-up column details. .......................................................................................... 36

 

Figure 2–25.  Schematic view of transfer trusses and girders between floors 5 and 7............................... 36

 

 

Figure 4–1. 

Reduced live load as a function of floor location based on the percentage method (for 
columns, walls, and piers).................................................................................................... 60

 

Figure 4–2. 

Wind load pressure versus elevation.................................................................................... 61

 

background image

List of Figures 

 

Draft for Public Comment 

xii

 

NIST NCSTAR 1-1, WTC Investigation

 

Figure 5–1. 

Design dead load criteria for WTC 1 and WTC 2: floor inside of core. .............................. 74

 

Figure 5–2. 

Design partition load criteria for WTC 1 and WTC 2: floor inside of core. ........................ 75

 

Figure 5–3. 

Design dead load criteria for WTC 1 and WTC 2: floor outside of core. ............................ 76

 

Figure 5–4. 

Design load criteria for WTC 7............................................................................................ 77

 

Figure 5–5. 

Design live-load criteria for WTC 1 and WTC 2: floor inside of core. ............................... 78

 

Figure 5–6. 

Design live-load criteria for WTC 1 and WTC 2: floor inside of core. ............................... 79

 

Figure 5–7. 

Design live-load criteria for WTC 1 and WTC 2: column inside of core. ........................... 80

 

Figure 5–8. 

Design live-load criteria for WTC 1 and WTC 2: floor outside of core. ............................. 81

 

Figure 5–9. 

Design live-load criteria for WTC 1 and WTC 2: column outside of core. ......................... 82

 

Figure 5–10.  Live-load reduction criteria for WTC 1 and WTC 2............................................................ 83

 

Figure 5–11.  Live-load reduction criteria for floors inside of core, except for tenant areas. .................... 84

 

Figure 5–12.  Live-load reduction criteria for floors inside of core, tenant areas. ..................................... 85

 

Figure 5–13.  Live-load reduction criteria for floors outside of core. ........................................................ 86

 

 

Figure 6–1. 

Wide-flange beam member with Type B damping unit....................................................... 94

 

Figure 6–2. 

Wind directions that produced the greatest displacements at the top of the tower 
during the wind tunnel tests. ................................................................................................ 95

 

Figure 6–3. 

Definition of grid system and tower configurations for wind tunnel tests at Colorado 
State University.................................................................................................................... 96

 

 

Figure 10–1.  Arrangement of floor 106 egress. ...................................................................................... 154

 

Figure 10–2.  Arrangement of floor 107 egress. ...................................................................................... 155

 

Figure 10–3.  Gypsum plank shaft partition............................................................................................. 162

 

Figure 10–4.  Gypsum plank installation. ................................................................................................ 163

 

Figure 10–5.  Typical finish details.......................................................................................................... 163

 

Figure 10–6.  Stairway detail at 26th floor............................................................................................... 163

 

 

Figure 12–1.  Section plan showing the final locations of the fuel oil distribution components. ............ 174

 

 

background image

 

NIST NCSTAR 1-1, WTC Investigation

 xiii

 

L

IST OF 

T

ABLES

 

Table P–1.  Federal building and fire safety investigation of the WTC disaster. .................................... xxiv

 

Table P–2.  Public meetings and briefings of the WTC Investigation.................................................... xxvii

 

 

Table 4–1.  Examples of dead loads given in NYC Building Code and BOCA Code. .............................. 45

 

Table 4–2.  Comparison of uniform live load values.  Examples of minimum uniformly distributed 

live loads. ............................................................................................................................. 46

 

Table 4–3.  Reduced live load for beams and girders. ................................................................................ 48

 

Table 4–4.  Base shears and overturning moments from reviewed codes for a building the height of 

WTC towers (1,368 ft). ........................................................................................................ 48

 

Table 4–5.  Design standards for concrete and steel. .................................................................................. 53

 

Table 4–6.  Compliance requirements for alterations. ................................................................................ 55

 

Table 4–7.  Excerpts of inspection requirements for materials and assemblies in  Article 10 of 1968 

NYC Building Code............................................................................................................. 57

 

Table 4–8.  Excerpts of inspection requirements for methods of construction in  Article 10 of 1968 

NYC Building Code............................................................................................................. 58

 

 

Table 5–1.  Live loads used in design of WTC 1 and WTC 2. ................................................................... 65

 

Table 5–2.  Percentage of live load per the 1968 NYC Building Code. ..................................................... 66

 

Table 5–3.  Base shears and overturning moments based on the 1968 NYC Building Code and wind 

tunnel tests. .......................................................................................................................... 69

 

 

Table 8–1.  Summary of Structural Integrity Inspections Completed for WTC 1 and WTC 2. ............... 127

 

Table 8–2.  Measured first mode natural frequencies for WTC 1............................................................. 131

 

Table 8–3.  Summary of natural frequency test results for floors of WTC 1, March 1971. ..................... 132

 

Table 8–4.  Summary of natural frequency test results for floors of WTC 1 and WTC 2, March 

1995.................................................................................................................................... 132

 

 

Table 12–1.  Summary of modifications to base emergency power system in WTC 7. ........................... 173

 

 

 

background image

List of Tables 

 

Draft for Public Comment 

xiv

 

NIST NCSTAR 1-1, WTC Investigation

 

 

This page intentionally left blank.

background image

 

NIST NCSTAR 1-1, WTC Investigation

 xv

 

L

IST OF 

A

CRONYMS AND 

A

BBREVIATIONS

 

Acronyms  

3M 

 

Minnesota Mining and Manufacturing Company 

ACI 

 

American Concrete Institute 

AIA 

 

American Institute of Architects 

AISC   

American Institute of Steel Construction 

ASME   

American Society of Mechanical Engineers 

ASTM  

ASTM International 

AWCI   

Association of Wall and Ceiling Industries 

AWS   

American Welding Society 

BBC 

 

Basic Building Code 

BOCA   

Building Officials and Code Administrators International 

CMU  

concrete 

masonry 

unit 

Con Edison 

Consolidated Edison 

CSU 

 

Colorado State University 

FDNY   

New York City Fire Department 

FSES   

Fire Safety Equivalency Systems 

GA  

Gypsum 

Association 

HVAC   

heating, ventilating, and air conditioning 

IBC  

International 

Building 

Code 

JB&B   

Jaros, Baum & Bolles 

KKE 

 

Karl Koch Erecting Company 

LERA   

Leslie E. Robertson Associates 

LL  

Local 

Law 

MER   

Mechanical Equipment Room 

MCC   

Municipal Code of Chicago 

MIT 

 

Massachusetts Institute of Technology 

NBC 

 

National Building Code 

NFPA   

National Fire Protection Association 

NIST   

National Institute of Standards and Technology 

background image

List of Acronyms and Abbreviations 

 

Draft for Public Comment 

xvi

 

NIST NCSTAR 1-1, WTC Investigation

 

NPL 

 

National Physical Laboratory 

NYC 

 

New York City 

OEM   

Office of Emergency Management 

PANYNJ 

Port Authority of New York and New Jersey 

PCF 

 

Pacific Car & Foundry Co. 

PDM   

Pittsburgh-Des Moines Steel Company 

P.L.  

Public 

Law 

PONYA 

Port of New York Authority (in 1972 PONYA changed to PANYNJ) 

RJA 

 

Rolf Jensen & Associates 

RS  

Reference 

Standard 

SBCCI 

Southern Building Code Congress International, Inc., published 

Southern Standard 

Building Code 

SFRM   

sprayed fire resistive material 

SHCR   

Skilling, Helle, Christiansen, & Robertson (structural engineers) 

SII 

 

Structural Integrity Inspection 

SSPC   

Steel Structures Painting Council 

TRCC   

Tishman Realty & Construction Company 

UBC 

 

Uniform Building Code 

UL 

 

Underwriters’ Laboratories, Inc. 

USC 

 

United States Code 

WSHJ   

Worthington, Skilling, Helle & Jackson 

WTC  

World 

Trade 

Center 

WTC 1  

World Trade Center 1 (North Tower) 

WTC 2  

World Trade Center 2 (South Tower) 

WTC 7  

World Trade Center 7 

Abbreviations  

°

C  

degrees 

Celsius 

°

F  

degrees 

Fahrenheit 

cfm 

 

cubic foot per minute 

cps 

 

cycles per second 

F

y

 

 

yield strength of steel 

ft   foot 

background image

Draft for Public Comment

 

List of Acronyms and Abbreviations 

NIST NCSTAR 1-1, WTC Investigation

 xvii

 

ft

2  

square foot 

gal  

gallon 

gph 

 

gallons per hour 

in.  

inch 

in.

2

  

square 

inch 

kip 

 

a force equal to 1,000 pounds 

ksi 

 

1,000 pounds per square inch 

kW  

kilowatt 

L   liter 

lb   pound 

m   meter 

µ

m  

micrometer 

min  

minute 

mph 

 

miles per hour 

pcf 

 

pounds per cubic foot 

plf 

 

pounds per linear foot 

psf 

 

pounds per square foot 

psi 

 

pounds-force per square inch 

s   second 

 

background image

List of Acronyms and Abbreviations 

 

Draft for Public Comment 

xviii

 

NIST NCSTAR 1-1, WTC Investigation

 

 

This page intentionally left blank.

background image

 

NIST NCSTAR 1-1, WTC Investigation

 xix

 

M

ETRIC 

C

ONVERSION 

T

ABLE

 

To convert from   

 

 

 

to  

 

 

 

Multiply by 

 

AREA AND SECOND MOMENT OF AREA 

square foot (ft

2

)      

square 

meter 

(m

2

  9.290 

304 

E-02 

square inch (in.

2

     

square 

meter 

(m

2

  6.4516 

E-04 

square inch (in.

2

     

square 

centimeter 

(cm

2

)  

6.4516 

E+00 

square yard (yd

2

     

square 

meter 

(m

2

  8.361 

274 

E-01 

 

ENERGY (includes WORK) 

kilowatt hour (kW 

 

h) 

 

 

 

 joule 

(J) 

   3.6 

E+06 

quad (1015 BtuIT)   

 

 

 

 

joule (J)   

 

 

1.055 056 E+18 

therm 

(U.S.) 

      

joule 

(J) 

 

 

 

1.054 

804 

E+08 

ton of TNT (energy equivalent) 

 

 

joule (J)   

 

 

4.184 E+09 

watt hour (W 

 

h) 

     

joule 

(J) 

 

 

 

3.6 

E+03 

watt second (W 

 

s) 

     

joule 

(J) 

 

 

 

1.0 

E+00 

 

FORCE 

dyne 

(dyn)       

newton 

(N) 

 

 

1.0 

E-05 

kilogram-force (kgf) 

 

 

 

 

newton (N) 

 

 

9.806 65 E+00 

kilopond (kilogram-force) (kp) 

 

 

newton (N) 

 

 

9.806 65 E+00 

kip (1 kip=1,000 lbf) 

 

 

 

 

newton (N) 

 

 

4.448 222 E+03 

kip (1 kip=1,000 lbf) 

 

 

 

 

kilonewton (kN)    

 

4.448 222 E+00 

pound-force 

(lbf) 

     

newton 

(N) 

 

 

4.448 

222 

E+00 

 

FORCE DIVIDED BY LENGTH 

pound-force per foot (lbf/ft)   

 

 

newton per meter (N/m) 

 

1.459 390 E+01 

pound-force per inch (lbf/in.)  

 

 

newton per meter (N/m) 

 

1.751 268 E+02 

 

HEAT FLOW RATE 

calorieth per minute (calth/min) 

 

 

watt (W)   

 

 

6.973 333 E-02 

calorieth per second (calth/s)   

 

 

watt (W)   

 

 

4.184 E+00 

kilocalorieth per minute (kcalth/min) 

 

watt (W)   

 

 

6.973 333 E+01 

kilocalorieth 

per 

second 

(kcalth/s) 

 

 watt 

(W) 

   4.184 

E+03 

background image

Metric Conversion Table 

 

Draft for Public Comment 

xx

 

NIST NCSTAR 1-1, WTC Investigation

 

To convert from   

 

 

 

to  

 

 

 

Multiply by 

 

LENGTH 

foot 

(ft) 

 

       

meter 

(m) 

 

 

 

3.048 

E-01 

inch 

(in) 

       

meter 

(m) 

 

 

 

2.54 

E-02 

inch 

(in.) 

       

centimeter 

(cm)  

 

2.54 

E+00 

micron 

(m) 

      

meter 

(m) 

 

 

 

1.0 

E-06 

yard 

(yd) 

       

meter 

(m) 

 

 

 

9.144 

E-01 

 

MASS and MOMENT OF INERTIA 

kilogram-force second squared  

per meter (kgf 

 s

2

/m) 

    

kilogram 

(kg)   

 

9.806 

65 

E+00 

pound foot squared (lb 

 

ft

2

)   

 

 

kilogram meter squared (kg 

 

m

2

4.214 011 E-02 

pound inch squared (lb 

 

in.

2

)  

 

 

kilogram meter squared (kg 

 

m

2

2.926 397 E-04 

ton, 

metric 

(t) 

      

kilogram 

(kg)   

 

1.0 

E+03 

ton, short (2,000 lb)  

 

 

 

 

kilogram (kg) 

 

 

9.071 847 E+02 

 

MASS DIVIDED BY AREA 

pound per square foot (lb/ft

2

)  

 

 

kilogram per square meter (kg/m

2

4.882 428 E+00 

pound per square inch  

(

not 

pound force) (lb/in.

2

)   

 

 

kilogram per square meter (kg/m

2

7.030 696 E+02 

 

MASS DIVIDED BY LENGTH 

pound per foot (lb/ft) 

 

 

 

 

kilogram per meter (kg/m) 

 

1.488 164 E+00 

pound per inch (lb/in.)   

 

 

 

kilogram per meter (kg/m) 

 

1.785 797 E+01 

pound per yard (lb/yd)   

 

 

 

kilogram per meter (kg/m) 

 

4.960 546 E-01 

 

PRESSURE or STRESS (FORCE DIVIDED BY AREA) 

kilogram-force per square centimeter (kgf/cm

2

)  pascal (Pa) 

 

 

9.806 65 E+04 

kilogram-force per square meter (kgf/m

2

pascal (Pa) 

 

 

9.806 65 E+00 

kilogram-force per square millimeter (kgf/mm

2

)  pascal (Pa) 

 

 

9.806 65 E+06 

kip per square inch (ksi) (kip/in.

2

 

 pascal 

(Pa)   6.894 

757 

E+06 

kip per square inch (ksi) (kip/in.

2

 

 kilopascal 

(kPa) 

  6.894 

757 

E+03 

pound-force per square foot (lbf/ft

2

 pascal 

(Pa)   4.788 

026 

E+01 

pound-force per square inch (psi) (lbf/in.

2

pascal (Pa) 

 

 

6.894 757 E+03 

pound-force per square inch (psi) (lbf/in.

2

kilopascal (kPa) 

 

 

6.894 757 E+00 

psi (pound-force per square inch) (lbf/in.

2

pascal (Pa) 

 

 

6.894 757 E+03 

psi (pound-force per square inch) (lbf/in.

2

kilopascal (kPa) 

 

 

6.894 757 E+00 

background image

Draft for Public Comment 

Metric Conversion Table 

NIST NCSTAR 1-1, WTC Investigation

 xxi

 

To convert from   

 

 

 

to  

 

 

 

Multiply by 

 

TEMPERATURE 

degree Celsius (

°

C) 

     

kelvin 

(K) 

 

 

T/K 

t/

°

C + 273.15 

degree 

centigrade 

     

degree 

Celsius 

(

°

C) 

  t/

°

≈ 

t /deg. cent. 

degree Fahrenheit (

°

F) 

    

degree 

Celsius 

(

°

C) 

  t/

°

C = (t/

°

F -

 

32)/1.8 

degree Fahrenheit (

°

F) 

    

kelvin 

(K) 

 

 

T/K 

(t/

°

F + 459.67)/1.8 

kelvin 

(K)       

degree 

Celsius 

(

°

C) 

  t/

°

C = T/K 2

 

273.15 

 

TEMPERATURE INTERVAL 

degree Celsius (

°

C) 

     

kelvin 

(K) 

 

 

1.0 

E+00 

degree 

centigrade 

     

degree 

Celsius 

(

°

C) 

  1.0 

E+00 

degree Fahrenheit (

°

F) 

    

degree 

Celsius 

(

°

C) 

  5.555 

556 

E-01 

degree Fahrenheit (

°

F) 

    

kelvin 

(K) 

 

 

5.555 

556 

E-01 

degree Rankine (

°

R)     

kelvin 

(K) 

 

 

5.555 

556 

E-01 

 

VELOCITY (includes SPEED) 

foot per second (ft/s) 

 

 

 

 

meter per second (m/s) 

 

3.048 E-01 

inch 

per 

second 

(in./s) 

    

meter per second (m/s) 

 

2.54 E-02 

kilometer per hour

 

(km/h) 

 

 

 

meter per second (m/s) 

 

2.777 778 E-01 

mile per hour (mi/h) 

 

 

 

 

kilometer per hour (km/h) 

 

1.609 344 E+00 

mile per minute (mi/min) 

 

 

 

meter per second (m/s) 

 

2.682 24 E+01 

 

VOLUME (includes CAPACITY) 

cubic foot (ft

3

)  

 

 

 

 

 

cubic meter (m

3

  2.831 

685 

E-02 

cubic inch (in.

3

 ) 

 

 

 

 

 

cubic meter (m

3

  1.638 

706 

E-05 

cubic yard (yd

3

 

 

 

 

 

cubic meter (m

3

  7.645 

549 

E-01 

gallon 

(U.S.) 

(gal) 

     

cubic 

meter 

(m

3

  3.785 

412 

E-03 

gallon 

(U.S.) 

(gal) 

     

liter 

(L) 

 

 

 

3.785 

412 

E+00 

liter 

(L) 

       

cubic 

meter 

(m

3

  1.0 

E-03 

ounce (U.S. fluid) (fl oz)  

 

 

 

cubic meter (m

3

  2.957 

353 

E-05 

ounce (U.S. fluid) (fl oz)  

 

 

 

milliliter (mL) 

 

 

2.957 353 E+01 

 

background image

Metric Conversion Table 

 

Draft for Public Comment 

xxii

 

NIST NCSTAR 1-1, WTC Investigation

 

 

This page intentionally left blank.

background image

 

NIST NCSTAR 1-1, WTC Investigation

 xxiii

 

P

REFACE

 

Genesis of This Investigation 

Immediately following the attack on the World Trade Center (WTC) on September 11, 2001, the Federal 
Emergency Management Agency (FEMA) and the American Society of Civil Engineers began planning a 
building performance study of the disaster.  The week of October 7, as soon as the rescue and search 
efforts ceased, the Building Performance Study Team went to the site and began their assessment.  This 
was to be a brief effort, as the study team consisted of experts who largely volunteered their time away 
from their other professional commitments.  The Building Performance Study Team issued their report in 
May 2002, fulfilling their goal “to determine probable failure mechanisms and to identify areas of future 
investigation that could lead to practical measures for improving the damage resistance of buildings 
against such unforeseen events.” 

On August 21, 2002, with funding from the U.S. Congress through FEMA, the National Institute of 
Standards and Technology (NIST) announced its building and fire safety investigation of the WTC 
disaster.  On October 1, 2002, the National Construction Safety Team Act (Public Law 107-231), was 
signed into law.  (A copy of the Public Law is included in Appendix A.)  The NIST WTC Investigation 
was conducted under the authority of the National Construction Safety Team Act.

 

The goals of the investigation of the WTC disaster were: 

 

To investigate the building construction, the materials used, and the technical conditions that 
contributed to the outcome of the WTC disaster. 

 

To serve as the basis for: 

 

Improvements in the way buildings are designed, constructed, maintained, and used; 

 

Improved tools and guidance for industry and safety officials; 

 

Recommended revisions to current codes, standards, and practices; and 

 

Improved public safety. 

The specific objectives were: 

1.

 

Determine why and how WTC 1 and WTC 2 collapsed following the initial impacts of the 
aircraft and why and how WTC 7 collapsed; 

2.

 

Determine why the injuries and fatalities were so high or low depending on location, 
including all technical aspects of fire protection, occupant behavior, evacuation, and 
emergency response;  

3.

 

Determine what procedures and practices were used in the design, construction, operation, 
and maintenance of WTC 1, 2, and 7; and 

4.

 

Identify, as specifically as possible, areas in current building and fire codes, standards, and 
practices that warrant revision. 

background image

Preface 

 

Draft for Public Comment 

xxiv

 

NIST NCSTAR 1-1, WTC Investigation

 

NIST is a nonregulatory agency of the U.S. Department of Commerce’s Technology Administration.  The 
purposes of NIST investigations under the National Construction Safety Team Act are to improve the 
safety and structural integrity of buildings in the United States, and the focus is on fact finding.  NIST 
investigative teams are required to assess building performance and emergency response and evacuation 
procedures in the wake of any building failure that has resulted in substantial loss of life or that posed 
significant potential of substantial loss of life.  NIST does not have the statutory authority to make 
findings of fault or negligence by individuals or organizations.  Further, no part of any report resulting 
from a NIST investigation into a building failure or from an investigation under the National Construction 
Safety Team Act may be used in any suit or action for damages arising out of any matter mentioned in 
such report (15 USC 281a, as amended by Public Law 107-231). 

Organization of the Investigation 

The National Construction Safety Team for this Investigation, appointed by the NIST Director, was led 
by Dr. S. Shyam Sunder.  Dr. William L. Grosshandler served as Associate Lead Investigator, 
Mr. Stephen A. Cauffman served as Program Manager for Administration, and Mr. Harold E. Nelson 
served on the team as a private sector expert.   The Investigation included eight interdependent projects 
whose leaders comprised the remainder of the team.  A detailed description of each of these eight projects 
is available at http://wtc.nist.gov.  The purpose of each project is summarized in Table P–1, and the key 
interdependencies among the projects are illustrated in Figure P–1.   

Table P–1.  Federal building and fire safety investigation of the WTC disaster. 

Technical Area and Project Leader 

Project Purpose 

Analysis of Building and Fire Codes and 
Practices; Project Leaders: Dr. H. S. Lew 
and Mr. Richard W. Bukowski 

Document and analyze the code provisions, procedures, and 
practices used in the design, construction, operation, and 
maintenance of the structural, passive fire protection, and 
emergency access and evacuation systems of WTC 1, 2, and 7. 

Baseline Structural Performance and 
Aircraft Impact Damage Analysis; Project 
Leader: Dr. Fahim H. Sadek 

Analyze the baseline performance of WTC 1 and WTC 2 under 
design, service, and abnormal loads, and aircraft impact damage on 
the structural, fire protection, and egress systems. 

Mechanical and Metallurgical Analysis of 
Structural Steel; Project Leader: Dr. Frank 
W. Gayle 

Determine and analyze the mechanical and metallurgical properties 
and quality of steel, weldments, and connections from steel 
recovered from WTC 1, 2, and 7. 

Investigation of Active Fire Protection 
Systems; Project Leader: Dr. David 
D. Evans 

Investigate the performance of the active fire protection systems in 
WTC 1, 2, and 7 and their role in fire control, emergency response, 
and fate of occupants and responders. 

Reconstruction of Thermal and Tenability 
Environment; Project Leader: Dr. Richard 
G. Gann 

Reconstruct the time-evolving temperature, thermal environment, 
and smoke movement in WTC 1, 2, and 7 for use in evaluating the 
structural performance of the buildings and behavior and fate of 
occupants and responders. 

Structural Fire Response and Collapse 
Analysis; Project Leaders: Dr. John 
L. Gross and Dr. Therese P. McAllister 

Analyze the response of the WTC towers to fires with and without 
aircraft damage, the response of WTC 7 in fires, the performance 
of composite steel-trussed floor systems, and determine the most 
probable structural collapse sequence for WTC 1, 2, and 7. 

Occupant Behavior, Egress, and Emergency 
Communications; Project Leader: Mr. Jason 
D. Averill 

Analyze the behavior and fate of occupants and responders, both 
those who survived and those who did not, and the performance of 
the evacuation system. 

Emergency Response Technologies and 
Guidelines; Project Leader: Mr. J. Randall 
Lawson 

Document the activities of the emergency responders from the time 
of the attacks on WTC 1 and WTC 2 until the collapse of WTC 7, 
including practices followed and technologies used.  

background image

Draft for Public Comment 

Preface 

 

NIST NCSTAR 1-1, WTC Investigation 

xxv

 

NIST WTC Investigation Projects

NIST WTC Investigation Projects

Analysis of 

Steel

Structural 

Collapse

Evacuation

Baseline 

Performance

& Impact 

Damage

Analysis of 
Codes and 

Practices

Emergency 

Response

Active Fire 

Protection

Thermal and 

Tenability 

Environment

Video/
Photographic 
Records

Oral History Data

Emergency 
Response 
Records

Recovered 
Structural Steel

WTC Building 
Performance Study
Recommendations

Government, 
Industry, 
Professional, 
Academic Inputs

Public Inputs

 

Figure P–1.  The eight projects in the federal building and fire safety 

investigation of the WTC disaster. 

National Construction Safety Team Advisory Committee 

The NIST Director also established an advisory committee as mandated under the National Construction 
Safety Team Act.  The initial members of the committee were appointed following a public solicitation.  
These were: 

 

Paul Fitzgerald, Executive Vice President (retired) FM Global, National Construction Safety 
Team Advisory Committee Chair 

 

John Barsom, President, Barsom Consulting, Ltd. 

 

John Bryan, Professor Emeritus, University of Maryland 

 

David Collins, President, The Preview Group, Inc. 

 

Glenn Corbett, Professor, John Jay College of Criminal Justice 

 

Philip DiNenno, President, Hughes Associates, Inc. 

background image

Preface 

 

Draft for Public Comment 

xxvi

 

NIST NCSTAR 1-1, WTC Investigation

 

 

Robert Hanson, Professor Emeritus, University of Michigan 

 

Charles Thornton, Co-Chairman and Managing Principal, The Thornton-Tomasetti Group, 
Inc. 

 

Kathleen Tierney, Director, Natural Hazards Research and Applications Information Center, 
University of Colorado at Boulder 

 

Forman Williams, Director, Center for Energy Research, University of California at San 
Diego 

This National Construction Safety Team Advisory Committee provided technical counsel during the 
Investigation and commentary on drafts of the Investigation reports prior to their public release. 

Public Outreach 

During the course of this Investigation, NIST held public briefings and meetings (listed in Table P–2) to 
solicit input from the public, present preliminary findings, and obtain comments on the direction and 
progress of the Investigation from the public and the Advisory Committee. 

NIST maintained a publicly accessible Web site during this Investigation at http://wtc.nist.gov.  The site 
contained extensive information on the background and progress of the Investigation. 

NIST’s WTC Public-Private Response Plan 

The collapse of the WTC buildings has led to broad reexamination of how tall buildings are designed, 
constructed, maintained, and used, especially with regard to major events such as fires, natural disasters, 
and terrorist attacks.  Reflecting the enhanced interest in effecting necessary change, NIST, with support 
from Congress and the Administration, has put in place a program, the goal of which is to develop and 
implement the standards, technology, and practices needed for cost-effective improvements to the safety 
and security of buildings and building occupants, including evacuation, emergency response procedures, 
and threat mitigation. 

The strategy to meet this goal is a three-part NIST-led public-private response program that includes: 

 

A federal building and fire safety investigation to study the most probable factors that 
contributed to post-aircraft impact collapse of the WTC towers and the 47-story WTC 7 
building, and the associated evacuation and emergency response experience. 

 

A research and development (R&D) program to (a) facilitate the implementation of 
recommendations resulting from the WTC Investigation, and (b) provide the technical basis 
for cost-effective improvements to national building and fire codes, standards, and practices 
that enhance the safety of buildings, their occupants, and emergency responders. 

 

background image

Draft for Public Comment 

Preface 

 

NIST NCSTAR 1-1, WTC Investigation 

xxvii

 

Table P–2.  Public meetings and briefings of the WTC Investigation. 

Date Location 

Principal 

Agenda 

June 24, 2002 

New York City, NY 

Public meeting: Public comments on the 

Draft Plan

 for the 

pending WTC Investigation. 

December 9, 2002 

Washington, DC 

Media briefing on release of the 

Public Update

 and NIST request 

for photographs and videos. 

April 8, 2003 
 

New York City, NY 

Joint public forum with Columbia University on first-person 
interviews. 

April 29-30, 2003 

Gaithersburg, MD 

National Construction Safety Team (NCST) Advisory Committee 
meeting on plan for and progress on WTC Investigation with a 
public comment session. 

May 7, 2003 

New York City, NY 

Media briefing on release of the 

May 2003 Progress Report

 

August 26-27, 2003 

Gaithersburg, MD 

NCST Advisory Committee meeting on status of WTC 
investigation with a public comment session. 

September 17, 2003 

New York City, NY 

Media briefing and public briefing on initiation of first-person 
data collection projects. 

December 2-3, 2003 

Gaithersburg, MD 

NCST Advisory Committee meeting on status and initial results 
and the release of the 

Public Update

 with a public comment 

session. 

February 12, 2004 

New York City, NY 

Public meeting: Briefing on progress and preliminary findings 
with public comments on issues to be considered in formulating 
final recommendations. 

June 18, 2004 

New York City, NY 

Media briefing and public briefing on release of the 

June 2004 

Progress Report.

 

June 22-23, 2004 

Gaithersburg, MD 

NCST Advisory Committee meeting on the status of and 
preliminary findings from the WTC Investigation with a public 
comment session. 

August 24, 2004 

Northbrook, IL 

Public viewing of standard fire resistance test of WTC floor 
system at Underwriters Laboratories, Inc. 

October 19-20, 2004 

Gaithersburg, MD 

NCST Advisory Committee meeting on status and near complete 
set of preliminary findings with a public comment session. 

November 22, 2004 

Gaithersburg, MD 

NCST Advisory Committee discussion on draft annual report to 
Congress, a public comment session, and a closed session to 
discuss pre-draft recommendations for WTC Investigation. 

April 5, 2005 

New York City, NY 

Media briefing and public briefing on release of the probable 
collapse sequence for the WTC towers and draft reports for the 
projects on codes and practices, evacuation, and emergency 
response. 

 

A dissemination and technical assistance program (DTAP) to (a) engage leaders of the 
construction and building community in ensuring timely adoption and widespread use of 
proposed changes to practices, standards, and codes resulting from the WTC Investigation 
and the R&D program, and (b) provide practical guidance and tools to better prepare facility 
owners, contractors, architects, engineers, emergency responders, and regulatory authorities 
to respond to future disasters. 

The desired outcomes are to make buildings, occupants, and first responders safer in future disaster 
events. 

background image

Preface 

 

Draft for Public Comment 

xxviii

 

NIST NCSTAR 1-1, WTC Investigation

 

National Construction Safety Team Reports on the WTC Investigation 

A draft of the final report on the collapses of the WTC towers is being issued as NIST NCSTAR 1.  A 
companion report on the collapse of WTC 7 is being issued as NIST NCSTAR 1A.  The present report is 
one of a set that provides more detailed documentation of the Investigation findings and the means by 
which these technical results were achieved.  As such, it is part of the archival record of this Investigation.  
The titles of the full set of Investigation publications are: 

NIST (National Institute of Standards and Technology).  2005.  

Federal Building and Fire Safety 

Investigation of the World Trade Center Disaster: Final Report of the National Construction Safety Team 
on the Collapses of the World Trade Center Towers.

  NIST NCSTAR 1.  Gaithersburg, MD, September. 

NIST (National Institute of Standards and Technology).  2005.  

Federal Building and Fire Safety 

Investigation of the World Trade Center Disaster: Final Report of the National Construction Safety Team 
on the Collapse of World Trade Center 7.

  NIST NCSTAR 1A.  Gaithersburg, MD, December. 

Lew, H. S., R. W. Bukowski, and N. J. Carino.  2005.  

Federal Building and Fire Safety Investigation of 

the World Trade Center Disaster: Design, Construction, and Maintenance of Structural and Life Safety 
Systems.

  NIST NCSTAR 1-1.  National Institute of Standards and Technology.  Gaithersburg, MD, 

September. 

Fanella, D. A., A. T. Derecho, and S. K. Ghosh.  2005. 

Federal Building and Fire Safety 

Investigation of the World Trade Center Disaster: Design and Construction of Structural Systems.  

NIST NCSTAR 1-1A.  National Institute of Standards and Technology.  Gaithersburg, MD, 
September.  

Ghosh, S. K., and X. Liang.  2005.  

Federal Building and Fire Safety Investigation of the World 

Trade Center Disaster: Comparison of Building Code Structural Requirements.

  NIST 

NCSTAR 1-1B.  National Institute of Standards and Technology.  Gaithersburg, MD, September. 

Fanella, D. A., A. T. Derecho, and S. K. Ghosh.  2005.  

Federal Building and Fire Safety 

Investigation of the World Trade Center Disaster: Maintenance and Modifications to Structural 
Systems.

  NIST NCSTAR 1-1C.  National Institute of Standards and Technology.  Gaithersburg, 

MD, September. 

Grill, R. A., and D. A. Johnson.  2005.  

Federal Building and Fire Safety Investigation of the World 

Trade Center Disaster: Fire Protection and Life Safety Provisions Applied to the Design and 
Construction of World Trade Center 1, 2, and 7 and Post-Construction Provisions Applied after 
Occupancy

.  NIST NCSTAR 1-1D.  National Institute of Standards and Technology.  Gaithersburg, 

MD, September.  

Razza, J. C., and R. A. Grill.  2005.  

Federal Building and Fire Safety Investigation of the World 

Trade Center Disaster: Comparison of Codes, Standards, and Practices in Use at the Time of the 
Design and Construction of World Trade Center 1, 2, and 7

.  NIST NCSTAR 1-1E.  National 

Institute of Standards and Technology.  Gaithersburg, MD, September. 

Grill, R. A., D. A. Johnson, and D. A. Fanella.  2005.  

Federal Building and Fire Safety 

Investigation of the World Trade Center Disaster: Comparison of the 1968 and Current (2003) New 

background image

Draft for Public Comment 

Preface 

 

NIST NCSTAR 1-1, WTC Investigation 

xxix

 

York City Building Code Provisions

.  NIST NCSTAR 1-1F.  National Institute of Standards and 

Technology.  Gaithersburg, MD, September. 

Grill, R. A., and D. A. Johnson. 2005. 

Federal Building and Fire Safety Investigation of the World 

Trade Center Disaster: Amendments to the Fire Protection and Life Safety Provisions of the New 
York City Building Code by Local Laws Adopted While World Trade Center 1, 2, and 7 Were in 
Use

.  NIST NCSTAR 1-1G.  National Institute of Standards and Technology.  Gaithersburg, MD, 

September. 

Grill, R. A., and D. A. Johnson. 2005. 

Federal Building and Fire Safety Investigation of the World 

Trade Center Disaster: Post-Construction Modifications to Fire Protection and Life Safety Systems 
of World Trade Center 1 and 2

.  NIST NCSTAR 1-1H.  National Institute of Standards and 

Technology.  Gaithersburg, MD, September. 

Grill, R. A., D. A. Johnson, and D. A. Fanella. 2005. 

Federal Building and Fire Safety Investigation 

of the World Trade Center Disaster: Post-Construction Modifications to Fire Protection, Life 
Safety, and Structural Systems of World Trade Center 7

.  NIST NCSTAR 1-1I.  National Institute of 

Standards and Technology.  Gaithersburg, MD, September. 

Grill, R. A., and D. A. Johnson. 2005. 

Federal Building and Fire Safety Investigation of the World 

Trade Center Disaster: Design, Installation, and Operation of Fuel System for Emergency Power in 
World Trade Center 7

.  NIST NCSTAR 1-1J.  National Institute of Standards and Technology.  

Gaithersburg, MD, September.

 

Sadek, F.  2005.  

Federal Building and Fire Safety Investigation of the World Trade Center Disaster: 

Baseline Structural Performance and Aircraft Impact Damage Analysis of the World Trade Center 
Towers.

  NIST NCSTAR 1-2.  National Institute of Standards and Technology.  Gaithersburg, MD, 

September.  

Faschan, W. J., and R. B. Garlock.  2005.  

Federal Building and Fire Safety Investigation of the 

World Trade Center Disaster: Reference Structural Models and Baseline Performance Analysis of 
the World Trade Center Towers.

  NIST NCSTAR 1-2A.  National Institute of Standards and 

Technology.  Gaithersburg, MD, September. 

Kirkpatrick, S. W., R. T. Bocchieri, F. Sadek, R. A. MacNeill, S. Holmes, B. D. Peterson, 
R. W. Cilke, C. Navarro.

 

 2005.  

Federal Building and Fire Safety Investigation of the World Trade 

Center Disaster: Analysis of Aircraft Impacts into the World Trade Center Towers, 

NIST 

NCSTAR 1-2B.  National Institute of Standards and Technology.  Gaithersburg, MD, September. 

Gayle, F. W., R. J. Fields, W. E. Luecke, S. W. Banovic, T. Foecke, C. McCowan, T. A. Siewert, and 
J. D. McColskey.  2005.  

Federal Building and Fire Safety Investigation of the World Trade Center 

Disaster: Mechanical and Metallurgical Analysis of Structural Steel.

  NIST NCSTAR 1-3.  National 

Institute of Standards and Technology.  Gaithersburg, MD, September. 

Luecke, W. E., T. A. Siewert, and F. W. Gayle.  2005.  

Federal Building and Fire Safety 

Investigation of the World Trade Center Disaster: Contemporaneous Structural Steel 
Specifications.

  NIST Special Publication 1-3A.  National Institute of Standards and Technology.  

Gaithersburg, MD, September. 

background image

Preface 

 

Draft for Public Comment 

xxx

 

NIST NCSTAR 1-1, WTC Investigation

 

Banovic, S. W.  2005.  

Federal Building and Fire Safety Investigation of the World Trade Center 

Disaster: Steel Inventory and Identification.

  NIST NCSTAR 1-3B.  National Institute of Standards 

and Technology.  Gaithersburg, MD, September. 

Banovic, S. W., and T. Foecke.  2005.  

Federal Building and Fire Safety Investigation of the World 

Trade Center Disaster: Damage and Failure Modes of Structural Steel Components.

  NIST 

NCSTAR 1-3C.  National Institute of Standards and Technology.  Gaithersburg, MD, September. 

Luecke, W. E., J. D. McColskey, C. McCowan, S. W. Banovic, R. J. Fields, T. Foecke, 
T. A. Siewert, and F. W. Gayle.  2005.  

Federal Building and Fire Safety Investigation of the World 

Trade Center Disaster: Mechanical Properties of Structural Steels.

  NIST NCSTAR 1-3D.  

National Institute of Standards and Technology.  Gaithersburg, MD, September.  

Banovic, S. W., C. McCowan, and W. E. Luecke.  2005.  

Federal Building and Fire Safety 

Investigation of the World Trade Center Disaster: Physical Properties of Structural Steels.

  NIST 

NCSTAR 1 3E.  National Institute of Standards and Technology.  Gaithersburg, MD, September.  

Evans, D. D., E. D. Kuligowski, W. S. Dols, and W. L. Grosshandler.  2005.  

Federal Building and Fire 

Safety Investigation of the World Trade Center Disaster: Active Fire Protection Systems.

  NIST 

NCSTAR 1-4.  National Institute of Standards and Technology.  Gaithersburg, MD, September.  

Kuligowski, E. D., and D. D. Evans.  2005.  

Federal Building and Fire Safety Investigation of the 

World Trade Center Disaster: Post-Construction Fires Prior to September 11, 2001.

  NIST 

NCSTAR 1-4A.  National Institute of Standards and Technology.  Gaithersburg, MD, September.  

Hopkins, M., J. Schoenrock, and E. Budnick.  2005.  

Federal Building and Fire Safety Investigation 

of the World Trade Center Disaster: Fire Suppression Systems.

  NIST NCSTAR 1-4B.  National 

Institute of Standards and Technology.  Gaithersburg, MD, September. 

Keough, R. J., and R. A. Grill.  2005.  

Federal Building and Fire Safety Investigation of the World 

Trade Center Disaster: Fire Alarm Systems.

  NIST NCSTAR 1-4C.  National Institute of Standards 

and Technology.  Gaithersburg, MD, September. 

Ferreira, M. J., and S. M. Strege.  2005.  

Federal Building and Fire Safety Investigation of the 

World Trade Center Disaster: Smoke Management Systems.

  NIST NCSTAR 1-4D.  National 

Institute of Standards and Technology.  Gaithersburg, MD, September. 

Gann, R. G., A. Hamins, H. E. Nelson, K. B. McGrattan, G. W. Mulholland, T. J. Ohlemiller, 
W. M. Pitts, and K. R. Prasad.  2005.  

Federal Building and Fire Safety Investigation of the World Trade 

Center Disaster: Reconstruction of the Fires in the World Trade Center Towers.

  NIST NCSTAR 1-5.  

National Institute of Standards and Technology.  Gaithersburg, MD, September. 

Pitts, W. M., and K. M. Butler.  2005.  

Federal Building and Fire Safety Investigation of the World 

Trade Center Disaster: Visual Evidence, Damage Estimates, and Timeline Analysis.

  NIST 

NCSTAR 1-5A.  National Institute of Standards and Technology.  Gaithersburg, MD, September. 

Hamins, A., A. Maranghides, K. B. McGrattan, E. Johnsson, T. J. Ohlemiller, M. Donnelly, 
J. Yang, G. Mulholland, K. R. Prasad, S. Kukuck, R. Anleitner and T. McAllister.  2005.  

Federal 

Building and Fire Safety Investigation of the World Trade Center Disaster: Experiments and 

background image

Draft for Public Comment 

Preface 

 

NIST NCSTAR 1-1, WTC Investigation 

xxxi

 

Modeling of Structural Steel Elements Exposed to Fire.

  NIST NCSTAR 1-5B.  National Institute of 

Standards and Technology.  Gaithersburg, MD, September. 

Ohlemiller, T. J., G. W. Mulholland, A. Maranghides, J. J. Filliben, and R. G. Gann.  2005.  

Federal 

Building and Fire Safety Investigation of the World Trade Center Disaster: Fire Tests of Single 
Office Workstations.

  NIST NCSTAR 1-5C.  National Institute of Standards and Technology.  

Gaithersburg, MD, September. 

Gann, R. G., M. A. Riley, J. M. Repp, A. S. Whittaker, A. M. Reinhorn, and P. A. Hough.  2005.  

Federal Building and Fire Safety Investigation of the World Trade Center Disaster: Reaction of 
Ceiling Tile Systems to Shocks.

  NIST NCSTAR 1-5D.  National Institute of Standards and 

Technology.  Gaithersburg, MD, September. 

Hamins, A., A Maranghides, K. B. McGrattan, T. J. Ohlemiller, and R. Anleitner. 2005. 

Federal 

Building and Fire Safety Investigation of the World Trade Center Disaster: Experiments and 
Modeling of Multiple Workstations Burning in a Compartment.

  NIST NCSTAR 1-5E.  National 

Institute of Standards and Technology.  Gaithersburg, MD, September. 

McGrattan, K. B., C. Bouldin, and G. Forney.  2005.  

Federal Building and Fire Safety 

Investigation of the World Trade Center Disaster: Computer Simulation of the Fires in the World 
Trade Center Towers.

  NIST NCSTAR 1-5F.  National Institute of Standards and Technology.  

Gaithersburg, MD, September. 

Prasad, K. R., and H. R. Baum.  2005. 

Federal Building and Fire Safety Investigation of the World 

Trade Center Disaster: Fire Structure Interface and Thermal Response of the World Trade Center 
Towers.

  NIST NCSTAR 1-5G.  National Institute of Standards and Technology.  Gaithersburg, 

MD, September. 

Gross, J. L., and T. McAllister.  2005.  

Federal Building and Fire Safety Investigation of the World Trade 

Center Disaster: Structural Fire Response and Probable Collapse Sequence of the World Trade Center 
Towers.

  NIST NCSTAR 1-6.  National Institute of Standards and Technology.  Gaithersburg, MD, 

September. 

Carino, N. J., D. P. Bentz, R. W. Bukowski, J. L. Gross, S. Kukuck, K. R. Prasad, and 
M. A. Starnes.  2005.  

Federal Building and Fire Safety Investigation of the World Trade Center 

Disaster: Passive Fire Protection.

  NIST NCSTAR 1-6A.  National Institute of Standards and 

Technology.  Gaithersburg, MD, September. 

Gross, J., F. Hervey, M. Izydorek, J. Mammoser, and J. Treadway.  2005.  

Federal Building and 

Fire Safety Investigation of the World Trade Center Disaster: Fire Resistance Tests of Floor Truss 
Systems.

  NIST NCSTAR 1-6B.  National Institute of Standards and Technology.  Gaithersburg, 

MD, September.  

Zarghamee, M. S., A. A. Liepins, F. W. Kan, M. Mudlock, O. O. Erbay, Y. Kitane, W. I. Naguib, 
A. T. Sarawit.  2005.  

Federal Building and Fire Safety Investigation of the World Trade Center 

Disaster: Component, Connection, and Subsystem Structural Analysis.

  NIST NCSTAR 1-6C.  

National Institute of Standards and Technology.  Gaithersburg, MD, September.  

background image

Preface 

 

Draft for Public Comment 

xxxii

 

NIST NCSTAR 1-1, WTC Investigation

 

Zarghamee, M. S., O. O. Erbay, Y. Kitane.  2005.  

Federal Building and Fire Safety Investigation of 

the World Trade Center Disaster: Global Structural Analysis of the Response of the World Trade 
Center Towers to Impact Damage and Fire.

  NIST NCSTAR 1-6D.  National Institute of Standards 

and Technology.  Gaithersburg, MD, September. 

McAllister, T., R. G. Gann, J. L. Gross, K. B. McGrattan, H. E. Nelson, W. M. Pitts, K. R. Prasad.  2005.  

Federal Building and Fire Safety Investigation of the World Trade Center Disaster: Structural Fire 
Response and Probable Collapse Sequence of World Trade Center 7.

  2005.  NIST NCSTAR 1-6E.  

National Institute of Standards and Technology.  Gaithersburg, MD, December. 

Gilsanz, R., V. Arbitrio, C. Anders, D. Chlebus, K. Ezzeldin, W. Guo, P. Moloney, A. Montalva, 
J. Oh, K. Rubenacker.  2005.  

Federal Building and Fire Safety Investigation of the World Trade 

Center Disaster: Structural Analysis of the Response of World Trade Center 7 to Debris Damage 
and Fire

.  NIST NCSTAR 1-6F.  National Institute of Standards and Technology.  Gaithersburg, 

MD, December. 

Kim, W.  2005.  

Federal Building and Fire Safety Investigation of the World Trade Center 

Disaster: Analysis of September 11, 2001, Seismogram Data

, NIST NCSTAR 1-6G.  National 

Institute of Standards and Technology.  Gaithersburg, MD, December. 

Nelson, K.  2005.  

Federal Building and Fire Safety Investigation of the World Trade Center 

Disaster:  The ConEd Substation in World Trade Center 7

, NIST NCSTAR 1-6H.  National 

Institute of Standards and Technology.  Gaithersburg, MD, December. 

Averill, J. D., D. S. Mileti, R. D. Peacock, E. D. Kuligowski, N. Groner, G. Proulx, and P. A. Reneke.  
2005.  

Federal Building and Fire Safety Investigation of the World Trade Center Disaster: Occupant 

Behavior, Egress, and Emergency Communication.

  NIST NCSTAR 1-7.  National Institute of Standards 

and Technology.  Gaithersburg, MD, September. 

Fahy, R., and G. Proulx.  2005.  

Federal Building and Fire Safety Investigation of the World Trade 

Center Disaster: Analysis of Published Accounts of the World Trade Center Evacuation.

  NIST 

NCSTAR 1-7A.  National Institute of Standards and Technology. Gaithersburg, MD, September. 

Zmud, J.  2005.  

Federal Building and Fire Safety Investigation of the World Trade Center 

Disaster: Technical Documentation for Survey Administration.

  NIST NCSTAR 1-7B.  National 

Institute of Standards and Technology. Gaithersburg, MD, September. 

Lawson, J. R., and R. L. Vettori.  2005.  

Federal Building and Fire Safety Investigation of the World 

Trade Center Disaster: The Emergency Response Operations.

  NIST NCSTAR 1-8.  National Institute of 

Standards and Technology.  Gaithersburg, MD, September. 

 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

xxxiii

 

A

CKNOWLEDGMENTS

 

The National Institute of Standards and Technology (NIST) would like to acknowledge the Port Authority 
of New York and New Jersey (PANYNJ) for its assistance in collecting and duplicating design and 
construction documents of World Trade Center (WTC) 1, 2 and 7, and making available office spaces for 
NIST investigation team members during the course of the investigation.  Saroj Bhol of PANYNJ is 
acknowledged for his efforts in response to document requests by NIST. 

The authors wish to acknowledge the following colleagues at NIST: Dat Duthinh who helped to catalogue 
design and construction data, and Harold “Bud” Nelson who was helpful in providing detailed 
information on the fire safety systems of WTC 1, 2 and 7.  

 

background image

Acknowledgments 

 

Draft for Public Comment 

xxxiv

 

NIST NCSTAR 1-1, WTC Investigation

 

 

This page intentionally left blank. 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

xxxv

 

E

XECUTIVE 

S

UMMARY

 

E.1 INTRODUCTION 

One of the four primary objectives of the National Institute of Standards and Technology (NIST) 
Investigation of the World Trade Center (WTC) disaster is to determine the procedures and practices that 
were used in the design, construction, operation, and maintenance of the structural, passive and active fire 
protection, and emergency and evacuation systems of WTC 1, 2, and 7 and the impacts these had on the 
buildings over their life, up to the attacks of September 11, 2001. 

To accomplish this objective, relevant information was collected by reviewing design and construction 
documents, correspondence, and memoranda related to the building projects; and tenant alterations; 
interviewing individuals involved in the design, construction, and maintenance of the buildings; obtaining 
information from regulatory and emergency services agencies of New York City; and reviewing books 
and published journal and magazine articles related to the WTC building projects. Information obtained 
from various sources was synthesized and summarized in this report. Specifically, this report presents: 

1.

 

Provisions used to design and construct the structural, fire protection, and egress systems of 
the buildings;  

2.

 

Tests performed to support the design of these systems;  

3.

 

Criteria that governed the design of the structural and fire protection systems;  

4.

 

Methods used to proportion structural members and other components of the buildings;  

5.

 

Innovative features, technologies, and materials that were incorporated in the design and 
construction of the structural and fire protection systems;  

6.

 

Details of variances to the contract documents granted by the Port Authority of New York 
and New Jersey (PANYNJ or Port Authority);  

7.

 

Fabrication and inspection requirements at the fabrication yard; and  

8.

 

Inspection protocol during construction.  

9.

 

Alterations made to the buildings to accommodate specific needs of tenants or to respond to 
changes to the Building Code of New York City as implemented in Local Laws (LL) and 
interpreted in rules. 

This report also addresses the fuel systems for the diesel generators that supplied emergency power to 
many of the tenants in WTC 7. 

background image

Executive Summary 

 

Draft for Public Comment 

xxxvi

 

NIST NCSTAR 1-1, WTC Investigation 

 

E.2 

DESCRIPTION OF WTC 1, 2, AND 7 

The WTC complex was located at lower west side of Manhattan, New York City, near the Hudson River. 
The complex was composed of seven buildings (referred to in this report as WTC 1 through WTC 7).  
The two towers, WTC 1 (North Tower) and WTC 2 (South Tower), were each 110 stories high.  WTC 3 
(Marriott Hotel) was 22 stories.  WTC 4 (South Plaza Building) and WTC 5 (North Plaza Building) were 
both nine-story office buildings.  WTC 6 (U.S. Customs House) was an eight-story office building.  These 
six buildings were built around a 5 acre WTC Plaza.  WTC 7 was a 47-story office building that was built 
just north of the six-building WTC site. 

The first six buildings on the sixteen-acre site were developed by the Port Authority.  Groundbreaking for 
WTC 1 and WTC 2 was in 1966, and the first tenant began to occupy WTC 1 in December 1970 and 
WTC 2 in January 1972.  Construction of the other buildings continued during the 1970s and the 1980s.  
WTC 7 was developed by a consortium comprising the Seven World Trade Company, and Silverstein 
Development Corporation, and was completed in 1987. 

The NIST Investigation is focused only on WTC 1, 2, and 7. 

WTC 1 and WTC 2 

Although the WTC towers were similar, they were not identical.  The height of WTC 1 at the roof level 
was 1,368 ft above the Concourse level, was 6 ft taller than WTC 2, and supported a 360 ft tall antenna 
for television and radio transmission.  Each tower had a square plan with the side dimension of 
approximately 207 ft.  The corners of the tower were chamfered 6 ft 11 in.  Each tower had a core service 
area of approximately 135 ft by 87 ft.  All elevators and three egress stairs were located within the core, 
although on any given floor the arrangements of the elevators and the location of the stairs varied.  
Placing all service systems within the core provided a nearly column-free floor space of approximately 
31,000 ft

2

 per floor outside the core.  The two towers had about 10 million ft

2

 of rentable floor area. 

The towers were designed as a “framed-tube” structural system with closely spaced exterior perimeter 
columns connected by spandrel beams around the perimeter at each floor level.  The core was designed as 
a conventional frame with a grid of columns interconnected with beams.  

The exterior walls were composed of box-shaped welded steel columns and spandrel beams comprised of 
a steel plate

.  

Each building face consisted of 59 columns spaced at 3 ft 4 in. on center.  As part of the 

framed-tube system, the exterior columns were designed structurally such that they resisted the total 
lateral loads and about 50 percent of gravity loads.  Below floor 7, the columns were combined in groups 
of three to form single base columns which were spaced 10 ft on center and extended to the footings.  An 
important architectural feature of the towers was the uniform look of the exterior walls, presented by the 
uniform width of the exterior columns up the height of the buildings.  This was produced by maintaining 
a constant exterior dimension the columns and changing the strength of the steel with height.  Thus, 
twelve different grades of steel, with yield strengths ranging from 36 ksi to 100 ksi, were used for the 
exterior columns.  The external cladding, which covered the columns and spandrel beams, consisted of 
aluminum sheets.  The window openings were infilled with glass fitted into aluminum covers and sealed 
with neoprene gaskets.  

background image

Draft for Public Comment 

 

Executive Summary 

NIST NCSTAR 1-1, WTC Investigation 

xxxvii

 

The core columns were of two types: welded box columns for the lower floors and rolled wide flange 
shapes for the upper floors.  They were designed to support about 50 percent of gravity loads.  Below 
floor 7 to the foundation, where there were fewer perimeter columns in the outer walls, bracings were 
used in the outer perimeter of the core area to increase lateral stiffness.  In the lower part of the towers, 
the outer core columns were designed to resist a portion of the lateral forces.  Hidden within the building, 
the core columns were thicker and larger on the lower floors.  Thus, core columns used fewer grades of 
steel.  The box columns were either 36 ksi or 42 ksi.  Core wide flange columns were one of four grades, 
yield strengths ranging from 36 ksi to 50 ksi, but most (approximately 90 percent) were primarily 36 ksi 
or 42 ksi steel.  

The floor system of WTC 1 and WTC 2 was composed of concrete-steel composite members.  The area 
inside the cores and on the mechanical floors was framed with rolled structural steel shapes with welded 
shear studs acting compositely with normal-weight concrete slabs.  The thickness of the slabs varied from 
4.5 in. to 8 in. depending on design loads.  The area outside the core, typically on tenant floors, was 
framed with steel trusses acting compositely with 4 in. thick lightweight concrete slabs cast on 1½ in., 
22 gauge fluted metal deck.  The trusses consisted of double angle top and bottom chords with round bar 
webs.  Some floors, immediately adjacent to the mechanical floors, used a hybrid of beam and truss 
framing acting compositely with the concrete slab. 

Fire protection of exposed structural steel members in the WTC towers was provided by applied fire 
resistive materials.  They were either sprayed fire resistive materials (SFRMs), gypsum wallboards, or a 
combination of the two, depending upon the type of structural members, to meet the requirements of 
Construction Classification of 1B of the 1968 New York City (NYC) Building Code.  All floor trusses 
and beams were protected with SFRM.  The columns inside the core were either covered with gypsum 
wall board or a combination of gypsum wall board and SFRM.  For the exterior columns, vermiculite 
plaster was applied to the side of the column facing the interior of the building, whereas SFRM was 
applied to other three faces.  No fire resistive material was specified for the underside of the metal deck, 
which was in contact with the concrete slab above.  For typical tenant floors, the ceiling was suspended 
from the steel trusses.  The space between the ceiling and the floor above was used for the mechanical and 
electrical systems. 

Elevators were the primary mode of routine ingress and egress from the towers for tens of thousands of 
people daily.  In order to minimize the total floor space needed for elevators, each tower was divided 
vertically into three zones by skylobbies, which served to distribute passengers among express and local 
elevators.  In this way, the local elevators within a zone were placed on top of one another within a 
common shaft.  Local elevators serving the lower portion of a zone were terminated to return to the space 
occupied by those shafts to leasable tenant space.  People transferred from express elevators to local 
elevators at the skylobbies which were located on the 44th and 78th floors in both towers.  Each tower 
had 99 passenger and 7 freight elevators, all located within the core of the building. 

WTC 7 

WTC 7 was a 47-story commercial office building constructed by Silverstein Properties as a tenant 
alteration on land owned by the Port Authority.  The overall dimensions of WTC 7 were approximately 
330 ft long, 140 ft wide, and 610 ft high.  It contained about 2 million ft

2

 of rentable floor area.  The 

building was constructed over a pre-existing electrical substation owned by Consolidated Edison 

background image

Executive Summary 

 

Draft for Public Comment 

xxxviii

 

NIST NCSTAR 1-1, WTC Investigation 

 

(Con Edison).  The original plans for the Con Edison Substation included supporting a high-rise building, 
and the foundation was sized for the planned structure.  However, the final design for WTC 7 had a larger 
footprint than originally planned.  

Above floor 7, the building had typical steel framing for high-rise construction.  The floor systems had 
composite construction with steel beams of 50 ksi yield strength supporting concrete slabs on metal deck, 
with a floor thickness of 5.5 in.  The core and perimeter columns supported the floor system and carried 
their loads to the foundation.  Above floor 7, the perimeter moment frame resisted wind forces. Below 
floor 7, a combination of moment and braced frames around the perimeter and a series of braced frames 
in the core resisted the wind load.  

Columns above floor 7 did not align with the foundation columns, so braced frames, transfer trusses, and 
transfer girders were used to transfer loads between these column systems, primarily between floors 5 
and 7.  Floors 5 and 7 were heavily reinforced concrete slabs on metal decks, with thicknesses of 14 in. 
and 8 in., respectively. 

Core columns were primarily rolled wide-flange shapes with a yield strength of either 36 ksi or 50 ksi, 
while the exterior columns were typically rolled W14 shapes with a yield strength of 36 ksi.  

E.3 CODE 

PROVISIONS 

FOR STRUCTURAL DESIGN 

The design of WTC 1, 2, and 7 was based on the 1968 edition of the NYC Building Code.  As an 
interstate compact under the U.S. Constitution, the Port Authority was not subjected to any state or local 
building codes.  In May 1963, the Port of New York Authority (PONYA or Port Authority) instructed the 
architect and structural engineer to prepare their designs for WTC 1 and WTC 2 in accordance with the 
NYC Building Code. At that time, the 1938 edition of that Code was in effect. In September of 1965, the 
PONYA instructed the architect and structural engineer to revise their designs for WTC 1 and WTC 2 to 
comply with the second and third drafts of the new NYC Building Code that was under development.  
Prior to issuance of this instruction, the Port Authority recognized that the draft version of the new 
NYC Building Code had incorporated advanced techniques and the Port Authority favored the use of 
advanced techniques in the design of the WTC towers.  By adopting the draft versions of the new NYC 
Building Code, WTC 1 and WTC 2 could be classified as Type 1-B Construction, and several features 
related to egress such as the elimination of the fire tower and the reduction of the number of egress stairs 
required from six to three with narrower doors were incorporated into the final design. 

The new Code was adopted on December 6, 1968. Subsequently, the NYC Building Code was amended 
by numerous Local Laws to improve safety requirements or to incorporate technological advances, some 
of which had impacts on the towers.  When WTC 7 was designed, the 1968 Building Code was in effect 
and the Local Laws impacting fire, life safety, and structural arrangements were in place, so these were 
incorporated into the original design of that building. 

To put the design of WTC 1, 2, and 7 into the context of building codes and practices of the time, the 
structural provisions of the 1968 edition of the NYC Building Code were compared with the structural 
provisions in a number of contemporaneous codes, as well as in the 2001 edition of the NYC Building 
Code, which is currently in effect.  Specifically, the following codes were selected for comparison of the 
structural provisions: the 1964 New York State Building Construction Code (NYSBC 1964); the 1965 
Building Officials and Code Administrators (BOCA) Basic Building Code (BOCA/BBC 1965); the 1967 

background image

Draft for Public Comment 

 

Executive Summary 

NIST NCSTAR 1-1, WTC Investigation 

xxxix

 

Municipal Code of Chicago Relating to Buildings (MCC 1967); and the 2001 edition of the NYC 
Building Code (NYCBC 2001).  The 1964 New York State Building Construction Code was selected for 
comparison, as it would have been a governing building code outside New York City limits.  The 1965 
BOCA Basic Building Code was selected, as it was typically adopted by local jurisdictions in the 
northeastern region of the United States.  The 1968 NYC Building Code is compared with the 1967 
Municipal Code of Chicago to see whether there are any substantial differences in the structural and fire 
safety requirements of the two codes. In the late 1960s and early 1970s, several tall buildings were built in 
Chicago, including the Sears Tower (110 stories) and the John Hancock Tower (100 stories).  The 2001 
edition of the NYC Building Code is compared with the 1968 version to examine the extent to which 
Local Laws have modified the code provisions. 

Structural provisions include those concerning design loads, such as dead loads, live loads (including live 
load reduction), wind loads, earthquake loads, and other loads. They also include provisions concerning 
what is called “structural work” in the NYC Building Codes (this term is not used in the other codes). The 
scope of “structural work” includes, but is not limited to, materials and methods of construction, design 
methods including design load combinations, and the materials of construction including concrete, 
masonry, steel, and wood. Structural provisions also include those for foundation design and construction. 

With respect to structural design provisions, the major changes from the 1968 to the 2001 edition of the 
NYC Building Code are the inclusion of seismic design requirements and updating of standards.  Of the 
codes contemporaneous with the 1968 NYC Building Code examined for this investigation, only the 
BOCA Basic Building Code had seismic design requirements, which were adopted from the 1962 edition 
of the Uniform Building Code (UBC). Taller buildings have longer periods of vibration, which means 
lower seismic design forces. Also, since New York City is in an area of moderate seismicity (UBC Zone 
2A), additional seismic detailing requirements are minimal to non-existent. 

The alternate live load reduction provisions for columns, walls, and piers of the 1968 and 2001 NYC 
Building Codes are the same as in the Chicago Municipal Code. The New York State Building Code has 
more liberal live load reduction provisions for upper portions of buildings.  The NYC Building Codes 
also have live load reduction provisions based on contributory floor area and live-to-dead load ratio. For 
live-to-dead load ratios of 0.625 or less, the New York City code provisions may yield higher live load 
reduction for columns, walls, and piers than allowed by the other codes. For beams and girders, the live 
load reduction provisions of the NYC Building Code are comparable to those of the New York State 
Building Code and the BOCA Basic Building Code.  The Chicago Municipal Code has more conservative 
requirements.  The maximum live load reduction allowed for beams and girders in the Chicago Municipal 
Code is 15 percent, compared with 40 percent in the other codes. 

When the wind load provisions in the codes are compared, the largest shear force at the base of a building 
is obtained from the BOCA Basic Building Code when the height of the building is taken equal to 
1,368 ft (i.e., the height of WTC 1).  Similarly, the largest overturning moment at the base of a building 
with the height of the WTC towers is also obtained from the BOCA Basic Building Code.  Thus, the NYC 
Building Code does not have the most stringent wind load provisions.  

The 1968 NYC Building Code requires that weights of partitions be considered in two ways: (1) using 
line loads at locations shown on plans or (2) using the equivalent uniform load.  Equivalent uniform loads 
must be used in areas where the locations of partitions are not shown on plans, or in areas where partitions 
can be relocated.   The 1964 New York State Building Construction Code did not have a specific 

background image

Executive Summary 

 

Draft for Public Comment 

xl

 

NIST NCSTAR 1-1, WTC Investigation 

 

provision in this regard.  The 1967 Municipal Code of Chicago prescribed a minimum partition load of 
20 psf.  The BOCA Basic Building Code required consideration of the actual weight of the partitions or 
an equivalent uniform load of at least 20 psf. 

The primary materials design standards referenced by the 1968 NYC Building Code, the Chicago 
Municipal Code, and the BOCA Basic Building Code are the 1963 edition of the American Concrete 
Institute’s (ACI’s), 

Building Code Requirements for Reinforced Concrete (ACI 318)

, and the American 

Institute of Steel Construction’s, 

Specifications for the Design, Fabrication and Erection of Structural 

Steel for Buildings (AISC 1963)

.  The New York State Building Code, being a performance code, does 

not adopt any specific standards by reference.  The 2001 NYC Building Code adopts the 1989 edition of 
ACI 318, AISC 1989, 

Specifications for Structural Steel Buildings – ASD and Plastic Design

, and AISC-

LRFD 1993, 

Load and Resistance Factor Design Specifications for Structural Steel Buildings

The NYC Building Codes have extensive and quite rigorous foundation design and construction 
requirements.  The foundation related provisions of the other codes are less extensive and typically less 
rigorous. 

The NYC Building Codes prescribe testing and inspection requirements for all materials, assemblies, 
forms and methods of construction.  The other three codes require that materials and methods of 
construction meet the criteria of generally accepted standards.  With respect to foundations, only the NYC 
Building Codes have specific requirements for foundation inspection. 

E.4 

STRUCTURAL DESIGN OF WTC 1, 2, AND 7 

For WTC 1 and WTC 2 the design criteria were established referencing provisions of the 1968 NYC 
Building Code as minimum.  The design dead loads and live loads specified in the design criteria were 
greater than or equal to corresponding design loads in the Building Code.  Live load reduction 
requirements given in the design criteria were equal to or more stringent than Code requirements. 

Wind forces on the towers were determined based on a series of wind tunnel tests that were conducted at 
the Colorado State University and the National Physical Laboratory, Teddington, Middlesex, United 
Kingdom.  Such tests were permitted by the Code to determine wind pressures in lieu of those tabulated 
in the Code.  The code prescribed base shear and overturning moment occur simultaneously on the same 
face of the tower, and these values are the same for all four faces.  The base shear and the overturning 
moment obtained from the wind tunnel tests represent the largest values related to most unfavorable wind 
direction; so, they may not occur simultaneously on the same face of the tower.  Thus, the base shear 
value obtained from the wind tunnel tests is about 42 percent greater than that obtained using the code 
prescribed wind pressure values, whereas the overturning moments obtained from the wind tunnel tests is 
about 65 percent greater than that obtained using the code prescribed wind pressure values. 

The allowable stress method in the 1963 American Institute of Steel Construction (AISC) 

Specification 

for the Design, Fabrication, and Erection of Structural Steel for Buildings

 was used to proportion the 

exterior columns and spandrels for the combined effects of axial compression, bending moment, and 
shear due to gravity and wind forces. Composite floor trusses were designed based on the AISC 
Specification.  The allowable stress method was also used to proportion the members in the hat trusses 
that were located between the 107th floor and the roof in WTC 1 and WTC 2. In the core area, composite 
steel beams, columns, and their connections were designed by the appropriate requirements in the 1963 

background image

Draft for Public Comment 

 

Executive Summary 

NIST NCSTAR 1-1, WTC Investigation 

xli

 

AISC Specification.  The ultimate strength method in the 1963 edition of the ACI 

Building Code 

Requirements for Reinforced Concrete

 was used to design the concrete floor slabs in WTC 1 and WTC 2.  

For WTC 7, the project specifications required that the structural steel be designed in accordance with the 
1968 edition of the NYC Building Code, edited and amended through January 1, 1985, and the 1978 
edition of the AISC

 Specification for the Design, Fabrication, and Erection of Structural Steel for 

Buildings.

  Design load criteria for WTC 7, listed on one of the structural drawings, show that the design 

values for the superimposed dead loads could not be ascertained, since the actual materials used for 
partitions, flooring, and ductwork were not specified.  The live loads in the design criteria were equal to 
those in the 1968 NYC Building Code at the floors where the type of occupancy was noted. No 
documents were found that indicated what live load reduction was used. 

No design criteria or calculations including wind load analysis of WTC 7 were available for this 
investigation.  However, a wind tunnel study of WTC 7 was carried out in 1983 by the University of 
Western Ontario at the request of the structural engineer of record. 

E.5 

INNOVATIVE FEATURES INCORPORATED IN STRUCTURAL DESIGN 

A number of innovative features were incorporated in the structural design of WTC 1 and WTC 2.  They 
were incorporated in both the lateral-load-resisting system and the gravity-load-carrying system. 

These features include the following: 

 

Application of the framed-tube system to resist lateral loads. 

 

Uniform exterior column geometry (14 in. by 14 in. cross-section) was maintained over most 
of the height of the 110-story buildings by using twelve different grades of steel. 

 

Use of deep spandrel plates as beam elements connecting perimeter columns. 

 

Use of long-span composite steel trusses for the floor systems. Composite action was 
achieved between the steel trusses and the concrete floor slab by extending the truss 
diagonals above the top chord into the slab.  

 

Application of viscoelastic dampers connecting the floor trusses to the perimeter framed tube 
system to control dynamic response. 

 

Use of wind tunnel test data to establish the wind loads used in the design of the towers. 

E.6 

FABRICATION AND CONSTRUCTION INSPECTIONS AND VARIANCES 

The contract documents for WTC 1 and WTC 2 between the Port of New York Authority and the steel 
fabricators and erector, and the construction contract specifications for WTC 7, indicate that inspection 
programs were instituted at the steel fabrication sites.  The inspection requirements were listed in the 
contract documents.  However, the records of inspections for both the WTC 1 and WTC 2 and the WTC 7 
projects were not available to the investigation.  The records for WTC 1 and WTC 2, which were kept in 
WTC 1 were destroyed, and the records for WTC 7 were discarded by the general contractor after 
retaining them for 7 years.  

background image

Executive Summary 

 

Draft for Public Comment 

xlii

 

NIST NCSTAR 1-1, WTC Investigation 

 

WTC 1 and WTC 2 

Fabrication and inspection requirements were contained in the contracts for the floor trusses, box core 
columns and built-up beams, members of the exterior wall, and rolled columns and beams.  In general, the 
inspection requirements from the specifications for the various contracts were at a minimum equivalent to 
those in the 1968 NYC Building Code.  The Code contains provisions that govern the fabrication and 
inspection of materials used in buildings.  However, in a number of cases, the contract requirements were 
more comprehensive and stringent than the corresponding provisions in the Code  The Code refers to the 
requirements in the 1963 AISC 

Specification for the Design, Fabrication, and Erection of Structural Steel 

for Buildings

 (AISC 1963).  The AISC Specification contained minimum fabrication requirements for the 

following: 

 

Straightening of materials 

 

Gas cutting 

 

Planing of edges 

 

Riveted and bolted construction – holes 

 

Riveted and high strength bolted construction – assembling 

 

Welded construction 

 

Finishing 

 

Tolerances 

Specific inspection requirements during fabrication of various structural members were covered in the 
contract documents between PONYA and individual fabricators.   

WTC 7 

The contract specification for WTC 7 required that structural steel for WTC 7 was to be fabricated in 
accordance with the applicable requirements in the 1968 NYC Building Code, the 1963 AISC 

Specification for the Design

Fabrication

and Erection of Structural Steel for Buildings

, and other 

specifications related to bolts, welds, and painting.  The specification also notes that there was a separate 
contract for testing and inspection.  This contract was not found.  However, specific requirements for 
inspection of shop and field welds by a testing agency were included in the specification. 

E.7 

INSPECTION PROTOCOL DURING CONSTRUCTION 

WTC 1 and WTC 2 

Karl Koch Erecting Co., the company that performed the structural steel erection work for WTC 1 and 
WTC 2, developed a quality control and safety program.  This program included information on ten 
different key areas that were to be addressed during construction, including: 

background image

Draft for Public Comment 

 

Executive Summary 

NIST NCSTAR 1-1, WTC Investigation 

xliii

 

 

Survey control 

 

Control of construction and erection loads 

 

Field welding 

 

Bolting of structural steel 

 

Control of stud welding operations 

 

Erection procedures 

 

Control of workmanship 

 

Control of erection tolerances 

 

As-built drawings 

 

Safety programs 

WTC 7 

The WTC 7 specifications contained general erection requirements for fasteners, anchor bolts, column 
bases, installation, and bracing.  The specification did not include any requirements for inspection. 

E.8 

VARIANCES GRANTED BY PANYNJ 

The Port Authority approved numerous variances in the fabrication and erection of structural members in 
WTC 1 and WTC 2.  The Office of the Construction Manager at the Port Authority approved variances to 
the contract documents after the structural engineer of record; Skilling, Helle, Christiansen, and 
Robertson (SHCR), reviewed the details of the variances and recommended approval.  In many cases, 
SHCR submitted alternative methods, which were incorporated into the variance. 

The variances that were granted for the structural members and their materials may be categorized into 
the following groups: 

 

Variances relating to fabrication/erection tolerances (box columns, box beams, and floor 
trusses) 

 

Variances relating to defective components (column trees and floor trusses) 

 

Variances relating to alternative fabrication/erection procedures (core columns, floor trusses, 
exterior wall columns, and beam seats) 

 

Variances relating to product substitutions (exterior wall) 

 

Variances relating to inspection practice (exterior wall and welds). 

background image

Executive Summary 

 

Draft for Public Comment 

xliv

 

NIST NCSTAR 1-1, WTC Investigation 

 

Fabrication and erection inspections identified many deviations from the contract drawings and 
specifications.  Many variance requests were based on inspection results.  

E.9 STRUCTURAL 

MAINTENANCE AND MODIFICATIONS DURING 

OCCUPANCY 

Both architectural and structural modifications were made to meet the occupancy needs of individual 
tenants throughout the history of occupancy of WTC 1, 2, and 7.  PONYA, later PANYNJ, reviewed all 
modifications to maintain the structural integrity of the buildings and to ensure that modifications were 
compatible with existing building conditions.  In order to guide tenants in their modification process, the 
PONYA issued 

Tenant Alteration Review Manual

 in 1971 and updated the manual periodically 

through 1997.  

In anticipation of structural degradation, the PANYNJ issued in 1986 the 

Standard for Structural Integrity 

Inspection of the World Trade Center Towers A & B

 to guide periodic inspection of structural members.  

Deteriorated and damaged members were identified for repair.  The standard was used by consultants who 
were retained by PANYNJ for systematic examination of WTC 1 and WTC 2.  

In 1998, the PANYNJ issued the 

Standards for Architectural and Structural Design 

for modification 

works. The standards included not only the design guide, but also included specifications and standard 
details to be used in modification works. Tenants proposing any modifications were required to follow the 
specified standards.  

Apart from the repairs following the 1993 bombing of WTC 1, most of the structural modifications in 
WTC 1 and WTC 2 were performed to accommodate tenant requirements.  Openings were cut in existing 
floors to construct new stairways linking two or more floors, and floor systems were reconstructed over 
previously cut openings.  In a number of cases, floor trusses outside of the core area and steel beams in 
the core area had to be reinforced due to heavy loads imposed by tenant requirements.  All such 
modifications were reviewed and approved by the structural engineer of record (SHCR). 

Similar to WTC 1 and WTC 2, most of the structural modifications in WTC 7 were done to accommodate 
tenant requirements. Horizontal members of the floor framing system were strengthened due to increased 
loading from high-density files. Strengthening of these beams and girders was achieved by welding cover 
plates to the bottom flanges, the underside of the top flanges, or both. In some cases, new beams were 
introduced to carry a portion of the new load. 

Structural Integrity Inspection Program 

In 1986, PANYNJ implemented an inspection program to detect, record, and correct any signs of distress, 
deterioration, or deformation that could signal structural problems. This structural integrity inspection 
program contained detailed guidelines on inspection, record-keeping, and follow-up procedures. 

Inspection findings were to be categorized as “Immediate,” “Priority,” or “Routine.” Repairs falling into 
the “Immediate” category included possible closure of the area and/or structure affected until interim 
remedial action could be implemented. The “Priority” category was for those conditions where no 
immediate action was required, or for which immediate action had been completed, but for which further 

background image

Draft for Public Comment 

 

Executive Summary 

NIST NCSTAR 1-1, WTC Investigation 

xlv

 

investigation, design, and implementation of interim or long-term repairs were to be undertaken on a 
priority basis (i.e., taking precedence over all other scheduled work). Repairs falling into the “Routine” or 
“non-priority” category were to be undertaken as part of a scheduled major work program or other 
scheduled project, or when routine facility maintenance was to be performed, depending on the type of 
repair that was required. An important requirement in the inspection program was that where inspection 
procedures involved the removal of fireproofing, such fireproofing was to be properly replaced on 
completion of inspection. 

In general, the structural integrity inspections findings indicated that the structural systems of WTC 1, 2, 
and 7 were in good condition. The inspections resulted in numerous routine and some priority 
recommendations for repairs, as outlined in the inspection standard.  According to the PANYNJ, all of the 
construction records on repairs following the inspections were lost on September 11, 2001.  Thus, it 
cannot be determined whether all of the recommended repairs were performed. 

Repair Work Following the 1993 Explosion 

The explosion of February 26, 1993, occurred on Level B2 near the center of the south wall of WTC 1 
and adjacent to WTC 3 (Vista Hotel). Structural steel columns, diagonal braces, and spandrel beams in 
the vicinity of the blast were damaged. Concrete floor slabs at Levels B1 and B2 and unreinforced 
masonry walls were also damaged over a large area. 

The explosion severely bent and tore out the diagonal brace between columns. Spandrel beams at level B1 
were also damaged by the blast. A crack developed along the field splice in a column. Ultrasonic testing 
determined that the crack extended across the full width of the weld on the south face of the column and 
at each end of the weld on the north face. Magnetic-particle testing procedure determined that the crack 
extended across the east face of the column. The explosion also damaged floor beams at levels B1 and 
B2. Concrete spandrel beams at level B3 also sustained damage. Masonry walls in WTC 1 were breached 
over distances of approximately 50 ft to the east and 120 ft to the west of the blast origin. 

The diagonal bracing members between levels B1 and B2 that were damaged by the explosion were 
removed and replaced with new members. New plates were added to the damaged spandrel beam at level 
B1. Also, the cracked weld on the south face of the spandrel beam at level B1 was removed and replaced. 

Six different inspections were performed before and after repairs were made to WTC 1. No anomalies 
were detected in the welds used to repair structural members. 

E.10 

CODE PROVISIONS FOR DESIGN OF THE FIRE SAFETY AND EGRESS 
SYSTEMS 

The fire safety provisions of the 1968 NYC Building Code (NYCBC 1968) were compared with four 
other building codes: the 1964 New York State Building Construction Code (NYSBC 1964), the 1965 
BOCA Basic Building Code (BOCA/BBC 1965), the 1967 Municipal Code of Chicago Relating to 
Buildings (MCC 1967), and the 2001 edition of the NYC Building Code (NYCBC 2001).  In addition, 
comparisons were made to the 1966 edition of National Fire Protection Association (NFPA) 101, Code 
for Safety to Life in Buildings and Structures.  While not a building code, NFPA 101 is widely adopted 
for its requirements for life safety in fires. 

background image

Executive Summary 

 

Draft for Public Comment 

xlvi

 

NIST NCSTAR 1-1, WTC Investigation 

 

The NYC Building Code was regularly amended by local laws, two of which, Local Law 5 (1973) and 
Local Law 16 (1984), had a significant influence on WTC 1 and WTC 2, even though the buildings were 
completed and occupied at the time of adoption. It is normal practice not to apply building code changes 
to existing buildings, but the Port Authority chose to follow the revised provisions and to retrofit the 
buildings as required under the new provisions.  The resulting changes to WTC 1 and WTC 2 are 
discussed primarily in the sections on modifications to the building systems. 

While New York City developed its own building code, their code development committees were 
influenced by the same forces that bore on the model codes.  Thus, there were relatively few differences 
between the NYC Building Code and the others.   

Construction Classification 

In Construction Classifications, the 1968 Building Code, the New York State Building Code, and the 
1965 BOCA all recognized Class 1A or Class 1B (with the same fire resistance ratings for building 
elements) for most unsprinklered buildings of unlimited height, while the 1967 Chicago Code recognized 
only 1A.  New York City imposed a 75 ft height limit on unsprinklered buildings with the adoption of 
Local Law 16 (1984). 

Active Systems 

At the time of construction, sprinklers were primarily for property protection and were rare even in 
high-rise buildings (except for underground spaces).  Fire alarm systems were mostly manually initiated 
but there was concern about smoke being recirculated through the heating, ventilating, and air 
conditioning (HVAC) systems, so smoke detectors controlled dampers at return shafts to prevent this.  
This is the arrangement of the fire alarm system originally installed in the towers.  Voice communication 
systems were a response to phased evacuation with the recognition that it was necessary to provide 
instructions to occupants who were relocated or held within the building at least until they were told to 
leave.  Requirements for voice systems first appeared in national standards in the mid-1980s, at the same 
time as NYC adopted LL 16 (1984). 

Technical Standards 

All building codes rely on referenced technical standards to provide the details of design, installation, 
operation, and maintenance of required systems.  Most building codes reference national (consensus) 
standards as published, but New York City cites their own reference standards that are based on these 
national standards but are often highly modified.  For example, fire alarm systems and fire sprinkler 
systems are addressed in Reference Standard (RS) 17, with Class E fire alarm systems (required in office 
occupancies) covered in RS 17-3A and general fire alarm system requirements in RS 17-5.  The former is 
entirely written by a NYC code committee, and the latter is based on NFPA 72 (National Fire Alarm 
Code) but highly modified by the deletion of many sections and modification of many others.  One major 
modification is that RS 17 does not include the “Survivability” section for high-rise voice communication 
systems that requires duplicate communication trunks so that loss on one trunk does not result in loss of 
communication with a floor.  However the voice communication system installed in WTC 1 and WTC 2 
was consistent with the National Fire Alarm Code (NFPA 72) in addition to RS 17 and had redundant 
trunks run in Stairways A and C.   

background image

Draft for Public Comment 

 

Executive Summary 

NIST NCSTAR 1-1, WTC Investigation 

xlvii

 

Egress Systems 

Prior to 1988, all building codes determined egress capacity by the (22 in.) Units of Exit Width method, 
which New York City still uses.  In 1988, other codes changed to a method involving an allowance of 
width per person, which provides credit for non-standard widths of corridors and doors, but for standard 
dimensioned components yields the same results.  Another difference in egress design is that New York 
City applies the occupant load factor for business occupancies (100 ft

2

 per person) to the net floor area 

while other codes use the gross floor area.  Other codes use net for some and gross for others.  The NYC 
Building Code allows doubling stair capacity allowances with one or tripling of the stair capacity on 
floors with two or more horizontal exits where other codes only allow doubling for one horizontal exit 
(see discussion of Windows on the World). 

Miscellaneous Details 

There are a number of detail differences between the NYC Building Code and the other building codes.  
The NYC Building Code has no requirements for fire extinguishers since they require occupant hose 
reels.  The 1968 NYC Building Code was the first code to include smoke developed ratings for finish 
materials in addition to flame spread.  Now, all of the codes have similar requirements.   

Specifications for the Original Buildings 

No contemporaneous documentation has been found that provides the rationale for the decision to select 
Class 1B for the WTC towers.  This decision, however, appears to have been made by the architect-of-
record on the basis of economics. 

As stated above the primary occupancy group was Group B (Business) with the Windows on the World 
space in WTC 1 being Group F (Assembly).  While there was a Port Authority cafeteria on the 44th floor, 
employee cafeterias not open to the public are specifically exempted from assembly classification because 
they do not increase occupant load and are only used intermittently.  Incidental mercantile spaces such as 
news stands and coffee bars at the concourse level are also exempt from reclassification in most building 
codes. 

The NYC Building Code and Port Authority practice required partitions to separate tenant spaces from 
each other and from common spaces such as the corridors that served the elevators, stairs, and other 
common spaces in the building core.  Fire rated partitions are intended to limit fire spread on a floor, to 
prevent spread of fire in one tenant space to that of another, Partitions separating tenant space from exit 
access corridors were permitted to be 1 h, although the Port Authority specified them to be 2 h, allowing 
dead ends to extend to 100 ft (rather than 50 ft with 1 h partitions), which permitted more flexibility in 
tenant layouts.  Partitions separating tenant spaces (so-called demising walls) were required to be 1 h (see 
Sec. 10.4.5).  Enclosures for vertical shafts, including stairways and transfer corridors, elevator hoistways, 
and mechanical or utility shafts were required to be of 2 h fire rated construction.  Protection of vertical 
shafts is intended to limit the spread of fire and smoke from floor to floor. 

The primary egress system for the office spaces was the three stairways located in the building core.  
These included two 44 in. (designated A and C) and one 56 in. wide (designated B) stairs which provided 
exactly the code required capacity for an occupant load of 390 per floor (39,000 ft

2

 net at 100 ft

2

 per 

background image

Executive Summary 

 

Draft for Public Comment 

xlviii

 

NIST NCSTAR 1-1, WTC Investigation 

 

person).  The layout within the building core was consistent with the Building Code requirements for 
maximum travel distance (200 ft unsprinklered, 300 ft sprinklered) and, while the separation was 
consistent with New York City requirements (15 ft and later 30 ft), it was short of the more common 
requirements found in all current building codes (one-half the diagonal of the space served if 
unsprinklered, or one-third the diagonal if sprinklered) on some of the floors where the transfer corridors 
brought the stair access closer together. 

There were 99 passenger elevators in each tower, arranged in three vertical zones to move occupants in 
stages to skylobbies on the 44th and 78th floors.  These were arranged as express (generally larger cars 
that moved at higher speeds) and local elevators in an innovative system first introduced in WTC 1 and 
WTC 2.  There were 8 express elevators from the concourse to the 44th floor and 10 express elevators 
from the concourse to the 78th floor as well as 24 local elevators per zone, which served groups of floors 
in those zones.  There were seven freight elevators, only one of which served all floors.  All elevators had 
been upgraded to incorporate firefighter emergency operation per American Society of Mechanical 
Engineers (ASME) A17.1 and Local Law 5 (1973). 

Consistent with practice at the time, the original fire alarm system in WTC 1 and WTC 2 was a manual 
system with four smoke detectors on each tenant floor, positioned to monitor for smoke entering the 
HVAC returns and arranged to stop the fans to prevent smoke circulation to non-fire areas.  Local Law 5 
(1973) included retroactive requirements for fire alarm systems and emergency voice communication 
systems in business occupancies over 100 ft in height.  Subsequently, such systems were installed in 
WTC 1 and WTC 2 with the required fire command center located in the underground parking garage, 
where it was destroyed by the blast in the 1993 bombing, rendering most fire safety features inoperable.  
Following the 1993 bombing, the fire command stations were relocated to the tower building lobbies, 
with a third monitoring location in the Port Authority offices.  The lobby location (within sight of the 
elevators) is specified in the NYC Building Code for fire command centers required in high-rise 
buildings.  There are no code requirements for off-site monitoring of fire alarm systems in this occupancy. 

Modifications to the Fire and Life Safety Systems  

The general practice is that buildings are governed by the building code in force at the time the building 
permits are issued except in the rare case of the adoption of retroactive requirements.  Local Laws 5 
(1973) and 16 (1984) were adopted after completion of WTC 1 and WTC 2 but did contain some 
retroactive provisions.  However, the Port Authority chose to implement virtually all of the provisions of 
LL 5/73 and LL 16/84, which drove most of the modifications to the fire and life safety systems that 
occurred over the life of the buildings.  These modifications included the complete sprinklering of the 
buildings and several upgrades to the fire alarm system. 

After the passage of Local Law 5, the Port Authority implemented a program to retrofit sprinklers and to 
offer tenants the option of sprinklering or compartmentation consistent with Local Law 5 provisions.  
Sprinklering of WTC 1 and WTC 2 was undertaken in three phases: Phase 1 was the sprinklering of 
below grade spaces completed with the original construction.  Phase 2 was begun after Local Law 5 was 
adopted and included the installation of sprinkler risers and other infrastructure and the installation of 
sprinklers in corridors, storage rooms, lobbies, and smaller tenant spaces for tenants not selecting the 
compartmentation option.  Phase 3 involved sprinklering the remaining tenant spaces, initially as tenants 
changed, and later on negotiated schedules.  This process was underway when, in 1984, Local Law 16 

background image

Draft for Public Comment 

 

Executive Summary 

NIST NCSTAR 1-1, WTC Investigation 

xlix

 

was adopted, which required sprinklers in new high-rise buildings, including offices.  Under Local 
Law 16 (1984) all floor spaces had to either be subdivided in accordance with the compartmentation 
requirement or sprinklered by February 8, 1988.  A 1997 report states that there were four floors and the 
skylobbies (all in WTC 1) left to be sprinklered and that the installation of sprinklers at these floors was 
underway (Coty 1997).  An October 1999 report states that sprinklering of the tenant floors was 
completed and sprinklering of the skylobbies was “currently underway” (PANYNJ 1999). 

Issues identified after completion of the buildings that were not related to amendments to the NYC 
Building Code that were addressed during the occupancy included the extension of the tenant separation 
walls to run slab to slab, upgrading of the fireproofing to 1½ in. on the floor trusses, and correction of the 
egress deficiencies for Windows on the World by creating three areas of refuge on each floor with 2 h 
separations, each including a stair.  These issues were identified through various independent reviews 
conducted by PANYNJ and contractors hired by PANYNJ to conduct “due diligence” surveys.  One 
example was the surveys conducted in 1996 by Rolf Jensen and Associates and Jaros, Gaum & Bolles 
which identified inconsistencies with the code and programs to address them, which are discussed in this 
report in detail. 

Innovations in Fire and Life Safety Features 

Little about the towers’ fire and life safety features would be considered novel or innovative.  The fire 
alarm systems as originally provided and as upgraded over the life of the buildings were of high quality 
and state-of-the-art, but followed accepted practice as it evolved in those years.  Similarly, the fire 
sprinkler system was high quality and state-of-the-art, following accepted practice with a few features 
following New York City practice that differed from the rest of the nation.  This included manually 
operated fire pumps with a so called “standpipe telephone system” to communicate with the pump 
operator.  Most codes and standards specify automatic fire pumps. 

Two features that were novel (and thus innovative) were the use of lightweight trusses in the floor system 
with fire protection of spray applied material on steel bars (rather than angles).  Another was the shaft 
enclosure system of reinforced gypsum planks with applied steel channels that formed the framing.  
While gypsum shaft enclosure systems are now common, this particular arrangement was not used before 
or since. 

Fuel System for Emergency Generators in WTC 7 

Several of the tenants in WTC 7 installed generators to supply critical operations with continuous power.  
These generators were installed on several floors within the building (5, 7, 8, and 9) and fed from small 
(275 gal) “day tanks” near the generators.  These day tanks were kept full by an automatic system of 
piping running to primary storage tanks (24,000 gal) located under the loading dock or a 6,000 gal tank in 
a 1st floor storage room associated with the generators for the Mayor’s Office of Emergency Management 
on the 7th floor.  Details of the system design and installation are found in NIST NCSTAR 1-1J.

1

 

                                                      

1

   This reference is to one of the companion documents from this Investigation.  A list of these documents appears in the Preface 

to this report. 

background image

Executive Summary 

 

Draft for Public Comment 

l

 

NIST NCSTAR 1-1, WTC Investigation 

 

E.11 FINDINGS 

The findings of this report are grouped into three categories: (1) general; (2) factors related to structural 
safety; and (3) factors related to fire safety. 

E.11.1 General 

Finding 1:

 The NYC Department of Buildings reviewed the WTC tower drawings in 1968 and provided 

comments to the PANYNJ concerning the plans in relation to the 1938 NYC Building Code.  The 
architect-of-record submitted to the PANYNJ responses to those comments, noting how the drawings 
conformed to the 1968 NYC Building Code.  All six comments made by the NYC Department of 
Buildings dealt with egress issues, but none questioned the large occupant loads for Windows on the 
World in WTC 1 or Top of the World in WTC 2.  

Finding 2:

 In 1993, the PANYNJ and the NYC Department of Buildings entered into a memorandum of 

understanding that restated the PANYNJ’s longstanding stated policy to ensure that its facilities in the 
City of New York meet and, where appropriate, exceed the requirements of the NYC Building Code.  The 
agreement also provided specific commitments to the NYC Department of Buildings regarding 
procedures to be undertaken by the PANYNJ to ensure that buildings owned or operated by the PANYNJ 
are in conformance with the Building Standards contained in the NYC Building Code.  Some salient 
points included in this agreement and the 1995 enhancement to the agreement are: 

 

Each project would be reviewed and examined for compliance with the Code. 

 

All plans would be prepared, sealed, and reviewed by New York State licensed professional 
engineers or architects. 

 

The PANYNJ engineer or architect approving the plans would be licensed in the State of 
New York and would not have assisted in the preparation of the plans.  

 

The person or firm performing the review and certification of plans for WTC tenants may be 
the same person or firm providing certification that the project had been constructed in 
accordance with the plans and specifications unless the proposed alteration would “change 
the character of the occupancy group under paragraph 27-237 of the NYC Building Code 
which would have been applicable to such space had such space been located in a privately 
owned building.” 

 

Variances from the Code, acceptable to the PANYNJ, would be submitted to the 
NYC Department of Buildings for review and concurrence. Disagreements between the 
PANYNJ and the NYC Department of Buildings over such variances from the Code would 
be referred to the Port Authority Board of Commissioners for resolution. 

Finding 3: 

While the PANYNJ entered into agreements with the NYC Department of Buildings in the 

1990s with regard to conformance of PANYNJ buildings constructed in New York City to the 
NYC Building Code and sought review and concurrence as required by the agreements, the PANYNJ was 
not required to yield, and appears not have yielded, approval authority to New York City.  The PANYNJ 
was created as an interstate entity “body corporate and politic,” under its charter, pursuant to Article 1 

background image

Draft for Public Comment 

 

Executive Summary 

NIST NCSTAR 1-1, WTC Investigation 

li

 

Section 10 of the U.S. Constitution permitting compacts between states, and like many other 
nongovernmental and quasi-governmental entities in the United States is not subject to building and fire 
safety code requirements of any governmental jurisdiction.   

Finding 4: 

State and local jurisdictions do not require retention of documents related to the design, 

construction, operation, maintenance, and modifications of buildings, with few exceptions.  These 
documents are in the possession of building owners, contractors, architects, engineers, and consultants.  
Such documents are not archived for more than about 6 years to 7 years, and there are no requirements 
that they be kept in safe custody physically remote from the building throughout its service life.  In the 
case of the WTC towers, the PANYNJ and its contractors and consultants maintained an unusually 
comprehensive set of documents, a significant portion of which had not been destroyed in the collapse of 
the buildings but could be assembled and provided to the investigation.  In the case of WTC 7, several 
key documents could not be reviewed since they were lost in the collapse of the building.   

Finding 5:

 Consistent with the practice at the time the (code) architect was responsible for specifying the 

fire protection and designing the egress system in accordance with the prescriptive provisions of the 
Building Code.  The architect and owner engaged the services of structural engineers to perform the 
structural design and to ensure that his/her design was properly implemented.  At that time the fire 
protection engineering profession was not sufficiently mature to require the same standard of care 
employed with the structural design.  There is no reason to believe that the involvement of a fire 
protection engineer at that time would have resulted in any differences in the design or performance of the 
fire protection systems.  However, the technical base and sophistication of the practice of fire protection 
engineering today is well advanced of where it was then.  Today, particularly when designing a building 
employing innovative features, the involvement of a fire protection engineer in a role similar to the 
structural engineer, and under the overall coordination of the Design Professional in Responsible Charge 
is central to the standard of care. Further, when designing the structure of selected tall buildings or 
selected other buildings to resist fires, or evaluating the fire resistance of such structures, it is essential for 
the structural engineer and the fire protection engineer to jointly provide the needed standard of care. 

E.11.2 Structural 

Safety 

Applicable Building Codes 

Finding 6:

 Although not required to conform to New York City codes, the PANYNJ adopted the 

provisions of the proposed 1968 edition of the NYC Building Code, more than 3 years before it went into 
effect.  The proposed 1968 edition allowed the PANYNJ to take advantage of less restrictive provisions 
and of technological advances compared with the 1938 edition, which was in effect when design began 
for the WTC towers in 1962.  The 1968 code: 

 

Changed partition loads from 20 psf to one based on weight of partitions per unit length (that 
reduced such loads for many buildings including the WTC buildings); and 

 

Permitted wind tunnel tests using models to establish design values for the wind load. 

Many of these newer requirements, instituted in the 1968 NYC Building Code, are contained in current 
model codes and building regulations. 

background image

Executive Summary 

 

Draft for Public Comment 

lii

 

NIST NCSTAR 1-1, WTC Investigation 

 

Structural Integrity 

Finding 7: 

Building codes lack

 

explicit structural integrity provisions to mitigate progressive collapse.  

Federal agencies have developed guidelines to mitigate progressive collapse and routinely incorporate 
such requirements in the construction of new federal buildings.  The United Kingdom incorporates such 
code requirements for all buildings.  New York City adopted by rule in 1973 a requirement for buildings 
to resist progressive collapse under extreme local loads.  The rules, which were adopted after the 
WTC towers were built but before WTC 7 was built, applied specifically to buildings that used precast 
concrete wall panels and not to other types of buildings.   

Finding 8: 

Building codes lack minimum structural integrity provisions for the means of egress 

(stairwells and elevator shafts) in the building core that are critical to life safety.  In most tall buildings the 
core is designed to be part of the vertical gravity load carrying system of the structure.  However, in many 
of those buildings, especially in regions where earthquakes are not dominant, the core may not be part of 
the lateral load carrying system of the structure.  Thus, the core may be designed to carry only vertical 
gravity loads with no capacity to resist lateral loads, i.e., overturning moment and shear loads.  In such 
situations, the structural designer may prefer the use of partition walls over structural walls in the core 
area to reduce building weight.  The decision to have the core carry a specified fraction of the lateral 
design loads or be made part of a dual system to carry lateral loads, each of which would enhance the 
structural integrity of the core if structural walls were used, is left to the discretion of the structural 
engineer. Alternatively, stairway/elevator cores built with concrete or reinforced concrete block, which 
are not part of the lateral load carrying system, may be able to provide sufficient structural integrity if 
they meet, for example, ASTM E1996-03, or other more appropriate test for impact resistance.  In the 
case of the WTC towers, the core had 2 h fire-rated partition walls with little structural integrity and the 
core framing was required to carry only gravity loads.  Had there been a minimum structural integrity 
requirement to satisfy normal building and fire safety considerations, it is conceivable that the damage to 
stairways, especially above the floors of impact, may have been less extensive. 

Finding 9: 

Standards and code provisions for conducting wind tunnel tests and for the methods used in 

practice to estimate design wind loads from test results do not exist.  Building codes allow the 
determination of wind pressures from wind tunnel tests for use in design.  Such tests are frequently used 
in the design of tall buildings.  Results of two sets of wind tunnel tests conducted for the WTC towers in 
2002 by independent commercial laboratories as part of insurance litigation, and voluntarily provided to 
NIST by the parties to the litigation, show large differences, of as much as about 40 percent, in resultant 
forces on the structures, i.e., overturning moments and base shears.  Independent reviews by a NIST 
expert on wind effects on structures and a leading engineering design firm contracted by NIST indicated 
that the documentation of the test results did not provide sufficient basis to reconcile the differences. 
Wind loads were a major governing factor in the design of structural components that made up the frame-
tube steel framing system. 

E.11.3 Fire 

Safety 

Applicable Building Codes 

Finding 10: 

Although not required to conform to New York City codes, the PANYNJ adopted the 

provisions of the proposed 1968 edition of the NYC Building Code, more than 3 years before it went into 

background image

Draft for Public Comment 

 

Executive Summary 

NIST NCSTAR 1-1, WTC Investigation 

liii

 

effect.  The 1968 edition allowed the PANYNJ to take advantage of less restrictive provisions compared 
with the 1938 edition that was in effect when design began for the WTC towers in 1962.  The 1968 code: 

 

Eliminated a fire tower

2

 as a required means of fire department access; 

 

Reduced the number of required stairwells from 6 to 3 and the size of doors leading to the 
stairs from 44 in. to 36 in.(by increasing stairway and door capacity allowances); 

 

Reduced the required fire rating of the shaft walls in the building core from 3 h to 2 h; and 

 

Permitted a 1 h reduction in fire rating for all structural components (columns from 4 h to 3 h 
and floor framing members from 3 h to 2 h) by allowing the owner/architect to select Class 
1B construction for business occupancy and unlimited building height. 

Many of these newer requirements, instituted in the 1968 NYC Building Code, are contained in current 
codes. 

Finding 11:

 In 1993, the PANYNJ adopted a policy providing for implementation of fire safety 

recommendations made by local government fire departments after a fire safety inspection of a PANYNJ 
facility and for the prior review by local fire safety agencies of fire safety systems to be introduced or 
added to a facility.  Later that year, the PANYNJ entered into an agreement with the New York City Fire 
Department (FDNY), which reiterated the policy adopted by the PANYNJ, recognized the right of FDNY 
to conduct fire safety inspections of PANYNJ properties in the City of New York, provided guidelines for 
FDNY to communicate needed corrective actions to the PANYNJ, ensured that new or modified fire 
safety systems are in compliance with local codes and regulations, and required third-party review of such 
systems by a New York State licensed architect or engineer. 

Standard Fire-Resistance Tests 

Finding 12: 

Code provisions with detailed procedures to analyze and evaluate data from fire resistance 

tests of other building components and assemblies to qualify an untested building element do not exist.  
Based on available data and records, no technical basis has been found for selecting the SFRM used (two 
competing materials were under evaluation) or its thickness for the large-span open-web floor trusses of 
the WTC towers.  The assessment of the fireproofing thickness needed to meet the 2 h fire rating 
requirement for the untested WTC floor system evolved over time: 

 

In October 1969, the PANYNJ directed the fireproofing contractor to apply ½ in. of 
fireproofing to the floor trusses.   

 

In 1999, the PANYNJ issued guidelines requiring that fireproofing be upgraded to 1½ in. for 
full floors undergoing alterations.   

                                                      

2

   A fire tower (also called a smoke-proof stair) is a stairway that is accessed through an enclosed vestibule that is open to the 

outside or to an open ventilation shaft providing natural ventilation that prevents any accumulation of smoke without the need 
for mechanical pressurization. 

background image

Executive Summary 

 

Draft for Public Comment 

liv

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Unrelated to the WTC buildings, an International Conference of Building Officials 
Evaluation Service report (ER-1244), re-issued June 1, 2001, using the same SFRM 
recommends a minimum thickness of 2 in. for “unrestrained steel joists” with “lightweight 
concrete” slab. 

Finding 13: 

Code provisions that require the conduct of a fire resistance test if adequate data do not exist 

from other building components and assemblies to qualify an untested building element are needed.  
Instead, several alternate methods based on other fire-resistance designs or calculations or alternative 
protection methods are permitted with limited guidance on detailed procedures to be followed.  Both the 
architect-of-record (in 1966) and the structural-engineer-of-record (in 1975) stated that the fire rating of 
the floor system of the WTC towers could not be determined without testing.  NIST has not found 
evidence indicating that such a test was conducted to determine the fire rating of the WTC floor system.  
The PANYNJ has informed NIST that there are no such test records in its files.   

Finding 14: 

Use of the “structural frame” approach, in conjunction with the prescriptive fire rating, 

would have required the floor trusses, the core floor framing, and perimeter spandrels in the WTC towers 
to be 3 h fire-rated, like the columns for Class 1B construction in the 1968 NYC Building Code.  Neither 
the 1968 edition of the NYC Building Code which was used in the design of the WTC towers, nor the 
2001 edition of the code, adopted the “structural frame” requirement.   The “structural frame” approach to 
fire resistance ratings requires structural members, other than columns, that are essential to the stability of 
the building as a whole to be fire protected to the same rating as columns.  This approach, which appeared 
in the Uniform Building Code (a model building code) as early as 1953, was carried into the 
2000 International Building Code (one of two current model codes) which states: “The structural frame 
shall be considered to be the columns and the girders, beams, trusses and spandrels having direct 
connections to the columns and bracing members designed to carry gravity loads.”  The WTC floor 
system was essential to the stability of the building as a whole since it provided lateral stability to the 
columns and diaphragm action to distribute wind loads to the columns of the frame-tube system. 

Finding 15: 

A technical basis to establish whether the construction classification and fire rating 

requirements in modern building codes are risk-consistent with respect to the design-basis hazard and the 
consequences of that hazard is needed.  The fire rating requirements, which were originally developed 
based on experience with buildings less than about 20 stories in height, have generally decreased over the 
past 80 years since historical fire data for buildings suggested considerable conservatism in those 
requirements.  However, for tall buildings, the likely consequences of a given threat to an occupant on the 
upper floors are more severe than the consequences to an occupant, say, on the first floor.  It is not 
apparent how the current height and area tables in building codes consider the technical basis for the 
progressively increasing risk to an occupant on the upper floors of tall buildings that are much greater 
than about 20 stories in height where access by firefighters without the availability of firefighter elevators 
is limited by physiological factors.  The maximum required fire rating in current codes applies to any 
building more than about 12 stories in height.  There are no additional categories for buildings above, for 
example, 40 stories and 80 stories, where different building classification and fire ratings requirements 
may be appropriate, recognizing factors such as the time required for stairwell evacuation without 
functioning elevators (e.g., due to power failure or major water leakage), the time required for first 
responder access without functioning elevators, the presence of skylobbies and/or refuge floors, and 
limitations on the height of elevator shafts.  The 110-story WTC towers, initially classified as Class IA 
based on the 1938 NYC Building Code, were classified as Class 1B before being built to take advantage 

background image

Draft for Public Comment 

 

Executive Summary 

NIST NCSTAR 1-1, WTC Investigation 

lv

 

of the provisions in the 1968 edition of the code.  This re-classification permitted a reduction of 1 h in the 
fire rating of the components (columns from 4 h to 3 h and floor framing members from 3 h to 2 h). 

Fire Performance of Structures 

Finding 16:

 Rigorous field application and inspection provisions and regulatory requirements to ensure 

that the as-built condition of the passive fire protection, such as SFRM, conforms to conditions found in 
fire resistance tests of building components and assemblies is needed.  For example, provisions are not 
available to ensure that the as-applied average fireproofing thickness and variability (reflecting the quality 
of application) is thermally equivalent to the specified minimum fireproofing thickness.  In addition, 
requirements are not available for in-service inspections of passive fire protection during the life of the 
building.  The adequacy of the fireproofing of the WTC towers posed an issue of some concern to the 
PANYNJ over the life of the buildings, and the availability of accepted requirements and procedures for 
conducting in-service inspections would have provided useful guidance 

Finding 17: 

Structural design does not consider fire as a design condition, as it does the effects of dead 

loads, live loads, wind loads, and earthquake loads.  Current prescriptive code provisions for determining 
fire resistance of structures—used in the design of the WTC towers and WTC 7—are based on tests using 
a standard fire that may be adequate for many simple structures and for comparing the relative 
performance of structural components in more complex structures.  A building system with 3 h rated 
columns and 2 h rated girders and floors could last longer than 3 h or shorter than 2 h depending upon the 
performance of the structure as a 3-dimensional system in a real fire.  The standard tests cannot be used to 
evaluate the actual performance (i.e., load carrying capacity) in a real fire of the structural component, or 
the structure as a whole system, including the connections between components.  Performance-based code 
provisions and standards are not available for use by engineers, as an alternative to the current 
prescriptive fire rating approach, to (1) evaluate the system performance of tall-building structures under 
real fire scenarios, and (2) enable risk consistent design with appropriate thickness of  passive protection 
being provided where it is needed on the structure.  Standards development organizations, including the 
American Institute of Steel Construction, have initiated development of performance-based provisions to 
consider fire effects in structural design. 

Finding 18: 

Detailed procedures to select appropriate design-basis fire scenarios to be considered in the 

performance-based design of the sprinkler system, compartmentation, and passive protection of the 
structure are needed.  The standard fire in current prescriptive fire resistance tests is not adequate for use 
in performance-based design.  While the NFPA 5000 model building code contains general guidance on 
design fire scenarios (the IBC Performance Code contains no such guidance), the details of the scenarios 
are left to the fire engineer and regulatory official.  The three major scenarios that are not considered 
adequately are: frequent but low severity events (for design of sprinkler system), moderate but less 
frequent events (for design of compartmentation), and a maximum credible fire (for design of passive fire 
protection on the structure).  The maximum credible fire scenario for passive protection of structures 
would assume that the sprinkler system is compromised or overwhelmed and that there is no active 
firefighting, as is explicitly considered for U.S. Department of Energy facilities.  These building-specific 
representative fire scenarios are similar in concept, though not identical, to the approach used in building 
design where the performance objectives and design-basis of the hazard are better defined (e.g., a two-
level design that includes an operational event with a 10 percent probability of occurrence in 50 years and 
a life safety event with a 2 percent probability of occurrence in 50 years). The design-basis fire hazards 

background image

Executive Summary 

 

Draft for Public Comment 

lvi

 

NIST NCSTAR 1-1, WTC Investigation 

 

for the WTC towers and WTC 7 are unknown, and it is difficult to evaluate the performance of the fire 
protection systems in these buildings under specific fire scenarios. 

Finding 19: 

Code provisions to ensure that structural connections are provided the same degree of fire 

protection as the more restrictive protection of the connected elements are needed.  The provisions that 
were used for the WTC towers and WTC 7 did not require specification of a fire-rating requirement for 
connections separate from those for the connected elements. It is not clear what the fire rating of the 
connections were when the connecting elements had different fire ratings and whether the applied 
fireproofing achieved that rating.  

Finding 20: 

A technical basis to establish whether the minimum mechanical and durability related 

properties of SFRM are sufficient to ensure acceptable in-service performance in buildings is needed.  
While minimum bond strength requirements exist, there are no serviceability requirements for such 
materials to withstand typical shock, impact, vibration, or abrasion effects over the life of a building.  
There are existing testing standards for determining many of these properties, but the technical basis is 
insufficient to establish serviceability requirements.  Knowledge of such serviceability requirements is 
relevant to determine the post-impact fireproofing condition of the WTC towers. 

Finding 21: 

Validated and verified tools for use in performance-based design practice to analyze the 

dynamics of building fires and their effects on the structural system that would allow engineers to 
evaluate structural performance under alternative fire scenarios and fire protection strategies are needed.  
Existing tools are either too simplified to adequately capture the performance of interest or too complex 
and computationally demanding and lack adequate validation.  While considerable progress has been 
made in recent years, significant work remains to be done before adequate tools are available for use in 
routine practice.  NIST has had to further develop and validate existing tools to investigate the fire 
performance of the WTC towers and WTC 7. 

Compartmentation and Sprinklers 

Finding 22

: Building fire protection is based on a four-level hierarchical strategy comprising detection, 

suppression (sprinklers and firefighting), compartmentation, and passive protection of the structure.   

 

Detectors are typically used to activate fire alarms and notify building occupants and 
emergency services. 

 

Sprinklers are designed to control small and medium fires and to prevent fire spread beyond 
the typical water supply design area of about 1,500 ft

2

 

Compartmentation mitigates the horizontal spread of more severe but less frequent fires and 
typically requires fire-rated partitions for areas of about 7,500 ft

2

.  Active firefighting 

measures also cover up to about 5,000 ft

2

 to 7,500 ft

2

 

Passive protection of the structure seeks to ensure that a maximum credible fire scenario, with 
sprinklers compromised or overwhelmed and no active firefighting, results in burnout, not 
overall building collapse.  The intent of building codes is also for the building to withstand 
local structural collapse until occupants can escape and the fire service can complete search 
and rescue operations. 

background image

Draft for Public Comment 

 

Executive Summary 

NIST NCSTAR 1-1, WTC Investigation 

lvii

 

Compartmentation of spaces is a key building fire safety requirement to limit fire spread.  The WTC 
towers initially had 1 h fire-rated partitions separating tenants (demising walls) that extended from the 
floor to the suspended ceiling, not the floor above (the ceiling tiles were not fire rated).  Over the years, 
these partitions were replaced with partitions that were continuous from floor to floor (separation wall) as 
required by the 1968 NYC Building Code.  Some partitions had not been upgraded by 1997, and a 
consultant recommended to the PANYNJ that it develop and implement a survey program to ensure that 
the remediation process occurred as quickly as possible.  It appears that with few exceptions, nearly all of 
the floors not upgraded were occupied by a single tenant, and it is not clear whether separation walls 
would have mattered in terms of meeting the 1968 code.  The PANYNJ adopted guidelines in 1998 that 
required such partitions to provide a continuous fire barrier from top of floor to underside of slab. 

Finding 23: 

Building codes typically require 1 h fire-rated tenant separations but do not impose minimum 

compartmentation requirements (e.g., 13,000 ft

2

) for buildings with large open floor plans to mitigate the 

horizontal spread of fire.  This is the case with both the 1968 NYC Building Code, which did not require 
sprinklers in occupied spaces on or above the ground floor, and the 2001 NYC Building Code, which 
requires sprinklers in Group E (Business) buildings over 100 ft in height.  The sprinkler option was 
chosen for the WTC towers in preference to the compartmentation option in meeting the subsequent 
requirements of Local Law 5 adopted by New York City in 1973.  Thus, if there was only one tenant on a 
WTC floor there would be no horizontal compartmentation requirement.  Conversely, if there were a 
large number of tenants on a WTC floor, it would be highly compartmented with separation walls.  The 
affected floors in the WTC towers were mostly open—with a modest number of perimeter offices and 
conference rooms and an occasional special purpose area.  Some floors had two tenants and those spaces, 
like the core areas, were partitioned (slab to slab).  Photographic and videographic evidence confirms that 
even non-tenant space partitions (such as those that divided spaces to provide corner conference rooms) 
provided substantial resistance to fire spread in the affected floors.  For the duration of about 50 to 100 
min prior to collapse of the WTC towers that the fires were active, the presence of undamaged 1 h fire-
rated compartments may have assisted in mitigating fire spread and consequent thermal weakening of 
structural components. 

Finding 24: 

State and local building regulations are needed that require installation of sprinklers in 

existing buildings on a reasonable time schedule, not as an option in lieu of compartmentation. 
Functioning sprinklers can provide significant improvement in safety for most common building fires and 
prevent them from becoming large fires.  NYC promulgated local laws in 1973 and 1984 to encourage 
installation of sprinklers in new buildings and is now considering a law to require sprinklers in existing 
buildings.  The WTC towers were fully sprinklered by 2001, about 30 years after their construction.  
Sprinklering of the tenant floors in the WTC towers was completed by October 1999, while sprinklering 
of the skylobbies was still underway at that time.  The sprinkler system was installed in three phases.  
Phase 1 was completed during initial building construction and included the sub-grade areas.  Phase 2 was 
completed in 1976, in compliance with Local Law 5, and included sprinklering the corridors, storage 
rooms, lobbies, and certain tenant spaces.  Phase 3 was begun in 1983 and completed in 2001 and resulted 
in fully sprinklering the buildings. 

Finding 25: 

Modern building codes allow a lower fire rating for structural elements when a building is 

sprinklered.  This trade-off provides an economic incentive to encourage installation of sprinklers.  
Sprinklers provide better intervention against small and medium fires, fires which are more likely to occur 
than a WTC disaster, as long as the water supply is not compromised and there is redundant technology in 

background image

Executive Summary 

 

Draft for Public Comment 

lviii

 

NIST NCSTAR 1-1, WTC Investigation 

 

place.  The required technical basis is not available to establish whether the “sprinkler trade-off” in 
current codes adequately considers fire safety risk factors such as: (1) the complementary functions of 
sprinklers and fire-protected structural elements, (2) the different fire scenarios for which each system is 
designed to provide protection, and (3) the need for redundancy should one system fail.  It is noteworthy 
that the British Standards Institution has established a group to review all the sprinkler trade-offs 
contained in their standards. No such formal review has yet been initiated in the United States.  Although 
the classification and fire rating of the WTC towers did not take advantage of the sprinkler-tradeoff since 
such provisions were not contained in the 1968 NYC Building Code, had such provisions existed, they 
would have permitted a lower fire rating for many WTC building elements.   

Use of Elevators in Emergencies 

Finding 26: 

With a few special exceptions, building codes in the United States do not permit the use of 

fire-protected elevators for routine emergency access by first responders or as a secondary method (after 
stairwells) for emergency evacuation of building occupants.  The use of elevators by first responders 
would additionally mitigate counterflow problems in stairwells.  While the United States conducted 
research on specially protected elevators in the late 1970s, the United Kingdom along with several other 
countries that typically utilize British standards have required such “firefighter lifts,” located in protected 
shafts, for a number of years.  Without functioning elevators (e.g., due to a power failure or major water 
leakage), first responders carrying gear typically require about a minute per floor to reach an incident 
using the stairs.  While it is difficult to maintain this pace for more than about the first 20 stories, it would 
take a first responder about an hour to reach, for example, the 60th floor of a tall building if that pace 
could be maintained.  Such a delay, combined with the resulting fatigue and physical effects on first 
responders that were reported on September 11, 2001, would make firefighting and rescue efforts difficult 
even in tall building emergencies not involving a terrorist attack.  Each of the WTC towers had 106 
elevators, and WTC 7 had 38 elevators.  By code, the elevators could not be used for fire service access or 
occupant egress during an emergency since they were not fire-protected, nor were they located in 
protected shafts.  The elevators were equipped through normal modernization with fire service recall.  
Most were damaged by the aircraft impacts; though prior to the impact in WTC 2 the elevators were 
functioning and contributed greatly to the much faster initial evacuation rate in WTC 2. 

 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

1

 

Chapter 1 

I

NTRODUCTION

 

1.1 BACKGROUND 

On September 11, 2001, the 110-story twin towers of the World Trade Center (WTC) complex

1

 (WTC 1 

and WTC 2) were each attacked by a hijacked Boeing 767 airplane.  The first airplane struck WTC 1 at 
8:46 a.m. Eastern Daylight Time, and the second airplane struck WTC 2 at 9:03 a.m. Eastern Daylight 
Time.  The impact of the airplanes caused severe damage to the buildings and significant fire.  WTC 1 
collapsed at 10:29 a.m. and WTC 2 at 9:59 a.m.  Debris from the collapse of the towers caused severe 
damage to surrounding buildings of the WTC complex (WTC 3 through WTC 7).  WTC 7, a 47-story 
office building, burned unattended for about 7 h before collapsing at 5:20 p.m.   

As stated in the Preface, the National Institute of Standards and Technology (NIST) Investigation is 
comprised of eight interdependent projects (refer to Table P–1).  This report presents the results of 
Project 1 “Analysis of Building and Fire Codes and Practices.”  The project was carried out to support 
one of the four primary objectives of the NIST Investigation, which is to determine the procedures and 
practices that were used in the design, construction, operation, and maintenance of the WTC 1, 2, and 7 
(for other objectives, see the Preface).  This report documents criteria used to design and construct the 
buildings and maintenance of the structural and fire safety systems. It also addresses innovative systems 
and materials that were incorporated into the design and construction process.  Based on this information, 
NIST has identified procedures and practices for which improvements are recommended.  

1.2 

SCOPE OF REPORT 

The assessment of the criteria, procedures, and practices that were used in the design, construction, 
operation, and maintenance of WTC 1, 2, and 7 involved reviewing the design and construction 
documents of these buildings, including design drawings, specifications, and design calculations.  In 
addition, since the 1968 New York City (NYC) Building Code was adopted by the Port of New York 
Authority (whose name was changed to the Port Authority of New York and New Jersey [PANYNJ or 
Port Authority] in 1972, and is subsequently referred to as the Port Authority herein) for design and 
construction of the WTC 1, 2, and 7, review of relevant provisions of that code and similar provisions of 
other contemporaneous codes was necessary to place in context the design and construction practices that 
were used for WTC 1, 2, and 7.  

Traditionally, owners and designers of major construction projects maintain the design and construction 
documents.  In the case of the WTC buildings, the design and construction documents that were kept at 
the Port Authority office in WTC 1 were destroyed when the tower collapsed.  Thus, available copies of 
design and construction documents of WTC 1, 2, and 7 had to be assembled from various sources that 
were associated with the WTC projects. 

                                                      

1

  The WTC complex was composed of seven buildings. They are referred to as WTC 1 through WTC 7 in this report.  For 

specific details, see Sec. 2.1. 

background image

Chapter 1 

 

Draft for Public Comment 

2

 

NIST NCSTAR 1-1, WTC Investigation 

 

NIST obtained a considerable amount of information (design drawings, shop drawings, specifications, 
project correspondence, and inspection reports) related to WTC 1 and WTC 2 from the structural 
engineering firm involved in the original design and subsequent modifications to WTC 1 and WTC 2.  
The Port Authority provided construction related files for WTC 1, 2, and 7, mostly pertaining to tenant 
alteration projects, wherein tenants modified parts of the buildings to meet their needs.  No document was 
obtained from the general contractor of WTC 1, 2, and 7 who had discarded the construction documents 
after retaining them for about 7 years.  As a result, records were not available from the general contractor 
pertaining to changes to the structural and fire safety systems that were made during construction.  

The information collected enabled NIST to document the following: 

 

Factors related to the design and construction of structural systems: 

 

Provisions used to design and construct the buildings.  

 

Criteria used to proportion structural members and other components of the buildings, 
including structural connections. 

 

Innovative systems, technologies, and materials that were incorporated in the design and 
construction. 

 

Tests performed to support the design, such as wind tunnel tests and tests of structural 
assemblies. 

 

Variances granted by the Port Authority, including the justification for those variances. 

 

Special fabrication and inspection requirements. 

 

Inspection protocols used during construction. 

 

Technical problems that occurred during construction of the buildings and their 
resolution. 

 

Comparison of the structural provisions in the 1968 New York City (NYC) Building Code 
with other contemporaneous code provisions: 

 

Differences between the 1968 NYC Building Code and the contemporaneous building 
codes of New York State, Chicago, and Building Officials Conference of America 
(BOCA), and the 2001 NYC Building Code. 

 

Maintenance of and modifications to the structural system: 

 

Guidelines used by the Port Authority for inspection, repair, and modifications.  

 

Structural integrity inspection programs during the occupancy of the buildings.  

 

Any significant modifications to and/or repairs of the original structural framing system 
by the owner or tenants during original construction and occupancy. 

background image

Draft for Public Comment 

 

Introduction 

NIST NCSTAR 1-1, WTC Investigation 

3

 

 

Factors related to the design and construction of the fire protection and egress systems: 

 

Provisions used to design and construct the fire protection and egress systems of the 
buildings.  

 

Building regulations adopted after the issuance of the certificates of occupancy that were 
applied to the buildings retroactively, including any provisions of New York City Local 
Laws, and any permits issued or special inspections required resulting from the 
installation of special hazards or equipment in the buildings. 

 

Comparison of the fire safety provisions in the 1968 NYC Building Code with other 
contemporaneous code provisions: 

 

Differences between the 1968 NYC Building Code and the contemporaneous building 
codes of New York State, Chicago, and Building Officials Conference of America 
(BOCA), and the 2001 NYC Building Code. 

 

Evolution of the life safety provisions in the NYC Building Code since the design of 
WTC 1 and WTC 2. 

 

Maintenance of and modifications to the fire protection and egress systems: 

 

Guidelines used by the Port Authority for inspection, repair, and modifications to fire 
protection and egress systems.  

 

Any repairs and modifications made to the passive and active fire protection systems 
from initial occupancy to September 11, 2001. 

 

The fuel system for emergency power in WTC 7 to determine: 

 

Locations of emergency power generating systems. 

 

Size and locations of the fuel storage tanks and distribution systems. 

 

Specific fire protection systems used for the fuel storage and distribution systems. 

 

Normal and emergency operating procedures.  

 

Maintenance history. 

This report provides an overview and comparison of building codes in use at the time when WTC 1, 2, 
and 7 were designed and constructed.  It includes a description of the buildings as designed and relates 
features of the buildings to the code requirements and accepted practices of the time.  Also presented is 
the evolution of codes during the time the buildings were in use and a description of how the buildings 
were modified and upgraded over the same period.  Even though many of the new code requirements did 
not apply to existing buildings, in several instances these new approaches were incorporated and systems 
upgraded accordingly.  Also identified were some issues that were not consistent with code requirements, 
such as the spray applied fireproofing and tenant separation walls that were eventually addressed by 

background image

Chapter 1 

 

Draft for Public Comment 

4

 

NIST NCSTAR 1-1, WTC Investigation 

 

upgrade projects.  The upgrades were performed on change of tenancy over many years.  The reader 
should note that the documentation of certain systems and their condition and arrangement on 
September 11, 2001 are included in other reports.   Specifically, the elevators and egress stairs are 
discussed in NIST NCSTAR 1-7, and the fire alarm, sprinkler, and smoke management systems in NIST 
NCSTAR 1-4.  This reference is to one of the companion documents from this Investigation.  A list of 
these documents appears in the Preface to this report. 

1.3 

DESIGN AND CONSTRUCTION REQUIREMENTS FOR WTC 1, 2, AND 7 

For most buildings constructed in the United States, building codes adopted by local jurisdictions 
establish minimum requirements for design and construction.  However, because the Port Authority is an 
interstate entity, which was established in 1921 under a clause in the U.S. Constitution, its construction 
projects are not required to comply with any state or local building code.  For the design of the WTC 
towers, which began in 1962, the Port Authority in May 1963 instructed the architect and engineers to 
prepare their designs of WTC 1 and WTC 2 to comply with the NYC Building Code.

2

  While not 

specifically stated in the 1963 letter to the architect, the 1938 edition of the Code was in effect at that 
time.  In areas where the Code was not explicit or where technological advances made portions of the 
1938 Code obsolete, the Port Authority also directed the architect and engineers to propose designs 
“based on acceptable engineering practice.”  When such situations occurred, the Port Authority required 
the architect and engineers to inform the Planning Division of the WTC.  The Port Authority established a 
special WTC office that reviewed and approved plans and specifications, issued variances, and conducted 
inspections during construction instead of the city agencies that would normally perform these duties.  

In September 1965, the Port Authority instructed the architect and engineers to revise their designs for 
WTC 1 and WTC 2 to comply with the second and third drafts of the NYC Building Code that was under 
development and to undertake any design modifications necessary to comply with the new code 
provisions.

3

  Prior to issuance of this instruction, the Port Authority recognized that the draft version of 

the new NYC Building Code had incorporated advanced techniques, and the Port Authority favored the 
use of advanced techniques in the design of the WTC towers.

4

  By adopting the draft versions of the new 

NYC Building Code, the Port Authority had an option of classifying WTC 1 and WTC 2 as Type 1-B 
Construction instead of Type 1-A Construction (see Sec. 9.1.3 for definition and fire protection 
requirements of Construction Type), and several architectural features related to egress were modified in 
the final design (see Sec. 10.1).  This relaxation of code requirements allowed the Port Authority to gain 
economic advantage.

5

  The new NYC Building Code (NYC BC 1968) was enacted by the City Council on 

October 22, 1968, approved by the Mayor on November 6, 1968, and became effective on December 6, 
1968. 

                                                      

2

  Letter dated May 15, 1963 from Malcolm P. Levy (Chief, Planning Division, World Trade Department, PANYNJ) to Minoru 

Yamasaki (architect, Minoru Yamasaki & Associates) (See Appendix A). 

3

  Letter dated September 29, 1965 from Malcolm P. Levy (Chief, Planning Division, World Trade Department, PANYNJ) to 

Minoru Yamasaki (architect, Minoru Yamasaki & Associates) (See Appendix A). 

4

   Memorandum dated June 22, 1965 from John M. Kyle (Chief Engineer, PANYNJ) to Malcolm P. Levy (Chief, Planning 

Division, World Trade Department, PANYNJ) (See Appendix A). 

5

  Memorandum dated January 15, 1987 fromLester S. Feld (Chief Structural Engineer, World Trade Department) to Robert J. 

Linn (Deputy Director, Physical Facilities, World Trade Department), (See Appendix A). 

background image

Draft for Public Comment 

 

Introduction 

NIST NCSTAR 1-1, WTC Investigation 

5

 

The Port Authority also required that all design concepts were to be reviewed before the final design by 
the Chief Engineer of the Port Authority and by the appropriate New York City agencies.  A letter in 1975 
from the architect-of-record for the WTC project to the Port Authority indicates that the New York City 
Building Department reviewed the design drawings of WTC 1 and WTC 2 in February 1968.

6

 

Unlike WTC 1 and WTC 2, which were developed and owned by the Port Authority, WTC 7 was 
developed on land owned by the Port Authority, but the building was owned by Seven World Trade 
Company and Silverstein Development Corporation, General Partners. It was designed and constructed as 
a “Tenant Alteration Project” of the Port Authority. When WTC 7 was designed in the mid-1980s, the 
1968 NYC Building Code with amendments was in effect. The Project Specifications for WTC 7, issued 
in 1984, required that the structural steel be designed in accordance with the then current NYC Building 
Code. 

The Port Authority developed a tenant alteration process for any modifications to leased spaces in WTC 1 
and WTC 2 to maintain structural integrity and fire safety. In 1971, the Port Authority issued the first 
edition of a set of requirements, 

Tenant Construction Review Manual

 (See NIST NCSTAR 1-1C, 

Appendix A), shortly after the first tenants occupied WTC 1 in December 1970 and before initial 
occupancy of WTC 2 in 1972.  The manual contained the technical criteria to be used in planning 
alterations (architectural, structural, mechanical, electrical, and fire protection) to suit the needs of 
tenants. The manual included applicable standards to be used by tenants and their agents and review 
criteria to be used by the Engineering Department of the Port Authority.  Alteration designs were to be 
completed by registered design professionals, and at the completion of the work, as-built drawings were 
to be submitted to the Port Authority.  The 1968 NYC Building Code was referenced, and specific code 
provisions were referenced in various checklists.  The review manual was updated in 1979, 1984, 1990, 
and 1997, at which times changes that had been made to the NYC Building Code were incorporated. In 
1998, the manual was replaced by 

Architectural and Structural Design Guidelines, Specifications, and 

Standard Details

 (see NIST NCSTAR 1-1C, Appendix F), which dealt specifically with alterations to 

WTC 1 and WTC 2. Since WTC 7 was built as a “tenant alteration project,” its design and construction 
followed the requirements in the 1984 edition of the 

Tenant Construction Review Manual

. Any 

modifications to the building after initial occupancy were carried out in accordance with the manual. 

1.4 ORGANIZATION 

OF 

REPORT 

This report is organized in fourteen chapters: 

 

Chapter 1 covers the background and the scope of the report. 

 

Chapter 2 presents architectural and structural descriptions of WTC 1, 2, and 7. 

 

Chapter 3 presents the evolution of building codes in the United States, the development of the 
building code of New York City, and design requirements and policies of the Port Authority 
of New York and New Jersey. 

                                                      

6

  Letter dated February 18, 1975 from Joseph H. Solomon (Architect, Emory Roth & Sons) to Malcolm P. Levy (General 

Manager, World Trade Center Operations), (See Appendix A). 

background image

Chapter 1 

 

Draft for Public Comment 

6

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Chapter 4 provides an overview and comparison of building codes in use at the time WTC 1, 
2, and 7 were designed and constructed.  Also presented is the evolution of codes during the 
time the buildings were in use and how the buildings were modified and upgraded over the 
same period.  The structural code provisions compared include the 1964 New York State 
Building Construction Code, the 1965 BOCA model building code, and the 1967 Municipal 
Code of Chicago.  A comparison was also made between the 1968 NYC Building Code and 
the current (2001) NYC Building Code. 

 

Chapter 5 presents the criteria for structures used to design WTC 1, 2, and 7. 

 

Chapter 6 presents innovative features incorporated in the structural design of WTC 1 and 
WTC 2. 

 

Chapter 7 presents the protocols for inspection of steel members during fabrication and 
erection, and variances that were requested by fabricators and the erector and granted by the 
Port Authority. 

 

Chapter 8 covers structural maintenance and modifications to WTC 1, 2, and 7 during 
occupancy. 

 

Chapter 9 compares the fire safety provisions in the 1964 New York State Building 
Construction Code (NYSBC 1964), the 1965 BOCA model building code (Basic Building 
Code), and the 1967 Municipal Code of Chicago (MCC 1967).  A comparison was also made 
between the 1968 NYC Building Code and the current (2001) NYC Building Code. This 
chapter also describes various construction classifications of buildings. 

 

Chapter 10 describes passive and active fire protection systems used in WTC 1, 2, and 7, and 
egress provisions in the WTC towers. 

 

Chapter 11 presents maintenance of and modifications to fire safety systems in WTC 1, 2, and 
7 during occupancy. 

 

Chapter 12 presents the fuel system distribution for emergency power generators in WTC 7. 

 

Chapter 13 presents the findings of this report. 

 

Chapter 14 covers the reference cited in this report.  

background image

 

NIST NCSTAR 1-1, WTC Investigation 

7

 

Chapter 2 

D

ESCRIPTION OF 

WTC

 

1,

 

2,

 AND 

2.1 

SITE PLAN OF WTC COMPLEX 

The World Trade Center (WTC) complex was located in Manhattan, New York City, near the Hudson 
River.  The complex was comprised of seven buildings (referred to in this report as WTC 1 through 
WTC 7).  Figure 2–1 depicts the locations of these buildings relative to the surrounding streets.  The two 
towers, WTC 1 (North Tower) and WTC 2 (South Tower), were each 110 stories high.  WTC 3 (Marriott 
Hotel) was 22 stories.  WTC 4 (South Plaza Building) and WTC 5 (South Plaza Building) were both nine-
story office buildings.  WTC 6 (U.S. Customs House) was an eight-story office building. These six 
buildings were built around a 5-acre WTC Plaza.  WTC 7 was a 47-story office building which was built 
just north of the six-building WTC site.  There was a six-story subterranean structure below a large 
portion of the WTC Plaza and WTC 1, 2, 3, and 6.  In order to build this subterranean structure, a 
bentonite slurry wall was built surrounding the perimeter of the subterranean structure prior to excavation.  
The slurry wall was replaced section by section with reinforced concrete wall which served as a 
continuous foundation wall for the subterranean structure.  The reinforced concrete wall was temporarily 
supported by rock anchors to provide lateral stability.  The permanent lateral support was provided by the 
subterranean floor slabs.  The application of slurry wall technology was considered to be an innovative 
idea (ENR 1964). 

The first six buildings on the site were developed by the Port Authority.  Groundbreaking for WTC 1 and 
WTC 2 was in 1966, and the first tenant began to occupy WTC 1 in December 1970 and WTC 2 in 
January 1972.  Construction of other buildings continued during the 1970s and the 1980s.

7

  Construction 

of the last building, WTC 7, was completed in 1987.  It was developed by a consortium of Seven World 
Trade Company and Silverstein Development Corporation. 

2.2 

DESCRIPTION OF WTC 1 AND WTC 2 

2.2.1 Building 

Description 

WTC 1 and WTC 2 (also known as North Tower and South Tower) each consisted of a 110-story 
structure above the Concourse level (109-story above the Plaza level) and 6-story structure below the 
Concourse level.

8

  Although the towers were similar, they were not identical.  The height of WTC 1 at the 

roof level was 1,368 ft above the Concourse level, 6 ft taller than WTC 2, and WTC 1 supported a 360 ft 
tall antenna for television and radio transmission.  Figure 2–2 shows the west elevation of WTC 1, and 
Fig. 2–3 shows a typical exterior wall from the foundation to floor 9. 

                                                      

7

  A brochure entitled “The World Trade Center” published by the Port of New York Authority, New York, NY and “World 

Trade Center Fact Sheet” published by the Port Authority of New York and New Jersey, New York, NY, April 1994. 

8

  The architectural and structural descriptions and dimensions of the WTC buildings in this report are based on the design 

drawings of these buildings obtained from the Port Authority of New york and New Jersey. 

background image

Chapter 2 

 

Draft for Public Comment 

8

 

NIST NCSTAR 1-1, WTC Investigation 

 

Each tower had a square plan with the side dimension of approximately 207 ft. The exterior columns 
(perimeter columns) were placed with respect to the column reference lines, wherein the geometric 
centers of the exterior columns were offset from the column reference lines (See Sec. A-A, Fig. 2–9).  
The four reference lines surrounding the base of the tower established the footprint of the building. The 
column reference lines were spaced at 207 ft 2 in.  The corners of the tower were chamfered 6 ft 11 in.  

Each tower had a core service area of approximately 135 ft by 87 ft.  All elevators were located within the 
core.  Three stairs were also located within the core except at the mechanical floors where the stairs were 
located outside the structural core area (the area enclosed by the four corner columns of the core). For 
detailed descriptions of the stair locations, see Table 2–1, NIST NCSTAR 1-7.  A typical architectural 
floor plan in the tower is shown in Fig. 2–4.  As can be seen in this figure, placing all service systems 
within the core provided nearly a column-free floor space of approximately 31,000 ft

2

 per floor outside 

the core.  The long axis of the core in WTC 1 was oriented in the east-west direction, while the long axis 
of the core in WTC 2 was oriented in the north-south direction.  Design wind forces

 

were different for the 

two towers (the presence of one tower had an effect on the wind pressures on the other tower, see NIST 
NCSTAR 1-2), and that resulted in somewhat different lateral-force resisting system design.  Thus, the 
two towers appear similar, but they were structurally different. 

The exterior walls were composed of steel columns and spandrel beams

.  

Above the 7th floor level, the 

columns were welded steel plate box columns of an approximately 14 in. square section. Each building 
face consisted of 59 columns spaced at 3 ft 4 in. on center.  Adjacent columns were interconnected at each 
floor level by deep spandrel plates, typically 52 in. deep.  As seen in Fig. 2–3, below floor 7, the columns 
are combined in groups of three to form single base columns which are spaced 10 ft on center. The 
external cladding, which covers the columns and spandrel beams, consisted of aluminum sheets.  The 
window openings were infilled with glass fitted into aluminum frames and sealed with neoprene gaskets. 

Fire protection of structural steel members in the WTC towers was provided by fire resistive materials, 
either sprayed fire resistive materials (SFRMs), gypsum wallboards, or a combination of the two, 
depending upon the type of structural members.  All floor trusses and beams were protected with SFRM.  
The columns inside the core were either covered with gypsum wall board or a combination of gypsum 
wall board and SFRM.  For the exterior columns, vermiculite plaster was applied to the side of the 
column facing the interior of the building, whereas SFRM was applied to the other three faces.  No fire 
resistive material was applied to the underside of the metal deck, which was in contact with the concrete 
slab above. For a detailed discussion of the passive fire protection of steel members, see NIST 
NCSTAR 1-6A. 

For typical tenant floors, the ceiling was suspended from the steel trusses.  The space between the ceiling 
and the floor above was used for the mechanical and electrical systems. 

Elevators were the primary mode of routine ingress and egress from the towers for tens of thousands of 
people on a daily basis.  In order to minimize the total floor space needed for elevators, each tower was 
divided into three zones by the skylobbies, which served to distribute passengers among express and local 
elevators (for details, see NIST NCSTAR 1-7). In this way, the local elevators within a zone were placed 
on top of one another within a common shaft.  Figure 2–5 shows the elevator riser diagram for WTC 1 
and WTC 2. People transferred from express elevators to local elevators at the skylobbies which were 
located on the 44th and 78th floors in the both towers. Each tower had 99 elevators within the core of the 
building, including seven freight elevators, most serving a particular zone, and dedicated express 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

9

 

elevators that served the restaurant, bars, and meeting rooms on floors 106 and 107 of WTC 1, as well as 
the observation deck in WTC 2. The concept of multiple elevators in a common shaft was first used in the 
WTC towers and has since become the norm for buildings taller than about 50 stories. This approach 
allowed an increase of useable space in WTC 1 and WTC 2 from 62 percent to 75 percent per floor 
(Sullivan 1964). 

The architectural design was performed by Minoru Yamasaki & Associates, with Emory Roth & 
Sons, P.C. serving as the architect of record.  The structural engineer of record was the firm of Skilling, 
Helle, Christiansen, Robertson (SHCR).  Jaros, Baum & Bollers were the mechanical engineers, and 
Joseph R. Loring & Associates were the electrical engineers.  Tishman Construction Corporation was the 
general contractor.  The foundation of the towers was designed by the Engineering Department of the Port 
of New York Authority (see footnote 6). 

2.2.2 Structural 

Description 

As described above (Sec. 2.2.1), both WTC 1 and WTC 2 were 116 stories above the foundation 
(110 stories above grade and 6 stories below grade).  The buildings were square in plan, 207 ft 2 in. by 
207 ft 2 in. (based on column reference lines), and with story heights of typically 12 ft.  The core area was 
approximately 135 ft by 87 ft in plan. (Approximate dimensions are stated as the dimensions on the 
architectural and structural drawings are given in reference to “column reference lines,” and they do not 
necessarily coincide with the centroid of the column cross section.) 

Each tower was comprised of five structural systems: a framed tube for the exterior walls above grade, 
simple frames (beams and columns with simple connections) for the core, braced frames for the exterior 
walls below grade, composite floor framing, and hat trusses at the roof level.  As a framed-tube system, 
the exterior walls of each tower, comprised of closely spaced columns that were connected by spandrel 
beams around the perimeter at each floor level, were designed to resist all lateral loads.  The resistance to 
lateral load was provided by the caltilever action of the tube.  All columns of a frame-tube building 
experience mainly axial forces.  For a square framed-tube building, the exterior columns on the faces 
normal to the wind direction are either in tension or in compression.  The columns in the windward-side 
wall are in tension, and the columns in the leeward-side wall are in compression. The side walls are 
analogous to the web of a beam, mainly in shearing action.  Thus, the axial forces in columns of the side 
walls vary from the windward side in tension to the leeward side in compression.  Figure 2–6 illustrates 
the axial force distribution in columns.  The figure also shows the shear-lag effect due to the in-plane 
flexibility of the spandrel beams.  The shear lag effect increases the column loads near the corners and 
decreases in the center region of the walls that are perpendicular to the direction of wind.  Analyses of the 
towers under wind loads indicate that the patterns of the axial force distribution in the columns due to 
wind loads are similar to those shown in Fig. 2–6 (NIST NCSTAR 1-2).  Typical cross sections of the 
exterior walls are shown in Fig. 2–7.  As seen in the figure, they were constructed of steel built-up 
columns and spandrel beams comprised of plates.  

Since the lateral loads are resisted mainly by the exterior walls in a framed tube system, the interior core 
columns do not contribute to the over-all lateral stiffness of the building.  For the WTC towers, both the 
exterior columns and the core columns were designed to support an approximately equal amount of the 
total gravity loads (see NIST NCSTAR 1-2).  In the typical WTC tower floor plan, the area inside the 
core was framed with structural steel shapes acting compositely with formed concrete slabs.  Most of the 

background image

Chapter 2 

 

Draft for Public Comment 

10

 

NIST NCSTAR 1-1, WTC Investigation 

 

floor beam members were connected to columns by simple connection.  The columns in the interior core 
of the towers were designed to carry mainly the gravity (vertical) loads, except in the atrium area (below 
floor 7 to the foundation), where there were fewer perimeter columns in the outer walls; bracings were 
used in the outer perimeter of the core area to increase lateral stiffness.  In the lower part of the towers, 
the outer core columns were designed to resist a portion of the lateral forces.  

Exterior Walls 

The exterior wall columns , built-up of steels plates, from the foundation level up to Elevation 363 ft 
(column splice point below floor 7, see Fig. 2–3) were spaced 10 ft on center, and they were connected by 
spandrels.  Between the Concourse Level and the foundation, these columns were braced diagonally to 
form braced frames in the plane of the exterior walls (Fig. 2–3).  Between Elevation 363 ft and floor 7, 
single exterior wall columns spaced 10 ft on center transitioned to three columns spaced 3 ft 4 in. on 
center (Fig. 2–8) to form “tree” assemblies. 

Between floors 9 and 107, the perimeter structure consisted of closely spaced, built-up box columns.  
Each building face consisted of 59 columns. The columns were fabricated by welding plates of steel to 
form an approximately 14 in. square section (Fig. 2–7).  The columns were interconnected at each floor 
level by 52 in. deep spandrel plates to form a 10 ft wide and 36 ft tall panel (Fig. 2–9).  Heavy end, or 
“butt” plates of 1.375 in. to 3 in. thick were welded to the top and bottom of each column.  Fillet welds 
were used inside the columns along three edges, with a groove weld on the fourth, outside edge.  The 
exterior walls were erected by connecting the prefabricated panels.  The panels were field-bolted to 
adjacent panels with dual splice plates (see Fig. 2–7), and columns were bolted to the adjacent columns, 
using ASTM International (ASTM) A 325 bolts except for the heaviest butt plates, where ASTM A 490 
bolts were used.  Other than at the mechanical floors, panels were staggered so that only one third of the 
columns were spliced (i.e., connected) in any one story (Fig. 2–10).  At the mechanical floors, the 
perimeter columns were spliced at the same level (i.e. floors 74 and 77).  These splices were both welded 
and bolted. 

At each corner of the building, the spandrel plate connected the column on one face of the building to the 
column on the other face at each floor level.  The corner spandrel plates between two floors were 
interconnected by a box-shape vertical member.  The vertical members were attached to the corner 
spandrels at alternate stories and thus, they are not continuous from the top of the building to the 
foundation.  The corner vertical members were attached to the building during the construction period to 
aid hoisting of construction material.  

Fourteen grades of steel were specified in the design documents for the perimeter columns, with 
minimum yield strengths of (36, 42, 45, 46, 50, 55, 60, 65, 70, 75, 80, 85, 90, and 100) ksi. Twelve grades 
of steels were actually used (See NIST NCSTAR 1-3).  Twelve grades of steel were specified for the 
spandrels, with the same strength levels as the columns, but without the two highest strength steels.  The 
structural engineering plans indicate that the flanges and webs of a given column section consist of a 
single grade (i.e., minimum yield strength) of steel, but each column and spandrel within a single 
prefabricated panel could be fabricated from different grades of steel.  The use of different grades of steel 
facilitated in maintaining uniform exterior dimensions of the exterior columns throughout the building as 
well as equalize the dead load stresses and shortening of very tall steel columns. 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

11

 

Columns in the upper stories were typically fabricated of thinner steel plates, as thin as 0.25 in., with the 
grade of steel dictated by the calculated gravity and wind loads.  In this manner, the gravity load on the 
lower stories was minimized.  In the lower stories the perimeter column webs were often more than 2 in. 
thick. 

The spandrels formed an integral part of the columns; there was no inner web plate at spandrel locations. 
Spandrels were generally specified with a yield strength lower than that of the column webs and flanges, 
as well as a heavier gauge than the adjacent inner webs. 

Core Columns 

As stated above, the core columns were designed to support approximately 50 percent of the gravity 
loads.  The core columns were of two types: welded box columns and rolled wide flange shapes  
(Fig. 2–11).  The columns in the lower floors were primarily very large box columns, as large as 12 in. 
by 52 in., comprised of welded plates up to 7 in. thick.  In the upper floors, the columns shifted to the 
rolled wide-flange shapes.  The transition floors are indicated in Fig. 2–12 for each of the core columns.  
Core columns were typically spliced at three-story intervals.  Diagonal bracing was used at the 
mechanical floors and in the area of the hat truss.  Steel used for core box columns was either 36 ksi or 
42 ksi.  Core wide flange columns were specified to be one of four grades, but were primarily 36 ksi and 
42 ksi steel; only about 1 percent of all the core columns were made of 45 ksi or 50 ksi steel.  

Foundation 

For the core columns, a column base plate distributed the column load to a steel grillage comprised of 
two-layers of steel beams.  The steel grillage, in turn, distributed the column load to the reinforced 
concrete spread footings, which were directly in contact with the bedrock.  

For the exterior columns, a large steel base plate, ranging from 7 to 9 ft

2

, was used to transfer the 

individual column load to the reinforced concrete wall footing.  The wall footing was placed around the 
perimeter of the tower.  The concrete footing was in direct contact with the bedrock. 

Floor Framing System 

The floor system of a framed-tube structure is designed for four main functions.  First, it supports the 
vertical gravity loads on the floor and transfers these loads to the external and core columns.  Second, as a 
diaphragm it distributes wind loads to the side walls of the framed tube structure. Third, it, together with 
the external frame, provides the stiffness to resist torsional motion of the building.  Fourth, it provides 
lateral support to the columns, thereby, keeping the columns stable.  The effectiveness of the framed-tube 
action is dependent on the inplane stiffness of the floor framing system.  If the floor inplane stiffness is 
low (flexible diaphragm), the framed tube action cannot be developed effectively, and the structure 
behaves like a moment-resisting frame.  On the other hand, if the inplane floor stiffness is high (rigid 
diaphragm), wind loads are distributed to the columns in the side frames, and the structure behaves like a 
framed tube.  For WTC 1 and WTC 2, the floor system was comprised of concrete-steel composite 
members as described below. A typical trussed-framed floor framing is shown in Fig. 2–13.  Analyses of 
the inplane stiffness showed that the typical floor system of WTC towers behaved as a stiff diaphragm 

background image

Chapter 2 

 

Draft for Public Comment 

12

 

NIST NCSTAR 1-1, WTC Investigation 

 

(see NIST NCSTAR 1-2A), and the WTC towers behaved more like a framed tube than a moment-
resisting frame. 

The floor inside the core and the mechanical floors were framed with structural steel shapes with welded 
shear studs, acting compositely with normal-weight concrete slabs.  The thickness of concrete slab in 
these floors varied from 4.5 in. to 8 in. depending upon the design load requirements. The area outside the 
core (typically tenant floors) was framed with steel trusses, acting compositely with 4 in. thick 
lightweight concrete slabs cast on 1½ in., 22 gauge fluted metal deck.  The trusses consisted of double 
angle top and bottom chords with round bar webs.  The composite action was achieved by the shear 
connection provided by the web bar extending above the top chord and into the slab in the form of a 
“knuckle” (see Fig. 2–14).  Pared trusses, spaced at 6 ft 8 in. on center, were supported at every other 
exterior column.  The metal deck which spanned parallel to the main trusses was directly supported by 
transverse bridging trusses spaced at 13 ft 4 in. and intermediate deck support angles spaced at 6 ft 8 in. 
from the transverse bridging trusses. The typical floor consisted of three truss zones; a long-span zone, a 
short-span zone, and a two-way zone (see Fig. 2–15).  The span of the trusses was about 35 ft in the short-
span zone and 60 ft in the long-span zone.   

The floor trusses were pre-assembled into floor panels.  The prefabricated floor panels were typically 
20 ft wide, containing two sets of double trusses in the interior and a single truss along each edge.  In 
addition, the bottom chord of each pair of trusses was attached to perimeter spandrels with viscoelastic 
dampers (see Fig. 2–16). The main purpose of these dampers was to supplement the steel frame in 
limiting wind-induced building oscillations.  

Pairs of flat bars (straps) extended diagonally from the top chord of the floor trusses to the perimeter 
columns (see Fig. 2–13).  Once in place, 4 in. of lightweight concrete was placed on the steel deck.  
Figure 2–17 shows an assembled floor panel before the concrete was placed. 

The minimum yield strengths of the steel for the design of the floor trusses were specified to be 36 ksi and 
50 ksi for different parts of the trusses.  According to the fabrication drawings prepared by Laclede Steel 
Company, both 36 ksi and 50 ksi steels were specified.  

Hat Trusses 

At the top of each tower (floor 107 to the roof), an assembly of hat trusses interconnected the core 
columns and the exterior wall panels (see Fig. 2–18).  Diagonals of the hat truss were typically W12 or 
W14 wide flange members.  In addition, four diagonal braces (18 in. by 26 in. box beams spanning the 
35 ft gap, and 18 in. by 30 in. box beams spanning the 60 ft gap) and four horizontal floor beams 
connected the hat truss to each perimeter wall at the floor 108 spandrel.  The hat truss was designed 
primarily to provide a base for antennae atop both towers, although only the WTC 1 antenna was actually 
built. The hat truss also controlled the expansion and contraction of the tower due to unequal column 
temperatures, although not specifically designed for this purpose. 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

13

 

2.3 

DESCRIPTION OF WTC 7 

2.3.1 Building 

Description 

WTC 7 was a 47-story commercial office building, completed in 1987.  Its location relative to the WTC 
Plaza is shown in Fig. 2–1.  It contained approximately 2 million ft

2

 of floor area.  A typical floor plan 

above floor 7 is shown in Fig. 2–19.  WTC 7 was connected to the WTC complex with a 120 ft wide 
elevated plaza at floor 3, and a 22 ft wide pedestrian bridge, also at floor 3. 

The overall dimensions of WTC 7 were approximately 330 ft long, 140 ft wide, and 610 ft high.  The 
building was constructed over a pre-existing electrical substation owned by Consolidated Edison 
(Con Edison).  The original plans for the Con Ed Substation included supporting a high-rise building, and 
the foundation was sized for the planned structure.  However, the final design for WTC 7 had a larger 
footprint than originally planned.  The building elevations are shown in Fig. 2–20. Over the years, 
numerous structural modifications were made throughout the building, mainly to suit its largest tenant, 
Salomon Brothers Inc. (later to become Salomon Smith Barney, now CitiGroup), who leased 25 of the 
47 floors.  One of the more substantial modifications was the addition of a penthouse that was used to 
house the chiller plant and the cooling towers for Salomon Brothers.  Also, large portions of the 41st and 
43rd floor slabs and the floor framing were removed on the east side of the building to accommodate 
trading floors for Salomon Brothers.  The removed floor areas were subsequently restored after the 
trading activity was moved to another venue.  

Above floor 7, the building had typical steel framing for high-rise construction.  The floor systems had 
composite construction with steel beams supporting concrete slabs on metal decks, with a floor thickness 
of 5.5 in.  The core and perimeter columns supported the floor system and carried their loads to the 
foundation.  The perimeter moment frame also resisted wind forces.  Columns above floor 7 did not align 
with the foundation columns, so braced frames, transfer trusses, and transfer girders were used to transfer 
loads between these column systems, primarily between floors 5 and 7.  Floors 5 and 7 were heavily 
reinforced concrete slabs on metal decks, with thicknesses of 14 in. and 8 in., respectively. 

The architectural design was performed by Emory Roth & Sons, P.C.  The structural engineer of record 
was the Office of Irwin G. Cantor, P.C. Syska & Hennessy, P.C. was the mechanical engineer.  Tishman 
Construction Corporation was the general contractor. 

Consolidated Edison Substation 

The Con Edison Substation was constructed in 1967 and consisted of a steel framed structure with cast-
in-place concrete floors and walls.  It was placed on the northern portion of the site and extended 
approximately 40 ft north of the north facade of WTC 7, as shown in Fig. 2–21.  Its southern boundary 
was irregular, but extended approximately one-third to two-thirds of the width of WTC 7.  The 
Con Edison Substation was three stories high. 

The substation’s lateral system consisted of a moment frame along the northern row of interior columns. 
Along the south edge of the substation there was a braced frame.  This braced frame was coincident with 
the north side of the WTC 7 core.  Lateral loads from WTC 7 were passed directly from the core above to 
the Con Edison braced frame below.  There were also two moment frames within the substation, oriented 
in the north-south direction, one on each end of the WTC 7 core. 

background image

Chapter 2 

 

Draft for Public Comment 

14

 

NIST NCSTAR 1-1, WTC Investigation 

 

The WTC 7 columns

,

 which were within the perimeter of the substation

,

 were supported by substation 

columns.  During the construction

 

of WTC 7, heavy plates were welded to the tops of the existing 

substation columns, which then supported the new building columns. 

The exterior columns above the Con Edison structure that did not align with the columns of the Con 
Edison structure were supported by a series of transfer girders.  The arrangements of the transfer girders 
are described in detail in Sec. 2.3.2 

2.3.2 Structural 

Description 

Typical Floor Systems above Floor 7

9

 

The typical floor framing system, shown in Fig. 2–22, was composed of rolled steel wide-flange beams 
with composite metal decking and concrete slabs.  Floors 8 through 45 had essentially the same framing 
plan, but the core layout varied over the height of the building.   

Floors 8 through 45 had floor slabs with a total thickness of 5.5 in. that were composed of 3 in., 20 gauge 
metal deck with 2.5 in., normal weight concrete of 3,500 psi.  There was one layer of 6x6 W1.4xW1.4 
welded wire fabric within the concrete.  The structural design drawings show a second layer of welded 
wire fabric placed over girders at the slab edges.  The fastening requirements for the metal deck are not 
shown on the drawings.  The drawings contain a note calling for 1.5 in., 20 gauge deck with 4 in. concrete 
topping (5.5 in. total) in the elevator lobbies, where there was a 3 in. floor finish specified by the 
architect. 

Typical floor framing for floors 8 through 20 and floors 24 through 45 consisted of 50 ksi wide-flange 
beams and girders.  A grid of beams and girders spanned between the core columns.  Core girders ranged 
in size from W16x31 to W36x135, depending on the span and load.  (W16x31 describes a steel wide-
flange beam, sometimes referred to as an ‘I’ beam; the nomenclature indicates the cross section is 
nominally 16 in. deep and weighs 31 lb per lineal foot.)  Beams spanned directly between the core and the 
exterior of the building, at approximately 9 ft on center.  On the north and east sides, the typical beam was 
a W24x55 with 28 shear studs, spanning 53 ft.  On the south side, the typical beam was a W16x26 with 
24 shear studs spanning 36 ft.  Between the exterior columns were moment connected girders that formed 
part of the lateral-load-resisting system of the building.  On floors 10, 19, and 20, a portion of the floor 
framing was reinforced with plates attached to the bottom flange.  Certain connections at these floors 
were also reinforced. 

Floors 21 to 23 had slightly heavier steel framing than the typical floors.  Core girders were generally one 
size class larger than the typical floor; the beams between the core and the south facade were W16x31 
instead of W16x26.  There were additional studs on the W24x55 beams on the north and west sides. 

Most of the beams and girders were made composite with the slabs through the use of shear studs.  
Typically, the shear studs were 0.75 in. in diameter by 5 in. long, spaced 1 ft to 2 ft on center.  

                                                      

9

  Structural descriptions are determined from the design drawings. 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

15

 

Floor Framing of Other Floors 

The remaining floors, floors 1 to 7 and floors 46 to 47, were atypical.  Floor 1 was built adjacent to the 
Con Edison substation and included the truck ramp for the WTC complex (see Fig. 2–21).  The floor was 
framed with steel beams that were encased in a formed concrete slab.  The floor slab was 14 in.  The 
southeast portion of the floor above the WTC truck ramp had a 6 in. formed concrete slab.  The floor 
slabs for floors 2, 3, 4, and 6 had a 3 in., 20 gauge metal deck with 3 in. normal weight concrete, for a 
total thickness of 6 in.  Floors 2 and 3 were also partial floors adjacent to the substation.  In addition, they 
had a floor opening on the south side to form the atrium above the ground level lobby.  Floor 4 was above 
the substation and had a large opening over most of the south side of the building to form a double-height 
space above the 3rd floor lobby.  Floor 5 had an 11 in. thick slab of normal weight concrete on top of 
3 in., 18 gauge steel deck for a total slab thickness of 14 in.  The slab was heavily reinforced with #7 
reinforcing bars spaced at 12 in. on center in both directions on top and #9 reinforcing bars spaced at 
12 in. on center on bottom.  This floor also had steel WT sections embedded in the 11 in. concrete slab 
above the steel deck.  The WT sections were designed to act as a horizontal truss within the plane of the 
floor between the perimeter and core columns (see Fig. 2–23).  Floor 6 had two openings on the floor to 
form a double-height mechanical space, one at the east side and the other at the southeast corner.  Floor 7 
had 5 in. normal weight concrete on top of 3 in., 18 gauge metal deck, which made a total thickness of 
8 in.  The slab was reinforced with #5 reinforcing bars spaced at 6 in. on center in both directions. 

Columns 

Core columns were primarily rolled wide-flange shapes of grade 36 or 50 steel.  As the loads increased 
toward the base of the building, many of these column sizes were increased through the use of built-up 
shapes.  These built-up columns had a W14x730 core with cover plates welded to the flanges (to form a 
box) or web plates welded between the flanges as shown in Fig. 2–24.  The reinforcing plate welds were 
specified to be continuous 0.5 in. fillet welds at the cover plates and 0.313 in. minimum at the web plates.  
Plate thickness ranged from 1.5 in to 8 in.  Steel used for reinforcing plates were specified as follows:  

Plate thickness t (in.): 

2 < t < 4  

ASTM A 588 Grade 50 

4 < t < 6  

ASTM A 572 Grade 42 

t > 6  

 

ASTM A 588 Grade 42 

Typical core column splices were specified to be milled.  The splice plates were welded or bolted to the 
outsides of the column web and flanges.  Built-up columns were also milled at their bearing ends, but the 
splice plates were fillet welded to the cover plates. 

Perimeter columns were nominally 14 in. wide-flange shapes (W14) of ASTM A 36 steel.  Perimeter 
column splices were similar to the core column splices. 

Column Transfer Trusses and Girders 

Because the layout of the substructure and Con Edison columns did not align with the column layout in 
the upper portion of WTC 7, a series of column transfers were constructed.  These transfers occurred 

background image

Chapter 2 

 

Draft for Public Comment 

16

 

NIST NCSTAR 1-1, WTC Investigation 

 

primarily between floors 5 and 7.  See Fig. 2–25 for a schematic rendering of the transfer trusses and 
girders. 

Columns 47 through 54, at the north facade, were transferred at floor 7 by cantilever girders to bring them 
in line with the substation columns, offset 6 ft to 9 ft to the south.  The back-span of these cantilevers was 
supported by the north side core columns.  The eastern most cantilever girder was connected to truss #1, 
and the western most cantilever girder was connected to truss #3. 

Column 76 was supported at floor 7 by truss #1.  The west side of truss #1 was supported by column 73, 
while the east side was supported by a transfer girder running north-south which was, in turn, supported 
by columns E3 and E4 at floor 5. 

Columns 58, 59, and 78 were transferred by simply supported girders at floor 7.  Column 78 was 
supported at floor 7 by a transfer girder that was supported at its north end by truss #2.  Column 77 was 
also supported by truss #2.  Truss #2 was supported by column 74 at its west end and by column 80 at its 
east end. 

Column 61 was supported by truss #3.  Truss #3 runs north-south and was supported by columns 62 and 
61A.  Truss #3 has a 10 ft cantilever span between column 61 and column 61A and an 18 ft back-span to 
column 62. 

 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

17

 

 

Figure 2–1.  WTC site plan. 

 

background image

Chapter 2 

 

Draft for Public Comment 

18

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Figure 2–2.  West elevation of WTC 1. 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

19

 

 

Figure 2–3.  Elevation of exterior wall from foundation to floor 9. 

background image

Chapter 2 

 

Draft for Public Comment 

20

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Figure 2–4.  Typical WTC tower architectural floor plan. 

 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

21

 

 

Figure 2–5.  Arrangement of express and local elevators. 

 

 

 

 

background image

Chapter 2 

 

Draft for Public Comment 

22

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Source:

 Robertson and See 1987. 

Figure 2–6.  Framed tube system. 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

23

 

 

Figure 2–7.  Cross section of perimeter columns. 

background image

Chapter 2 

 

Draft for Public Comment 

24

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

 

Figure 2–8.  Typical WTC tower exterior wall tree panel. 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

25

 

 

 

Figure 2–9.  Typical WTC tower exterior wall panel. 

background image

Chapter 2 

 

Draft for Public Comment 

26

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Figure 2–10.  Elevation of exterior wall frame illustrating 

staggered panel construction. 

 

Figure 2–11.  Typical welded box members and rolled shapes 

between floor 83 and floor 86. 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

27

 

 

Figure 2–12.  Core column layout in WTC towers. 

background image

Chapter 2 

 

Draft for Public Comment 

28

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Figure 2–13.  Typical floor-framing plan. 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

29

 

 

 

 

Source:

 PONYA 1967. 

Figure 2–14.  Prefabricated floor panel used in WTC 1 and WTC 2. 

background image

Chapter 2 

 

Draft for Public Comment 

30

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Figure 2–15.  Typical WTC floor truss framing zone. 

 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

31

 

 

 

Figure 2–16.  Position of viscoelastic damper. 

background image

Chapter 2 

 

Draft for Public Comment 

32

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Source:

 Unknown. 

Figure 2–17.  Perimeter column wall panel and steel truss floor modules. 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

33

 

 

Figure 2–18.  Hat truss. 

 

Figure 2–19.  Typical floor plan above floor 7. 

background image

Chapter 2 

 

Draft for Public Comment 

34

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Figure 2–20.  Perimeter elevations of WTC 7. 

 

Figure 2–21.  Floor 1 plan of WTC 7. 

 

background image

Draft for Public Comment 

 

Description of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

35

 

 

Figure 2–22.  Framing plan for floor 8 through floor 45. 

 

Figure 2–23.  Floor 5 diaphragm plan. 

background image

Chapter 2 

 

Draft for Public Comment 

36

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Figure 2–24.  Typical built-up column details. 

 

Figure 2–25.  Schematic view of transfer trusses and girders between floors 5 and 7. 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

37

 

Chapter 3 

D

EVELOPMENT OF 

B

UILDING 

C

ODES

 

Since World Trade Center (WTC) 1, 2, and 7 were designed according to the New York City (NYC) 
Building Code, it is important to understand the evolution of this building code.  This chapter presents the 
historical background of the development of the NYC Building Code.  This chapter also summarizes the 
Port Authority policies for design and construction of its buildings.  

3.1 

BUILDING CODE DEVELOPMENT IN THE UNITED STATES 

In the United States, building codes were introduced to minimize losses from fire. Following large fires in 
major cities such as Boston, New York, Chicago, and Baltimore in the late 1800s, the first model building 
code was developed by the fire insurance industry. The National Board of Fire Underwriters (predecessor 
of the American Insurance Association) published the 

National Building Code

 in 1905. Subsequently, the 

Pacific Coast Building Officials Conference (predecessor of the International Conference of Building 
Officials) issued the 

Uniform Building Code

 (UBC) in 1927, the Southern Building Code Congress 

International Inc. (SBCCI) published its 

Southern Standard Building Code

 in 1946, and the Building 

Officials and Code Administrators, Inc. (BOCA) published the 

Basic Building Code

 in 1950. In the mid-

1980s, the Basic Building Code was changed to the 

BOCA National Building Code 

(NBC). The three 

model building codes, namely the BOCA National Building Code, the Southern Standard Building Code, 
and the Uniform Building Code, were revised annually to incorporate developments in new materials, 
construction methods, and practices, and new editions were published every three years. 

Before the issuance of the 

International Building Code

 (IBC) in 2000, which was published by the 

International Code Council (an amalgamation of the three model code organizations), most local and state 
building codes in the United States were patterned after one of the three model building codes.  The 
model codes were sometimes adopted by these jurisdictions in their entirety and other times with 
significant modifications.  The version adopted is law in that jurisdiction.  In early 1900s the National 
Fire Protection Association (NFPA) initiated the development of a “life safety code” for safety of 
building occupants.  This code, while not a building code, is frequently used as a supplement to the 
building codes.  In 2002, NFPA also published a model building code known as the 

NFPA Building 

Construction and Safety Code

 (NFPA 5000).  A number of major cities in the United States have 

developed their own building codes to meet their specific needs, such as San Francisco for earthquake 
resistant design and New York City for high-rise buildings.  At the present time, 44 states have adopted 
IBC with some modifications

,

10

 and it is being considered for adoption by New York City. 

These model building codes establish minimum requirements to safeguard life, health, property, and 
public welfare through provisions pertaining to the design, construction, and quality of materials, use and 
occupancy, and maintenance of buildings. When buildings are designed, constructed, and maintained 
according to building code requirements, they are considered to have met minimum requirements. While 

                                                      

10

 The International Code Council updates the number of local jurisdictions that have adopted IBC (www.iccsafe.org). 

background image

Chapter 3 

 

Draft for Public Comment 

38

 

NIST NCSTAR 1-1, WTC Investigation 

 

building code regulations address a number of objectives demanded by society, the primary objectives of 
building codes are structural stability and fire safety. 

3.2 

NEW YORK CITY BUILDING CODE 

The New York City (NYC) Building Code is part of the Administrative Code of New York City.

11

  

Although New York City had laws governing construction as early as 1674, after a tenement fire in 1860 
took 20 lives, New York City modified and strengthened building safety laws extensively.  New York 
City building laws are amended from time to time by Local Laws to improve safety requirements or to 
incorporate technological advances.  

Local Laws are enacted by the NYC Council.  Any member can introduce a bill to the Council for the 
purpose of amending the Building Code requirements.  When passed by the Council and approved by the 
Mayor, the bill becomes a Local Law.  The current Building Code was enacted on December 6, 1968.  
Through 2002, 79 Local Laws were adopted that modified the 1968 Building Code.  

To aid the implementation of and to clarify Building Code requirements, New York City issues “rules.” 
Typically these rules are initiated by City Government offices such as the Department of Buildings and 
the Department of Environment, and issued by the Building Commissioner.  The rules do not require 
enactment by the City Council, and new rules issued by the Building Commissioner can be put into effect 
expeditiously.  The rules, although are not part of the Building code, are required to be complied with for 
design, construction, and maintenance of buildings. 

The 1968 NYC Building Code includes “Reference Standards,” including standard test methods 
published by the American Society for Testing and Materials (ASTM), and design standards published by 
other organizations such as the American Concrete Institute and the American Institute of Steel 
Construction.  These reference standards may include modifications to the provisions in the published 
standards, or they may be stand-alone requirements developed by New York City. 

At the time the WTC project was begun (early 1960s), the 1938 NYC Building Code, which was first 
adopted on January 1, 1938, was in effect and enforced throughout the five boroughs.  In the late 1950s, it 
was noted that “great changes have occurred in all facets of the building industry” and that “As a result of 
these developments, and the failure in many instances, of the Code to keep pace, there had been a 
growing dissatisfaction with it” (Schaffner 1964).  Thus, in 1960, the Building Commissioner requested 
the New York Building Congress to form a working committee to study the problem.  The committee 
recommended that the Code should not be rewritten by a group of volunteers and that a local educational 
institution should conduct a study to develop an approach to solve the problem.  The Polytechnic Institute 
of Brooklyn conducted the study, and in July 1961, the Institute made the following recommendations 
(Schaffner 1964): 

1.

 

The NYC Building Code should be completely rewritten.  The new Code should provide for 
frequent periodic revision through a committee or board appointed solely for this purpose. 

                                                      

11

 The historical information about the development the New York City Building Code may be found at the New York City/the 

Buildings Department web site (www.nyc.gov). 

background image

Draft for Public Comment 

 

Development of Building Codes 

NIST NCSTAR 1-1, WTC Investigation 

39

 

2.

 

The new Code should be a combination of performance and specification types with heavy 
emphasis on performance, wherever possible, and with liberal reference to accepted national 
standards. 

3.

 

The BOCA Basic Building Code should be used as a guide for the development of the NYC 
Building Code. 

4.

 

The Code should be rewritten by a private professional group such as an engineering 
company, architectural firm, educational institution, or any combination of the three. Those 
rewriting the Code should work closely with the NYC Building Department.  They should be 
supported, for review purposes, by volunteer committees composed of representatives of 
professional, trade, and industry associations. 

In April 1962, New York City signed an agreement with the Polytechnic Institute of Brooklyn for the 
writing of a new Code to be completed in 3 years.  The first draft was completed in 1964.  A public 
relations document highlighted the “major advantages to be gained from recommendations in the 
proposed new Building Code” (Bell and Stanton 1964).  One of these related to “area and height 
limitations,” and it was stated that: 

Area and height limitations will be liberalized and present unrealistically 
high construction requirements for fire protection in structures of low 
combustible content such as auditoriums, halls, schools, institutions and 
residences will be significantly reduced and considerable economy will 
result. 

On December 6, 1968, Local Law 76 repealed the 1938 code and replaced it with the 1968 Code, which 
itself has been subsequently amended by Local Laws.  As is the general custom with changes to building 
codes, the new provisions generally are not applied to existing buildings (those approved under the prior 
code) provided they do not represent a danger to public safety and welfare. 

Between 1969 and 2002, there were 79 Local Laws adopted that modified the 1968 code.  Of particular 
importance with regard to fire protection and life safety are Local Law 5, adopted in 1973, and Local 
Law 16, adopted in 1984 (see NIST NCSTAR 1-1D).  Local Law 5, among other things, added 
requirements on compartmentation of large floor areas, and Local Law 16 added requirements for 
sprinklers in high-rise buildings (greater than 100 ft).  Local Law 5 is particularly significant because its 
provisions, which are reviewed in Sec. 11.1, applied retroactively to existing office buildings taller than 
100 ft in height.  Local Law 84, which was passed in 1979, revised the compliance dates of Local Law 5 
so that full compliance was required by February 7, 1988. 

background image

Chapter 3 

 

Draft for Public Comment 

40

 

NIST NCSTAR 1-1, WTC Investigation 

 

3.3 

PORT AUTHORITY POLICIES FOR DESIGN AND MODIFICATIONS TO 
BUILDINGS 

3.3.1 

Procedures for PANYNJ Owned Projects 

Established in 1921, the Port of New York Authority (PONYA)

12

 was a self-supporting, public interstate 

agency and is not subject to the local laws of jurisdictions where its properties are constructed.  This 
means that for the construction of the WTC buildings, the PONYA was not bound by the NYC Building 
Code or any regulations requiring inspection or approval of the building construction or operation. The 
PONYA could establish its own requirements, conduct its own inspections, and enforce its own rules 
without independent oversight. 

The PONYA established an office to act as the Authority Having Jurisdiction for their facilities generally, 
and there was a special office for the towers.  The PONYA staff reviewed and approved plans, monitored 
construction, and developed specifications.  They developed a series of manuals that described the 
building infrastructure (sprinkler systems, fire alarm systems, smoke control systems) and how tenants 
would interface systems in their space to the building. Large tenants were generally permitted to contract 
for their own systems as long as they were compatible and complied with the manuals. Smaller tenants 
could use the PONYA office for this purpose. In either case approvals and inspections were performed by 
the PONYA and did not involve the City services (Department of Buildings or Fire Department). 

To reaffirm and formally state the Port Authority’s “long standing policy” that its facilities meet or 
exceed New York Building Code requirements, a memorandum of understanding between the Port 
Authority and the New York City Department of Buildings was established in 1993.

13

  Specific 

commitments were made by the Port Authority to the Department of that would ensure that any building 
construction project undertaken by the Port Authority or by any of its tenants at the buildings owned and 
operated by the Port Authority that were located within the Department of Buildings’ jurisdiction conform 
to the NYC Building Code. 

A summary of the 1993 agreement follows: 

 

The Port Authority was to thoroughly review and examine all plans for conformance with the 
requirements of the then current NYC Building Code. Such reviews were to be conducted by 
New York State licensed professional engineers or architects retained or employed by the Port 
Authority. Plans for projects undertaken by Port Authority tenants were to be prepared and 
sealed by a New York State licensed professional engineer or architect retained or employed 
by the tenant. Similarly, for projects undertaken by the Port Authority, plans were to be 
prepared and sealed by a New York State licensed professional engineer or architect retained 
or employed by the Port Authority. 

 

The Port Authority was to maintain a file containing the most recent drawings, plans, and 
other documents required in connection with the review of the project for code conformance. 

                                                      

12

 In 1972, PONYA’s name was changed to the Port Authority of New York and New Jersey (PANYNJ). 

13

 Memorandum of Understanding between the New York City Department of Buildings and PANYNJ, 1993 (WTCI-160-P, see 

Appendix A). 

background image

Draft for Public Comment 

 

Development of Building Codes 

NIST NCSTAR 1-1, WTC Investigation 

41

 

 

The Port Authority was required to obtain the certification of a New York State licensed 
professional engineer or architect that any tenant projects undertaken at any of its facilities 
was constructed in accordance with the approved plans and specifications for the project. Such 
certification was to be kept in the project file described in item 2 above. 

 

The Port Authority was required to provide copies of any project files to the Department of 
Buildings at any time. 

 

The Port Authority was to promptly advise the Department of Buildings of any variances from 
code requirements that were proposed on a project. In cases where the Department of 
Buildings believed that such variances were unacceptable, further review by the Port 
Authority Board of Commissioners was required. 

 

The Port Authority was required to perform building inspections and structural integrity 
inspections on a cyclical basis for all of its structures located in New York City. 

 

The Port Authority was responsible for life safety in buildings at its facilities. The Department 
of Buildings was not responsible for any type of inspection or review. 

 

Personnel from the Port Authority and the Department of Buildings were not to be held 
personally responsible under any provision of this agreement. 

A supplement to the 1993 agreement was executed in 1995.

14

  The supplement added that the design 

professional responsible for performing the review and certification of plans for WTC tenants must not be 
the same design professional providing certification that the project had been constructed in accordance 
with the plans and specifications. But the plans were to be approved by the Port Authority and held for 
possible inspection by the City if the Port Authority so chose. 

3.3.2 

Review of Tower Plans by New York City Department of Buildings 

While the Port Authority facilities, including the WTC buildings, were not required to undergo review or 
approval by the NYC Department of Buildings, a letter dated February 18, 1975, from Joseph Solomon of 
Emory Roth & Sons (the code architect for the towers) to Malcolm Levy, General Manager, World Trade 
Center Operations states, “The Building Department reviewed the tower drawings in 1968 and made six 
comments concerning the plans in relation to the old code.  Specific answers noting how the drawings 
conformed to the new code with regard to these points were submitted to the Port Authority on March 21, 
1968.” 

NIST has attempted to locate the March 21, 1968, letter without success.  NIST hoped to gain information 
about the six points and the level of review provided by the NYC Department of Buildings because they 
were under no obligation to conduct any review.  However, NIST located a letter dated January 25, 1968, 
from Mr. Solomon to Mr. Levy that appears to list the six items questioned in the NYC Department of 
Buildings’ review (note that the letter states five points and contains five numbered paragraphs, which are 

                                                      

14

 Supplement to Memorandum of Understanding between the New York City Department of Buildings and PANYNJ (1995) 

(WTCI-113-P; see Appendix A). 

background image

Chapter 3 

 

Draft for Public Comment 

42

 

NIST NCSTAR 1-1, WTC Investigation 

 

followed by an additional point in an unnumbered paragraph).

15

  The copy of this letter provided by 

PANYNJ is illegible.  Both the original and the NIST reconstructed copies are shown in Appendix B. 

It is interesting to note that all six points raised deal with egress issues.  They do not address innovative 
features of the building, and egress from Windows on the World is not mentioned even though the 
restaurant was a part of the design from the beginning. 

3.3.3 

Procedures for Tenant Alteration Projects 

To maintain structural integrity and fire safety, the Port Authority developed a tenant alteration process 
for any modifications to leased spaces in WTC 1 and WTC 2 for tenants who would adapt their spaces to 
their own needs.  In 1971, shortly after the first tenants occupied WTC 1 in December 1970 and before 
initial occupancy of WTC 2 in 1972, the Port Authority issued the first edition of a set of requirements the 

Tenant Construction Review Manual

.  The manual contained the technical criteria to be used in planning 

alterations (architectural, structural, mechanical, electrical, fire protection, and others).  Applicable 
standards to be used by tenants and their agents and review criteria to be used by the Engineering 
Department of the Port Authority were included.  Registered design professionals were to complete 
alteration design, and at the completion of the work, as-built drawings were to be submitted to the Port 
Authority.  The manual referenced the 1968 NYC Building Code, and specific code provisions were 
referenced in various checklists.  The review manual was updated in 1979, 1984, 1990, and 1997, at 
which times changes that had been made to the NYC Building Code were incorporated. In 1998, the 
manual was replaced by the 

Architectural and Structural Design Guidelines, Specifications, and Standard 

Details

, which dealt specifically with alterations to WTC 1 and WTC 2. 

Since WTC 7 was built as a “tenant alteration project,” its design and construction followed the 
requirements of the 1984 edition of the 

Tenant Construction Review Manual

. Any modifications to the 

building after initial occupancy were carried out in accordance with the Manual. 

 

                                                      

15

 Letter dated January 25, 1968 from Joseph H. Solomon (Emery Roth & Son) to Malcolm P. Levy (General Manager, 

World Trade Center Operations) (see Appendix B). 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

43

 

Chapter 4 

C

ODE 

P

ROVISIONS FOR 

S

TRUCTURAL 

D

ESIGN

 

This chapter presents a summary of the provisions for structural design in the 1968 edition of the New 
York City (NYC) Building Code, and comparison of structural provisions of this code with similar 
provisions of other contemporaneous codes.  As previously noted in Chapter 1, the design of the World 
Trade Center (WTC) towers was based on the 1968 Code, and so was the design for WTC 7.  The 
contemporaneous codes compared include the 1964 New York State Building Construction Code 
(NYSBC 1964), the 1965 Building Officials and Code Administrators (BOCA) model building code 
(Basic Building Code [BBC]), and the 1967 Municipal Code of Chicago (MCC 1967).  A comparison 
was also made between the 1968 NYC Building Code and the current (2001) NYC Building Code.  The 
current NYC Building Code (NYCBC 2001) consists of the code adopted in 1968 with modifications 
made over the years by adoption of Local Laws. 

This chapter also provides a summary of the criteria used for the design of WTC 1, 2, and 7.  Only those 
provisions that relate to the design of WTC 1, 2, and 7 are discussed here.  Unless otherwise noted, 
referenced article and section numbers are from the 1968 edition of the NYC Building Code. 

4.1 CONTEMPORANEOUS 

CODES 

 

Three contemporaneous codes were selected for code comparison.  The 1964 New York State Building 
Construction Code was selected, as it would have been a governing building code outside the New York 
City limits.  The 1965 BOCA Basic Building Code was selected as it was typically adopted by local 
jurisdictions in the northeastern region of the United States.  The 1968 NYC Building Code is compared 
with the 1967 Municipal Code of Chicago to note any substantial differences in the structural and fire 
safety requirements of the two codes.  In the late 1960s and early 1970s, several tall buildings were built 
in Chicago including the Sears Tower (110 stories) and the John Hancock Tower (100 stories).  In 
addition, the 2001 edition of the NYC Building Code is compared with the 1968 version to examine the 
extent to which Local Laws have modified the code provisions, and in most cases, is only addressed in 
areas where changes have occurred between the two versions.  

A provision by provision comparison was made between the 1968 NYC Building Code and these four 
codes and documented in NIST NCSTAR 1-1B, 

Comparison of Building Regulatory and Code 

Requirements for WTC 1, 2 and 7

.  The only code provisions compared were the requirements related to 

structural stability.  This chapter presents a summary of substantial differences noted in the comparison.  
This summary focuses on the following topics: 

 

Loads to be considered in the design of buildings. 

 

Requirements for materials, design, and construction. 

With respect to structural stability, no Local Law other than Local Law 17 (seismic provisions for new 
construction) has been adopted that modified the structural requirements of the 1968 NYC Building Code. 

background image

Chapter 4 

 

Draft for Public Comment 

44

 

NIST NCSTAR 1-1, WTC Investigation 

 

Hence, comparison between the structural requirements of the 1968 and 2001 NYC Building Code is not 
discussed here, with the exception of earthquake loads. 

4.2 LOADS 

A key aspect of any structural design is the loading that the structure is intended to support. Building 
codes provide minimum values for the different types of loads that are considered in typical building 
designs.  The designer is permitted to use larger values for these loads but is not permitted to use smaller 
values without approval by the building official.  This section compares the specified loads in the selected 
codes. Similarities and differences are noted. 

4.2.1 Dead 

Loads 

Dead loads refer to loads that are permanently present in a building.  They include, for example, the 
weight of the structural components, the weights of permanent partitions, the weights of floor and wall 
finishes, and the weights of service equipment that is part of the building (elevator equipment, plumbing, 
electrical, heating, air conditioning, and ventilation systems).  Weights of the structural components are 
computed from the sizes of the members and the densities of the materials, and codes typically provide 
default density values for different materials.  The dead loads of partitions and walls are typically 
prescribed in terms of weight per unit area of wall, and the weight per unit length of wall or partition is 
determined from these prescribed values and the heights of the partitions or walls.  Floor finishes and 
ceilings are typically specified in terms of a uniform load per unit area of floor or ceiling.  Table 4–1 
gives examples of the minimum values of dead load prescribed in Reference Standard RS 9-1 in the 1968 
New York City (NYC) Building Code and in Appendix J of the 1965 BOCA Basic Building Code.  There 
are no corresponding provisions in the 1964 New York State Building Construction Code or the 
1967 Municipal Code of Chicago.  All building codes permit the designer to use weights based on 
available data that are greater than the specified minimum values in the code, but the designer is not 
permitted to use lower values without approval of the Code Official. 

According to the 1968 NYC Building Code, weights from service equipment (plumbing stacks, piping, 
heating, ventilating, and air conditioning [HVAC], etc.) are to be included in the dead load (C26-901.2).

16

  

The weight of equipment that is part of the occupancy of a given area is to be considered as live load (see 
next section).  The 1964 New York State Building Construction Code and the 1967 Municipal Code of 
Chicago do not have a provision in this regard.  The 1965 BOCA Basic Building Code has a similar 
provision but does not cite specific types of service equipment as the NYC Building Code. 

The 1968 NYC Building Code requires that weights of partitions be considered in two ways: (1) using 
line loads at locations shown on plans or (2) using the equivalent uniform load given in Reference 
Standard RS 9-1.  The stipulated equivalent uniform load depends on the partition weight, for example, if 
a partition weighs 201 plf to 350 plf, it may be taken into account by designing for a uniform load of 
20 psf. The uniform loading approach, however, is not permitted in certain situations for which actual 
partition weights must be used.  Equivalent uniform loads must be used in areas where the locations of 
partitions are not shown on plans, or in areas where partitions can be relocated.  The 1964 New York 

                                                      

16

 Refers to section number in the 1968 New York City Building Code. 

background image

Draft for Public Comment 

 

Code Provisions for Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

45

 

Table 4–1.  Examples of dead loads given in NYC Building Code and BOCA Code. 

 NYC 

BOCA 

Walls and Partitions 

Hollow concrete block – 8 in. thick 
Clay tile, nonload bearing – 8 in. thick 
Plaster partition, metal studs and lath, gypsum plaster both sides 

53 psf 
34 psf 
18 psf 

50 psf 
36 psf 
18 psf 

Floor Finishes 

Resilient flooring 
Hardwood flooring 7/8 in. thick (1 in. for BOCA) 
Cement, 1 in. thick 

2 psf 
4 psf 

12 psf 

2 psf 
4 psf 

12 psf 

Ceilings 

Suspended acoustical tile 
Suspended metal lath and gypsum plaster 

2 psf 
9 psf 

– 

10 psf 

Miscellaneous Materials 

Marble 
Concrete (normal density stone or gravel) 
Reinforced concrete (normal density) 

168 pcf 

a

 

144 pcf 
150 pcf 

168 pcf 
144 pcf 
150 pcf 

a.  Note that the units in the 1968 NYC Building Code are given incorrectly as “psf.” 

State Building Construction Code does not have a specific provision in this regard.  The 1967 Municipal 
Code of Chicago prescribes a minimum partition load of 20 psf.  The BOCA Basic Building Code 
requires consideration of the actual weight of the partitions or an equivalent uniform load of at least 
20 psf. 

4.2.2 Live 

Loads 

Live loads are those resulting from the use and occupancy of the building, and include loads such as 
weights of occupants, furniture, filing cabinets, safes, mechanical equipment, and other items that the 
structure is called upon to support.  Live loads are specified in terms of weight per unit of floor (or roof) 
area or in terms of concentrated loads.  The values specified in codes are based largely on load survey 
data, experience, and judgment. 

Floor Live Loads 

In general, values of minimum uniformly distributed live loads specified in codes are organized on the 
basis of use or occupancy of spaces, and there is no consistency in the names of these use categories.  
Thus, comparison between codes is not straightforward.  Table 4–2 gives some examples of minimum 
uniformly distributed live loads for floors.  It is seen that there is general agreement in the values of these 
selected minimum uniform live loads specified by the four codes. 

background image

Chapter 4 

 

Draft for Public Comment 

46

 

NIST NCSTAR 1-1, WTC Investigation 

 

Table 4–2.  Comparison of uniform live load values.  Examples of minimum uniformly 

distributed live loads. 

 

1968 NYC 

1964 NYS 

1967 Chicago 

1965 BOCA 

Office space 

50 psf 

50 psf 

50 psf 

50 psf 

Restaurant 

100 psf 

100 psf 

– 

100 psf 

Lobbies 

100 psf 

100 psf 

100 psf 

100 psf 

Stairways 

100 psf 

100 psf 

75–100 psf 

a

 100 

psf 

Rest rooms 

40 psf 

60 psf 

– 

– 

Hospital operating room 

60 psf 

60 psf 

40 psf 

60 psf 

School classroom 

40 psf 

60 psf 

40 psf 

– 

a.  Depends on occupancy, for example, 75 psf for business, 100 psf for schools. 

The codes also specify concentrated live loads placed so as to result in maximum stresses. 

Live-Load Reduction 

There is a low likelihood that the full design floor live loads will be present on all floors of a building at 
the same time.  In addition, the likelihood that the complete area any one floor is loaded with the design 
live load decreases as the floor area increases.  To account for these factors, building codes permit “live-
load reductions” in calculating the design loads for primary members (columns and girders) that support 
the roof and floors.  The codes use several methods for live-load reduction (CTB&UH 1980): 

1.

 

Percentage Method

—In this method, the live-load reduction increases by a certain percentage 

with increasing numbers of floors, with a limit on the maximum value of reduction (typically 
50 percent). 

2.

 

Tributary Area Method

—The live load is reduced as the accumulated tributary area that a 

member supports is increased.  The limiting value depends on the ratio of live load to dead 
load. The type of occupancy affects whether a reduction is permitted. 

3.

 

Live Load to Dead Load Ratio

—The permitted reduction depends on the ratio of live load to 

dead load, provided that the dead load is greater than the live load.   

The 1968 NYC Building Code uses the tributary area method and permits the percentage method as an 
alternative for columns, piers, and walls.  The 1964 New York State Building Construction Code and the 
1967 Municipal Code of Chicago use the tributary area method for beams and girders and the percentage 
method for columns and walls.  The 1965 BOCA Basic Building Code uses a tributary method that is 
similar to the New York State Code. 

Figure 4–1 compares the reduced live load for columns, walls, and piers on the basis of the percentage 
method for three of the codes.  The permitted reductions are similar with the exception of the roof and top 
floor, where the 1968 NYC Building Code and the 1967 Municipal Code of Chicago are more 
conservative (less reduction permitted) than the 1964 New York State Building Construction Code. 

Table 4–3 compares the reduced live loads for beams and girders for the selected codes.  For the 1968 
NYC Building Code, the reduced value of live load for a given contributory area depends on the live load 

background image

Draft for Public Comment 

 

Code Provisions for Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

47

 

to dead load ratio, with lower values permitted for lower live load to dead load ratios.  For the 1964 New 
York State Building Construction Code and the 1965 BOCA Basic Building Code, the values shown in 
the table are based on a reduction factor of 0.08 percent/ft

2

.  The lowest reduced value, however, is 

limited to 40 percent or  

 

D

L

D

L

33

.

4

1

33

.

3

%

100

 

(4–1)

whichever is larger, where 

L/D

 is the live load to dead load ratio. As the ratio of live load to dead load 

increases, less live-load reduction is permitted.  A comparison of the values in Table 4–3 shows that the 
1967 Municipal Code of Chicago did not permit as large a reduction in live load for the same contributory 
area as the other codes. 

4.2.3 Wind 

Load 

The effect of wind on buildings is accounted for in the building codes by specifying a uniform pressure to 
be applied horizontally to a building.  These pressures are to be applied in any direction so as to obtain the 
most critical loading condition. 

The pressure due to wind varies with the square of the wind speed, and wind speed increases with height.  
Thus building codes specify minimum design wind pressures that increase with elevation.  The variations 
of pressure with height, however, are not the same among the building codes compared.  Figure 4–2 
compares the specified wind pressure versus height relationships for the four selected codes.  Several 
observations are noted: 

 

For buildings up to 600 ft in height, the 1964 New York State Building Construction Code 
prescribes the largest wind pressures. 

 

The 1967 Municipal Code of Chicago prescribes the lowest wind pressures for buildings up to 
900 ft in height. 

 

The 1968 NYC Building Code and the 1965 BOCA Basic Building Code provide similar wind 
pressures for buildings up to 700 ft in height; for taller buildings the BOCA Code specifies 
larger pressures. 

For a building height of 1,370 ft (the approximate heights of WTC 1 and WTC 2), the wind pressure 
distribution specified by the 1965 BOCA Basic Building Code would result in the largest shear force and 
overturning moment at the base of the building. 

 

 

background image

Chapter 4 

 

Draft for Public Comment 

48

 

NIST NCSTAR 1-1, WTC Investigation 

 

Table 4–3.  Reduced live load for beams and girders. 

Contributary Area 

(ft

2

1968 NYC  

Building Code (%) 

1967 Chicago 

Municipal Code (%) 

1956 NY State and 

1965 BOCA Codes (%) 

100 or less 

100 

100 

100 

100–149 100 

95 

100 

150–199 80 

to 

85

a

 95  84 

to 

88

b

 

200–299 80 

to 

85

a

 90  76 

to 

84

b

 

300–449 60 

to 

75

a

 85  64 

to 

76

b

 

450–599 50 

to 

70

a

 85  52 

to 

64

b

 

600 and more 

40 to 65

a

 85  40 

to 

52

b

 

a. Permitted value depends on live load to dead load ratio; less reduction permitted with higher ratio. 
b. The lowest value is limited to 40 percent, or 100 percent of (3.33 L/D –1)/(4.33 L/D), whichever is greater. 

Assuming wind is blowing in the direction perpendicular to the face of the tower, a comparison using the 
specified wind pressures from the aforementioned codes reveals that the largest shear force at the base of 
a building the height of the WTC towers is obtained from the BOCA Basic Building Code.  Similarly, the 
largest overturning moment at the base of a building the height of the WTC towers is also obtained from 
the BOCA Basic Building Code.  The lowest base shear and moment are obtained from the 1968 and 
2001 New York City Codes. The base shear from the New York City Codes is approximately 8 percent 
less than that from the BOCA code, while the base moment is approximately 11 percent less (see 
Table 4–4). 

Table 4–4.  Base shears and overturning moments from reviewed codes for a building the 

height of WTC towers (1,368 ft). 

 

1968 

NYC Building 

Code 

2001 

NYC Building 

Code 

1964 NY State 

Code 

1967 Chicago 

Municipal 

Code 

1965 

BOCA/BBC 

Base 

Shear 

(kip) 

9,250 9,250 9,460 8,610 9,970 

Overturning 

Moment 

(ft kip x 10

3

 at 

footing) 

7,621 7,621 7,572 7,446 8,470 

The 1968 NYC Building Code permits the designer to use wind pressure values, other than specified 
minimums, on the basis of wind tunnel tests and with approval of the building official.

17

 The following 

wording is provided in Sec. 6 of Reference Standard RS 9-5, “Minimum Design Wind Pressures.” 

In lieu of the design wind pressures established in sections 1 and 2 of this 
reference standard, and subject to review and approval of the 
commissioner, design wind pressures may be approximated from 
suitably conducted model tests.  The tests shall be predicated on a basic 
wind velocity of 80 mph at the 30 ft level, and shall simulate and include 
all factors involved in considerations of wind pressure, including 
pressure and suction effects, shape factors, functional effects, gusts, and 
internal pressures and suctions. 

                                                      

17

 See Sub-article 904.0, the1968 New York City Building Code. 

background image

Draft for Public Comment 

 

Code Provisions for Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

49

 

The other three contemporaneous codes do not have a similar provision for conducting model tests to 
determine the design wind pressure. 

Thus the 1968 NYC Building Code presumes a wind with a speed of 80 mph measured 30 ft above the 
ground.  The 1964 New York State Building Construction Code, on the other hand, states that the 
prescribed wind loads “are based on a design wind speed of 75 mph at a height of 30 ft above grade 
level.”  Both the 1965 BOCA Basic Building Code and the 1967 Municipal Code of Chicago do not 
specify the design wind speed. 

4.2.4 Earthquake 

Load 

The 1968 NYC Building Code did not have provisions for earthquake loads. Among the selected 
contemporaneous codes, only the 1965 BOCA Basic Building Code had earthquake load provisions.  
These are contained in Appendix K-11 of that Code and were adapted from the 1962 edition of the 
Uniform Building Code. 

The 2001 edition of the NYC Building Code contains seismic design provisions from the 1988 edition of 
the Uniform Building Code (UBC 1988), including the 1990 Accumulative Supplement. These provisions 
were put into effect in 1996 as a result of Local Law 17 (1995).  Significant modifications to the 1988 
Uniform Building Code were made, and described in Reference Standard RS 9-6.   

For example, the paragraph on “Minimum Seismic Design,” is modified to read: 

The following types of construction shall, at a minimum, be designed and 
constructed to resist the effects of seismic ground motions as provided in this 
section:  

new structures on new foundations; 

new structures on existing foundations; and 

enlargements in and of themselves on new foundations.   

Buildings classified in New York City occupancy group J-3 and not 
more than three stories in height need not conform to the provisions of 
this section.  The Commissioner may require that the following types of 
construction be designed and constructed to incorporate safety measures 
as necessary to provide safety against the effects of seismic ground 
motions at least equivalent to that provided in a structure to which the 
provisions of the section are applicable:  

new buildings classified in occupancy group J-3 and which are three 
stories or less in height; and 

enlargements in and of themselves where the costs of such enlargement 
exceeds sixty percent of the value of the building. 

In the subdivision on “Criteria Selection” the following paragraph was added:  

Seismic Zone.  The seismic zone factor, Z, for buildings, structures and portions 
thereof in New York City shall be 0.15.  The seismic zone factor is the effective 
zero period acceleration for S

1

 type rock. 

background image

Chapter 4 

 

Draft for Public Comment 

50

 

NIST NCSTAR 1-1, WTC Investigation 

 

Another significant amendment is the addition of consideration of soil liquefaction that was not found in 
the Uniform Building Code. 

4.2.5 Other 

Loads 

Temperature and Shrinkage 

The 1968 NYC Building Code included provisions dealing with types of loadings not considered in the 
other codes that were compared.  Two examples are “thermal forces” and “shrinkage.”  
Section C26-905.7 deals with thermal forces and includes the following requirement: 

…For exterior exposed frames, arches, or shells regardless of plan 
dimensions, the design shall provide for the forces and/or movements 
resulting from an assumed expansion and contraction corresponding to 
an increase or decrease in temperature of forty degrees F for concrete or 
masonry construction and sixty degrees F for metal construction… 

Section C26-905.8 on shrinkage includes the following requirement: 

The design of reinforced concrete components shall provide for the 
forces and/or movements resulting from shrinkage of the concrete in the 
amount of 0.0002 times the length between contraction joints for 
standard weight concrete, and 0.0003 times the length between 
contraction joints for lightweight concrete…. 

Abnormal loads (Progressive collapse consideration) 

The 1968 NYC Building Code did not have provisions for design against progressive collapse of 
buildings due to abnormal loads.  Abnormal loads would include explosions resulting from ignition of gas 
or industrial liquids, vehicle impacts, gross construction errors, and the like.  In response to the collapse 
of a concrete panel building in Ronant Point, England in 1968, the NYC Building Code by rule

18

 adopted 

the progressive collapse provisions in August 2, 1973.  However, on August 7, 1973, the Department of 
Buildings issued a memorandum to clarify the type of structures to which the new progressive collapse 
provisions apply.  These include structures with connections that rely on friction due to gravity loads to 
transfer tension, compression and shear forces in the structural members. Thus, for cast-in-place concrete 
construction having adequate joint reinforcement, the new progressive collapse provisions would not 
apply.  Similarly, for structural steel construction with bolted, riveted or welded connections to transfer 
tension, compression and shear forces, the provisions would not apply. In practical sense, the new 
provisions would apply to precast construction wherein joint forces are transferred by friction developed 
by gravity loads. 

                                                      

18

 The rules intrepret the code to clarify the intent of the code. 

background image

Draft for Public Comment 

 

Code Provisions for Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

51

 

4.2.6 

Distribution of Loads 

Another topic that is addressed only in the 1968 (and 2001) NYC Building Code is the distribution of 
loads, which is covered in Article 7 of Sub-chapter 9. Section C26-906.1 deals with vertical loads and 
states: 

Distribution of vertical loads to supporting members shall be determined 
on the basis of a recognized method of elastic analysis or system of 
coefficients of approximation.  Elastic or inelastic displacements of 
supports shall be considered and, for the distribution of dead loads, the 
modulus of elasticity of concrete or composition [composite] sections 
shall be reduced to consider plastic flow.  Secondary effects due to 
warping of the floors shall be considered. 

Section C26-906.2 deals with distribution of horizontal forces. Because this section provides important 
information in the design assumptions to be used in the design of high-rise buildings, several key sections 
are repeated here:  

The following provisions shall apply to superstructure framing only, and 
shall not apply to structures wherein horizontal loads are transmitted to 
the foundation by staycables, arches, non-rectangular frames, or by 
frames, trusses, or shear walls not oriented in vertical planes. 

(a) Distribution of horizontal loads to vertical frames, trusses and 
shear walls.  

- Horizontal loads on the superstructure shall be assumed to 

be distributed to vertical frames, trusses, and shear walls by floor and 
roof systems acting as horizontal diaphragms.  The proportion of the total 
horizontal load to be resisted by any given vertical frame, truss, or shear 
wall shall be determined on the basis of relative rigidity, considering the 
eccentricity of the applied load with respect to the center of resistance of 
the frames, trusses, or shear walls.  For vertical trusses, web 
deformations shall be considered in evaluating the rigidity.   

(b) Distribution of horizontal loads within rigid frames of tier 
buildings.  

-  

(1) ASSUMPTIONS. - The distribution of horizontal loads within rigid 
frames of tier buildings may be determined on the basis of a recognized 
method of elastic analysis or, subject to limitations in paragraph two of 
this subdivision, may be predicated on one or more of the following 
simplifying assumptions:  

a.  Points of inflection in beams or columns are at their midspan and 
midheight, respectively.  The story shear is distributed to the columns in 
proportion to their stiffnesses. 

b.  The change in length of columns due to axial effects of the horizontal 
loads may be neglected. 

c.  Vertical column loads due to horizontal forces are taken by the 
exterior columns only, or are resisted by the columns in proportion to the 
column distances from the neutral axis of the bent. 

background image

Chapter 4 

 

Draft for Public Comment 

52

 

NIST NCSTAR 1-1, WTC Investigation 

 

(2) LIMITATIONS.  - 

a.  For buildings over 300 ft in height, the change in length of the 
columns, due to the effects of the horizontal loads, shall be evaluated or 
the framing proportioned to produce regular movements of the 
successive joints at each floor so that warping of the floor system may be 
neglected. 

b.  Simplifying assumptions used in design shall be subject to approval 
by the commissioner for any of the following conditions or 
circumstances: 

1. For buildings over 300 ft in height or for buildings with a height-

width ratio greater than five. 

2.  At two-story entrances or intermediate floors. 

3.  Where offsets in the building occur. 

4.  Where transfer columns occur. 

5.  In any similar circumstances of irregularities or discontinuities in the 

framing. 

4.3 DESIGN 

STANDARDS 

Article 10 of the 1968 NYC Building Code is entitled “Structural Work,” and it provides minimum 
requirements for materials, design, and construction of all structural elements in buildings.  Section 4.3.1 
compares design standards in the selected building codes.  Section 4.3.2 discusses design load 
combinations that were specified in the selected building codes. 

4.3.1 Design 

Standards 

Design standards are those documents that are used to proportion the structural elements and their 
connections.  The principal structural materials in the WTC buildings were concrete and steel, and the 
design standards were those produced by the American Concrete Institute (ACI) and the American 
Institute of Steel Construction (AISC).  The ACI produced the standard known as ACI 318, 

Building 

Code Requirements for Reinforced Concrete

,

19

 and the AISC produced the following: 

 

Specification for the Design, Fabrication and Erection of Structural Steel for Buildings 
(AISC 1963)  

 

Specifications for Structural Steel Buildings–ASD and Plastic Design (AISC 1989)  

 

Load and Resistance Factor Design Specifications for Structural Steel Buildings (AISC 1993) 

                                                      

19

 In 1999, the title was changed to 

Building Code Requirements for Structural Concrete.

 

 

background image

Draft for Public Comment 

 

Code Provisions for Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

53

 

Table 4–5 summarizes the concrete and steel design standards adopted by the codes that were compared.  
The 1964 New York State Building Construction Code was a performance standard and did not adopt 
design standards by reference.  Thus, at the time the WTC towers were being designed, the other two 
codes (Chicago and BOCA) referenced the same concrete and steel design standards as the New York 
City code. 

Table 4–5.  Design standards for concrete and steel. 

Material 

1968 NYC Code 

2001 NYC Code 

1967 Chicago 

Code 

1965 BOCA 

Code 

Concrete 

ACI 318-63 

ACI 318-89 

ACI 318-63 

ACI 318-63 

Steel 

AISC 1963 

AISC 1989 
AISC 1993 

AISC 1963 

AISC 1963 

The 1963 edition of ACI 318 permits reinforced concrete members to be designed by either the working 
stress (or allowable stress) method or by the ultimate strength method.  The 1963 AISC specification, on 
the other hand, is based on allowable stress design.  The design method affects the loads used in the 
design calculations. 

4.3.2 Load 

Combinations 

The loads prescribed by the codes are used in different combinations to assess the governing design 
condition.  The codes distinguish between sustained loads and loads of short duration or infrequent 
occurrence.  For allowable stress design, two approaches are used for dealing with these two categories of 
loads, as will be discussed.  For ultimate strength design, the prescribed loads are multiplied by specified 
load factors.  In either case, the designer considers all applicable load combinations and determines the 
most critical condition, which becomes the design basis for a particular element. 

Allowable Stress Design 

The 1968 NYC Building Code defines two categories of loads: 

 

Basic loads, which include dead load, live load, and reduced live load where applicable; and 

 

Loads of infrequent occurrence, which include wind load, thermally induced load, shrinkage 
induced load, and unreduced live load where live load reduction is permitted.   

Under the 1968 NYC Building Code, stresses in structural elements may not exceed the allowable values 
specified in the referenced design standards under the following load combinations

20

 

The sum of the basic loads multiplied by a factor equal to 1. 

 

The factored sum of one or more basic loads and one load of infrequent occurrence, where the 
load factor equals 0.75. 

                                                      

20

 See Section C26-1001.4 of the 1968 NYC Building Code. 

background image

Chapter 4 

 

Draft for Public Comment 

54

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

The factored sum of one or more basic loads plus two or more loads of infrequent occurrence, 
where the load factor equals 0.6. 

The 2001 NYC Building Code is similar with the exception that it includes earthquake load as another 
load of infrequent occurrence. 

The other Codes that were compared use a different approach for dealing with loads of infrequent 
occurrence.  The 1964 New York State Building Construction Code states that stress due to wind load 
may be ignored if it is less than one-third of the stress due to dead load plus imposed load excluding wind 
load.  If the stress due to wind load exceeds this limit, the allowable stress for the material is permitted to 
be increased by 1/3. 

The 1967 Municipal Code of Chicago uses a similar approach and states: “For combined stresses due to 
dead, live, and wind load, the allowable stresses in materials may be increased 1/3, provided the section 
thus determined is at least as strong as that required for dead and live load alone. Snow load shall be 
considered a live load.” 

The 1965 BOCA Basic Building Code is similar except that wind load or earthquake load is considered 
along with dead load and live load (including snow load).  The same 1/3 increase in allowable stress is 
permitted under wind or earthquake load.  The BOCA Code also explicitly states that wind load is 
permitted to be neglected if it results in stress less than one-third the stress due to dead load plus live load. 

Ultimate Strength Design 

In the 1960s, ultimate strength design was standardized only for reinforced concrete. As shown in 
Table 4-5, the three codes from the 1960s referenced ACI 318-63, which includes the following load 
combinations to establish the design loads (U) for structural members: 

1.  For structures where wind and earthquake loads may be neglected, U = 1.5 D + 1.8 L. 

2.  For structures where wind load must be included, U = 1.25 (D + L) or U = 0.9 D+ 1.1 W, 

whichever produces the most unfavorable condition for the member. 

3.  For structures where earthquake loading is included, E shall be substituted for W in 

condition 2. 

4.  In structures where effects of shrinkage and temperature are included, the effects of such 

items shall be considered on the same basis as the effects of dead load. 

The 2001 NYC Building Code refers to ACI 318-99, which includes many more load combinations to be 
considered. These are as follows: 

1.  For all structures, U = 1.4 D + 1.7 L. 

2.  For structures where wind load must be included, U = 0.75[1.4 D + 1.7 L + 1.7 W)] or  

U = 0.9 D + 1.3 W, whichever produces the most unfavorable condition for the member. 

background image

Draft for Public Comment 

 

Code Provisions for Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

55

 

3.  For structures where resistance to earthquakes must be included, the load combinations of 

condition 2 are used with 1.1 E substituted for W. 

4.  For structures where resistance to earth pressure (H) must be included,  

U = 1.4 D + 1.7 L + 1.7 H or 0.9 D + 1.7 H, whichever produces the most unfavorable 
condition.   

5.  For structures where resistance to fluid pressure (F) must be included,  

U = 1.4 D + 1.7 L + 1.4 F or 0.9 D + 1.7 F, whichever produces the most unfavorable 
condition. 

6.  For structures where resistance shrinkage and temperature (T) must be included,  

U = 0.75 (1.4 D + 1.4 T + 1.7 L) > 1.4 (D + T).   

7.  For structures where resistance to impact must be taken into account, such effects shall be 

included with live load L. 

4.4 

ALTERATION OF EXISTING BUILDINGS 

The compared codes have provisions to address code compliance when existing buildings are altered.  
The provisions of all codes, other than the 1964 New York State Building Construction Code, are broadly 
similar. In general, whether the altered building or only the alternations need to comply with code 
requirements depends on the ratio of alterations to the total building expressed either in terms of cost or 
dimensions. When the ratio is low, even the alterations may not have to be in compliance with the code, 
provided stipulated conditions are met. The 1964 New York State Building Construction Code, however, 
requires that any addition or alteration, regardless of building value, shall be made in conformity with that 
code. It is silent as to the structure being altered. Table 4–6 summarizes code provisions related to 
alterations. 

Table 4–6.  Compliance requirements for alterations. 

Code Provisions 

1968 New York City 
Building Code 

Alterations exceeding 60 percent of building value (in any 12 month period):

 The 

entire building shall be made to comply with the requirement of the code. 

Alterations between 30 percent and 60 percent of building value (in any 12 month 
period):

 Only those portions of the building altered shall be made to comply with the 

requirements of the code. 

Alteration under 30 percent of building value (in any 12 month period):

 Those 

portions altered may, at the option of the owner, be altered in accordance with the 
requirement of the code, or altered in compliance with their previously required 
condition and with the same or equivalent materials and equipment, provided the 
general safety and public welfare are not thereby endangered. 

2001 New York City 
Building Code 

Same as 1968 Code, except that wording for alterations 

less than 30 percent

 of 

building values was changed to: “those portions of the building altered may, at the 
option of the owner, be altered in accordance with the requirements of this code, or 
altered in compliance with the applicable laws in existence prior to December sixth, 
nineteen hundred sixty-eight, provided the general safety and public welfare are not 
thereby endangered.” 
In addition, certain alterations are required to conform to the code regardless of 

background image

Chapter 4 

 

Draft for Public Comment 

56

 

NIST NCSTAR 1-1, WTC Investigation 

 

Code Provisions 

magnitude or cost.  These include, among others:  
Alterations to standpipes, sprinklers, or interior fire alarm and signal systems;  
Alterations to equipment for heating or storing water;  
Sprinkler, alarm protection, and emergency lighting requirements for places of 
assembly. 

1964 New York State 
Building Construction 
Code 

Addition or alteration:

 Any addition or alteration, regardless of cost, made to a 

building shall be made in conformity with applicable regulations of the code. 

1967 Municipal Code 
of Chicago 

More than 50 percent:

 Such buildings and structures shall be made to conform to all 

requirements of the code that are applicable to new buildings and structures. 

25 percent to 50 percent:

 All new constructions shall conform to the requirements of 

the code for new buildings or structures of like area, height and occupancy.   

25 percent or less:

 Certain exceptions can be made that allow the use of materials that 

conform to the strength and fire resistance for the materials with which the building is 
constructed.  Otherwise, all new construction shall conform to the requirements of this 
code for a new building. 

1965 BOCA Basic 
Building Code 

“In the reconstruction, repair, extension or alteration of existing buildings, the 
allowable working stresses used in design shall be as follows: 
1.  

Building extended:

 If altered by an extension in height or area, all existing 

structural parts affected by the addition shall be strengthened where necessary and all 
new structural parts shall be designed to meet the requirements for buildings hereafter 
erected. 
2.  

Building repaired:

 When the uncovered structural parts are found unsound, such 

parts shall be made to conform to the requirements for buildings hereafter erected. 
3.  

Existing live load:

 When an existing building heretofore approved is altered or 

repaired within the limitation prescribed in Sec. 106.3 (alteration under 50 percent) and 
106.4 (alteration under 25 percent), the structure may be designed for the loads and 
stresses applicable at the time of erection, provided that public safety is not 
endangered. 
4.  

Posted live load:

 May be posted for original approved live loads.” 

4.5 

MATERIALS AND METHODS OF CONSTRUCTION 

The compared codes have requirements for the materials and construction methods.  Each code makes 
distinctions in materials and methods that depend on the nature of inspection and conformance with 
standards.  

The 1968 NYC Building Code prescribes testing and inspection requirements for all materials, 
assemblies, forms, and methods of construction.  A distinction is made between materials and methods 
subject to “controlled inspection” and those that are not subject to controlled inspection.  Materials and 
methods subject to controlled inspections “shall be inspected and/or tested to verify compliance with code 
requirements.”  In general, activities related to controlled inspections “shall be made and witnessed by or 
under the direct supervision of an architect or engineer retained by or on behalf of the owner or lessee, 
who shall be, or shall be acceptable to, the architect or engineer who prepared or supervised the 
preparation of the plans.”  On the other hand, materials and methods not designated for controlled 
inspection “shall be inspected and/or tested to verify compliance with code requirements by the person 
superintending the use of the material or its incorporation into the work…” 

background image

Draft for Public Comment 

 

Code Provisions for Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

57

 

The 1968 NYC Building Code provides tables to indicate which materials and methods are subject to 
controlled inspections and which are not.  Table 4–7 includes excerpts from the requirements for 
inspection of materials and assemblies.  A footnote to the table in the code states that “All structural 
materials and assemblies subject to controlled inspection shall be tested and/or inspected at their place of 
manufacture and evidence of compliance with the provisions of this subchapter shall be provided as 
stipulated in sub-articles 1003.0 through 1011.0.”  Table 4–8 is an excerpt of the inspection requirements 
for methods of construction.  A footnote to the companion table in the code states that “All construction 
operations designated for controlled inspection shall be inspected by the architect or engineer designated 
for controlled inspection during the performance of such operation.” 

Table 4–7.  Excerpts of inspection requirements for materials and assemblies in  

Article 10 of 1968 NYC Building Code. 

Material Elements 

Subject 

to Controlled Inspection 

Elements Not Subject to Controlled 

Inspection 

Steel 

None 

All structural elements and connections 

Concrete 

Materials for all structural elements 
proportioned on the basis of calculated 
stresses 70 percent or greater, of basic 
allowable stresses.  See Sec. 1004.0 for 
specific requirements relating to “quality 
control of materials and batching.” 

(1) All materials for all structural elements 
proportioned on the basis of calculated stresses 
less than 70 percent or greater of basic allowable 
values.   
(2) Concrete materials for: 

(a) Short span floor and roof construction 
proportioned as per Sec. 1004.8. 
(b) Walls and footings for buildings in 
Occupancy Group J-3. 

(3) Metal reinforcement. 

The 1968 NYC Building Code required that the installation of “sprayed-on fire protection” of structural 
members (except those encased in concrete) be subjected to controlled inspection requirements, as 
defined above.  There were, however, no specific provisions on what testing was required. 

The 1964 New York State Building Construction Code and the 1965 BOCA BBC make distinctions 
between “controlled” and “ordinary” materials in reference to establishing allowable stresses.  For 
example BOCA defines “controlled materials” as those that are “certified by an accredited authoritative 
agency as meeting accepted engineering standards for quality.”  Ordinary materials are those that do not 
conform to the requirements for controlled materials.   

The 1967 Municipal Code of Chicago specifies that all materials and methods used in the design and 
construction of buildings shall be classified as “controlled materials” or “ordinary materials.”  According 
to the Chicago Code, “controlled materials” means a building, structure, or part thereof, which has been 
designed or constructed under the following conditions: (a) All controlled materials must be selected or 
tested to meet the special strength, durability and fire resistance requirements upon which the design is 
based. (b) The design, preparation of working drawings, including details and connections, the checking 
and approval of all shop and field details and the inspection of the work during construction shall be 
under the supervision of a registered architect or structural engineer (Sec. 69-3.1). 

background image

Chapter 4 

 

Draft for Public Comment 

58

 

NIST NCSTAR 1-1, WTC Investigation 

 

Table 4–8.  Excerpts of inspection requirements for methods of construction in  

Article 10 of 1968 NYC Building Code. 

Material 

Operations Subject to Controlled 

Inspection 

Operations Not Subject to Controlled 

Inspection 

Steel 

(1) Welding operations and the tensioning of 
high strength bolts in connections where the 
calculated stresses in the welds or bolts are 50 
percent or more of basic allowable values. 
(2) Connection of fittings to wire cables for 
suspended structures, except where cables 
together with their attached fittings are proof-
loaded to not less than 50 percent of ultimate 
capacity. 

(1) Welding operations and the tensioning of 
high strength bolts in connections where the 
calculated stresses in the welds or bolts are less 
than 50 percent of basic allowable values. 
(2) All other fabrication and erection operations 
not designated for controlled inspection. 

Concrete 

Except for those operations specifically 
designated in this table as not subject to 
controlled inspection, for all concrete, the 
operations described in Sec. 1004.5(a) shall be 
subject to controlled inspection.” 

(1) All operations relating to the constriction of 
members and assemblies (other than prestressed 
concrete) which involve the placement of a total 
of less than 50 cubic yards of concrete and 
wherein said concrete is used at levels of 
calculated stress 70 percent or less of basic 
allowable values. 
(2) placing and curing of concrete for all: 

(a) short span floor and roof construction as 
per Sec. 1004.8. 
(b) Walls and footings for buildings in 
Occupancy Group J-3. 

(3) Size and location of reinforcement for walls 
and footings in Occupancy Group J-3. 
(4) All other operations not described in 
Secs. C26-1004.5(a). 

4.6 

STABILITY, BRACING, AND SECONDARY STRESSES 

The 1968 and 2001 NYC Building Codes are the only codes of those compared that include provisions for 

stability

bracing

, and 

secondary

 

stresses

.  The provisions are the same in the two editions of the code.  

Stability, in this case, refers to resistance to sliding or overturning of the building on its foundation.  The 
NYC Building Code requires a factor of safety of 1.5 against failure by sliding or overturning.  The 
required stability is to be provided solely by the dead load plus any permanent anchorage that is provided. 
Bracing refers to lateral support to prevent buckling of compression members (columns and walls).  The 
NYC Building Code requires that the bracing be proportioned to resist a load of at least 2 percent of the 
total design compression load in the braced member plus any transverse shear load on the bracing 
member.  Secondary stresses refer to stresses associated with transverse deflection of a member. In 
trusses, for example, secondary stresses arise because joints are not true pins, and some bending is 
introduced, which results in transverse displacements of the individual elements.  The NYC Building 
Code requires that secondary stresses in trusses be considered in designing the size of the individual 
elements. 

background image

Draft for Public Comment 

 

Code Provisions for Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

59

 

4.7 DEFLECTION 

LIMITATIONS 

All five codes contain limits on vertical deflections of floor and roof assemblies.  Except for the NYC 
Building Codes (both the 1968 and 2001 versions), the deflection limits relate to crack formation of 
plastered building components.  The deflection is limited to 1/360 of the span for plastered members and 
1/240 of the span for non-plastered members.  The NYC Building Codes refer to the reference standards 
for deflection limits in addition to the 1/360 of the span limit.  For concrete members, ACI 318-63 
specifies limits for both short- and long-term deflections of beams and one-way slabs.  For steel members, 
the 1963 AISC Specification specifies deflection limits to avoid damage to plastered ceilings and to limit 
deflections of flat roofs. 

4.8 LOAD 

TESTS 

Building codes generally allow load tests to ascertain the adequacy of load carrying capacity of structural 
members.  Specifically, building codes allow load tests or tests of in-place materials:  

 

To verify adequacy of structural design for a member or an assembly; 

 

To verify adequacy of partially completed construction; 

 

To prequalify structural members or assemblies before used in service; 

 

To verify adequacy of questionable completed structure; and 

 

To determine concrete strength by means of core tests. 

The NYC Building Codes have provisions to cover all five categories.  The New York State Code had 
provisions for (1) and (4).  The Chicago Municipal Code had provisions for (1), (4) and (5).  The 
BOCA/Basic Building Code had provisions for (1) and (2).  

  

background image

Chapter 4 

 

Draft for Public Comment 

60

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

 

Figure 4–1.  Reduced live load as a function of floor location based on the percentage 

method (for columns, walls, and piers). 

 

background image

Draft for Public Comment 

 

Code Provisions for Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

61

 

 

Figure 4–2.  Wind load pressure versus elevation. 

background image

Chapter 4 

 

Draft for Public Comment 

62

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

This page intentionally left blank.

 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

63

 

Chapter 5 

S

TRUCTURAL 

D

ESIGN OF 

WTC

 

1,

 

2,

 AND 

5.1 

DESIGN CRITERIA  

As stated in Sec. 1.1, the design of World Trade Center (WTC) 1 and WTC 2 was governed by the second 
and third drafts of the 1968 New York City (NYC) Building Code.  The 1968 Code also governed the 
design of WTC 7.  However, different design values were allowed by the Building Code if they were 
more conservative than minimum design requirements specified in the Building Code.  

In a number of cases, the design of the WTC 1 and WTC 2 were based on values that were more 
conservative than those specified in the 1968 NYC Building Code, such as live loads for the tenant spaces 
outside the central core area and wind loads for the towers.  These will be presented in further detail 
below.  No design calculations are available for review of the actual design criteria used for the design of 
WTC 7.  The materials presented in this chapter pertain mainly to WTC 1 and WTC 2. 

5.1.1 Loads 

As presented in Chapter 4, the building codes specify minimum design values for vertical and lateral 
loads.  In the NYC Building Code, Chapter 26, Article 9 prescribes the minimum loads to be used in the 
design of buildings and their parts. Section C26-900.2, Standards, refers to Reference Standard RS-9 for 
the minimum dead, live, and wind loads, which are incorporated by reference into Article 9.  In no case 
does the Code allow for the loads used in design to be less than the minimum values contained in that 
article. In this section, actual design loads used for design are presented and compared with the New York 
City Code requirements. 

Dead Loads 

The unit dead loads specified for the various structural members are contained in the Design Criteria for 
WTC 1 and WTC 2 (WSHJ 1965a).  Different criteria were established for members located inside the 
core and outside the core.  

Floor Inside of Core 

The core area in a representative upper floor of WTC 1 and WTC 2 is illustrated in Fig. 2–13.  Unit 
design dead loads for the beams, columns, and slabs within the core area of the towers are summarized in  
Fig. 5–1.

21

  In all cases, the dead loads in the design criteria were greater than or equal to the 

corresponding dead loads prescribed in the Code. Examples of design dead loads in the 1968 NYC 
Building Code are listed in Table 4–1.  A comprehensive list of the dead loads prescribed in the Code is 
given in Annex A1 of the report entitled 

Comparison of Building Code Structural Requirements 

(NIST 

NCSTAR 1-1B).  For equivalent uniform loads for partitions (according to C26-901.3(b) of the NYC 

                                                      

21

 In Fig. 5–1, “contact” fireproofing is listed. This is a type of fireproofing that is sprayed on to steel members. 

background image

Chapter 5 

 

Draft for Public Comment 

64

 

NIST NCSTAR 1-1, WTC Investigation 

 

Building Code), the equivalent uniform partition loads in Reference Standard RS 9-1 may be used in lieu 
of actual partition weights when partitions are not shown on the plans.  The actual values for design are 
given in the design criteria shown in Fig. 5–2.  As allowed by the Code, the actual partition loads, which 
were less than specified 20 psf in the Code for a partition of 201 plf to 350 plf, were used in the design of 
WTC 1 and WTC 2. 

Floor Outside of Core 

Unit dead loads for areas outside of the core are specified in the design criteria for the following structural 
members: one-way long-span floor trusses, one-way short-span floor trusses, two-way floor trusses, 
beams on framed floors, bridging, columns, steel deck, and reinforced concrete slabs.  The design criteria 
vary depending upon the floor level.  Figure 5–3 contains sample design criteria for the long-span floor 
trusses at typical floor levels.  For a further description of dead loads used in design, see NIST 
NCSTAR 1-2.  The dead loads in the design criteria for all of the structural members were greater than or 
equal to the corresponding dead loads prescribed in the Code. 

Design Criteria for WTC 7 

Design load criteria for WTC 7 are summarized in Fig. 5–4.  These criteria appear on Sheet S-24, Typical 
Superstructure Sections and Details, in the structural drawings (The Office of Irwin G. Cantor 1983). 
Because the actual materials used for the partitions, flooring, and ductwork were not specified, the 
reasonableness of these design values cannot be ascertained. 

Live Loads 

Design Criteria for WTC 1 and WTC 2 

Specified live loads are given in the Design Criteria for WTC 1 and WTC 2 (WSHJ 1965a).  As in the 
case of dead loads, different live-load criteria were established for members located inside the core and 
outside the core.  

 

Floor inside of core.

 Live loads to be used in the design of the beams and columns within the 

core area are summarized in Fig. 5–5, Fig. 5–6, and Fig. 5–7.  As can be seen from the figures, 
except for floor 109 and areas occupied by equipment, the design live load varied from 40 psf 
to 100 psf.  For all occupancies or use of spaces common to the design criteria and the Code, 
the live loads in the design criteria were equal to the corresponding live loads prescribed in the 
Code (which are given in Annex A1 of NIST NCSTAR 1-1B/

Comparison of Building Code 

Structural Requirements

).  

 

Floor outside of core.

 Like the unit dead loads, design live loads outside of the core area 

varied with the floor level.  At most floor levels, a design live load of 100 psf was specified 
for the slabs (see Fig. 5–8 from the Design Criteria). At mechanical floors 7, 41, 75, and 108, 
a 75 psf live load was used.  Figure 5–9 shows sample design criteria for the columns at the 
floor levels noted in the figure.  Live loads specified in the design criteria were equal to or 
greater than the corresponding live loads prescribed in the Code.  It should be noted that the 
100 psf live load used is twice the design live load specified in the NYC Building Code. 

background image

Draft for Public Comment 

 

Structural Design of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

65

 

Table 5–1 compares live loads used for the design of floors with corresponding values specified in the 
1968 NYC Building Code. In most cases, they are the same.  Major differences are noted for the design 
live loads for corridors within the core, tenant spaces outside of the core, and passenger elevator lobbies 
on the tenant floors. Note that the design live load for the tenant spaces are twice the code specified value. 

Table 5–1.  Live loads used in design of WTC 1 and WTC 2. 

Use of Spaces 

1968 

NYC Code 

(psf) 

WTC Design 

Criteria 

(psf) 

Cafeteria 100 

100 

Closets (tenant floors) 

100 

100 

Concourse 100 

100 

Corridors within core (mechanical equipment 
floor)  

75 100 

Corridors within core (skylobby floor) 

100 

100 

Corridors within core (typical office floor) 

75 

75 

Duct offset space  

75 

75 

Electric closet  

75 

75 

Electric substation & transformer room 

75 

75 

Expansion tank room  

75 

75 

Janitor’s closets  

100 

100 

Kitchen 100 

100 

Local passenger elevator lobbies (skylobby floors) 

100 

100 

Main shuttle elevator lobbies (skylobby floors) 

100 

100 

Mechanical equipment rooms 

75 

75 

Men’s toilets 

40 

40 

Observation lobby 

100 

100 

Tenant space outside core 

50 

100 

Passenger elevator lobbies (tenant floors) 

100 

75 

Powder rooms 

40 

40 

Restaurant 100 

100 

Roof 30 

40 

Secondary motor rooms  

75 

75 

Service room (mechanical equipment floor) 

75 

100 

Service room (tenant floor) 

75 

100 

Sprinkler tank room  

75 

75 

Stairs 75 

100 

Telephone closets 

80 

75 

Tenant spaces within core 

50 

56 

Woman’s toilets 

40 

40 

background image

Chapter 5 

 

Draft for Public Comment 

66

 

NIST NCSTAR 1-1, WTC Investigation 

 

Design Criteria for WTC 7 

As noted previously, design criteria for WTC 7 are summarized in Fig. 5–4.  These criteria appear on 
Sheet S-24, Typical Superstructure Sections and Details, in the structural drawings (The Office of Irwin 
G. Cantor 1983).  For the floor levels where the type of occupancy was noted on Sheet S-24, the live 
loads in the design criteria were equal to those given in the Code. 

5.1.2 

Live Load Reduction 

Code Requirements  

Provisions for live-load reduction in the 1968 NYC Building Code are contained in Sub-article 903.0, 
Live Load Reduction.  According to C26-903.1, live load reduction is not permitted on roofs.  The 
allowable reduced live load for floor members is determined by multiplying the basic live load value from 
Reference Standard RS 9-2 (see above) by the percentages given in Table 9-1 of the Code, which is 
reproduced in Table 5–2. These percentages are a function of the contributory floor area, which is defined 
in C26-903.3, and the ratio of live load to dead load. 

Table 5–2.  Percentage of live load per the 1968 NYC Building Code. 

Ratio of Live Load to Dead Load

a

 

Contributory 

Area (ft

2

0.625 or less 

2 or more 

149 or less 

100 

100 

100 

150–299 80 

85 

85 

300–449 60 

70 

75 

450–599 50 

60 

70 

600 or more 

40 

55 

65 

a.  For intermediate values of live load/dead load, the applicable percentages of live load 

may be interpolated. 

Contributory floor areas are computed as follows (C26-903.3): 

 

For one-way and two-way slabs: product of the shorter span length and a width equal to one-
half the shorter span length.  Ribbed slabs shall be considered as though the slabs were solid. 

 

For flat plate or flat slab construction: one-half the area of the panel. 

 

For columns, girders, or trusses framing into columns: the loaded area directly supported by 
the column, girder, or truss.  For columns supporting more than one floor, the loaded area 
shall be the cumulative total area of all the floors that are supported. 

 

For joists and similar multiple members framing into girders or trusses, or minor framing 
around openings: twice the loaded area directly supported but not more than the area of the 
panel in which the framing occurs. 

background image

Draft for Public Comment 

 

Structural Design of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

67

 

No live load reduction is permitted (C26-903.2(b)) for members and connections (other than columns, 
piers, and walls) supporting: 

 

Floor areas used for storage (including warehouses, library stacks, and record storage); 

 

Areas for parking of vehicles; 

 

Areas for places of assembly, for manufacturing; and  

 

Areas for retail or wholesale sales. 

The maximum live load reduction is 20 percent for columns, piers, and walls supporting such areas. 

Live-load reduction is also not permitted for calculating shear stresses at the heads of columns in flat slab 
or flat plate construction (C26-903.2)). 

As an alternative procedure, live load reduction for columns, piers, and walls may be taken as 15 percent 
on the top floor, increased successively at the rate of 5 percent on each successive lower floor, with a 
maximum reduction of 50 percent. For girders supporting 200 ft

2

 or more of floor area, the live-load 

reduction is 15 percent. 

Design Criteria for WTC 1 and WTC 2 

Live-load reduction criteria from the Design Criteria for WTC 1 and WTC 2 are given in Fig. 5–9 
(WSHJ 1965a). The figure shows the percentage of design live load from the Design Criteria that was 
used in the design of structural members.  For floor members, these percentages were the same as those 
from the 1968 Code, except in the case where the live load to dead load ratio was 2 or more and the 
loaded area tributary to the floor member was between 150 ft

2

 and 299 ft

2

; in this case, the code-

prescribed percentage is 85 percent, while the value in the Design Criteria was 90 percent, which is more 
stringent than the code requirement (see Fig. 5–10). 

Figure 5–11 shows the design live loads from the Design Criteria for the tenant areas inside of the core. 
The solid line represents the reduced live load that was used in the design of the beams; these values were 
computed in accordance with the live-load reduction provisions in the Design Criteria (see Fig. 5–10). 
The unreduced live load specified in the Design Criteria for tenant spaces inside the core was 100 psf, 
which matches the design live load shown in Fig. 5–12 for tributary areas up to 200 ft

2

.  Also included in 

this figure are two other sets of data points: one set represents the reduced live load computed in 
accordance with the 1968 Code provisions with a live load to dead load ratio equal to one and the other 
set is the Code equivalent uniform load for partitions, which is a constant 6 psf for partition weights up to 
100 plf.  The Code requires a 50 psf live load in tenant areas (office areas without storage) per Reference 
Standard RS 9-2.  The 50 psf live load plus the 6 psf partition load is shown in the figure for tributary 
areas up to 150 ft

2

.  Figure 5–12 clearly shows that the design live loads specified in the Design Criteria, 

including live load reduction, were greater than those required by the Code for office areas without 
storage. 

Figure 5–13 contains the design criteria for live load reduction for the floor areas outside of the core for 
the floor levels that are noted in the figure.  These criteria are the same as those for the tenant space inside 

background image

Chapter 5 

 

Draft for Public Comment 

68

 

NIST NCSTAR 1-1, WTC Investigation 

 

of the core (see Fig. 5–12).  Similar criteria were also provided in the Design Criteria for other floor 
levels. 

5.1.3 Wind 

Load 

In lieu of using its prescribed pressures, the 1968 NYC Building Code allows “suitably conducted model 
tests” to establish design wind pressures, subject to review and approval of the Building Commissioner 
(Item 6 in Reference Standard RS 9-5).  The tests are to be based on a basic (fastest-mile) wind velocity 
of 80 mph at 30 ft above ground and are to simulate and include all factors involved in consideration of 
wind pressure, including pressure and suction effects, shape factors, functional effects, gusts, and internal 
pressures and suctions. 

Design Criteria for WTC 1 and WTC 2 

Design wind forces on the towers were determined based on a series of wind tunnel tests that were 
conducted at the Colorado State University (CSU) and the National Physical Laboratory (NPL) in the 
United Kingdom.  Specific details on these tests can be found in NIST NCSTAR 1-1A. 

The design wind loadings of the exterior walls of WTC 1 and WTC 2 consisted of shear forces and 
overturning moments that were computed at each floor level in the two principal directions of the towers 
due to the equivalent design wind velocity of 98 mph from 24 wind directions equally spaced at 
15 degrees intervals around the tower. The equivalent design wind velocity was defined as the mean wind 
velocity averaged over a 20 min period at a height of 1,500 ft above the ground and was based on a 
50 year return period.  

The shear forces 

S

 and overturning moments 

M

 at each floor level were comprised of static and dynamic 

components: 

 

M

M

M

S

S

S

±

=

±

=

 

(5–1)

where the first and second terms indicate, respectively, the mean or steady-state components and the 
dynamic components. The static components of the shear and moments were calculated from the 
following equations. 

 

)

(

2

1

)

(

)

(

2

1

)

(

2

2

2

z

C

DH

V

z

M

z

DHC

V

z

S

M

o

S

o

ρ

=

ρ

=

 

(5–2)

where: 

=

ρ

 

design air density = 0.0023 slugs per cubic foot 

=

o

V

  mean design wind velocity = 98 mph averaged over 20 min at a height of 1,500 ft above 

ground 

background image

Draft for Public Comment 

 

Structural Design of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

69

 

=

S

C

  shear force coefficients from wind tunnel tests 

=

M

C

  overturning moment coefficients from wind tunnel tests  

=

D

 

plan dimension of building 

=

H

 height 

of 

building 

The dynamic components of the shear forces and overturning moments at any height 

z

 were calculated 

from the following equations. 

 

dz

z

S

z

M

dz

z

z

m

A

n

z

S

H

z

H

z

o

)

(

)

(

)

(

)

(

4

)

(

2

2

=

µ

π

=

 

(5–3)

In the first of these equations, 

o

n

 is the natural frequency of oscillation of the building, and 

A

 is the 

amplitude of oscillation at the top of the tower corresponding to a mean design wind velocity.  The 
quantity )

(

z

m

 is the mass per unit height of the building, and 

)

(

z

µ

 is the mode amplitude at height 

for 

unit amplitude at the top of the building.  Using sets of shear and overturning moment coefficients 
obtained from the wind tunnel tests (WSHJ 1966a), the shear forces and overturning moments at each 
floor were computed. 

A comparison of the base shear and moment obtained from using the wind pressures from the 1968 NYC 
Building Code and the wind tunnel test results are shown in Table 5–3.  The code-based values of base 
shear and overturning moment occur simultaneously on the same face of the tower, whereas the base 
shear and the overturning moment obtained from the wind tunnel tests represent the largest values related 
to most unfavorable wind direction, thus they may not occur simultaneously on the same face of the 
tower.  For the description used to compute the values based on the wind tunnel tests, see NIST 
NCSTAR 1-2.  The wind load used to design the towers are greater than that based on the code specified 
wind pressure values. 

Table 5–3.  Base shears and overturning 

moments based on the 1968 NYC Building Code 

and wind tunnel tests. 

 

1968 

NYC Building Code 

Wind 

Tunnel Tests 

Base Shear 

(kip) 

9,250 13,100 

Overturning 

Moment 

(10

3

 ft kip) 

7,621 12,600 

For external cladding and glazing, design wind pressures were specified in the WTC Design Criteria. 
Outward (negative) pressure acting normal to the surface varied from 65 psf below the 7th floor to 
125 psf at the 109th floor.  Inward (positive) pressures varied from 45 psf below the 7th floor to 55 psf at 

background image

Chapter 5 

 

Draft for Public Comment 

70

 

NIST NCSTAR 1-1, WTC Investigation 

 

the 108th floor.  These pressures are based on the results of a series of wind tunnel tests that were 
performed specifically for this purpose (WSHJ 1967a).  

Design criteria were also established for the antenna mast located on top of WTC 1 (WSHJ 1973).  The 
antenna and its components were to be designed for the following conditions: 

 

A mean wind speed of 140 mph in any direction and no ice coating; 

 

A mean wind speed of 110 mph in any direction with an ice coating of ½ in. over all exposed 
unheated metallic surfaces with a minimum air temperature of 20 

°

F; 

 

A mean wind speed of 110 mph in any direction and no ice coating under a range of air 
temperatures from 10 

°

F to 90 

°

F; 

 

A mean wind speed of 40 mph in any direction and no ice coating under a range of air 
temperatures from –15 

°

F to 105 

°

F; and 

 

Dynamic effects of wind associated with the mean wind speeds specified above (dynamic 
effects of wind gusts were obtained by multiplying the mean wind forces by a factor of 5). 

The requirement of a ½ in. thick coating of ice is consistent with the requirement in C26-905.6 of the 
1968 NYC Building Code for the design of open-framed or guyed towers.  Also, the NYC Code requires 
that exterior exposed frames, arches, or shells be designed for the forces and/or movements resulting from 
an increase or decrease in temperatures of 60 

°

F for metal construction (C26-905.7).  These requirements 

are less stringent than those contained in the design criteria.  The design criteria contain a section on how 
the wind forces were computed based on these velocities. 

Design Criteria for WTC 7 

No design criteria or calculations were available for WTC 7 with respect to wind loads. However, a wind 
tunnel study of WTC 7 was carried out in 1983 by the University of Western Ontario at the request of the 
structural engineer of record, Irwin G. Cantor, Consulting Engineers (Isyumov 1983). No document is 
available to show whether the wind tunnel test results were used in design of WTC 7. 

5.1.4 Aircraft 

Impact 

No building code in the United States has specific design requirements for impact of an aircraft, and thus, 
buildings are not specifically designed to withstand the impact of fuel-laden commercial aircraft.  
However, since the collision of a B-25 bomber into the Empire State Building in 1945, designers of high-
rise buildings have become aware of the potential of the crash of aircrafts into buildings.  A three-page 
document from the Port Authority of New York and New Jersey (PANYNJ or Port Authority) indicates 
that the impact of a Boeing 707 aircraft flying at 600 mph was analyzed during the design stage of the 
WTC towers in February/March 1964.

22

  

                                                      

22

 Letter with an attachment dated November 13, 2003 from John R. Dragonette (Retired Project Administrator, Physical 

Facilities Division, World Trade Department) to Saroj Bhol (Design and Engineering Department, PANYNJ). 

background image

Draft for Public Comment 

 

Structural Design of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

71

 

No documents on the aircraft impact analysis are available to review the criteria and method used in the 
impact analysis of a Boeing 707 aircraft on the WTC tower and to verify the assertion in the three-page 
document that “…such collision would result in only local damage which could not cause collapse or 
substantial damage to the building and would not endanger the lives and safety of occupants not in the 
immediate area of impact.”  Without the original calculations of the aircraft impact analysis, any 
comment on the document would be a speculation.  In March 1964, a calculation was made by the Port 
Authority to determine the period of vibration of the tower due to an aircraft impact at the 80th floor.

23

 

Although no conclusion was stated on the calculation sheet, it clearly indicates that the Port Authority 
recognized during the design stage the possibility of an aircraft impact on the tower. 

5.2 

STRUCTURAL DESIGN REQUIREMENTS 

According to sub-article 1002.0 of the NYC Building Code (Adequacy of the Structural Design), the 
design of structural members was to conform to the applicable material standards mentioned in sub-
articles 1003.0 through 1011.0 (C26-1002.1).  If such computations as prescribed in these standards 
cannot be executed due to “practical difficulties,” the structural design can be deemed adequate if the 
member or assembly performs satisfactorily when subjected to load tests in accordance with 1002.4(a).  
Provisions to determine the adequacy of completed or partially completed structures are also provided. 
Prequalifying load tests (C26-1002.4(a)) can be used to establish the strength of a member or assembly 
prior to having such members or assemblies incorporated into a structure.  The test specimens are to be a 
true representation of the actual members or assemblies in all aspects, including the type and grade of 
material used. Support conditions for the members or assemblies being tested are to simulate the 
conditions of support in the building, except that conditions of partial fixity might be approximated by 
conditions of full or zero restraint, whichever produces a more severe stress condition in the member 
being tested. In regard to strength requirements, the member or assembly must be capable of supporting 
the following (note: no specific reference to a particular type of building material is given in this section 
of the Code): 

1.

 

Without visible damage (other than hairline cracks) its own weight plus a test load equal to 
150 percent of the design live load plus 150 percent of any dead load that will be added at the 
site, and 

2.

 

Without collapse its own weight plus a test load equal to 50 percent of its own weight plus 
250 percent of the design live load plus 250 percent of any dead load that will be added at the 
site. 

The latter loading is to remain in place for a minimum period of one week, and all loading conditions in 
Article 9 of the Code are to be considered. Exceptions to the above load conditions are also given in this 
section. 

The member or assembly is also subject to the following deflection requirements: the recovery of the 
deflection caused by the superimposed loads listed in item 1 above must be at least 75 percent. Also, the 
deflection under the design live load is limited to the values prescribed in C26-1001.5. 

                                                      

23

 A three-page calculation dated March 2, 1964 by E. Liu (Structural Engineer, the Port of New York Authority)  

(WTCI-408-LERA) 

background image

Chapter 5 

 

Draft for Public Comment 

72

 

NIST NCSTAR 1-1, WTC Investigation 

 

The Code also gives requirements for tests on models less than full size. The similitude, scaling, and 
validity of the analysis are to be attested to by an officer or principal of the firm or corporation making the 
analysis. The firm or corporation is to be approved by the Building Commissioner. 

5.2.1 Concrete 

Requirements 

According to sub-article 1004.0, design of reinforced concrete structural members was to conform to the 
requirements in that section and Reference Standard RS 10-3, which is the 1963 edition of 

Building Code 

Requirements for Reinforced Concrete

 (ACI 1963) with modifications, which was applicable to the 

design of WTC 1 and WTC 2.  These modifications include the replacement of the requirements of 
ACI 318 Secs. 902 (Design loads) and 903 (Resistance to wind, earthquake, and other forces) with the 
following: “Building code requirements for loads and infrequent stress conditions shall apply.”  
“Infrequent stress conditions” refer to such conditions as wind and earthquake.  In other words, all loads 
are to be determined in accordance with the 1968 Code.  In case of concrete structures designed by the 
ultimate strength design method, design (factored) loads are to be determined in accordance with 
Sec. 1506 of ACI 318-63. 

According to the specifications for WTC 7 (WTC 7 Project Specifications 1984), the 1983 edition of 
ACI 318 was applicable (ACI 1983). 

5.2.2 Steel 

Requirements 

Design of steel structural members was to conform to the requirements in sub-article 1005.0 and 
Reference Standard RS 10-5, which is the 1963 edition of 

Specification for the Design, Fabrication, and 

Erection of Structural Steel for Buildings 

(AISC 1963b) with modifications, which was applicable to the 

design of WTC 1 and WTC 2.  Similar to the design of reinforced concrete members, the NYC Building 
Code replaced the provisions of Sec. 1.3 (Loads and Forces) of the AISC Specification with a statement: 
“The provisions of the building code for loads shall apply.”  Other notable modifications to the AISC 
Specification are: 

 

The following paragraph is added to the definition of composite construction in Sec. 1.11.1: 
“Concrete materials shall meet the applicable requirements of the building code.  Where 
concrete having a unit weight less than 130 pcf is used, the capacity of the shear connectors to 
resist applied load under the proposed conditions of use shall be investigated…” 

 

Sec. 1.25.5 on field connections during erection is deleted and replaced with the following: 
“…No holes, copes or cuts of any type shall be made to facilitate erection unless specifically 
shown on the shop drawings or authorized in writing by the party or parties designated for 
inspection of such work.” 

The 1968 NYC Building Code requires that Reference Standards RS 10-6 and 10-7 be used for light 
gauge cold formed steel and open web steel joists, respectively (see 

Comparison of Building Regulatory 

and Code Requirements for WTC 1, 2, and 7

 [NIST NCSTAR 1-1B]). 

According to the specifications for WTC 7 (WTC 7 Project Specifications 1984), the 1978 edition of the 
AISC Specification was applicable (AISC 1978). 

background image

Draft for Public Comment 

 

Structural Design of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

73

 

5.2.3 

Methods Used to Proportion Structural Members 

The general methods that were used to proportion the structural members and components of the 
buildings are given in detail in Sec. 2.3 of NIST NCSTAR 1-1A.  Since the 1968 NYC Building Code 
adopted the 1963 AISC Specification and the 1963 ACI 318, all steel members were designed following 
the allowable stress design procedure, and the concrete sections were proportioned following the ultimate 
strength design procedure (see Sec. 4.3.1).  

background image

Chapter 5 

 

Draft for Public Comment 

74

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–1.  Design dead load criteria for WTC 1 and WTC 2: floor inside of core. 

background image

Draft for Public Comment 

 

Structural Design of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

75

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–2.  Design partition load criteria for WTC 1 and WTC 2: floor inside of core. 

background image

Chapter 5 

 

Draft for Public Comment 

76

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–3.  Design dead load criteria for WTC 1 and WTC 2: floor outside of core. 

background image

Draft for Public Comment 

 

Structural Design of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

77

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–4.  Design load criteria for WTC 7. 

background image

Chapter 5 

 

Draft for Public Comment 

78

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–5.  Design live-load criteria for WTC 1 and WTC 2: floor inside of core. 

background image

Draft for Public Comment 

 

Structural Design of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

79

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–6.  Design live-load criteria for WTC 1 and WTC 2: floor inside of core. 

background image

Chapter 5 

 

Draft for Public Comment 

80

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–7.  Design live-load criteria for WTC 1 and WTC 2: column inside of core. 

background image

Draft for Public Comment 

 

Structural Design of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

81

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–8.  Design live-load criteria for WTC 1 and WTC 2: floor outside of core. 

background image

Chapter 5 

 

Draft for Public Comment 

82

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–9.  Design live-load criteria for WTC 1 and WTC 2: column outside of core. 

background image

Draft for Public Comment 

 

Structural Design of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

83

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–10.  Live-load reduction criteria for WTC 1 and WTC 2. 

background image

Chapter 5 

 

Draft for Public Comment 

84

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–11.  Live-load reduction criteria for floors inside of core, except for tenant areas. 

 

background image

Draft for Public Comment 

 

Structural Design of WTC 1, 2, and 7 

NIST NCSTAR 1-1, WTC Investigation 

85

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–12.  Live-load reduction criteria for floors inside of core, tenant areas. 

background image

Chapter 5 

 

Draft for Public Comment 

86

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 5–13.  Live-load reduction criteria for floors outside of core. 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

87

 

Chapter 6 

I

NNOVATIVE 

F

EATURES 

I

NCORPORATED IN 

S

TRUCTURAL 

D

ESIGN

 

6.1 INNOVATIVE 

FEATURES 

A number of innovative features, which were applied to the design of a super high-rise steel building for 
the first time, were incorporated in the structural design of World Trade Center (WTC) 1 and WTC 2.  
They were incorporated in both the lateral-load-resisting system and the gravity-load-carrying system. 

These features include the following: 

 

Application of the framed-tube system to resist lateral loads. 

 

Uniform exterior column geometry (14 in. by 14 in. cross-section) was maintained over most 
of the height of the 110-story buildings by using 12 different grades of steel. 

 

Use of deep spandrel plates as beam elements connecting perimeter columns. 

 

Use of long-span composite steel trusses for the floor system to develop diaphragm action in 
super tall buildings and to develop composite action by extending truss diagonals into the 
concrete slab. 

 

Application of sprayed fire resistive materials on open-web steel trusses for fire protection.  

 

Application of viscoelastic dampers connecting the floor trusses to the perimeter framed tube 
system to control dynamic response. 

 

Use of wind tunnel test data to establish the wind loads used in the design of the towers. 

Several prominent features are described below in detail. 

6.2 LATERAL-LOAD-RESISTING 

SYSTEM 

The structural design of high-rise buildings (over 40 stories) is usually controlled by lateral loads.  It is 
well known that for high-rise buildings, the most efficient way to resist lateral loads is by mobilizing the 
exterior framing system.  As described in Sec. 2.2.2, the lateral-load-resisting system of WTC 1 and 
WTC 2 used the framed-tube concept wherein the lateral loads are resisted by the exterior frames.  A 
framed-tube system does not depend on shear walls or other bracing systems to resist lateral loads.  
Typically, the exterior wall is comprised of moment resisting frames with closely spaced columns and 
deep spandrel beams to form a Vierendeel-truss-type structural form.  

In the United States, the first application of a framed-tube system was the 43-story DeWitt-Chestnut 
apartment building (later renamed The Plaza on DeWitt) in Chicago, which was completed in 1965.  This 
building used reinforced concrete for the structural framing system.  Since then, many variations of this 

background image

Chapter 6 

 

Draft for Public Comment 

88

 

NIST NCSTAR 1-1, WTC Investigation 

 

structural system have been used in a number of buildings.  WTC 1 and WTC 2 were the first super high-
rise steel buildings that were designed using the framed-tube concept.  

The framed-tube system of WTC 1 and WTC 2 was comprised of closely spaced steel columns that were 
connected by deep spandrel plates.  To assess the stiffness characteristics of the wall panel, a series of 
model tests using one-quarter scale models made of thermoplastics were carried out prior to final design 
of the frame-tube system (Gardner 1966).  The model tests allowed the evaluation of changes in the 
overall stiffness of the wall panels as the sizes of the members that made up the wall panels varied, which 
included columns, spandrels, and stiffeners. The results of the model tests guided the design of the wall 
panels. Detailed descriptions of the tests are given in NIST NCSTAR 1-1A. 

The columns and spandrels were shop-assembled and welded into 36 ft high by 10 ft wide panels, which 
consisted of three columns and three spandrels as shown in Fig. 2–9.  These panels were erected on site 
by bolting the base plate of an upper column to a cap plate of a lower column (see Fig. 2–10).  Such 
splices were staggered so that only one-third of the panels were spliced at each story level, except at the 
base of the building and at the mechanical floors where all of the panels were spliced at the same level. In 
such cases, supplemental welds were employed to improve connection capacity.  Spandrels were 
connected at midspan with high-strength bolted shear connections. 

6.3 

COMPOSITE FLOOR SYSTEM 

As described in Sec. 2.2.2, outside of the central core area, floor construction of WTC 1 and WTC 2 
typically consisted of 4 in. of lightweight concrete on fluted metal deck supported by a series of 
composite floor trusses that spanned between the core and the exterior walls.  The floor trusses consisted 
of double angles that were used for the top and bottom chords and round bars that were used for the 
diagonals.  What made the floor system in WTC 1 and WTC 2 innovative was that (1) use of the 
lightweight composite floor system, comprised of lightweight concrete slab on long-span open-web steel 
trusses, to provide lateral stability of columns and diaphragm action in super tall buildings, 
(2) development of composite action by extending truss diagonals into the concrete slab (see Fig. 2–14), 
and (3) application of sprayed fire resistive materials on open-web steel trusses for fire protection (For 
detailed description, see NIST NCSTAR 1-6B).  

The first recorded tests on composite open-web steel joists were conducted under a project jointly 
sponsored by Granco Steel Products and Laclede Steel Company (who manufactured the trusses for 
WTC 1 and WTC 2) in September 1964.

24

  In this study, the overall performance of non-composite joists 

was compared with composite joists.  The joists were manufactured with their webs projecting above the 
top chord.  The tests revealed that the composite joists had greater moment capacities and smaller 
deflections than the non-composite joists. 

Since composite action was achieved by the “knuckle” functioning as a shear connector, a test program 
was carried out by Laclede Steel Company to determine the failure loads of the shear knuckles.  The shear 
knuckle tests are described in detail in NIST NCSTAR 1-1A.  The test results indicated that shear 
strengths of the knuckles were found to be well over the allowable values used in the design of the 
composite trusses. 

                                                      

24

 See Sec. 1.1 of Sen and Galambos (1968). 

background image

Draft for Public Comment 

 

Innovative Features Incorporated in Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

89

 

Additional tests on open-web joists were performed at Washington University (Tide and Galambos 1968).  
The findings, which were reported in February of 1968, were similar to those reported from the previous 
tests.  In particular, the specimens with extended web diagonals into the concrete slab serving as shear 
connectors were shown to be strong and stiff, and failure was due to crushing of the concrete near the 
connectors.  Further tests conducted at Washington University are reported in Sen and Galambos (1968).  
In summary, the findings from this study confirmed those obtained from earlier research programs. 

The composite floor trusses used in the WTC towers were similar to those that were tested only in the 
sense that the webs were used as shear connectors.  Other than that, they were different in all other 
aspects, including member sizes and overall lengths.  It may have been the first time that this type of floor 
construction was used in a high-rise building, especially of this size. 

6.4 

VISCOELASTIC DAMPING UNITS 

Viscoelastic damping units were used in the structural system of WTC 1 and WTC 2 to supplement the 
tubular steel frame in limiting wind-induced building oscillations.  According to Mahmoodi (1987), “The 
selection, quantity, shape, and location of the dampers was based on the dynamic analysis of the towers 
(computer modeling, wind tunnel, etc.) and of the damping required to achieve performance standards.”  
This may have been the first application of damping units for this purpose in tall building structures, and 
would certainly qualify it as an innovative system at that time. 

The damping units were uniformly distributed throughout both of the buildings.  One hundred four (104) 
dampers were used on each floor from the 7th to the 107th floor.  The planned locations of damping units 
on the various floors of the buildings are contained in structural drawings D-AB1-2 through D-AB1-14.2 
(WSHJ 1967).  As the buildings oscillated from the wind, part of the energy of oscillation was dissipated 
by shear deformations in the viscoelastic part of the damping units. 

Two testing programs were carried out to test the effectiveness and efficiency of the damping units in 
controlling building motion due to wind.  The Minnesota Mining and Manufacturing Company (3M) 
conducted the first set of tests in May of 1967.

25

  The Massachusetts Institute of Technology (MIT) 

conducted the second test program during 1968 and 1969.

26

  These tests included variations in 

(1) amplitude and frequency of the applied cyclic axial deformation, (2) ambient temperature, and (3) a 
static preload superimposed on the simple harmonic loading.  In general, it was found that “…the energy 
absorbing capabilities of the elements are generally adequate to provide the expected damping under 
design conditions and that the elements do perform satisfactorily under limited variations of loading 
conditions, speed of oscillation, duration of oscillation, and ambient temperature.”  Detailed descriptions 
of these tests are given in NIST NCSTAR 1-1A. 

Two different types of damping units were used in WTC 1 and WTC 2.  Type A damping units were used 
on floors with trusses spanning between the core and the outside wall, and were located between the 
bottom chords of the floor trusses and the columns of the outside wall (Fig. 2–16).  Type B damping units 
were used on floors that had wide-flange beams spanning between the core and the outside walls (i.e., 

                                                      

25

 Letter dated June 22, 1967 and enclosure from Don Caldwell of 3M to Peter Chen of SHCR (WTCI-501-L;see Appendix B of 

NIST NCSTAR 1-1A without appendixes that are contained in WTCI-501-L). 

26

 “Test Program for World Trade Center Viscoelastic Damping Units,” by Stephen H. Crandall of MIT, May 20, 1968 (WTCI-

501-L, see Appendix B of NIST NCSTAR 1-1A). 

background image

Chapter 6 

 

Draft for Public Comment 

90

 

NIST NCSTAR 1-1, WTC Investigation 

 

floors 7, 9, 41, 43, 75, 77, and 107).  This type of damping unit was located between the bottom flanges 
of the floor beams and the outside wall, as shown in Fig. 6–1.  The use of dampers increased significantly 
the critical damping ratio of the towers.  The reduction of oscillation during strong winds was estimated to 
be about 12 percent of the amplitudes without dampers.  Expected time period during which building 
oscillation might be perceived by the occupants was estimated to be reduced by about 34 percent 
(SHCR 1967). 

Type B damping units were slightly longer than Type A damping units.  Also, the connections between 
Type A damping units and the floor trusses were different than those between Type B damping units and 
the wide-flange beams.  Sheet DA-3 in the structural drawings shows specific details for each type of 
damping unit (WSHJ 1967). 

Worthington, Skilling, Helle & Jackson (WSHJ) initially inquired about different types of viscoelastic 
damping materials in a letter to 3M in 1964.

27

 A follow-up letter from them to 3M contained the physical 

and mechanical properties required for the viscoelastic material, based on calculations they had 
performed.

28

  Additional correspondence on various aspects of the damping units, including the results of 

tests that were run at 3M that measured the properties of the damper material and the strength of an 
assembled damping unit prototype, was exchanged subsequent to these letters.  In particular, it was noted 
that testing of an assembled truss damping unit by 3M was completed and that the results agreed with the 
theoretical predictions.

29

 

6.5 

WIND TUNNEL TESTS 

Wind tunnel tests were part of an overall wind program that was developed by WSHJ for the design of the 
WTC (WSHJ 1964).  Details of the wind program are given in NIST NCSTAR 1-1A.  Briefly, the 
program consisted of four parts: 

 

Meteorological Program

 was to determine the mean wind speeds, the return periods, the 

magnitude of wind shear and gradient, the directional characteristics of the wind, and the 
energy spectra of wind gusts that were expected at the site of the WTC. 

 

Wind Tunnel Program

 was to (a) develop a physical model of lower Manhattan and subject 

the model to wind velocities obtained from the meteorological program, (b) obtain static and 
dynamic responses of the WTC towers, (c) study construction problems, and (d) study the 
effect of the structural parameters on the integrity of the towers. 

 

Structure Damping Program 

was to determine the critical damping ratio of the structural 

system and to determine ways of increasing this ratio. 

                                                      

27

 Letter dated July 16, 1964 from Alan G. Davenport of WSHJ to Carl A. Dahlquist of 3M (WTCI-450-L; see NIST 

NCSTAR 1-1A, Appendix D). 

28

 Letter dated November 23, 1964 from Richard D. Steyert of WSHJ to Carl A. Dahlquist of 3M (WTCI-450-L; see NIST 

NCSTAR 1-1A, Appendix D). 

29

 Internal correspondence dated February 1966 by Richard D. Steyert of WSHJ (WTCI-450-L; see NIST NCSTAR 1-1A, 

Appendix D). 

background image

Draft for Public Comment 

 

Innovative Features Incorporated in Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

91

 

 

Physiological Program 

was to determine acceptable levels of response to wind-induced 

excitations as measured by perception levels of a cross-section of the population. 

Wind tunnel tests were conducted at Colorado State University (CSU) and the National Physical 
Laboratory (NPL), located in Teddington, Middlesex, United Kingdom (WSHJ 1964).  Tests were 
conducted on single-tower and twin-tower configurations subject to uniform and turbulent flow 
conditions. 

6.5.1 

Tests Conducted at CSU 

Over 2,000 tests were conducted at the CSU Microclimatological Wind Tunnel to study the behavior of 
static and aeroelastic models (WSHJ 1964).  One of the most important requirements in the modeling 
process was to achieve correct simulation of the wind velocity profile (considering both surface roughness 
and its influence on wind velocity with respect to height) as it approached the model of lower Manhattan. 
From the southeast direction, wind traveled across Brooklyn to the site of the WTC, which was a 
relatively rough urban area. From the southwest, wind traveled mainly across open water.  

Aside from wind velocity, the principal variables in the wind tunnel tests were the following: 

 

Spacing of towers 

 

Number of towers 

 

Damping 

 

Wind direction 

 

Boundary layer characteristics 

 

Relative stiffnesses of the models 

It was found that the models oscillated in the wind due to vortex shedding, gust buffeting, and wake 
buffeting under certain combinations of the variables listed above. 

Two hundred tests were run at CSU to study the effect of tower spacing on the response of the buildings. 
It was concluded that the “as planned” spacing was satisfactory. 

Aeroelastic tests and measurements of steady pressure for single-tower and twin-tower configurations in 
uniform flow provided a comparison between the performance of the models at CSU and at the NPL. The 
CSU report concluded that the aeroelastic tests at the two locations were in good qualitative and 
quantitative agreement (WSHJ 1965c). Models used for the pressure tests at the CSU were constructed of 
clear acrylic plastic at a scale of 1/500, the same scale used in the aeroelastic tests 

The aeroelastic tests were designed to determine the predominant sway motion (i.e., deflections or 
amplitudes) of the towers and to provide a check of the steady-state component of the overturning 
moment at the base. To determine the pressure distribution on the towers, tests were conducted using 
models with pressure points along a regular grid. From these tests, shear forces and overturning moments 
were obtained along the height of the towers. 

background image

Chapter 6 

 

Draft for Public Comment 

92

 

NIST NCSTAR 1-1, WTC Investigation 

 

The tests also indicated that large lateral deflections at the top of the building occurred for wind velocities 
in the range of 125 mph to 130 mph for angles of incidence within approximately 10 degrees of normal 
(see Fig. 6–2).  The results are plotted in Figs. 19 and 20 in WSHJ (1965c). The deflections showed a 
consistent dependence on the degree of damping and were shown to be inversely proportional to the 
damping ratio. 

Tests were also conducted at CSU using the southeast and southwest models of lower Manhattan 
subjected to turbulent flow conditions (WSHJ 1966c).

30

  Both single-tower and twin-tower configurations 

were considered. Definition of the grid system and tower configurations used in the tests is illustrated in 
Fig. 6–3.  Also shown in the figure are the experimentally determined fundamental frequencies of the 
towers in the two principal directions in cycles per second (cps).  Included in these tests were 
measurements of the maximum deflections at the tops of the towers (aeroelastic tests; wood models) and 
pressures along the height of the towers (thermoplastic models). 

Similar to the other tests described above, test results for the single-tower model indicated that the most 
severe oscillations were transverse to the wind and occurred with the wind blowing within a small range 
of angles on either side of the normal to a face. The results also showed that an increase in turbulence, 
which was characteristic of the southeast model of lower Manhattan, appeared to suppress vortex 
shedding but gave rise to turbulence excitation with increased wind speed. Finally, it was observed that 
greater levels of damping reduced the dynamic response of the single tower in all cases, more so in 
uniform flow conditions than in turbulent conditions. 

Based on the results obtained from the twin-tower wind tunnel tests, it was concluded that the response of 
the WTC towers was governed by three aerodynamic factors: (1) Magnitude of the effective turbulence 
forces induced by the wind flow, (2) Magnitude of the effective forces induced by vortex shedding and 
turbulence in the structure’s own wake, and (3) Effective aerodynamic damping and coupling forces 
generated by the motion of the tower through the airflow. It was also noted that the effective mass, the 
effective stiffness, the mode of vibration, and the mechanical damping of the towers influenced these 
factors (WSHJ 1966). 

A theoretical method was derived and was used to predict the dynamic behavior of the towers 
(WSHJ 1966c). Results from the theoretical models were compared to the results from the wind tunnel 
tests. A comprehensive discussion on this comparison can be found in WSHJ (1966c). 

The results from the wind tunnel tests were used in the design of the exterior columns and spandrels, 
which is discussed in Sec. 2.3.2 of this report. 

The extensive wind tunnel testing that was performed to establish the lateral wind loads used in the design 
of WTC 1 and WTC 2 was state-of-the-art at that time. 

                                                      

30

 The meteorological program found that winds were stronger from westerly and northerly quadrants.  Wind from the southeast 

direction was chosen in the wind tunnel program not because the velocity from this direction was the greatest, but because 
winds from this direction were the most turbulent (wind in this direction traveled over Brooklyn, which is a relatively rough 
urban terrain).  Turbulence plays an important part in the dynamic excitation of structures, especially tall, slender structures.  A 
fundamental discussion on turbulence and resulting aeroelastic phenomena can be found in Simiu and Scanlon (1996). 

background image

Draft for Public Comment 

 

Innovative Features Incorporated in Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

93

 

6.5.2 

Tests Conducted at NPL 

Tests were performed on single-tower and twin-tower models at NPL to measure deflections at the tops of 
the towers in both smooth (uniform) flow and turbulent flow conditions (Whitbread and Scruton 1965). 
The models were constructed of light timber framework supported on diaphragms at 6 in. intervals from a 
central 2 in. diameter aluminum tube. The models had an external covering of plywood. 

Principal differences between the CSU and NPL models were (WSHJ 1965c): (1) the model scale was 
1/400 at the NPL compared to 1/500 at the CSU, (2) displacements were determined from output of 
accelerometers mounted near the tops of the models at NPL compared with strain gauges at CSU, and 
(3) displacements were recorded on a resetting digital voltmeter at the NPL compared with chart records 
at CSU. In the NPL tests, a grid of tubes in a plane normal to the wind stream was used to provide the 
required velocity profile over the height of the model. According to Whitbread and Scruton (1965), the 
velocity profile achieved in this manner was similar to that observed in the tests carried out at CSU on the 
model of lower Manhattan. 

As noted previously, WSHJ reported that the overall results obtained from the tests conducted at NPL 
were in good qualitative and quantitative agreement with those obtained from the tests performed at CSU. 

 

 

background image

Chapter 6 

 

Draft for Public Comment 

94

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

 

 

 

 

 

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 6–1.  Wide-flange beam member with Type B damping unit. 

 

 

 

background image

Draft for Public Comment 

 

Innovative Features Incorporated in Structural Design 

NIST NCSTAR 1-1, WTC Investigation 

95

 

 

Source:

 WSHJ 1965c.  Reproduced with permission of The Port Authority of New York and 

New Jersey. 

Figure 6–2.  Wind directions that produced the greatest displacements at the top of the 

tower during the wind tunnel tests. 

 

 

background image

Chapter 6 

 

Draft for Public Comment 

96

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Source: 

WSHJ 1966c. Reproduced with permission of The Port Authority of New York and New Jersey. 

Figure 6–3.  Definition of grid system and tower configurations for wind tunnel tests at 

Colorado State University. 

 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

97

 

Chapter 7 

F

ABRICATION AND 

C

ONSTRUCTION 

I

NSPECTIONS AND 

 

V

ARIANCES

 

7.1 INTRODUCTION 

The contract documents for World Trade Center (WTC) 1 and WTC 2 between Port Authority of New 
York and New Jersey (PANYNJ or Port Authority) and the steel fabricators and erector, and the 
construction contract specifications for WTC 7, indicate that inspection programs were instituted at the 
steel fabrication sites.  For WTC 1 and WTC 2, the documents reviewed revealed that the inspection 
requirements were part of the contract.  For WTC 7, the project specifications list inspection 
requirements. The records of inspections for both the WTC 1 and WTC 2 and the WTC 7 projects were 
not available to the investigation.  According to PANYNJ, the records for WTC 1 and WTC 2, which 
were kept in WTC 1, were destroyed, and the records for WTC 7 were discarded by the general contractor 
after retaining them for 7 years.  In this section, the inspection requirements for WTC 1 and WTC 2 and 
for WTC 7 are described briefly.  NIST NCSTAR 1-1A provides more detailed description of the 
inspection requirements. 

7.2 

FABRICATION INSPECTION REQUIREMENTS FOR WTC 1 AND WTC 2 

As described in Sec. 1.3, the Port of New York Authority (PONYA) instructed the consultants to comply 
with the second and third drafts of the 1968 New York City (NYC) Building Code for their designs of 
WTC 1 and WTC 2.  The Code contains provisions that govern the fabrication and inspection of materials 
used in buildings.  Thus, in general, the requirements in the specifications of the contracts with various 
steel fabricators were equivalent to those in the Code at a minimum.  However, in a number of cases, the 
contract specifications were more comprehensive and stringent than the corresponding provisions in the 
Code.  Section C26-1000.7, Material and Methods for Construction, of the Code refers to the 
requirements in Reference Standard RS 10-5, which is the 1963 American Institute of Steel Construction 
(AISC) 

Specification for the Design, Fabrication, and Erection of Structural Steel for Buildings

 

(AISC 1963).  The AISC Specification, Sec. 1.23 contained minimum fabrication requirements for the 
following: 

 

Straightening of materials 

 

Gas cutting 

 

Planing of edges 

 

Riveted and bolted construction – holes 

 

Riveted and high strength bolted construction – assembling 

 

Welded construction 

background image

Chapter 7 

 

Draft for Public Comment 

98

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Finishing 

 

Tolerances 

Specific inspection requirements during fabrication of various structural members were covered in the 
contract documents between PONYA and individual fabricators.  The individual contract documents 
which contain the inspection requirements during fabrication are found in appendixes of NIST 
NCSTAR 1-1A. 

Some salient features of the fabrication inspection requirements for different structural framing systems 
are presented below. 

7.2.1 Floor 

Trusses 

The contract between the PONYA and the Laclede Steel Company, the manufacture of the floor trusses, 
contained the specifications for fabrication, including welding of structural steel, and also a quality 
control and inspection program (see Appendix E of NIST NCSTAR 1-1A).  In addition to the quality 
control requirements for steel fabrication in the AISC Specification (AISC 1963), Chapter three of the 
contract included a list of specific requirements for inspection during fabrication, including: continual 
visual inspection and surveillance of the fabrication process of steel trusses by qualified contractor’s 
supervisory personnel; physical and nondestructive testing welding of truss panel points; and full-scale 
testing of completely fabricated steel truss components. 

7.2.2 

Box Core Columns and Built-Up Beams 

The contract between the PONYA and the Stanray Pacific Corporation contained the specifications for 
the box core columns and built-up beams from the 9th story to the roof.  The requirements for fabrication, 
including welding of structural steel, inspection, and quality control, were in the contract specification.  
Appendix E of NIST NCSTAR 1-1A addresses the applicable sections of the contract specifications and 
other quality control requirements in detail. 

In addition to the inspection requirements in the contract, special requirements were added for inspection, 
testing, coordination, and supervision by an independent testing agency at the fabrication plant before 
structural components left the fabrication yard.  These additional requirements were necessary because a 
major portion of the steel used for the core structural members was to be produced in Japan and 
England.

31

 The description of a comprehensive program for “supervision, coordination, inspection, and 

testing based on the use of the personnel and facilities of a local independent testing agency supervised by 
a resident engineer (a professional engineer employed full time by the structural engineer Skilling, Helle, 
Christiansen, & Robertson [SHCR])” was attached to the letter sent from Leslie Robertson of SHCR to 
Malcolm P. Levy of PONYA (see footnote 31). The scope of this program was two-fold: 

 

To provide the Port Authority assurance through adequate documentation that fabricated steel 
conformed to the contract documents and to ensure on-time delivery of fabricated steel. 

                                                      

31

 Letter dated June 5, 1967, from Leslie E. Robertson of SHCR to Malcolm P. Levy of PONYA (WTCI-491-L; see NIST 

NCSTAR 1-1A, Appendix E). 

background image

Draft for Public Comment 

 

Fabrication and Construction Inspections and Variances 

NIST NCSTAR 1-1, WTC Investigation 

99

 

 

To provide detailed inspection by checklist and by non-destructive testing prior to final 
acceptance of the members. 

The responsibilities of the resident engineer included the following items: 

 

Prior to fabrication, performing a complete study of the fabricator’s quality control 
procedures, proposed fabrication procedures, provisions for storage of incoming material, and 
provisions for loading and shipping of completed building components. 

 

Ensuring proper interpretation of the contract drawings and specifications. 

 

Directing the work performed by the independent testing agency and its inspectors. 

 

Performing surveillance of the quality of work on a continuous basis. 

The structural engineer (SHCR) also recommended that an independent testing agency be hired for mill 
inspection of Japanese steel.

32

  The main responsibility of the testing agency was to verify the accuracy of 

the certified mill testing reports by witnessing tests at the manufacturing mill. Procedures were 
established for witnessing the tests at both Stanray Pacific and Pacific Car & Foundry in the United 
States.  The Port Authority subsequently contracted with Superintendence Inc., an international inspection 
agency, who provided the mill inspections in both countries.

33

 

The Port Authority set forth requirements for the independent testing portion of the mill inspection 
program.

34

  The requirements, which were part of PONYA’s overall quality control program on fabricated 

steel for the WTC, depended on whether the steel was from a domestic source or from a foreign source.  
For steel obtained from domestic sources, the independent testing portion of the mill inspection program 
consisted of the following: 

 

For steel with yield points less than 50,000 psi, one tensile test and one check analysis on 
samples selected at random from 1 out of 10 heats. 

 

For steel with yield points of 50,000 psi and higher, one tensile test, one bend test, and a check 
analysis on samples selected at random from 1 out of 10 heats. 

For steel obtained from foreign sources: 

 

For steel with yield points less than 50,000 psi, one tensile test and one check analysis on 
samples selected at random from 1 out of 10 heats to be performed abroad.  In addition, one 
sample suitable for a tensile test from 1 out of 4 heats was to be shipped by the inspection 
agency to a laboratory in the United States for tensile testing and check analysis. 

                                                      

32

 Letter dated April 5, 1967 from Leslie E. Robertson of SHCR to Malcolm P. Levy of PONYA (WTCI-489-L; see NIST 

NCSTAR 1-1A, Appendix E). 

33

 Letter dated September 21, 1967 from R. M. Monti of PONYA to R. E. Morris of the Stanray Pacific Corporation 

(WTCI-490-L; see NIST NCSTAR 1-1A, Appendix E). 

34

 Letter dated November 13, 1967 from R. M. Monti of PONYA to R. E. Morris of Stanray Pacific Corp. (WTCI-498-L; see 

NIST NCSTAR 1-1A, Appendix E). 

background image

Chapter 7 

 

Draft for Public Comment 

100

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

For steel with yield points of 50,000 psi and higher, one tensile test, one bend test, and a check 
analysis on samples selected at random from 1 out of 10 heats to be performed abroad.  In 
addition, one set of samples suitable for machining into a tensile specimen and a bending 
specimen was to be selected at random from 1 out of 4 heats and shipped by the inspection 
agency to a laboratory in the United States for testing. 

The Port Authority paid special attention to the quality control of structural steel members fabricated 
using steels produced in Japan and England. 

7.2.3 

Exterior Columns from Elevation 363 ft to the 9th Floor Splice 

The Pittsburgh-Des Moines Steel Company (PDM) fabricated the column trees, as depicted in Fig 2–8, 
from elevation 363 ft to the 9th floor splice.  Per the contract specifications, PDM developed the 
procedures for quality control and welding (see Appendix E of NIST NCSTAR 1-1A).  The final draft of 
the quality control program was submitted to the PONYA on September 28, 1967, and was subsequently 
approved by SHCR. 

Different specifications were written by PDM for the different types of welds that were to be used in the 
manufacture of the column trees. These specifications were reviewed and approved by SHCR, and 
subsequently approved by the PONYA. 

The PONYA hired the Pittsburg Testing Laboratory, an independent inspection company, in 1967, for 
mill inspection at PDM’s suppliers’ plants and for fabrication inspection at PDM’s shop. 

7.2.4 

Exterior Columns Above the 9th floor Splice 

The contract between the PONYA and the Pacific Car & Foundry Co. (PCF) contains the specifications 
for the exterior walls (box columns and spandrel plates as shown in Figs. 2–9 and 2–11) from the 9th 
story splice to the roof.  Requirements for fabrication and welding of structural steel are in the 
specification, and inspection and quality control requirements are in Sec. 105 of the contract.  These 
requirements can be found in Appendix E of NIST NCSTAR 1-1A. 

The quality control and welding procedures were prepared by PCF, and subsequently reviewed by SHCR 
and approved the PONYA, subject to the following conditions: 

 

The first three full penetration spandrel butt welds performed by each new welding machine 
operator or welder was to be subjected to ultrasonic testing. 

 

Where a spandrel weld was rejected, all welds made by the same welder or welding machine 
were to be tested by the ultrasonic testing technique for the spandrel in question, as well as for 
the spandrels produced immediately before and after the subject spandrel. 

 

Approval of the Pacific Car & Foundry Co. quality control and testing program did not 
include approval of any welding process or procedure subject to American Welding Society 
qualification tests. 

background image

Draft for Public Comment 

 

Fabrication and Construction Inspections and Variances 

NIST NCSTAR 1-1, WTC Investigation 

101

 

 

Visual inspection was to be carried out by certified Pacific Car & Foundry Co. inspection 
personnel on 100 percent of all types of welds included in the work. 

Weekly inspection reports were submitted by the SHCR resident engineer at the Pacific Car & Foundry 
plant in Seattle, WA, to the SHCR home office in New York.

35

  These reports reference a test jig that was 

built by Pacific Car & Foundry. Fabricated wall panels were checked for compliance with required 
tolerances on the jig before they were approved for shipment. 

7.2.5 

Rolled Columns and Beams 

The contract between the PONYA and the Montague-Betts Company, Inc. contains the specifications for 
the rolled core columns, interior columns, louver wall struts, and rolled beams that were used in both 
towers.  Requirements for fabrication and welding of structural steel are in the specifications, and 
inspection and quality control requirements are in the contract.  These requirements can be found in 
Appendix E of NIST NCSTAR 1-1A.  

The quality control and testing program was part of the contract. In particular, the following specific 
points were to be included in the quality control program: 

 

Material received should be checked against the certified mill test reports for size, grade, heat 
number, and color code.  One copy of each certified mill report should be submitted to 
PONYA and SHCR. 

 

Overhangs, gross laminations, excessive slag inclusions, and similar defects should be defined 
and repair procedures for these defects should be outlined. 

 

Certification papers for each welder and welding machine operator should be submitted to 
PONYA and SHCR.  Welding procedures must be prepared and the fabricator must perform 
qualification tests where applicable.  All welds should receive 100 percent visual inspection. 
Non-destructive testing of welds needs to be described. 

 

The amount of periodic inspection of work in progress and the persons performing this 
inspection should be described.  The inspection of finished work should be documented in 
reports submitted to PONYA and SHCR. 

7.2.6 Other 

Requirements 

Where problems arose in the fabrication yards, particularly when it came to fabrication tolerances, 
specific requirements that addressed the specific problems were adopted.  The typical method used to 
remedy a problem was for the fabricator to submit a procedure for correction to the PONYA.  The 
procedure was subsequently accepted or rejected by SHCR, and final approval by the PONYA was 
contingent upon the fabricator satisfying the requirements set forth by SHCR.  These variances from the 
original specifications are presented in Chapter 8 of this report. 

                                                      

35

 Weekly inspection reports contained in WTCI-749-L. 

background image

Chapter 7 

 

Draft for Public Comment 

102

 

NIST NCSTAR 1-1, WTC Investigation 

 

7.3 

FABRICATION INSPECTION REQUIREMENTS FOR WTC 7 

No contract documents were available to review for the inspection requirements during fabrication of 
structural members for WTC 7. However, WTC 7 project specifications for structural steel referred to the 
following codes and standards for fabrication: 

 

New York City (NYC) Building Code (1968) 

 

Specification for the Design, Fabrication, and Erection of Structural Steel for Buildings, AISC 

 

Specifications for Structural Joints using ASTM International (ASTM) High Strength Bolts, 
ASTM A 141 Rivets, and ASTM A 307 Unfinished Bolts, Research Council on Riveted and 
Bolted Structural Joints 

 

Specifications for Structural Joints using ASTM A 325 or A 490 Bolts, AISC 

 

Code of Standard Practice

, AISC (except that the first sentence of Sec. 4, paragraph d shall 

not apply) 

 

Code of Arc and Gas Welding in Building Construction, AWS Standard Code D1.1, American 
Welding Society 

 

Steel Structures Painting Manual

, Vols. 1 and 2, Steel Structures Painting Council (SSPC) 

 

Handbook of Bolts, Nut and Rivet Standards, Industrial Fasteners Institute 

Structural steel was to be fabricated and assembled in the shop to the “greatest extent possible” according 
to these codes and standards. 

The project specification called for a separate contract for testing and inspection of fabrication including 
welding.  This contract was not available to the NIST investigation, and implementation of this contract 
could not be ascertained.  

7.4 

INSPECTION DURING CONSTRUCTION 

Construction of WTC 1 and WTC 2 was overseen and managed by the Tishman Realty & Construction 
Company (TRCC), acting as the construction manager.  In that role, TRCC as the general contractor 
coordinated the scheduling of the various activities required on the project, including the day-to-day 
construction activities at the site.  The Port Authority required that all correspondence pertaining to 
administration of a prime contractor’s contract, including contract changes, matters pertaining to field 
problems, job progress, and schedule be submitted to TRCC.

36

  Karl Koch Erecting Co. (KKE) performed 

structural steel erection (see NIST NCSTAR 1-1A).  As pointed out in Sec. 7.1, the record of construction 
and inspection were not available to the investigation.  However, construction inspection identified a 
number of problems during the erection of WTC 1 and WTC 2, such as material defects, damaged 

                                                      

36

 General instructions from Malcolm P. Levy of PONYA to prime contractors for WTC contracts [WTCI-239-P; see Appendix F 

of NIST NCSTAR 1-1A]. 

background image

Draft for Public Comment 

 

Fabrication and Construction Inspections and Variances 

NIST NCSTAR 1-1, WTC Investigation 

103

 

structural members, fabrication errors, and fabricated and field welding defects.  In a number of cases, the 
Port Authority granted construction variance and repair requests by the fabricators and the erector, and 
they are presented in Sec. 7.5. 

Although WTC 7 project specifications have general erection requirements for fasteners, anchor bolts, 
column bases, installation, and bracing, no inspection requirements during construction are given in the 
specifications.  Further, the records of construction and inspection documents were not available to the 
investigation. 

7.4.1 

Erection Marks and Marking System WTC 1 and WTC 2 

To facilitate steel erection, a marking system for structural steel in WTC 1 and WTC 2 was developed by 
the Port of New York Authority and Nassau Bridge Detailers.  The marking system was devised to 
identify following structural members: 

 

Exterior wall columns – below the first story splice 

 

Exterior wall columns – above the first story splice 

 

Core columns 

 

Louver wall struts 

 

Vertical bracings at exterior wall columns 

 

Vertical bracings at core columns 

 

Interior pipe posts and hangers 

 

Floor beams 

 

Horizontal bracings at exterior walls 

 

Prefabricated floor units 

 

Loose deck and loose power/telephone cells for beam-framed areas 

 

Anchor bars and anchor plates 

 

Shear studs  

 

Viscoelastic damping units 

 

Grillages, column base plates and anchor bolts 

This system was used by the fabricators to properly identify the different steel members/pieces that were 
used in the tower construction.  For detailed description of the marking system, see Appendix F of NIST 
NCSTAR 1-1A. 

background image

Chapter 7 

 

Draft for Public Comment 

104

 

NIST NCSTAR 1-1, WTC Investigation 

 

7.4.2 

Quality Control and Inspection Program for WTC 1 and WTC 2 

A quality control and inspection program was developed by Karl Koch Erecting Co., who performed 
structural steel erection work, submitted to the Port Authority for approval.  The quality control and 
inspection program included information on the following: 

 

Survey control 

 

Control of construction and erection loads 

 

Field welding 

 

Bolting of structural steel 

 

Control of stud welding operations 

 

Erection procedures 

 

Control of workmanship 

 

Control of erection tolerances 

 

As-built drawings 

 

Safety programs 

For detailed description of the inspection program, see Appendix F of NIST NCSTAR 1-1A.  Section 7.5 
cites a number of construction errors identified during construction inspection. 

7.5 VARIANCES 

GRANTED 

The WTC towers were very complex steel frame buildings.  The structural frames of the towers 
incorporated many beams, columns and trusses that were formed by welding steel plates.  During 
fabrication and erection of structural members, errors were noted by the steel fabricators and the erector.  
Such errors included mainly dimensional deviations of structural members from the design and 
fabrication drawings.  The PONYA was requested by the fabricators and the erector to approve variances 
to contract drawings and specifications.  

For variance requests, the following procedure was established by the PONYA. All variances resulting 
from difficulties encountered in complying with the contractual requirements for fabrication or erection 
were submitted by the fabricators or erector to the Office of the Construction Manager of PONYA.  
Variances were also requested when, in the opinion of a fabricator or erector, an alternative detail or 
procedure was warranted.  For expediency, such requests were usually submitted at the same time to the 
SHCR. 

Typically, the Office of the Construction Manager approved a variance after SHCR reviewed the details 
of the variance and recommended its approval.  In many cases, SHCR submitted alternative methods, 
which were incorporated into the variance. 

background image

Draft for Public Comment 

 

Fabrication and Construction Inspections and Variances 

NIST NCSTAR 1-1, WTC Investigation 

105

 

The variances that were granted may be categorized into the following groups: 

 

Fabrication/erection tolerances 

 

Defective (cracked, laminated, misfit) components 

 

Fabricator/erector-preferred procedure 

 

Material substitutions 

 

Frequency/rate of weld inspections 

Listed below are types of variances granted by PONYA for each of the above categories.  NIST 
NCSTAR 1-1A gives a detailed listing of fabrication and erection related variance requests by fabricators 
and the erector. 

7.5.1 

Variances Relating to Fabrication and Erection Tolerances 

The following is a list of approved variance requests for fabrication and erection of box beams, box 
columns, and floor trusses. 

 

Flange offset of 3/16 in. instead of 1/8 in. from the web for box-column sections fabricated by 
Stanray Pacific Corporation. 

 

Out-of-square tolerances of box beams and a maximum twist of box columns by Mosher Steel 
Company. 

 

Greater depth of the floor truss end bearing of 20 trusses (4.5 in. vs. specified 4 in.) by 
Laclede Steel Company. 

 

Field modification procedures for vertical struts of floor trusses to meet erection tolerances by 
Karl Koch Erecting Company. 

 

Change of fabrication tolerances of floor trusses by Laclede Steel Company. 

 

Fabrication modifications of floor trusses to avoid erection difficulties to Laclede Steel 
Company by the PONYA. 

7.5.2 

Variances Relating to Defective Components 

The following is a list of specific requests relating to variances for defective components of column trees 
and floor trusses. 

 

Fabrication error for truss connectors that were 1/4 in. narrower than the required width by 
Laclede Steel Company. 

background image

Chapter 7 

 

Draft for Public Comment 

106

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Fabrication errors of placing filler plate at incorrect locations at the bearing end of floor 
trusses by Laclede Steel Company. These errors were approved by the inspection company 
Pittsburgh Testing Laboratory subject to approval by SHCR. 

 

Repair procedures to correct fabrication errors by Laclede Steel Company. 

 

Repair procedure to correct laminations in column trees by Pittsburgh-Des Moines Steel 
Company. 

 

Repair procedure to correct cracks that developed in a number of column trees by Pittsburgh-
Des Moines Steel Company. 

 

Repair procedure to correct fabrication errors by adding back up plates by Pittsburgh-Des 
Moines Steel Company. 

 

Repair procedure for butt welds in column trees by Pittsburgh-Des Moines Steel Company. 

7.5.3 

Variances Relating to Alternate Fabrication and Erection Procedures 

The following is a list of specific requests relating to variances for alternate fabrication and erection 
procedures of core columns, floor trusses, exterior wall columns, and beam seats. 

 

Deviation of weld splice location of core columns from the contract drawings by Stanray 
Pacific Corporation. 

 

Use of Hobart automatic arc welding equipment to expedite welding process by Laclede Steel 
Company. 

 

Elimination of clipped corners of stiffener plates in the exterior wall columns by Pacific Car & 
Foundry. 

 

Substitution of different beam seat angles of (8 by 6 by 7/8) in. with (8 by 6 by 1) in. angles 
by Pacific Car & Foundry. 

7.5.4 

Variances Relating to Product Substitutions 

The following is a list of specific requests relating to variances for product substitutions in the exterior 
wall. 

 

Substitution of different steel plates with yield strengths ranging from 42 ksi to 100 ksi for 
specific plates that were originally specified for use in the exterior wall by Pacific Car & 
Foundry. 

 

Substitution of 3/4 in. thick plates for 5/8 in. and ½ in. thick plates by Pittsburgh-Des Moines 
Steel Company. 

 

Substitution of ASTM A36 steel with ASTM A 441 modified steel by Pittsburgh-Des Moines 
Steel Company. 

background image

Draft for Public Comment 

 

Fabrication and Construction Inspections and Variances 

NIST NCSTAR 1-1, WTC Investigation 

107

 

7.5.5 

Variances Relating to Inspection Practice 

The following is a list of specific requests relating to variances in inspection practice for the exterior wall 
and welds. 

 

Modifications to radiographic inspection procedures for butt-weld joints by Pittsburgh-Des 
Moines Steel Company was not approved. Instead, SHCR suggested an alternate program to 
be followed. 

 

Revision to the quality control program with respect to the minimum inspection rate for welds 
by Stanray Pacific Corporation 

background image

Chapter 7 

 

Draft for Public Comment 

108

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

This page intentionally left blank. 

 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

109

 

Chapter 8 

S

TRUCTURAL 

M

AINTENANCE AND 

M

ODIFICATIONS DURING 

O

CCUPANCY

 

8.1 INTRODUCTION 

Both architectural and structural modifications were made to meet the occupancy needs of individual 
tenants throughout the history of occupancy of the World Trade Center (WTC) 1, 2, and 7.

37

  Examples of 

modifications include openings cut in existing floors to construct new stairways linking two or more 
floors, and reinforcement of floor framing members to accommodate heavy loads imposed by tenants.  
All modifications were reviewed by the Port of New York Authority (PONYA), later called the Port 
Authority of New York and New Jersey (PANYNJ), to maintain structural integrity of the buildings and 
to ensure that modifications were compatible with existing building conditions.  In order to guide tenants 
in their modification process, the PONYA issued 

Tenant Alteration Review Manual 

(PONYA 1971).  

This manual was first issued in 1971 soon after the first tenant occupied WTC 1 in December 1970, and 
subsequently updated periodically through 1997.  

In anticipation of structural degradation, in 1986, the PANYNJ issued the 

Standard for Structural 

Integrity Inspection of the World Trade Center Towers A & B 

(PANYNJ 1986) to guide periodical 

inspection of structural members. Deteriorated and damaged members were identified for repair.  The 
standard was used by consultants who were retained by PANYNJ for systematic examination of WTC 1 
and WTC 2. 

In 1998, the PANYNJ issued the 

Standards for Architectural and Structural Design 

(PANYNJ 1998) for 

modification works.  The standards included not only the design guide, but also included specifications 
and standard details to be used in modification works.  Tenants proposing any modifications were 
required to follow the requirement specified in the standards.  

In this chapter, the documents described above are presented, and significant modification and repairs to 
the structural systems of WTC 1, 2, and 7 are summarized.  NIST NCSTAR 1-1C provides more detailed 
description of structural maintenance and modification during occupancy of WTC 1, 2, and 7. 

8.2 

TENANT CONSTRUCTION REVIEW MANUALS 

PONYA issued the first edition of the Tenant Construction Review Manual in 1971, shortly after the first 
tenants occupied WTC 1 in December 1970 and prior to initial occupancy of WTC 2 in January 1972. 
Subsequent editions were issued in 1979, 1984, 1990, and 1997. 

                                                      

37

 The manual and standards mentioned below and the records on structural modifications, inspection and maintenance presented 

in this chapter were made available to the NIST investigation by PANYNJ.  The 

Tenanat Alteration Review Manual, 

the 

Standard for Structural Integrity Inspection of the World Trade Center Towers A & B, and 

the 

Standard for Structural 

Integrity Inspection of the World Trade Center Towers A & B 

are given in Appendices A through F of NIST NCSTAR 1-1C. 

background image

Chapter 8 

 

Draft for Public Comment 

110

 

NIST NCSTAR 1-1, WTC Investigation 

 

The purpose of these manuals was to present the technical criteria, standards, and requirements that were 
to be followed by tenants that were planning construction work in any PONYA facility. The manuals 
included the criteria that were used by the Engineering Department of the Port Authority when reviewing 
proposed construction or alterations. Requirements were given for alterations and modifications to 
architectural, structural, geotechnical, civil, mechanical, plumbing, and fire protection systems. 

The General Requirements section of the manual required that all tenants submit an application form to 
the Port Authority outlining the scope of work, the design criteria, and the plans prior to construction. The 
design was to be performed by a registered architect or licensed professional engineer. Contractors were 
required to comply with all applicable provisions of federal, state, municipal, local, and departmental 
laws, ordinances, rules, regulations, and orders, except where stricter requirements were contained in the 
project specifications. 

8.2.1 1971 

Edition 

The 1971 edition of the Tenant Construction Review Manual (see footnote 37) requires that all structural 
modifications conform to the provisions of the 1968 New York City (NYC) Building Code.  Registered 
design professional were to submit structural calculations for review by PONYA.  The PONYA structural 
reviewer was responsible for the structural integrity of all walls and partitions.  Building frames were 
checked for stability and sidesway, including the effects of these on the columns. 

A comprehensive inspection program was implemented for all construction. Inspection was required 
during various phases of construction and was mainly to be performed in accordance with the 1968 NYC 
Building Code Sec. C26-106.3 (Materials, Assemblies, Forms and Methods of Construction; Inspection 
Requirements) and Sec. C26-107.3 (Service Equipment; Inspection Requirements). The architect, 
engineer, or other person who supervised the work was required by PONYA to be present at final 
inspection. 

8.2.2 1979 

Edition 

In the 1979 edition of the Tenant Construction Review Manual (see footnote 37), structural requirements 
were modified and expanded. Significant differences between the 1971 and 1979 editions were based on 
updates of the Structural Chapter of the 1968 NYC Building Code. These include:  

 

Rules and regulations relating to resistance to progressive collapse under extreme local loads. 

 

Rules and regulations for the design of composite construction with metal decks or 
lightweight concrete.  

 

Rules related to structural design based on electronic computer computations.  

 

Rules for application and protection of sprayed-on fireproofing (BSA Cal. #118-68-GR).

38

 

                                                      

38

 Denotes number of the New York City Board of Standards and Appeals (BSA) document. 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

111

 

 

Rules for arc and gas welding and oxygen cutting of steel covering the specifications for 
design, fabrication, and inspection of arc and gas welded steel structures and the qualification 
of welders and supervisors (BSA Cal. #1-38-SR). 

Significant updates to controlled inspection of materials, operations, and equipment include: 

 

Inspection requirements for proper use of admixtures for concrete. 

 

Deletion of the requirement for checking welders’ licenses or qualifications as this item was 
covered in the new rules and regulations relating to structural items. 

 

Acceptance of mill, manufacturers’, and suppliers’ inspection and test reports as evidence of 
compliance with the provisions of the Code for all structural materials and assemblies. 

 

Inspection of spray-on fireproofing since such inspection was added for the first time in 
C26-502.2(f) of the 1968 NYC Building Code in 1976 (Local Law 55). This new section of 
the code required that the installation of all sprayed-on fire protection of structural members, 
except those encased in concrete, be subject to the controlled inspection requirements of 
C26-106.3, which requires all materials designated for controlled inspection were to be 
inspected and/or tested to verify compliance with code requirements. All required inspections 
and tests were to be made and witnessed by or under the direct supervision of an architect or 
engineer who the owner retained and who was acceptable to the architect or engineer who 
prepared the plans. The architect or engineer was to file with the NYC Building Department 
signed copies of all inspection and test reports, together with a signed statement that the 
material and its use or incorporation into the building complied with code requirements.  

8.2.3 

1984 Edition, Revised 1990 

Except for some editorial changes, the requirements of the 1984 edition of the Tenant Construction 
Review Manual remained virtually the same as those of the 1979 edition. In the revised March 1990 
edition, requirements were added concerning the role of consultants working on the project who were not 
the architect or engineer of record. 

The scope of structural review of the alterations and/or modifications consisted of compliance with the 
applicable codes, standards, and design criteria given in the Structural Review section of the manual. In 
particular, the provisions of the then applicable New York City (NYC) Building Code were to be satisfied 
for work performed in New York City.  

The revised March 1990 edition (see footnote 37) of the manual included a requirement that all structures 
were to be designed for earthquake zone 2 forces in accordance with the BOCA (Building Officials Code 
Administrators, Inc.) code.  Local laws that contained seismic provisions more stringent than those in the 
BOCA code were to take precedence. Also, reference was made to ASTM International (ASTM) E 580, 
Standard Practice for Application of Ceiling Suspension Systems for Acoustical Tile and Lay-in Panels in 
Areas Requiring Moderate Seismic Restraint for lightweight ceilings to resist seismic forces. 

The Controlled Inspection section of the manual contained a comprehensive inspection program that was 
to be implemented for all construction.  Controlled inspection requirements were abstracted from the 

background image

Chapter 8 

 

Draft for Public Comment 

112

 

NIST NCSTAR 1-1, WTC Investigation 

 

NYC Building Code Secs. C26-106.3 and 107.3.  All materials, equipment, and construction designated 
by the Code for controlled inspection were required to be inspected and/or tested to verify compliance 
with the Code.  Controlled inspection was required to be made and witnessed by or under the direct 
supervision of a registered architect or professional engineer retained by the tenant and acceptable to the 
architect or engineer responsible for the plans.  

The inspection requirements were significantly reorganized and modified in the revised March 1990 
edition of the manual. Requirements for approval/acceptance of materials and controlled inspections were 
abstracted from the applicable sections of the NYC Building Code. 

8.2.4 1997 

Edition 

The requirements of the 1997 edition of the Tenant Construction Review Manual are essentially the same 
as those in previous editions of the manual.  The most notable change was related to earthquake design.  
The manual added horizontal force factors for overhead signs, anchorage for suspended ceilings weighing 
more than 4 psf, elevator and counterweight guardrails and supports, sprinkler piping, gas and high hazard 
piping, other piping, and heating, ventilation, and air conditioning (HVAC) ducts, along with new notes 
pertaining to sprinkler piping, other piping, and HVAC ducts.  These requirements were added to the 
manual to ensure that potential overhead hazards would not fall on building occupants during a seismic 
event. 

No significant changes were made to the inspection requirements from the 1990 edition of the manual.  

8.3 

STANDARDS FOR STRUCTURAL INTEGRITY INSPECTION OF THE WTC 
TOWERS 

To guide the PANYNJ in the evaluation of the structural integrity of the WTC towers, the Engineering 
Department of PANYNJ issued 

Standards for Structural Integrity Inspection of the World Trade Center 

Towers A & B

 (PANYNJ 1986)

39

 in 1986.  These standards were used to identify structural degradation, 

and to repair damaged structural members. 

Three methods were used to evaluate the structural integrity of the towers: (1) statistical inspections, 
(2) review of maintenance and tenant complaint reports, and (3) building movement and deformation 
measurements.  

In the first method, periodic visual inspection of selected structural components in “higher-potential 
trouble areas” was to be made initially by qualified outside consultants. The periodic inspections were to 
be supplemented by occasional visual inspections when the structure was exposed during tenant 
remodeling or general maintenance work. 

In the second method, various reports were to be examined by the Engineering Department of PANYNJ, 
which could possibly shed light on underlying structural problems.  Maintenance reports of non-structural 
repairs, water leakage, and tenant complaints about unusual building movements, vibration, or noise are 
examples of such reports. 

                                                      

39

 See Appendix E of NIST NCSTAR 1-1C for the complete document. 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

113

 

In the third method, the performance of systems within the buildings was to be evaluated by the 
Engineering Department through measurement of movement or deformation using appropriate tests and 
instruments.  Measurements were to be performed on individual components in the towers as well as on 
the entire towers themselves. 

8.3.1 Visual 

Inspections 

Since the visual inspection of the entire structure, or even a major portion of WTC 1 or WTC 2, was not 
practical, a statistical inspection program was implemented.  This approach involved sampling those 
components and systems that were important to structural integrity at locations with “a relatively higher 
potential for occurrence of defects or problems.” 

Visual inspection was to be supplemented by the use of simple hand tools, measurements, and recording 
techniques, as required.  Loose, cracked, or rust-stained spray-on fireproofing and concrete or masonry 
encasement covering structural steel members and connections was to be removed prior to examining the 
steel.  After inspection, any removed fireproofing had to be properly replaced.  Also, where it was 
necessary to drill a hole through a structural steel element to provide access for a borescope or any other 
device for inspection, the access hole was to be sealed with weld metal, body putty, or caulking, as 
appropriate. 

Periodic inspection of WTC 1 and WTC 2 was to be carried out on the following components at various 
time intervals: 

1.

 

TV antenna mast on the top of WTC 1.

  This program consisted of four parts: 

(a) inspection of the structural steel elements in the antenna, (b) inspection of the high tensile 
bolts and studs, (c) inspection of the weatherproof enclosure, and (4) inspection of the 
radomes. Inspection of these components was to be performed on a “continuing basis,” as 
weather and operational restrictions permitted. A complete inspection of the mast structure 
within the weatherproof enclosure was to be performed at least once a year; the other 
components were to be inspected at least once every 3 years. 

2.

 

Exterior roof and wall elements.

  Every year, the exterior roof and wall elements were to be 

inspected for signs of water intrusion. Roof leakage was to be ascertained from an 
examination of the spaces immediately below the roof areas. Wall leakage was to be 
determined from signs of water staining on interior finishes. 

3.

 

Room occupancies.  

An inspection of room occupancies and uses throughout both towers 

was to be performed on an annual basis to verify that design live load was not exceeded. 

4.

 

Accessible column envelopes, including fireproofing.

  Every 2nd year, accessible columns 

were to be inspected for bowing or deviation from plumb. Also, fireproofing was to be 
examined for signs of rust or cracking. Inspection for lateral displacement or rotation of 
columns in elevator shafts, where the columns were braced on only one axis by connecting 
beams or concrete slabs, was required. 

5.

 

Fireproofing and masonry partitions on diagonal bracing and transfer trusses.

  

Fireproofing and masonry partitions enclosing the diagonal bracing on exterior column lines 

background image

Chapter 8 

 

Draft for Public Comment 

114

 

NIST NCSTAR 1-1, WTC Investigation 

 

in both towers below the Service Level Floor and the transfer trusses below floor 1 in WTC 2 
under exterior and core columns were to be inspected every 2nd year for cracking, stains, and 
other possible signs of structural distress. 

6.

 

Hat truss members.

  Every 2nd year, the hat truss members between floor 107 and the roof 

in the core area were to be inspected.  

7.

 

Exterior box columns and spandrel plates.

  Exterior box columns and spandrel plates 

under column trees below floor 7 were to be inspected every 4th year.  Exterior aluminum 
covers and spray-on fireproofing were to be removed to gain access to the exterior surfaces of 
the box columns and spandrel plates.  Both the columns and plates were to be visually 
inspected for bowing or distortion, cracking, and corrosion.  Visual inspection was also 
required for accessible welds.  Ultrasonic testing of full or partial penetration welds and 
adjacent base metal was to be performed where base metal thickness exceeded 1.5 in. 

The interior of the box columns was to be examined by a borescope for the presence of water 
and the existence of rust on the interior plate surface.  This was to be accomplished by 
drilling an access hole in the column or the spandrel plate.  

The “tree” junction where the three superstructure columns merged was also to be inspected. 
The top surface of the horizontal diaphragm plate that capped the tapered box column just 
below the point where the three separate columns merged was to be examined, as was the 
exterior column plate between this location and the column splice at elevation +372 ft 4 in. 

8.

 

Steel floor framing over mechanical spaces.  

Every 4th year, the steel floor framing over 

mechanical spaces and other areas without suspended ceilings was to be inspected. 

9.

 

Concrete slabs, partitions, and finishes.  

Concrete slabs, partitions, and finishes were to be 

inspected every 4th year for signs of distress, which could indicate excessive structural 
deformation. 

Occasional inspections were also to be made of the structural steel framing, connections, and concrete 
slabs when general repairs or remodeling was done that involved removing ceilings, partitions, finishes, 
or other coverings.  In particular, the top of the concrete slab was to be examined for cracking, spalling, 
and exposed or corroded top reinforcement. Where reinforcing bars were corroded and where concrete 
had spalled, repairs were to be made as tenant relocation permitted. 

8.3.2 Review 

of 

Reports 

General maintenance reports and complaints from tenants were to be used to search for possible problems 
related to underlying structural defects. Water damage caused by leaks at the roof level or at the exterior 
walls, broken plumbing, and cracks in partitions or the concrete floor slab were to be reviewed to 
determine whether such events were caused by structural deformations. Records were to be kept of tenant 
complaints of building sway, floor vibration, sagging ceilings, unusual noise, and other items. Visual 
inspection of the appropriate area of the building was to be performed where a reasonable assessment of 
the data in the reports or logs was tied to a specific structural element or system. Reports and log data 
were to be correlated with testing and measurements. 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

115

 

8.3.3 Periodic 

Measurements 

Periodic measurements of various types of deformation and vibration were to be made by the Engineering 
Department of PANYNJ for the purposes of monitoring changes in certain important characteristics of the 
buildings.  Adverse changes in such measurements were assumed to reflect possible structural 
deterioration. 

Measurements of the following items were to be performed on a periodic basis: 

1.

 

Natural frequency of the towers.

  Accelerometers were to be used to measure natural 

frequencies of the towers on a monthly basis.  Wind speed and direction were also to be 
recorded at that time. 

Accelerometers were installed only in WTC 1. 

2.

 

Natural frequency of the TV mast on WTC 1.

  Accelerometers and amplifiers were to be 

installed within the heated enclosure of the TV mast on the top of WTC 1 at a level of about 
2/3 of the height of the mast above its base.  One accelerometer was to be oriented to measure 
N-S displacements, and one was to be oriented to measure E-W displacements.  Displacement 
measurements, as well as wind speed and direction, were to be recorded once a month. 

There is no evidence that accelerometers were installed on the TV mast. 

3.

 

Natural frequency of the floor construction.

  The natural frequency of the floor 

construction was to be measured when floor space had been emptied due to tenant change or 
remodeling.  The natural frequency and damping values of the floor structure were to be 
measured by performing a “heel drop” test.  In such tests, vibrations induced in the floor 
structure by a vertical impact were recorded using an accelerometer attached to the floor.  
Vibration measurements were also taken for an impact load of 100 lb dropped from 
approximately 6 in. above the floor slab on to a 1 in. thick neoprene pad. 

4.

 

Viscoelastic dampers.

  This program consisted of continuously measuring and recording the 

movements of WTC 1. Wind speed and direction were also to be measured. It was anticipated 
that such measurements would continue until the end of 1985 or longer, depending on 
available funds. 

Twelve viscoelastic damping units (four units from each of three floors) were to be removed 
from WTC 1 annually and were to be tested by the Minnesota Mining and Manufacturing 
Company (3M), who were the manufacturers of the damping units. Temperature effects and 
shear strength were to be tested. 

5.

 

Plumbness and level.

  Building plumbness and floor level checks were to be performed 

semiannually for each tower, preferably in the early morning hours in August when wind 
velocity was low and outside air temperatures were moderate. 

background image

Chapter 8 

 

Draft for Public Comment 

116

 

NIST NCSTAR 1-1, WTC Investigation 

 

Building plumbness was to be determined by measuring the offsets from a vertical laser 
beam, which was to be projected up from the bottom of freight elevator shaft 50, to the shaft 
walls. Offset measurements were to be taken at 20-story intervals. 

Floor levelness was to be determined by measuring the relative elevation of 16 benchmarks 
on the floor slab at floor 70 of each tower. 

8.3.4 Recordkeeping 

Standards for Structural Integrity Inspection

 lists the defects and signs of distress that were to be noted 

and recorded during inspection of the structural steel and the reinforced concrete.  Detailed descriptions of 
the defects and signs of distress are given in NIST NCSTAR 1-1C. 

In general, a description was to be made of the defect or indication of distress.  Measurements, sketches, 
and photographs were to be provided in those cases where a written description was not adequate.  The 
use of a tape recorder was also permitted. 

If defects that appeared to require more than routine attention were uncovered, a separate report of such 
findings was to be submitted to the Engineering Department, PANYNJ.  For conditions of a serious 
nature, immediate notification was to be made to the Engineering Department in person. 

Three categories of urgency were established for repairs.  Repairs falling into the “immediate” category 
included possible closure of the area and/or structure affected until interim remedial action (such as 
shoring or removal of a potentially unsafe element or structure) could be implemented.  Such action was 
to be undertaken immediately after discovery, and a description of the action taken and recommendations 
for permanent repair were to be included in the inspection report. 

The “priority” category was for those conditions where no immediate action was required, or for which 
immediate action had been completed, but for which further investigation, design, and implementation of 
interim or long-term repairs should be undertaken on a priority basis (i.e., taking precedence over all other 
scheduled work). 

Repairs falling into the “routine” or “non-priority” category could be undertaken as part of a scheduled 
major work program or other scheduled project, or when routine facility maintenance was to be 
performed, depending on the type of repair that was required. 

Standards for Structural Integrity Inspection

 outline the various measurements and test data that were to 

be recorded during the inspection process.  Also given are the criteria that determine whether a possible 
problem may exist, based on the recorded measurements. 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

117

 

8.4 

STANDARDS FOR ARCHITECTURAL AND STRUCTURAL DESIGN 

Standards for Architectural and Structural Design 

 was issued on February 27, 1998, by PANYNJ and 

contained architectural and structural design requirements, specifications and standard details for tenant 
alterations that were to be made specifically at WTC 1 and WTC 2.

40

  

Prior to any design work, the tenant’s consultants were required to perform a field inspection of all areas 
that would be affected by the alterations so that the latest information was available for all structural 
elements, including, but not limited to truss reinforcement, stair openings in slabs, and core-hole 
locations. 

Tenants are required to submit calculations and construction drawings to PANYNJ for review and 
approval.  All construction documents were required to be signed and sealed by a professional engineer or 
registered architect licensed to practice in the state of New York. 

Minimum loads to be used in the calculations were also specified. Calculations to compare the proposed 
loading with the allowable loads were required to conform to the latest edition of the NYC Building 
Code.  Both allowable stress design and load-and-resistance-factor design were acceptable design 
methods. 

All work was required to conform to the latest edition of the NYC Building Code, including any 
revisions. Provisions in the latest editions of the following codes took precedence over those in the NYC 
Building Code whenever they were more stringent: 

 

American Institute of Steel Construction, Specification for the Design, Fabrication and 
Erection of Structural Steel for Buildings. Supplement 1 is specifically excluded. 

 

American Concrete Institute, Standard Building Code Requirements for Reinforced Concrete, 
ACI 318. 

 

American Welding Society, Structural Welding Code – Structural Steel (AWS D1.1) and 
Reinforcing Steel (AWS D1.4). 

Any steel plates that were added to reinforce existing framing or for other reasons were required to 
conform to ASTM A36, and any reinforcing bars that were added were required to conform to 
ASTM A 615 Grade 60. 

Welding materials for structural steel and reinforcing steel were required to be E7018 conforming to 
American Welding Society (AWS) A5.1 

Specifications for Covered Carbon Steel Arc Welding 

Electrodes

. Specifications for non-shrink grout were also specified. 

8.5 

STRUCTURAL INSPECTION PROGRAMS 

Beginning in 1990, the Port Authority of New York and New Jersey implemented a systematic facility 
condition survey program of WTC 1 and WTC 2 using 

Standards for Structural Integrity Inspection

                                                      

40

 The complete document is in Appendix F of NIST NCSTAR 1-1C. 

background image

Chapter 8 

 

Draft for Public Comment 

118

 

NIST NCSTAR 1-1, WTC Investigation 

 

which was developed in 1986.  WTC 7, which was not owned by PANYNJ, was also inspected based on 
the criteria in 

Standards for Structural Integrity Inspection

 .  Prior to 1990, both WTC 1 and WTC 2 were 

inspected occasionally by the Engineering Department of PANYNJ. 

The survey program included: 

1.

 

Condition survey of WTC 2 in 1990 by the Engineering Quality Assurance Division of 
PANYNJ. 

2.

 

Condition survey of WTC 1 in 1991 by the Office of Irwin G. Cantor, Consulting Engineers, 
for the Engineering Quality Assurance Division of PANYNJ. 

3.

 

Condition survey of WTC 7 in 1997 by Ammann & Whitney for the Engineering Quality 
Assurance Division of PANYNJ. 

4.

 

Due diligence physical condition survey of WTC 1 and WTC 2 in 2000 by Merrit and Harris 
for PANYNJ prior to entering into a long-term leasing contract for the WTC buildings with 
Silverstein Properties.  

In addition to these four separate condition surveys, Leslie E. Robertson Associates (LERA) and other 
engineering firms conducted periodic inspections of the towers under the WTC Structural Integrity 
Inspection (SII) Program, which was based on the proposal originally submitted to PANYNJ by LERA 
in 1990. 

This section summarizes the findings of these condition surveys.  Detailed descriptions of the condition 
survey programs and findings are given in NIST NCSTAR 1-1C.  

8.5.1 

Facility Condition Survey of WTC 2 

The scope of work, which was designed to minimize impact on tenant and facility operations, included 
inspection of (1) the exterior wall system (columns, spandrel plates, and splices), (2) core columns 
(including column splices and lateral bracing below the 7th floor), (3) the space frame (hat trusses), 
(4) floor systems (floor slabs and decks, trusses, rolled beams, bridging, and connections), and (5) the 
damping system. Thirty floors throughout WTC 2 were selected for inspection, including all four of the 
two-story mechanical equipment rooms. 

Inspection Procedures and Methodology 

To assess the condition of the structural system in the tower, both visual inspection and nondestructive 
testing methods were performed. The thickness of steel members was checked using an ultrasonic 
thickness gauge. Fillet welds were tested for cracks and discontinuities using magnetic particle or dye 
penetration test methods, and groove welds were tested using the ultrasonic method. 

Exterior Walls (Columns and Spandrels) 

Exterior columns and spandrels were inspected at (1) column field splice connections, (2) spandrel field 
splice connections, and (3) the inside of the spandrel plate face at the column/floor truss seat connections. 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

119

 

A total of 59 column splices were inspected and all were found to be in good condition.  On two of the 
floor levels, the columns had only three bolts at the splice location, although the design called for four. 
According to the report, this had no effect on structural integrity. 

Spandrel plates, splice plates, and spandrel bolted connections were also found to be in good condition. 
Scattered rust stains were observed on the spandrel fireproofing as well as on the inside of some of the 
steel box columns. 

No priority recommendations were made in the report.  The report recommended that a long-term 
maintenance program be developed and implemented to clean and paint the inside surfaces of the exterior 
box columns to prevent further corrosion of the structural steel. 

Core Columns 

Core columns were inspected from elevator shafts and from office area floors. Twenty-five elevator shafts 
were randomly selected for inspection, and the elevator core framing was primarily inspected with 
fireproofing materials in place.  In general, some defects were found in the fireproofing.  In most of the 
shafts, several small regions and a few large areas of fireproofing were found to missing from core 
framing members.  In the worst case, 100 percent of the fireproofing was found to be missing from the 
south face of column 908 between floors 27 and 29 in elevator shaft number 1.  Exposed steel members 
exhibited only isolated locations of light surface corrosion. 

Gypsum wallboards surrounding the elevator shafts were also found to be in good condition, although 
isolated holes were detected at various locations. 

Inspection of column splices and eccentric-braced column connections with fireproofing removed showed 
that all bolts, welds, and structural steel were in good condition. 

No priority recommendations for repair were made in the 1990 report.  The report recommended that the 
fireproofing that was missing from the framing members in the elevator shaft be replaced, including those 
regions where the fireproofing was removed for inspection.  It also recommended that the holes in the 
gypsum wallboards surrounding the elevators be repaired. 

Space Frame (Hat Trusses) 

From floor 107 to floor 110, a steel space frame system, also known as “hat trusses” was interconnected 
with columns in the core and the exterior walls.  The hat trusses were constructed of rolled wide-flange 
and welded-box sections, and were designed to support a future antenna.  Thirty three locations were 
inspected visually from the floor below.  Visual inspections of truss connections were made closely at six 
locations after removing the fire resistant material (“fireproofing”).  The space frame system was found to 
be in good condition.  The exposed areas exhibited light surface corrosion.  Both bolted and welded 
connections were found to be in good condition with no significant deterioration. 

background image

Chapter 8 

 

Draft for Public Comment 

120

 

NIST NCSTAR 1-1, WTC Investigation 

 

Floor Framing 

In the main lobby, beams and connections that were inspected within the core area were found to be in 
good condition. Fireproofing was missing at various locations, exposing light surface corrosion on these 
elements. 

On floors 9 through 41, the floor framing that was inspected was also found to be in good condition.  
Light corrosion was observed on all core beams and beam connections, and on floor truss connections.  
The most significant deficiencies were found at the damping units, where a number of such units were 
missing from 1 to 4 fasteners in the connections to the framing members. 

Floor framing on floors 43 through 75 were found to be in good condition. The most significant 
deficiencies were found on floors 64 and 75.  A deformed bottom chord was found on the main truss 
along column 343 on floor 64; no signs of distress were observed.  On the 75th floor, untightened bolts 
were found at truss seat connections at several locations, which, according to the report, had no 
significant affect on the structural integrity of the framing, since they served for erection purposes. 

The floor framing on floors 77 through 107 was found to be in good condition with light surface 
corrosion observed on all core framing beams and connections.  The most significant deficiencies were 
concrete slabs that had separated from the metal deck at floors 93 and 108.  According to the report, 
structural integrity was not comprised, since the metal deck served as only formwork for the concrete. 

The floor framing and slabs were found to be in good condition except where hairline cracks were found 
in concrete beam encasement at various locations on all four mechanical equipment room levels.   

No priority recommendations for repair were made in the report.  All of the deficiencies noted above were 
considered to have no significant effect on structural integrity. 

Damping System 

Visual inspection of damping units noted missing non-structural fasteners.  Of 30 floors examined, at 
least 1 damping unit on each of 4 floors (18, 29, 37 and 38) had missing fasteners, ranging from 1 to 4.  
No priority recommendations for repair were made in the report. 

Mechanical Equipment Rooms (Floors 7-8, 41-42, 75-76, 108-109) 

The floor framing and slab inspected on the Mechanical Equipment Room (MER) floors were found to be 
in good condition.  On all MER floors, most of the structural framing was inaccessible due to HVAC 
ducts, fans, electrical equipment, or plumbing. 

Hairline cracks were found in concrete beam encasement at various locations on all four MER floors. 
Exposed steel exhibited light surface corrosion, and no deterioration was found at the underside of floor 
slabs. 

The report recommended no priority repair.  As mentioned above, all the deficiencies found were 
considered to have no significant effect on structural integrity.  The report recommended that utility 
supports found to be bowed or vibrating be replaced as part of the facility’s regular maintenance program. 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

121

 

Roof 

Roof framing, which consisted of rolled steel wide flange beams supporting a structural concrete slab, 
was found to be in good condition.  Hairline cracks in the fireproofing and in the underside of the 
concrete slab were found at various locations. 

No priority recommendations for repair were made in the report.  The report recommended repairs that 
were none structural in nature. 

8.5.2 

Facility Condition Survey of WTC 1 

The scope of the survey was based on experience gained from the survey of WTC 2 in 1990.  As in the 
case of the WTC 2 survey, the scope of work was designed to minimize impact on tenant and facility 
operations.  The exterior wall system, core columns, floor framing, damping system, space frame (hat 
truss), mechanical equipment rooms, and roof were inspected. 

Exterior Walls (Columns and Spandrels) 

A total of 28 exterior column splices were inspected throughout 14 office floors on floors 9 through 106. 
Nondestructive testing was performed on the plate splice welds, and ultrasonic testing was performed to 
verify plate thickness at 26 of these locations.  All inspected columns splices were found to be in good 
condition. 

The inside faces of the steel box column plates exhibited scattered areas of light to moderate corrosion 
and peeling paint.  Ultrasonic thickness testing on the outer column plates above and below the splice 
location indicated no cross-section loss. 

Spandrel plates, splice plates, and bolted connections were also found to be in good condition.  Scattered 
rust stains were observed on the spandrel fireproofing. 

On the floors above 106, only the joints at floor 108 were inspected. No structurally significant 
deterioration was found. 

No priority recommendations for repair were made in the report.  The report noted that missing 
fireproofing should be replaced on the spandrel plates and splices. 

Core Columns 

Core columns were inspected in 13 elevator shafts with fireproofing left in place.  Corner core column 
splices were inspected on two office area floors.  Core floor beam to column connections were also 
inspected at 25 of 56 locations on 14 floors. 

The exterior wall column splices were found to be in good condition.  Results from nondestructive testing 
of the splice plate welds were acceptable, and results from ultrasonic thickness testing showed no 
significant loss in member thickness. 

background image

Chapter 8 

 

Draft for Public Comment 

122

 

NIST NCSTAR 1-1, WTC Investigation 

 

Several small areas and a few large areas of fireproofing were missing from some of the steel beams and 
columns in the express elevator shafts.  According to the report, the probable cause of missing 
fireproofing on the columns was due to the high speed of the elevators moving up and down the shafts. 
All exposed steel was found to be in good condition with light to medium surface rust. 

Gypsum wallboards were found to be in good condition, except for two isolated holes in two elevator 
shafts at the 58th and 69th floors. 

Similar to the case of the express elevator shafts, fireproofing was found to be missing on some of the 
steel columns and beams, and some isolated holes were found in some of the gypsum wallboards in the 
local elevator shafts. 

Inspection of core corner column splices and floor beam to column connections showed all of the 
elements to be in good condition. 

No priority recommendations were made in the report.  The report recommended that missing 
fireproofing from the framing members in the elevator shafts be replaced, including those regions where 
the fireproofing was removed for inspection during the condition survey. It also recommended that the 
holes in the gypsum wallboards be repaired. 

Floor Framing 

Fourteen office floors (11, 13, 22, 30, 35, 52, 54, 61, 65, 78, 84, 86, 90, and 93) were selected for 
inspection.  Inspection of the structural elements at these levels followed the following sequence: 

1.

 

Six long-span trusses and two short-span trusses were selected from the plans for even, 
random distribution of inspection locations throughout the floor area. 

2. 

Floor framing, damping unit, utility supports, steel decking, inside faces of steel spandrel 
plates, spandrel splices, and core concrete or rolled steel members were visually inspected. 
Structural steel members were examined for signs of deformation or corrosion with 
fireproofing still in place.

 

3.

 

Fireproofing was removed to inspect the condition of steel framing members at the following 
locations: (a) six truss locations, (b) one core floor beam, (c) two spandrel plate splices, and 
(d) two exterior columns (plaster removal).  Visual inspections were made using lights, 
scrapers, wire brushes, and mirrors for signs of cracking, deformation, or corrosion. 

4.

 

Nondestructive testing was performed on column splice welds and welded floor framing 
connections.  Testing was performed by the Port Authority’s Materials and Research 
Division. 

On 2 of the 14 floors inspected, column splices on 7 core columns were inspected after removal of the 
gypsum board firewalls. Top sides of exposed concrete floor slabs were also inspected where carpeting or 
floor tiles had previously been removed. 

Two typical conditions were observed during inspection of the floor trusses: (1) small areas of 
fireproofing were missing at scattered locations throughout the floor framing, and (2) the underside of the 
floor trusses exhibited light rust.  Welds were tested at various connections and were found to be in good 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

123

 

condition.  In some cases, the connection of the truss to the exterior spandrel plate had one bolt and a 
weld instead of the typical two-bolt connection.  These field welds were also tested and were found to be 
in good condition. 

The metal deck and concrete slabs that were inspected were also found to be in good condition, except for 
the slab in the southeast corner of the 60th floor where cracks were found on the top surface. 

The report made no priority recommendations for repair for any of the floor framing members.  Routine 
recommendations were made as follows: (1) patch elastomeric sealer at the construction joint south of 
columns 504 and 505 under the 13th floor, (2) even though the modifications made to the bridging trusses 
at the 10th and 61st floors did not meet the original design, no further modifications were needed, (3) 
patch spalls that were created in concrete slabs when partition rails were removed, and (4) patch cracks on 
the 60th floor with elastomeric sealer 

Damping System 

At all of the locations that were inspected, the damping units did not have fireproofing covering them.  
Light rust was observed on the surfaces of the units.  A non-structural bolt was missing on one of the 
damping units under the 30th floor. 

Space Frames (Hat Trusses) 

A total of 199 members were inspected in the space frame (hat truss).  Light rust was found on diagonal 
braces, beams, and connections where fireproofing was missing.  No priority recommendations were 
made in the report.  Routine recommendations were made to replace missing fireproofing. 

Mechanical Equipment Rooms and Space Frame 

All four mechanical equipment room floor levels (floors 7-8, 41-42, 75-76, and 108-109) were inspected.  
Floor slabs at these levels were found to be in good condition with scattered cracks found on the slab 
surfaces.  Scattered patches of fireproofing were found missing from the underside of the metal decks 
outside the core area. 

A concrete encased beam on the 110th floor was subjected to steam from a leaking steam valve.  
Moderate rusting was found on the member, but no significant section loss was found. 

Hangers supporting ducts and piping were visually inspected, and some were found to be subject to 
excessive vibration.  Loose hanger rods and fatigue of pipe supports were also found at various locations.  
Beams that supported the duct hangers had fireproofing missing where the hangers were mounted. 

The report included a priority recommendation to replace the leaking valve under the 110th floor that 
caused the floor beam to corrode.  Routine recommendations were made to repair cracks in the concrete 
slabs and to repair hangers that were found to be vibrating, bowed, sagged, and/or deformed. 

background image

Chapter 8 

 

Draft for Public Comment 

124

 

NIST NCSTAR 1-1, WTC Investigation 

 

Roof 

No significant structural deficiencies were found at the roof level. Cracking and spalling of the concrete 
slab was found in localized areas of the roof. 

No priority recommendations were made in the report. Routine recommendations included removing and 
replacing existing patches in the roof slab and patching spalled areas in the concrete slabs. 

8.5.3 

Facility Condition Survey of WTC 7 

The scope of work was designed to minimize impact on tenant and facility operations and was limited to 
unoccupied floors and floors that had vacant space.  The column splices, wind bracing system, interior 
beam connections, floor slabs, and the Consolidated Edison (Con Edison) Substation were all inspected. 

According to the report, no problems or deterioration were found on the column splices, wind bracing, or 
the interior beam connections at any of the locations that were inspected.  Rust buildup was found 
between the flanges of members that rested on top of one another at the main roof level where the steel 
framing was exposed.  The report  recommended that the steel be cleaned and painted to prevent further 
deterioration, even though this was not considered to be a structural problem. 

Fireproofing was found to be missing from the steel framing at various locations where utility supports 
were installed on all of the floors that were inspected. It was most prominent on the fifth floor framing 
above the main lobby and the second floor framing above the loading dock area. It was recommended in 
the report that the fireproofing be replaced. 

Loose concrete was found on the north face of column 51 on the 46th floor of the cooling tower area. 
Silverstein Properties personnel immediately removed the loose concrete. 

Floor slabs were found to be in good condition. No deficiencies were found, except for some shrinkage 
cracks on the top of some of the exposed slabs and some damage to the metal deck. 

The Con Edison station was found to be in very good condition, and no action was required at that time. 

8.5.4 

Due Diligence Condition Survey of WTC 1 and WTC 2 

This section discusses the findings of the condition survey of WTC 1 and WTC 2, which was performed 
by Merritt & Harris, Inc. in 2000 for PANYNJ (Merritt & Harris 2000).  On-site evaluations were 
performed to assess the general physical condition of the property, as it existed at that time.  In particular, 
WTC 1, WTC 2, WTC 4, WTC 5, the retail mall and plaza, central services, and the subgrade were 
inspected.  The following discussion focuses on the findings for WTC 1 and WTC 2. 

Inspection Procedures and Methodology 

Observations were limited to those portions of the project that were visible during walk-through.  In many 
areas, building finishes concealed structural components from view.   

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

125

 

Findings of Inspection 

Merritt & Harris reported the following findings and recommendations for both WTC 1 and WTC 2. 

According to the report, the building structure appeared to be in good overall condition, based on 
observations of portions of the structure that were not concealed by building finishes.  No apparent 
movement or settlement of foundations was observed, and interior slabs were reported to be in good 
condition. 

The report noted that LERA and other engineering firms had performed, on a regular basis, SII of various 
structural systems and that those studies had indicated the following deficiencies: (1) rusting of steel 
columns in the elevator shafts, (2) missing fireproofing, and (3) floor coring damage.

41

  The due diligence 

condition survey report went on to note that the most recent SII recommended repairs were underway at 
the time the report was written. 

Damping units had been tested every 5 years, most recently in 1996.  The report noted that approximately 
two-dozen damping units were kept in stock for replacement.  The report also stated that LERA strongly 
recommended that the analysis of wind acceleration measurements be continued. 

The report noted that an ongoing program of re-fireproofing structural steel members was in place at the 
time of the inspection.  Re-fireproofing the structural steel was supposed to provide a 2 h fire rating for 
those members.  Such work was performed on an entire floor when the space was being built-out for new 
occupancy.  At the time of inspection by Merritt & Harris, Inc., approximately 30 floors had been 
completed in the two towers. 

8.5.5 

Structural Integrity Inspection Program 

In 1986, PANYNJ implemented an inspection program to detect, record, and correct any signs of distress, 
deterioration, or deformation that could signal structural problems. This structural integrity inspection 
program, which was based on an inspection and testing plan prepared by LERA, contained detailed 
guidelines on inspection, record-keeping, and follow-up procedures. 

Inspection findings under this program were to be categorized as “Immediate,” “Priority,” or “Routine.” 
Repairs falling into the “immediate” category included possible closure of the area and/or structure 
affected until interim remedial action (such as shoring or removal of a potentially unsafe element or 
structure) could be implemented. Such action was to be undertaken immediately after discovery, and a 
description of the action taken and recommendations for permanent repair were to be included in the 
inspection report. The “priority” category was for those conditions where no immediate action was 
required, or for which immediate action had been completed, but for which further investigation, design, 
and implementation of interim or long-term repairs should be undertaken on a priority basis (i.e., taking 
precedence over all other scheduled work).  Repairs falling into the “routine” or “non-priority” category 
could be undertaken as part of a scheduled major work program or other scheduled project, or when 
routine facility maintenance was to be performed, depending on the type of repair that was required. An 
important requirement in the inspection program was that where inspection procedures involved the 
removal of fireproofing, such fireproofing was to be properly replaced on completion of inspection. 
                                                      

41

 Detailed findings of the Structural Integrity Inspections are given in NIST NCSTAR 1-1C. 

background image

Chapter 8 

 

Draft for Public Comment 

126

 

NIST NCSTAR 1-1, WTC Investigation 

 

A summary of the findings from the SII can be found in NIST NCSTAR 1-1C. 

LERA’s proposed plan to monitor the structural integrity of the World Trade Center Complex included 
WTC 1, WTC 2, WTC 4, WTC 5, WTC 6, the Vista Hotel, and the subgrade.

42

 The plan called for 

inspection/monitoring of the following items in WTC 1 and WTC 2: 

 

TV mast (WTC 1 only) 

 

Roof water tightness and curtain wall 

 

Space usage 

 

Accessible columns, including exterior box columns at locations of spandrel intersections and 
“tree’ junctions below floor 7 and above floor 1 (Plaza Level) 

 

Bracing at exterior column line below elevation 294 ft 0 in., and in WTC 2 only, the transfer 
trusses below floor 1 under exterior columns 

 

Hat truss between floor 107 and the roof 

 

Floor framing for mechanical spaces 

 

Floor framing for tenant areas 

 

Concrete slabs, partitions, and finishes 

 

Steel framing, slabs, and the like where exposed for general repairs or tenant remodeling 

 

Measurement of natural frequency of tower and TV mast 

 

Floor natural frequency 

 

Damping units 

 

Plaster ceilings in main lobby 

 

Marble wall panel supports 

 

Review of maintenance reports 

 

Fire stairs 

Inspection and monitoring of these items were to occur at regular intervals. A summary of the structural 
integrity inspections conducted and their corresponding dates is given in Table 8–1. 

                                                      

42

 Letter dated January 12, 1990, from Saw-Teen See of Leslie E. Robertson Associates to Suren Batra of the Port Authority of 

New York and New Jersey (WTCI-123-P). 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

127

 

Table 8–1.  Summary of Structural Integrity Inspections Completed for 

WTC 1 and WTC 2. 

Inspection Program 

Date(s) of Inspection Reports 

Space Usage Survey 

1995, 1996, 1997, 1998, 1999 

Accessible Columns 

1993, 1995, 1996, 1997, 1998 

Plaza Level Box Columns 

1998 

Bracing Below Elevation 294 ft 0 in. 

1991, 1995 

Hat Trusses 

1992, 1995 

Floor Framing Over Mechanical Areas 

1992, 1996, 1999 

Floor Framing Over Tenant Areas 

1992, 1995, 1997, 1999 

Natural Frequency Measurements 

1993, 1995, 2000 

Natural Frequencies of Floors 

1995 

Viscoelastic Damping Units 

1996 

Space Usage Surveys 

The purpose of the space usage surveys was to identify possible structural overloading of the slabs and 
floor framing due to changes in occupancies and uses and/or due to additions of heavy equipment or 
furniture.  Surveys were conducted annually over a 5-year period starting in 1995, with two surveys 
conducted in 1996.  The only priority recommendation was made in the 1995 report, which advised 
PANYNJ to distribute the load of the granite slabs on floor 106 of WTC 1 over a larger area. 

Accessible Columns 

Surveys of the accessible columns (columns in the core area that are not enclosed by an architectural 
finish, which can be visually inspected) in the elevator shafts of WTC 1 and WTC 2 were performed to: 

 

Ascertain the condition of the accessible columns with respect to rusting, cracking, bowing, 
and deviation from plumb; 

 

Identify specific locations of structural distress or damage; 

 

Identify locations of damage to the fireproofing; 

 

Identify lateral displacement or rotation of the column about a vertical axis where the column 
is directly braced on only one axis by connecting beams or concrete slabs; and 

 

Identify deformations of the slabs-on-ground surrounding each column at the sublevel. 

Accessible column surveys were performed approximately every two years, starting in 1993 and ending 
in 1998.  Priority recommendations were made in the 1996 report and also in the 1998 report.  The later 
report recommended that missing fireproofing be repaired as part of a scheduled work program on 
columns at various locations in WTC 1 and WTC 2. 

background image

Chapter 8 

 

Draft for Public Comment 

128

 

NIST NCSTAR 1-1, WTC Investigation 

 

Plaza Level Box Columns 

The purpose of the inspection of the Plaza Level box columns was to assess their overall structural 
integrity, including the condition of the fireproofing.  The proposed inspection interval was four years.  
One such inspection was conducted in April of 1998.  The east face of WTC 1 and the north face of 
WTC 2 were visually inspected between the Concourse Level ceiling and the underside of the Plaza Level 
slab.  The columns between the Concourse floor level and ceiling level were inaccessible due to their 
enclosures. 

The report recommended no immediate and priority repairs. However, it noted that fireproofing was 
missing from approximately 2 percent to 3 percent of the Plaza Level box columns and seated beam 
connections in WTC 1 and about 1 percent to 2 percent in WTC 2.  The report recommended that

 

PANYNJ to clean all exposed steel on Plaza Level columns 236, 242, and 248 in WTC 1 and 
repair damaged fireproofing on columns and seated beam connections in both towers.

 

Bracing Below Elevation 294 ft 0 in. 

Below Elevation 294 ft 0 in. (Sublevel 1) in both WTC 1 and WTC 2, diagonal bracing was used in place 
of deep spandrels between the exterior columns to resist lateral loads from the tower above. 

The purpose of the inspection of the bracing system below elevation 294 ft 0 in. in the perimeter walls of 
the towers was to: 

 

Assess the overall performance and structural integrity of the bracing (and, in 1991 only, the 
transfer trusses below elevation 310 ft 0 in. in WTC 2); 

 

Identify specific locations of structural distress or damage; 

 

Identify locations of damage to the structural fireproofing systems; and 

 

Provide recommendations for remedial work for both structural and fireproofing damage. 

Bracing surveys were performed in 1991 and 1995.  No immediate and priority recommendations were 
made in these reports.  Routine recommendations were made to repair damaged fireproofing at several 
locations.  These included PANYNJ to clean, repair, and reinstall fireproofing on structural members at 
Level B6 in the Mechanical Equipment Rooms of both towers.  PANYNJ to repair all spray fireproofing 
on the braces in WTC 1 and 2 and the transfer truss in WTC 2 between columns 242 and 248. 

Hat Trusses 

The purpose of the inspection of the hat trusses between floor 107 and the roof was to: 

 

Assess the overall performance and structural integrity of the hat trusses; 

 

Identify specific locations of structural distress or damage; 

 

Identify locations of damage to the structural fireproofing systems; and 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

129

 

 

Provide recommendations for remedial work for both structural and fireproofing damage. 

Hat truss surveys were performed in 1992 and 1995.  Although no immediate and priority 
recommendations were made in the SII reports, routine recommendations were made to repair 
fireproofing and gypsum wallboard at various locations in WTC 1 and WTC 2.  No follow-up actions 
were stated in the report.  Fireproofing that was removed during the Facility Condition Survey inspections 
performed by the PANYNJ in 1990 and 1991 for WTC1 and WTC 2, respectively, was found not to be 
repaired. 

Floor Framing for Mechanical Areas 

The inspection program for the floor framing supporting the mechanical equipment rooms (MER) 
consisted of the following: 

 

Assess the overall performance and structural integrity of the steel and concrete framing 

 

Identify locations of defects and signs of distress in slabs, partitions, column enclosures, and 
concrete supports for mechanical equipment; 

 

Identify locations of damaged fireproofing; 

 

Compare the findings with those of previous inspections; and 

 

Provide recommendations and procedures for remedial work for both structural and 
fireproofing damages and/or inadequacies. 

Surveys were conducted in 1992, 1996, and 1999.  No immediate repair recommendation was reported in 
the 1992, 1996 and 1999 reports.  Priority recommendations were made in the 1996 and 1999 reports.  
The 1996 priority recommendation called for reapplication of fireproofing at various locations in WTC 1 
and WTC 2.  The 1999 priority recommendation called for repair of a water leak in an overhead pipe on 
floor 75 of WTC 1.  The report included routine recommendations for repair of cracked and spalled 
concrete slabs in the 1996 and 1999 reports. 

The reports indicated that damaged concrete masonry unit (CMU) walls in Level B6 of WTC 1 and 
WTC 2 still existed in 1996.  These damages were found initially during the structural integrity inspection 
of the diagonal bracing in 1991 and again in 1995.  Similarly, damaged fireproofing on the perimeter 
diagonal bracing members at this level in WTC 1 and WTC 2, which was initially found in 1991 and 
1995, still existed in 1999. 

Floor Framing for Tenant Areas 

The inspection program for the floor framing supporting the tenant areas consisted of the following: 

 

Assess the overall performance and integrity of the steel and concrete framing; 

 

Identify locations and signs of distress in slabs, partitions, column enclosures, and steel 
framing; 

background image

Chapter 8 

 

Draft for Public Comment 

130

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Identify locations of inadequate fireproofing; and 

 

Provide recommendations and procedures for remedial work for both structural and 
fireproofing damage and/or inadequacies. 

Surveys for floor framing supporting tenant areas were conducted in 1992, 1995, 1997, and 1999.  No 
immediate recommendation was made in the 1992, 1995, 1997 and 1999 reports.  Priority 
recommendations were made in the 1999 report concerning restoration of fireproofing on a truss on 
floor 89 in WTC 2, repair of spalled concrete on floor 89 of WTC 2 and floors 33 and 91 in WTC 1, and 
repair of damaged reinforcement on floor 91 of WTC 1.

 

In the 1992, 1995 and 1997 reports, 

PANYNJ was directed to replace or repair damaged fireproofing on steel members.

 

Natural Frequency Measurements 

The purpose of this inspection program was to determine the natural frequencies of oscillation of WTC 1 
due to wind excitation.  Only WTC 1 was instrumented with accelerometers at six locations on floor 108, 
which measured the accelerations in both principal directions of the building with respect to time due to 
wind.  These natural frequencies were to be compared with corresponding values that had been 
determined in the past.  A significant change in the tower’s dynamic behavior was considered to be a 
possible indication of diminishing structural integrity.  According to the reports, characteristics that may 
have been observed or inferred by review of the recorded acceleration data were: 

 

Integrity of the lateral-load-resisting system; 

 

Condition of the viscoelastic damping system; 

 

Condition of other sources of inherent structural damping; and 

 

Other changes that affect fundamental characteristics of the lateral-load-resisting system. 

Reports were prepared by LERA in 1993, 1995, and 2000.

43

  The 1993 and 1995 reports compared the 

available measured first mode natural frequencies of WTC 1 to those determined by the structural 
engineer in 1966, which were 0.084 Hz in the north-south direction and 0.096 in the east-west direction 
(WSHJ 1966).  A summary of the measured first mode natural frequencies from the 1995 report, which 
contained the most current data, is shown in Table 8–2.  No recordings were reported for the period 
between 1981 and 1991. 

                                                      

43

 These reports were prepared by Leslie E. Robertson Associates [WTCI 4073/66-L, 4056/66-L, 4094/66-L]. 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

131

 

Table 8–2.  Measured first mode natural frequencies for WTC 1. 

Measured Frequency (Hz) 

Date 

Wind Speed (mph) and 

Direction 

N-S E-W 

10/11/78 11.5, 

E/SE  0.098 

0.105 

01/24/79 33.0, 

E/SE  0.089 

0.093 

03/21/80 41.0, 

E/SE  0.085 

0.092 

12/11/92 49.0

a

 0.087 

0.092 

02/02/93 20.0, 

NW  0.085 

0.095 

03/13/93 32.0, 

NW  0.085 

0.094 

03/10/94 14.0, 

W  0.094 

0.094 

12/25/94 37.0, 

W  0.081 

0.091 

a.  No direction was given in the report. 

Both the 1993 and 1995 reports concluded that the measured and computed first mode frequencies 
compared well, especially for the greater wind speeds.  The 1995 report also concluded that the February 
1993 bombing had no permanent measurable effect on the dynamic response of WTC 1. Both reports 
recommended that WTC 2 be instrumented similarly to WTC 1. 

The 2000 SII report pointed out that PANYNJ had not been able to analyze the data acquired from the 
instrumentation of WTC 1 since 1998 because the PANYNJ laboratory that contained playback and 
analytical equipment necessary to assess the recorded data was dismantled in the fall of 1998.  The report 
recommended that the capability to assess and analyze the accelerometer data be re-established as soon as 
possible.  The report further recommended that WTC 1 be additionally instrumented at a mid-level floor, 
and that WTC 2 be instrumented at its top floor and at a mid-level floor.  

Natural Frequencies of Floors 

The purpose of this inspection program was to determine the natural frequencies of the floor systems in 
WTC 1 and WTC 2 and to compare them with corresponding values that had been determined in the past.  
A significant change in the vibration characteristics of the floor system was considered to be a possible 
indication of diminishing structural integrity.  

For purposes of determining the natural frequencies of the floor construction, a typical tower floor was 
divided into three zones, which corresponded to the type of floor truss that was used in that zone: short-
span zone, long-span zone, and two-way zone. 

Vibration characteristics of the floor systems were studied both analytically and experimentally.  In 1971, 
Teledyne Geotronics of Long Beach, CA made field measurements of vertical vibration on floors 13, 27, 
and 32 of WTC 1 using seismometers.  The field measurements were obtained under the direction of 
Skilling, Helle, Christiansen, Robertson (SHCR).  SHCR also made analytical estimates of the natural 
frequencies of the floor systems at that time (SHCR 1971).  They determined that the natural frequencies 
of the long-span and short-span trusses, considering viscoelastic damping, were 4.6 Hz and 7.9 Hz, 
respectively.  A summary of the natural frequency test results for WTC 1 is contained in Table 8–3. 

background image

Chapter 8 

 

Draft for Public Comment 

132

 

NIST NCSTAR 1-1, WTC Investigation 

 

Table 8–3.  Summary of natural frequency 

test results for floors of WTC 1, 

March 1971. 

Floor Zone 

Frequency Range (Hz) 

Long-span 

4.6 to 5.1 

Two-way 

4.6 to 5.7 
7.0 to 7.9 

Short-span 7.9 

In March of 1995, Cerami and Associates, of New York, NY, made field measurements on floors 17, 22, 
26, 38, and 88 of WTC 1 and floors 23, 24, an 58 of WTC 2 using the following equipment: piezo-electric 
accelerometer, vibration meter, peak band pass filter, and strip chart recorder (Cerami 1996).  The floors 
were subjected to a standard heel-drop test or by jumping in place.  All field work was performed under 
the direction of LERA.  A summary of the test results for WTC 1 and WTC 2 are given in Table 8–4. 

The SII report produced by LERA in April of 1995 summarized the analytical and experimental results to 
date (LERA 1995). Based on the available data, the report concluded that there had been no significant 
measurable change in the performance of the typical floor systems in WTC 1 and WTC 2. 

Table 8–4.  Summary of natural frequency 

test results for floors of WTC 1 and WTC 2, 

March 1995. 

Floor Zone 

Frequency Range (Hz) 

WTC 1 

Long-span 

4.5 to 5.3 

Two-way 

4.6 to 4.9 
6.6 to 7.6 

Short-span 

7.8 to 8.8 

WTC 2 

Long-span 

4.8 to 5.6 

Two-way 

4.9 to 5.4 
7.5 to 7.8 

Short-span 

7.9 to 8.0 

Viscoelastic Damping Units 

A summary of the integrity of the viscoelastic damping units in WTC 1 and WTC 2 was given in a report 
by LERA in 1996 (LERA 1996). Also given in the report is a historical review related to the performance 
of the damping units. 

The report concluded that based on the then available studies, the integrity of the damping units was 
good, and that no action was required at that time beyond the routine testing of the damping units. 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

133

 

Inspections Related to Explosion of February 16, 1993 

Six different inspections were performed before and after repairs were made to WTC 1 in the aftermath of 
the terrorist attack in February 1993.  Summaries of these inspections were reported in a series of 
inspection reports prepared for the PANYNJ.

44

   No anomalies were detected in the welds used to repair 

structural members. 

8.5.6 

Summary of Structural Integrity Inspection Programs 

In general, the structural integrity inspections found that the structural systems of WTC 1, 2, and 7 were 
in good condition.  The inspection consultants made numerous routine and some priority 
recommendations for repairs to the PANYNJ.  According to the PANYNJ, all of the construction records 
on repairs following the inspections were lost on September 11, 2001.  Thus, it cannot be determined 
whether all of the recommended repairs were performed.  However, in 1999, the PANYNJ issued 
guidelines requiring that fireproofing be upgraded for steel floor trusses when full floors were undergoing 
alterations. 

8.5.7 

Modifications and Repairs to Structural Framing Systems of WTC 1, 2, and 7 

Most of the modifications to the structural systems of WTC 1, 2, and 7 were done to accommodate tenant 
requirements (see NIST NCSTAR 1-1C). These generally involved cutting holes in existing floor slabs to 
construct new stairways linking two or more floors or reconstructing the floor system over previously cut 
openings. In other cases floor or column members were reinforced to accommodate new floor loadings 
imposed by tenant requirements. 

Modifications to the structural systems were to follow the Tenant Construction Review Manuals of 
PANYNJ, which are summarized in Sec. 8.2. 

Modifications and Repairs Made to WTC 1 

Openings Made in Floor Slabs 

Slab openings were made in the floor slabs on the following floors during the following years: 

1.

 

Floors 93 to 95, 1978 (openings were made in floors 94 and 95 between columns 901, 902, 
1001, and 1002 in core) 

2.

 

Floors 99 to 101, 1979 (openings were made in floors 100 and 101 between columns 707, 
708, 806, and 807 in core, and in floor 99 between columns 701, 702, 801, and 802) 

3.

 

Floors 89 and 90, 1985 (opening was made in floor 90 between columns 901, 902, 1001, and 
1002) 

4.

 

Floor 107, 1995 (opening was made in floor 107; location could not be determined) 

                                                      

44

 These reports can be found in WTCI-67-L. 

background image

Chapter 8 

 

Draft for Public Comment 

134

 

NIST NCSTAR 1-1, WTC Investigation 

 

5.

 

Floors 105 to roof, 1997 (opening was made in floor 105 near columns 704 and 804A in the 
core) 

6.

 

Floors 93 to 100, 1999 (openings were made on all floors; location could not be determined) 

Most openings were made to accommodate new stairs and elevators. 

Closing of Previously Opened Floor Slabs 

Openings that had been cut primarily for stairways were subsequently closed on the following floors 
during the following years: 

1.

 

Floor 95, 1972 and 1985 (new beams and floor deck were added near lines 124 and 239) 

2.

 

Floors 91 and 92, 1987 (new beams and floor deck were added between columns 901, 902, 
1001, and 1002 in the core) 

3.

 

Floors 96 and 100, 1998 (new beams and floor deck were added between columns 119 and 
123 on floor 96 outside of the core and near columns 707, 708, 806, and 807 on floor 100) 

Structural Members that were Reinforced 

Various floor members were reinforced to accommodate floor loads that were greater than the original 
design loads.  Members were reinforced on the following floors during the following years: 

1.

 

Floors 97 to 100, 1979 (cover plates were added on existing beams on floor 98 between 
columns 601 and 602 and between columns 701 and 702; on floor 98, diagonals were added 
to existing floor trusses on the east side of the core between columns 218 and 221; on floor 
99, floor trusses along lines 309, 311, 313, 315, 317, 319, 321, 323, 325, 327, and 329 were 
reinforced; and, on floor 99, core perimeter columns were reinforced) 

2.

 

Floor 86, 1996 (floor trusses were reinforced in the northwest corner of the building) 

3.

 

Floor 85, 1998 (cover plates were added to existing beams and existing floor trusses were 
reinforced) 

4.

 

Floors 47 and 48, 2001 (floor trusses were reinforced) 

Repair Work Following the February 26, 1993, Explosion 

Damage from the Explosion 

The explosion of February 26, 1993, occurred on Level B2 near the center of the south wall of WTC 1 
and adjacent to WTC 3 (Vista Hotel).  Structural steel columns, diagonal braces, and spandrel beams in 
the vicinity of the blast were damaged.  Concrete floor slabs at Levels B1 and B2 and unreinforced 
masonry walls were also damaged over a large area. A detailed description of damage of structural 
members and subsequent repairs is given in NIST NCSTAR 1-1C. 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

135

 

Briefly, the explosion tore out the diagonal brace between column 324 at Level B2 and column 327 at 
Level B1 and severely bent the diagonal brace between column 324 at Level B2 and column 321 at 
Level B1.  Spandrel beams at Level B1 from column 321 to 324 and from column 324 to 327 were also 
damaged by the blast.  Spandrels were bowed and cracked and some had missing bolts. 

The explosion caused a crack along the field splice in column 324.  Ultrasonic testing determined that the 
crack extended across the full width of the weld on the south face of the column and at each end of the 
weld on the north face.  A magnetic-particle testing procedure determined that the crack extended across 
the east face of the column and the majority of the weld on the west face as well. 

The explosion also damaged floor beams framing into the tower side of column 324 at Levels B1 and B2. 
Concrete spandrel beams at Level B3 between columns 318 and 330 also sustained damage.  Masonry 
walls in WTC 1 were breached over distances of approximately 50 ft to the east and 120 ft to the west of 
the blast origin. 

Repair Work 

The diagonal bracing members between Levels B1 and B2 that were damaged by the explosion were 
removed and replaced with new members. 

New plates were added to the damaged spandrel beam at Level B1 between columns 324 and 327 and 
between columns 321 and 324.  Also, the cracked weld on the south face of the spandrel beam at 
Level B1 near column 324 was removed and replaced. 

An eight-step procedure was prescribed for repair of the crack in column 324 immediately adjacent to the 
field weld at the column splice above Level B2.  No documentation was found to confirm that this crack 
was repaired according to that procedure. 

Repairs were made to the floor beams framing into columns 321, 324, and 327. Repairs were also made to 
connections between floor beams and columns on Levels B3 and B4. Along the south face of WTC 1, the 
damaged concrete spandrel beams were demolished and replaced. 

Modifications and Repairs Made to WTC 2 

Openings Made in Floor Slabs 

Slab openings were made in the floor slabs on the following floors during the following years: 

1.

 

Floor 77, 1979 (openings were made at nine locations in the northeast quadrant of the 
building) 

2.

 

Floor 96, 1987 (opening was made near columns 901 and 902 in the southeast quadrant of the 
building) 

3.

 

Floors 94 and 95, 1993 (opening was made between columns 507, 508, 607 and 608) 

4.

 

Floors 99 to 101, 1997 (openings were made; locations could not be determined) 

background image

Chapter 8 

 

Draft for Public Comment 

136

 

NIST NCSTAR 1-1, WTC Investigation 

 

5.

 

Floor 99, 1998 (opening as made between columns 601, 602, 701, and 702 in the core on 
Floor 99) 

6.

 

Floors 25 and 26, 1999 (opening was made near column 901 in the core) 

7.

 

Floors 88 and 89, 1999 (openings were made; locations could not be determined) 

Most openings were made to accommodate new stairs. 

Closings of Previously Opened Floor Slabs 

Openings that had been cut were subsequently closed on the following floors during the following years: 

1.

 

Floors 37 and 38, 1997 (new framing and floor deck was added near column 608) 

2.

 

Floors 95 and 96, 2000 (new beams and floor deck were added between columns 901, 902, 
1001, and 1002) 

Structural Members that were Reinforced 

Members were reinforced on the following floors during the following years: 

1.

 

Floor 96, 1993 (a number of floor trusses and their connections were reinforced in the 
northeast quadrant of the building) 

2.

 

Floor 81, 1991 (two-way floor trusses were reinforced in area occupied by United Parcel 
Service) 

Other Modifications 

In 1994, the slab in the elevator lobby on floor 90 (bounded by columns 702, 703, 902, and 903) was 
repaired for Fiduciary Trust; NIST has not found evidence of the reason for this modification.  The 
existing slab was demolished and was replaced with a 5 in. thick lightweight aggregate concrete slab. 

Modifications and Repairs Made to WTC 7 

Modifications Made due to New Loading Requirements 

Members were reinforced primarily to accommodate floor loads that were greater than the loads for 
which these members were originally designed.  Members were reinforced on the following floors during 
the following years: 

1.

 

Floor 38, 1988 (cover plates were added to existing beams along lines 30, 35, 37 and 40) 

2.

 

Floor 24, 1989 (cover plates were added to existing beam on line 45 and to two adjacent 
beams) 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

137

 

3.

 

Floor 47, 1989 (cover plates were added to existing beams on line 2-5 and to the existing 
girder on line 56) 

4.

 

Floors 11 and 12, 1990 (cover plates were added to eight existing beams and girders in the 
northwest corner of the building on floor 11, and to three existing beams between lines 48 
and 49 and to the girder between columns 70 and 73 on floor 12) 

5.

 

Floor 19, 1991 (cover plates were added to existing beams; location could not be determined) 

6.

 

Floor 12, 1992 (cover plates were added to 11 existing beams in the northwest corner of the 
building, and a new beam was added between existing beams) 

7.

 

Floors 18 and 19, 1992 (cover plates were added to existing beams on lines 31, 32, and 33) 

8.

 

Floor 28, 1993 (additional shear studs were added to existing beams located in the 
mechanical/electrical room) 

9.

 

Floors 7 and 8, 1993 (a new beam was added between lines 7 and 8) 

10.

 

Floors 7-29, 1994 (cover plates were added to 22 existing beams between lines 5 and 25 on 
the south side of the building and on each floor between levels 7 and 29, and to eight existing 
beams on the east side of the building between lines 31 and 37) 

11.

 

Floor 20, 1995 (cover plates were added to existing beams along lines 23 and 25, and WT 
sections and cover plates were added to existing beams east of line 19) 

12.

 

Floor 37, 1999 (a new beam was added between two existing beams along lines 76 and 77) 

13.

 

Floor 13, 1999 (additional shear studs were added to an existing beam; location could not be 
determined) 

14.

 

Floor 40, 1999 (four new beams were added near column 76 and WT sections were welded to 
the bottom of two existing beams) 

15.

 

Floor 31, 2000 (cover plates were added to an existing beam between columns 77 and 80) 

16.

 

Floor 38, 2000 (cover plates were added to existing beams between columns 76 and 77 and 
between columns 77 and 78, and to existing girders between columns 76 and 79, 77 and 80, 
and 78 and 81) 

17.

 

Floor 39, 2000 (new beams were added between columns 76 and 77) 

Openings Made in Floor Slabs 

The floor slabs on floors 41 and 43 were completely removed on the east side of the building to 
accommodate the trading floors for Salomon Brothers Inc.  Columns 76, 78, 79, 80, and 81 were 
reinforced with plates that ran from the top of the 39th floor to the underside of the 49th floor due to the 
removal of the floor slab at the 39th floor.  Similarly, column 74 was reinforced with plates that ran from 

background image

Chapter 8 

 

Draft for Public Comment 

138

 

NIST NCSTAR 1-1, WTC Investigation 

 

the top of the 43rd floor to the underside of the 44th floor due to the removal of the floor slab at the 43rd 
floor. 

Other slab openings were made in the floor slabs on the following floors during the following years: 

1.

 

Floors 3 and 4, 1989 (openings were made on the 3rd floor on the west, north, and east sides 
of the building; on the 4th floor, openings were made on the north side of the building) 

2.

 

Floor 3, 1989 (openings were made near columns 24 and 25) 

3.

 

Floor 11, 1990 (opening was made between columns 77, 78, 80, and 81) 

4.

 

Floor 43, 1994 (opening was made near column 71 in the core area) 

Modifications Made to Beam Webs and Flanges 

Modifications were made to beam webs and flanges on the following floors during the following years: 

1.

 

Floor 28, 1993 (openings were cut in the web of an existing beam; location could not be 
determined) 

2.

 

Floors 4 to 7, 16, 21, 29, 38, and 45, 1993 (notches were cut in the bottom flanges of various 
beams and plates were welded to the upper side of the bottom flanges) 

3.

 

Floor 1, 1998 (notch was cut into the top flange of an existing beam, and two plates were 
welded under the top flange; location could not be determined) 

4.

 

Floors 36 to 44, 1999 (openings were cut in the web of an existing beam framing into column 
75 on all floor levels; the beams was reinforced with web plates and a WT section welded to 
its bottom flange) 

5.

 

Floors 42 and 44, 1999 (openings were cut in the webs of numerous beams along the north 
and east sides of the building) 

Other Modifications 

A list of structural modifications that were made to WTC 7 prior to April of 1997 is given in Chapter IV, 
Sec. A(5) of the Facility Condition Survey Report for WTC 7 (PANYNJ 1997).  The following is a 
summary of the modifications that are noted in that report: 

1.

 

In the Convention Area on the 3rd floor between column numbers 45 and 48A, steel plates 
were installed around the perimeter of the room between the slab and the floor surface 
(behind the wall coverings and above the suspended ceiling).  According to the PANYNJ 
report, these plates were installed to protect attendees of the Convention Center from the 
magnetic field generated from the Con Ed Substation beneath the conference rooms.  No 
documentation was located that provides any additional details on this modification. 

background image

Draft for Public Comment 

 

Structural Maintenance and Modifications during Occupancy 

NIST NCSTAR 1-1, WTC Investigation 

139

 

2.

 

On the north side of the 5th floor generator room, masonry block walls were added to 
partition the eight transformer vaults installed for Salomon Brothers.  The vaults were 
between columns 46 and 53. No documentation was located that provides any additional 
details on this modification. 

3.

 

A penthouse was constructed on the 47th floor roof to house the chiller plant and the cooling 
towers for Salomon Brothers.  The chiller plant was an enclosed steel-framed structure with 
corrugated steel walls. It was approximately 25 ft in height and took up about one-third of the 
square footage of the 47th floor roof.  The cooling towers were supported on a steel frame 
and were enclosed by louvered walls on the north and south sides and by the chiller plant and 
the bulkhouse on the east and west sides, respectively.  No documentation was located that 
provides any additional details on this modification. 

The list of modifications in the PANYNJ report also included the removal of the floor slabs on floors 41 
and 43 to accommodate the trading floors for Salomon Brothers, as noted above. 

 

background image

Chapter 8 

 

Draft for Public Comment 

140

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

This page intentionally left blank. 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

141

 

Chapter 9 

C

OMPARISON OF 

F

IRE 

S

AFETY 

C

ODES AND 

P

RACTICES

 

9.1 

COMPARISON OF FIRE PROVISIONS IN BUILDING CODES 

9.1.1 Introduction 

The 1968 New York City (NYC) Building Code (NYCBC 1968) was compared with four other building 
codes to determine the extent to which the codes and mandatory referenced standards were utilized in the 
design and construction of the towers.  The other codes are: the 1964 New York State Building 
Construction Code (NYSBC 1964); the 1965 Building Officials and Code Administrators/Basic Building 
Code (BOCA/BBC 1965); the 1967 Municipal Code of Chicago Relating to Buildings (MCC 1967); and 
the 2001 edition of the NYC Building Code (NYCBC 2001).  In addition, comparisons of fire safety 
requirements were made to the 1966 edition of the National Fire Protection Association (NFPA 101), 
Code for Safety to Life in Buildings and Structures.  While not a building code, National Fire Protection 
Association (NFPA) 101 is widely adopted for its requirements on life safety in fires. 

The codes selected for comparison are laws or nationally or regionally recognized model regulations that 
reflect the standards of practice of the time.  The 1964 New York State Building Construction Code was 
the governing building code outside the New York City limits.  The 1965 BOCA Basic Building Code 
was typically adopted by local jurisdictions in the northeastern region of the United States.  The 1968 
NYC Building Code is compared with the 1967 Municipal Code of Chicago (MCC) to see whether there 
are any substantial differences in the fire safety requirements of the two codes.  In the late 1960s and early 
1970s, several tall buildings were built in Chicago including the Sears Tower (110 stories) and the John 
Hancock Tower (100 stories), both of which were classified as business use and incorporated innovative 
design features.  In addition, the 2001 edition of the NYC Building Code was compared with the 1968 
version to examine the extent to which Local Laws modified the code provisions, and in most cases, is 
only addressed in areas where changes occurred between the two versions. 

A provision by provision comparison was made between the 1968 NYC Building Code and these codes.  
The code provisions that were compared are limited to the requirements related to structural stability, 
active and passive fire safety, and emergency egress and are presented in the reports NIST NCSTAR 1-E 
and 1-F.   

The NYC Building Code was regularly modified by local laws, two of which, Local Law 5 (1973) and 
Local Law 16 (1984), had a significant influence on the fire and life safety features of WTC 1 and 
WTC 2, even though the buildings were completed and occupied at the time of adoption. Normal practice 
is not to apply building code changes to existing buildings, although Local Laws 5 (1973) and 16 (1984) 
did contain some retroactive provisions.  The Port Authority of New York and New Jersey (PANYNJ or 
Port Authority) chose to follow the revised provisions and to retrofit the buildings as required under the 
new provisions.  The resulting changes to WTC 1 and WTC 2 are discussed primarily in the sections on 
modifications to the building systems and in reports NIST NCSTAR 1-G and 1-H.  Local Laws 5 (1973) 
and 16 (1984) were in place at the time WTC 7 was designed and constructed, and the requirements of 

background image

Chapter 9 

 

Draft for Public Comment 

142

 

NIST NCSTAR 1-1, WTC Investigation 

 

these local laws were reflected in that building.  There were no significant revisions to the NYC Building 
Code that affected the fire and life safety features of WTC 7. 

9.1.2 

Interrelation of Codes, Standards, and Practices 

The provisions contained in building codes generally specify what is required under specific conditions.  
The building codes contain references to standards that provide further details on how the provisions are 
to be implemented to meet the intent of the code.  New York City makes use of nationally recognized 
technical standards but adopts them with modifications to meet local needs and accepted practices.  These 
modified standards are known as Reference Standards (RS) and are available from the city.  Reference 
standards take on the force of law when they are included in the building regulation as mandatory 
references and enforced by the regulatory official.  For the WTC towers, the Port Authority utilized the 
New York City reference standards and the source standards from NFPA and others in design guidelines, 
manuals, and procurement contracts associated with system upgrades. 

In some cases, trade associations and professional societies develop practices that may guide how 
building design and construction work is done.  While not strictly enforceable unless referenced in the 
code, such practices represent a consensus of what is reasonable or prudent.  A few, relevant practices are 
discussed in this section. 

9.1.3 

Comparison of New York City and Contemporary Building Codes 

While New York City developed its own building code, its code development committees were 
influenced by the same forces that bore on the national model codes.  Thus, there were relatively few 
differences between the NYC Building Code and the others.   

Construction Classification 

The model building codes classify building constructions into different “Types.” Although there are some 
variations in categories, they are reasonably consistent.

45

  The main categories are Type 1 (fire resistive), 

Type 2 (non-combustible), Type 3 (combustible), Type 4 (heavy timber), and Type 5 (ordinary).   

Types 1 and 2 are constructed with non-combustible exterior and interior bearing walls and columns.  Fire 
resistance ratings (see Fire Ratings) are greatest for Type 1, and Type 2 is any (non-combustible) 
construction not meeting Type I requirements.  For Type 3, exterior bearing walls are non-combustible 
and interior bearing walls and some columns may employ approved combustible materials.  Type 4 is 
known as 

heavy timber,

 which utilizes large, solid cross section wooden members such as in post and 

beam construction.  Type 5 is traditional wood frame construction.  Common non-combustible structural 
elements are made of steel or reinforced concrete.  Combustible structural elements are usually made of 
solid- or engineered-wood and laminates. 

Combustibility of the materials in a structural element is determined in an ASTM International 
(ASTM) E 136 test in which the material is placed in a furnace at 750 

°

C (1,380 °F), which is a “typical” 

                                                      

45

 Construction type definitions varied among the model codes until an effort in the 1970s by the Board for the Coordination of 

the Model Codes to eliminate unnecessary differences. 

background image

Draft for Public Comment 

 

Comparison of Fire Safety Codes and Practices 

NIST NCSTAR 1-1, WTC Investigation 

143

 

fire temperature.  Some minor surface burning (e.g., from paint or coatings) is allowed in the first 30 s, 
but there cannot be any significant energy release as indicated by more than a 30 

°

C (54 

°

F) increase in 

the furnace temperature, and the test specimen cannot lose more than half its initial mass.  Materials that 
pass are designated non-combustible, and the rest are combustible.   

Within each construction type, there are several sub-categories determined by the fire resistance ratings of 
the columns, beams, and floor supports.  In some codes, these sub-categories are identified by letters 
following the type (e.g., 1B or 3A) or by a set of three numbers that represent the fire resistance required 
(in hours) of the columns, beams, and floors, respectively (e.g., Type 1 [3,3,2]).   

For unsprinklered office buildings, the following construction classes are permitted in the five building 
codes reviewed. 

 

Type 1A and 1B—NYCBC 1968, NYSBC 1964, BOCA/BBC 1965 (Unlimited height) 

 

Type 1A, 1B, 1C, 1D—NYCBC 2001 (Height limited to 75 ft)  

 

Type 1A only—MCC 1967 (Unlimited height) 

The 1938 NYC Building Code did not include Type 1B construction for office occupancies.  The reasons 
for the inclusion of Type 1B construction for office occupancies in the 1968 NYC Building Code are not 
recorded (recordkeeping in the codes and standards development process was very poor prior to the 
Hydrolevel vs. ASME Supreme Court decision in 1982).  The codes then and now tend to follow each 
other, as champions of changes to one code usually try to change all of the codes.   

The 1950 edition of the Basic Building Code (BOCA), the regional model code used in the Northeastern 
United States,  included a Type 1B construction class with unlimited height and area for business and low 
hazard storage occupancies without sprinklers.  Among other model codes, the Standard Building Code 
(1946-47 edition, SBCCI) had a Type 2 construction similar to Type 1B for business occupancies and 
buildings more than 80 ft in height; the National Building Code (1934 edition, NBFU) had a semi-
fireproof construction similar to Type 1B for buildings above 75 ft; and the Uniform Building Code (1927 
edition, ICBO) had a Type 2 construction similar to Type 1B for buildings above 75 ft.  The 1968 NYC 
Building Code is consistent with the 1950 BOCA in its inclusion of the Type 1B construction. 

Mandatory sprinkler requirements for new high-rise buildings was first introduced in the NYC Building 
Code in 1984 (by Local Law 16), in BOCA in 1984, and in the Chicago Building Code (which allows a 
compartmentation alternative) in 1975.  Before Local Law 16 was adopted, the 1968 NYC Building Code 
permitted Type 1A, 1B, 1C, and 1D construction for sprinklered office buildings of unlimited height.  In 
the 2001 NYC Building Code, the minimum permitted construction classification for sprinklered office 
buildings of unlimited height is Type 1C. 

Selection of Construction Type for WTC Towers 

The 1938 NYC Building Code recognized one construction type for buildings of unlimited height and 
area, namely Class 1—Fireproof Structures, which required a 4 h fire rating for columns and a 3 h rating 
for floors.  In the 1968 NYC Building Code, Group I (Noncombustible) construction was subdivided into  
“Class 1A—4-hr protected” and “Class 1B—3-hr protected” construction.  Class 1A specified similar 

background image

Chapter 9 

 

Draft for Public Comment 

144

 

NIST NCSTAR 1-1, WTC Investigation 

 

protection as the previous Class 1, and Class 1B specified a 3 h rating for columns and girders supporting 
more than one floor and a 2 h rating for floors including beams.  Both Class 1A and Class 1B construction 
permitted unlimited height and area for unsprinklered business occupancy.  

If a building qualifies for more than one construction classification, such as Class 1A or Class 1B, all of 
the building codes do not say which classification should be used.  In such situations, the classification 
selected for construction is at the discretion of the owner/architect.   

Fire Ratings 

The structural elements of a building are protected against failure in fire for a specified period, as 
determined in the ASTM E 119 test.  The intent of the fire rating requirements is for the structure as a 
minimum to withstand design loads (including fire) without local structural collapse until occupants can 
escape and the fire service can complete search and rescue operations.   

Fire resistance requirements in the building codes are greatest for structural members that are essential to 
the stability of the building as a whole.  These include columns and other major gravity load carrying 
members that connect directly to columns such as girders and trusses.   

For various construction classes, the building codes specify different fire resistance ratings.  The building 
codes reviewed all specify fire resistance ratings for high-rise office occupancies as follows: 

 

Type 1A  

 

Columns:  4 h (supporting more than one floor) 

 

Beams:  3 h (floor construction) 

 

Type 1B 

 

Columns:  3 h (supporting more than one floor)   

 

Beams: 2 h (floor construction). 

 

Type 1C (for sprinklered buildings only) 

 

Columns:  2 h (supporting more than one floor) 

 

Beams:  1½ h (floor construction). 

The choice among permitted construction classes for a particular building is made by the architect and/or 
the owner.  Thus, an unsprinklered high-rise office building that was designed according to the 
1968 version of the NYC Building Code could follow either Type 1A or 1B, and if designed subsequent 
to the passage of Local Law 16/1984, a high-rise office building would have to be sprinklered but it could 
follow Type 1C as a minimum classification.  Similar reductions in the minimum required fire resistance 
ratings for sprinklered buildings are found in all national model building codes over this period, as 
requirements for fire sprinklers, especially in high-rise buildings, have become common. 

background image

Draft for Public Comment 

 

Comparison of Fire Safety Codes and Practices 

NIST NCSTAR 1-1, WTC Investigation 

145

 

Type 1B, and eventually Type 1C, construction was permitted for high-rise office occupancies because 
this occupancy is considered low risk.  Most other use groups in high-rise buildings were restricted to 
Type 1A, which is the construction type with the maximum structural fire protection defined in these 
codes. 

Practice Related to Fire Resistance Ratings 

Building codes specify fire resistance ratings for the structural members of buildings as a function of 

 

Building height, 

 

Construction type, and 

 

Use group (Occupancy), 

with modifications for the presence of fire sprinklers.  In the International Building Code (IBC 2003), 
Section 703.2 states, 

The fire-resistance ratings of building elements shall be determined in 
accordance with the test procedures set forth in ASTM E 119 or in 
Section 703.3.  Where materials, systems or devices that have not been 
tested as part of a fire-resistance-rated assembly are incorporated into the 
assembly, sufficient data shall be made available to the building official 
to show that the required fire-resistance rating is not reduced.   

This section appears to have been based on the 1981 BOCA (Sec. 1403.1.1) which required that, “The fire 
resistance ratings of building assemblies and structural elements shall be determined in accordance with 
the test procedures set forth in ASTM E 119…” 

IBC Section 703.3 allows the fire resistance of a building element to be established by: 

 

Fire resistance designs documented in approved sources 

 

Prescriptive designs of fire-resistance-rated building elements prescribed in Section 720, or 

 

Calculations in accordance with Section 721. 

These alternative methods were included in the other model building codes on which the IBC is based.  
For example, the 1997 Uniform Building Code contains tables of prescribed ratings for specific materials 
and assemblies which may be depended on as an alternate to ASTM E 119 testing.  The 1994 Standard 
Building Code permits calculated fire resistance using specified methods or testing by ASTM E 119. 

In the 1968 New York City (NYC) Building Code, Section C26-501.1 requires that,  

Samples of all materials or assemblies required by this code to have a 
fire-resistance rating, … shall be tested under the applicable test 
procedures specified herein … .  The fire-resistance rating of materials 
and assemblies listed in reference standard RS 5-1 (which references 

background image

Chapter 9 

 

Draft for Public Comment 

146

 

NIST NCSTAR 1-1, WTC Investigation 

 

ASTM E 119) may be used to determine conformance with the fire 
resistance requirements of this code. 

In traditional practice, the architect (sometimes different from the design architect, called the code 
architect) specifies the fire resistance ratings needed to comply with the building code.  The required 
ratings are normally not shown on the architectural drawings (although the construction type may be);  
rather they are shown in the supporting material submitted to the building department for plans review.   

Building codes require that an ASTM E 119 test be performed to determine the details of the assembly 
that would meet the requirement.  In some cases the architect may choose to use an assembly that has 
already been tested and rated.  Such assemblies are listed by testing laboratories in directories, databases 
accessed on test laboratory web sites, or in test reports available from manufacturers of materials used in 
the assemblies such as the producers of fireproofing products.  These sources are very detailed and 
indicate the thickness of the specific product tested that is required to achieve a specific hourly rating.  
Enforcement officials are expected to verify that even the smallest details are followed or that the 
variations do not affect performance.  Alternatively, some codes include descriptions of generic 
assemblies that can be assumed to achieve specified ratings, or provide calculation methods to determine 
the thickness of spray applied material needed to achieve a specific rating.  These methods are often based 
on W/D (width to depth) ratios, which must be applied differently as a function of member geometry. 

An additional variable that affects the needed thickness of fireproofing is whether the assembly is  
restrained.  It is traditionally assumed that an assembly that is thermally restrained requires less 
fireproofing.  Note that the NIST tests of the floor assemblies used in the towers showed the opposite.  
However, the definition of restrained is not trivial and needs to be specified by the structural engineer. 

In some cases, it is not clear who actually determines the required thickness of fireproofing material.  If 
the bid specifications for the fireproofing contract simply require the assemblies to be sprayed to achieve 
a specific hourly rating (which may be the case where a specific product is not identified to be used), then 
the thickness determination may be left to the fireproofing contractor.   

Standards of practice for spray applied fireproofing are contained in the Underwriters Laboratories (UL) 
guide card (UL 2001) (although technically this only applies when a UL Listed assembly is used) and in 
manuals published by the Association of Wall and Ceiling Industries (AWCI 1997).  There is also the 
American Institute of Architects Masterspec on Spray Applied Fireproofing (AIA 2000) that is similar to 
the Association of Wall and Ceiling Industries (AWCI) manual.  Additional guidance may be provided by 
the manufacturers of fireproofing materials that are specific to the characteristics of those products. 

The UL guide information (BXUV) includes a number of limitations on the application of listed 
assemblies, including: 

 

Limits on the size (flange width and web depth, pipe outer diameter) without the use of a 
mechanical break such as metal lath or fasteners, 

 

Use of bonding agents or conduct of a bond strength test in accordance with ASTM E 736 
whenever the steel is painted (other than a paint specified in the listing) 

 

Conduct of thickness testing in accordance with ASTM E 605. 

background image

Draft for Public Comment 

 

Comparison of Fire Safety Codes and Practices 

NIST NCSTAR 1-1, WTC Investigation 

147

 

The AWCI Technical Manual contains similar limitations and instructions, including the production of a 
test report on thickness and density, bond strength, correction of deficiencies, and patching procedures.  
Further, the AWCI manual describes a quality assurance program and requires that the fireproofing 
contractor retain the services of the licensed engineer or architect qualified to make the determination of 
restrained and unrestrained members.  The AWCI manual is not cited as a mandatory reference in any 
model code; rather it is voluntarily followed by contractors that are members of the association.  The 
American Institute of Architects (AIA) Masterspec is similar to the AWCI manual, except that it is 
written to be incorporated into the fireproofing contract, which would make it enforceable against the 
contractor.   

Some building codes require that spray applied fireproofing on steel structural members be subjected to 
inspection at the time of installation.  Local Law 55 (1976) amended the 1968 NYC Building Code  to 
require that all required, spray-applied fireproofing of structural members except those encased in 
concrete be subjected to a controlled inspection, meaning that it must be conducted under the supervision 
of a building inspector or a licensed design professional who assumes responsibility for compliance.  This 
provision applied to all installations after the date of enactment (November 1, 1976) and was not 
retroactive.  The inspection was to include verification of the thickness of the material, its density, and its 
adhesion, each utilizing a specific ASTM test method.  There are no code requirements nor general 
practice by which spray applied fireproofing is inspected over the life of the building.  Most building 
codes contain a requirement that spray applied fireproofing that is installed in areas where it is subject to 
mechanical damage shall be protected and maintained in a serviceable condition.  For a detailed 
discussion of the fireproofing system found in the towers, see NIST NCSTAR 1-6A. 

9.1.4 Occupancy 

Group 

All building codes define categories of occupancy (which may have more than one sub-class).  The group 
designations vary in different codes.  The ones presented here are those used in the 1968 NYC Building 
Code.  These are: 

 

High Hazard (Group A) 

 

Storage (Groups B-1 and B-2) 

 

Mercantile (Group C) 

 

Industrial (Group D-1 and D-2)  

 

Business (Group E) 

 

General Assembly (Group F-1 through F-4) 

 

Educational (Group G) 

 

Institutional (Groups H-1 and H-2) 

background image

Chapter 9 

 

Draft for Public Comment 

148

 

NIST NCSTAR 1-1, WTC Investigation 

 

 

Residential (Groups J-1 through J-3) 

 

Miscellaneous (Group K) 

Building codes use occupancy as a surrogate for risk factors that determine the level of performance 
needed.  For example, occupancy is determined by a combination of factors such as types and quantity of 
combustible contents, common ignition sources, and typical occupant characteristics.  Business 
occupancies (which includes office buildings) are considered among the lowest risk because they 
typically contain grades of furniture that constitute relatively low combustible loads, few ignition sources, 
and a population that is predominately adult, and not sleeping.  The most risky occupancies are High 
Hazard, in which are found highly flammable, toxic, or explosive materials, and Institutional 
(e.g., hospitals and prisons) in which occupants are likely to be incapable of unassisted egress. 

In some codes, including the 1968 NYC Building Code, occupancy groups are subclassified with a “fire 
index” rating in hours.  For example, “high hazard” occupancy is assigned a fire index of 4 h, while 
“business” occupancy is assigned a fire index of 2 h.  These fire indexes are used to specify the 
performance of separations between spaces of different use in a mixed-use building.  For example, spaces 
of different use with the same fire index are separated by a partition of lower rating than for uses with a 
different fire index.  Many buildings are mixed use because they contain spaces used for different 
purposes as defined in the building codes. 

Business (Group E) 

The business use group includes all office buildings, but this can range from a construction office in a 
trailer temporarily located on a construction site to a high-rise office building like the World Trade 
Center.  Business occupancies are characterized by an average occupant load, occupants who are 
generally physically fit and do not sleep in the space.  Combustibles are average in quantity and include 
higher quality furniture and paper. 

Assembly (Group F) 

The assembly use group includes any place used for the gathering of more than 50 people for civic, social, 
or religious functions, recreation, food and drink, or awaiting transportation.  Assembly use is 
characterized by the highest occupant loads, which may include families with small children and older 
adults.  Combustibles are light in quantity and vary in character depending on specific use. 

9.1.5 Egress 

Systems 

The 1968 NYC Building Code contains requirements for the number and capacity of stairs and for the 
assumed occupant load that are similar to requirements in the other contemporaneous codes 
(see Appendix A).  Codes of the time required that multiple stairs be located “as remote from each other 
as practicable.”  New York City permits scissor stairs,

46

 and the code requires the exit doors to be at least 

15 ft apart.  Local Law 16 (1984) first imposed a remoteness requirement of 30 ft or one-third the 

                                                      

46

 Scissor stairs refers to two separate interior stairways contained within the same enclosure and separated by a fire rated 

partition. 

background image

Draft for Public Comment 

 

Comparison of Fire Safety Codes and Practices 

NIST NCSTAR 1-1, WTC Investigation 

149

 

maximum travel distance of the floor (whichever is greater), which was not retroactive, so it did not apply 
to WTC 1 and WTC 2 but did apply to WTC 7. 

The 1968 NYC Building Code also contains a requirement that, “ …vertical exits should extend in a 
continuous enclosure to discharge directly to an exterior space or at a yard, court, exit passageway or 
street floor lobby …” (C26-602.4).  Similar requirements are found in the 1965 BOCA Basic Building 
Code and in 1966 NFPA 101, but not in the 1964 New York State Building Construction Code or the 
1966 Municipal Code of Chicago.  Current code language (2003 IBC, section 1003.6) defines continuous 
as:  not “ … interrupted by any building element other than a means of egress component.”  

The requirement for exit stairs to discharge to a public way was the subject of ongoing discussion with 
respect to the A and C stairs in WTC 1 and WTC 2 terminating at the mezzanine level, which was not at 
street level but rather at the Plaza level.  The Port Authority’s position was that the Plaza was a street and 
the Concourse was an underground street, and that the arrangement met the intent of the Code.  NIST 
found PANYNJ documents indicating that the NYC Department of Buildings agreed with this 
interpretation (e.g., Solomon 1975), but did not find any documents from the NYC Department of 
Buildings confirming this.  Thus, the issue continued to come up as a variance with the Code as late as 
1996 (see Section 11.4). 

9.2 

SUMMARY OF DIFFERENCES BETWEEN CODES  

In Construction Classifications, NYC Building Code 1968, NYS Building Code 1964 and 
BOCA/BBC 1965 all recognized Class 1A or Class 1B (with the same fire resistance ratings for building 
elements) for most unsprinklered buildings of unlimited height while MCC 1967 recognized only 
Class 1A.  New York City imposed a 75 ft height limit on unsprinklered buildings with the adoption of 
LL 16 (1984). 

At the time of construction, sprinklers were primarily for property protection and were rare even in high-
rise buildings (except for underground spaces).  Fire alarm systems were mostly manually initiated, but 
there was a concern about smoke being recirculated through the heating, ventilating, and air conditioning 
(HVAC) systems, so smoke detectors controlled dampers at return shafts to prevent this.  This is the 
arrangement of the fire alarms system originally installed in the towers.  Voice communication systems 
were a response to phased evacuation with the recognition that it was necessary to provide instructions to 
occupants who were relocated or held within the building at least until they were told to leave.  
Requirements for voice systems first appeared in national standards in the mid-1980s (e.g., the 1985 
edition of NFPA 72F), at the same time as New York City adopted LL 16-1984. 

All building codes rely on referenced technical standards to provide the details of design, installation, 
operation, and maintenance of required systems.  Most building codes reference national (consensus) 
standards as published, but New York City cites its own Reference Standards that are based on the 
national standards but are often highly modified.  For example, fire alarm systems and fire sprinkler 
systems are addressed in RS 17, with Class E fire alarm systems (required in office occupancies) covered 
in RS 17-3A and general fire alarm system requirements in RS 17-5.  The former is written entirely by a 
NYC code committee, and the latter is based on NFPA 72 (National Fire Alarm Code), but highly 
modified by the deletion of many sections and modification of many others.  One major modification is 
the fact that RS 17 does not incorporate the NFPA 72 “Survivability” section for high-rise voice 

background image

Chapter 9 

 

Draft for Public Comment 

150

 

NIST NCSTAR 1-1, WTC Investigation 

 

communication systems, which requires duplicate communication trunks so that loss on one trunk does 
not result in loss of communication with a floor.  However the Port Authority explicitly applied these 
survivability requirements from NFPA 72 in the specification of the voice communication systems 
installed in the towers following the 1993 bombing, as evidenced by the specification of Style R 
communication trunks routed in duplicate in stairways A and C, with interleaved speaker wiring. 

Prior to 1988 all building codes determined egress capacity by the (22 in.) Units of Exit Width method, 
which New York City still uses.  In 1988, other codes changed to a method involving an allowance of 
width per person which provides credit for non-standard widths of corridors and doors, but for standard 
dimensioned components yields the same results.  Another difference in egress design is that New York 
City applies the occupant load factor for business occupancies (100 ft

2

 per person) to the net floor area 

while other codes use the gross floor area.  The NYC Building Code allows doubling the allowable stair 
capacity with the provision of one horizontal exit or tripling of the stair capacity on floors with two or 
more horizontal exits, where all the other codes only allow doubling for one horizontal exit.  For a 
discussion of how this impacted WTC 1, see Sec. 10.1.1, Egress Provisions from Windows on the World. 

There are a number of detail differences between NYC Building Code and the other building codes.  The 
NYC Building Code has no requirements for fire extinguishers since they require occupant hose reels.  
The NYC Building Code in 1968 was the first code to include smoke developed ratings for finish 
materials in addition to flame spread.  Now all of the codes have similar requirements.  Most of these 
differences can be traced to the specific wording and citations by referring to the reports, NIST 
NCSTAR 1-E, 1-F, and 1-G.

background image

 

NIST NCSTAR 1-1, WTC Investigation 

151

 

Chapter 10 

I

NFLUENCE OF 

C

ODES AND 

S

TANDARDS ON THE 

D

ESIGN AND 

C

ONSTRUCTION OF 

WTC

 

1

 AND 

WTC

 

10.1 

EGRESS SYSTEM DESIGN 

One of the largest impacts to the design of World Trade Center (WTC) 1 and WTC 2 resulting from the 
decision to follow the 1968 New York City (NYC) Building Code rather than the 1938 Code was the 
impact on the emergency egress system.  The other large impact was the use of the 1-B Construction 
Class introduced in the 1968 Code rather than the 1-A Class that would have been required under the 
1938 Code, in Sec. 9.1.3, see “Selection of Construction Type.”  In 1963, the Port Authority of New York 
and New Jersey (PANYNJ or Port Authority) instructed the designers of the WTC to follow the then 
current 1938 NYC Building Code.  During this time, the code was in the process of being revised, and in 
1965, the Port Authority directed its designers to adopt the draft version of the new code for their final 
designs.  Some of the advantages of the new draft code were noted to be the following (Levy 1965): 

 

Fire towers

47

 could be eliminated; 

 

Provisions for exit stairs were more “lenient;” and 

 

Criteria for partition weights were more “realistic.” 

It was not certain whether all the changes being proposed to the 1938 code would be incorporated into the 
final version of the new code.  Thus in 1966, the Chief Engineer of the Port Authority suggested that the 
“architect/engineers prepare a listing of the elements of the design which do not conform to old code 
requirements, but are acceptable under the new.  With this list in hand, we could initiate discussions, at 
top level in the Building Department, to see if we can secure agreement to go along with our design 
(Kyle 1966).”  

A one-page document,

48

 dated “2/15/67”, with the initials “CKP” listed the following items: 

1.  Fire tower corridors [sic] eliminated. 

2.  Number of stairs reduced from 6 to 3. (Old plans had 5 stairs at 3’-8” 

and 1 stair at 4’-8” for a total population of 390. New plans have 2 
stairs at 3’-8” and 1 stair at 4’-8” allowing a population of 390.) 

3.  The size of doors leading to the stairs are [sic] changed from  

3’-8” to 3’-0”. 

                                                      

47

 A “fire tower” is a stair tower enclosed within a 4 h fire rated shaft that is entered through a naturally ventilated vestibule.  The 

1938 Code stipulated that one of the required exits in most buildings over 75 ft in height be a fire tower. 

48

 “Changes to Building to Conform to New York City Building Code,” dated 2/15/67. 

background image

Chapter 10 

 

Draft for Public Comment 

152

 

NIST NCSTAR 1-1, WTC Investigation 

 

4.  All stairs exit through a lobby. Old plans had fire tower stair exiting 

through a fire enclosed corridor. 

5.  Shaft walls are changed from a 3-hour rating to a 2-hour rating. 

6.  Corridors are limited to a 100’ dead end and with a 2-hour rating. 

7.  Additional [word(s) missing] changed from 20 pounds per square 

foot to 6 pounds per square foot (based on partition weight of 
50 pounds to 100 pounds per linear foot). 

Apparently, this list represents elements of the WTC design that would not have satisfied the 1938 code, 
but did satisfy the then-current draft version of the new code. 

Thus, the provision of three egress stairs located within the core exactly provided the 6½ units of required 
capacity for the occupant load in the office spaces.  By locating the stairs at the edges of the core it, could 
be argued that they were as far apart as practical, but on some floors the provision of transfer corridors to 
go around equipment and to recover tenant space from the termination of local elevator shafts brought the 
stairs quite close with far less than the one third the maximum travel distance of the floor  requirement of 
the 1968 NYC Building Code.  The proximity of the stairs on some floors also resulted in standpipe 
spacings that exceeded the maximum 140 ft distance from any point on a floor in the 1968 NYC Building 
Code, since the standpipes were located in the stairways. 

10.1.1 

Egress Provisions from Windows on the World 

The 106th and 107th floors of WTC 1 contained the 

Windows on the World

 complex, consisting of the 

Windows on the World

 restaurant, the 

Greatest Bar on Earth

, numerous banquet and function rooms, 

kitchens and support areas, and offices from which the operation was run.  While the configuration of the 
space may have changed over the life of the building these functions were all present from the time the 
building was first occupied.   

Restaurants, bars, and function rooms are classified in building codes as assembly use, which carries a 
significant increase in occupant load and consequent provisions for egress.  The design occupant load for 
assembly space is 15 ft

2

 per occupant as opposed to the 100 ft

2

 per occupant for the office use on most of 

the floors.  Thus, while the design number of occupants on an office floor was 390, the design number of 
occupants for these floors was over 1,000 each (the exact number depends on the area of kitchens, 
dishwashing, and office space on the floor, all of which is at 100 ft

2

 per occupant). 

Locating assembly space high in a building poses particular challenges to egress design since the capacity 
of an egress component is not permitted to be decreased in the direction of travel.  Thus where more or 
wider stairs are provided to meet capacity requirements these must be continued all the way down through 
the building with the associated impacts on space utilization.  

Since Windows on the World first opened in April 1976 (Bhol 2005), it is unclear what conditions existed 
from that date to the time the agreed solution was implemented in 1995.  The dates suggest that the need 
to provide for egress by the large occupant load of these floors was identified as a result of the 
Memorandum of Understandings between the Port Authority and the NYC Department of Buildings and 
FDNY executed in 1993 following the bombing.  The Windows on the World facilities were closed 

background image

Draft for Public Comment 

 

Influence of Codes and Standards 

NIST NCSTAR 1-1, WTC Investigation 

153

 

following the bombing and reopened in 1996 after a complete refurbishment that included the egress 
system changes (Bhol 2005). 

A letter dated January 27, 1995, from the PANYNJ to the Deputy Commissioner of the NYC Department 
of Buildings documents the confirmation of a meeting on December 6, 1994, at which they reached 
agreement on a plan to address egress requirements from the 106th and 107th floors (Fasullo 1995).  The 
details of the agreed solution are summarized below.  The Deputy Commissioner of the NYC Department 
of Buildings signed the letter to show concurrence with the agreed solution, as verification of meeting 
code requirements.   

The basis for the agreed solution was to divide each floor into three areas of refuge in accordance with 
Section 27-372 of the (then current) NYC Building Code to provide additional capacity to the existing 
stairs in accordance with Section 27-367 of the (then current) NYC Building Code.  Identical provisions 
were included in the version of the 1968 NYC Building Code in effect when the buildings were built as 
sections C26-604.5 and C26-603.3 respectively (the NYC Building Code was renumbered as the result of 
changes in New York State Laws, effective September 1, 1986). 

The code provisions cited above allow for a doubling of allowed stair capacity when one area of refuge is 
provided on a floor and tripling the stair capacity for two or more areas of refuge on a floor.  These areas 
of refuge must be separated by 2 h construction, be large enough for the expected occupant load at 3 ft

2

 

per occupant, each contain at least one stair, and have access to at least one elevator (above the 11th 
floor).  Since three distinct areas of refuge were provided on each floor, the tripling of the capacity of the 
three stairs resulted in a maximum permitted occupant load of 1,170 people per floor. 

Attached to (and referenced in) the letter were two plans entitled “106th Floor Egress Plan” and 
“107th Floor Egress Plan” that detailed the arrangement.  The 2 h separation walls snaked across the 
floors and were not aligned on the two floors.  Some areas that needed to remain open to free passage 
were protected with so-called Won-doors (accordion doors that are fire rated and are closed automatically 
on activation of the fire alarm system).  Details of the egress system design calculations and 
corresponding NYC Building Code requirements are included on the plans to demonstrate that they met 
code requirements.  Figures 10–1 and 10–2 are the actual attachments to the letter which included both 
diagrams of the arrangement of the rated partitions and the calculation of occupant loads for the 106th and 
107th floors, respectively.  Important details of the calculations have been enlarged by NIST. 

By comparison to the (current) model building codes, the International Building Code and NFPA 5000, 
permit a doubling (but not tripling except in IBC Type I-2 and I-3 institutional uses) of the stair capacity 
for the provision of a horizontal exit on a floor.  The horizontal exit must consist of a 2 h fire rated 
separation, contain at least one stair on each side, and have sufficient space for the expected occupant 
load at 3 ft

2

 per person.  A horizontal exit must be continuous down through the building to grade 

(NFPA 11.2.4.3.1 and IBC 1021.2), unless the floor assemblies are at least 2 h with no unprotected 
openings. 

 

background image

 

 

1

54 

NIST NCSTAR 1-1, WTC Investigatio

n

Cha

p

ter 10

 

Draft for Public

 Comment

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey.  Enhancement by NIST. 

Figure 10–1.  Arrangement of floor 106 egress. 

background image

 

 

NIST NCSTAR 1-1, WTC Investigatio

n

 

15
5

Draft for Public

 Comment

 

 

 

Influenc

e of Co

des an

d Stand

ards

 

Source:

 Reproduced with permission of The Port Authority of New York and New Jersey.  Enhancement by NIST.   

Figure 10–2.  Arrangement of floor 107 egress. 

background image

Chapter 10 

 

Draft for Public Comment 

156

 

NIST NCSTAR 1-1, WTC Investigation

 

The concept of using horizontal exits to create areas of refuge was to provide a protected space in which 
occupants could wait to get into stairs that do not have adequate capacity for the numbers of people.  In 
the world of post-September 11, 2001, it is unclear whether people will be comfortable waiting in a large 
queue to enter an egress stair, and what the impact would be of such a large group of people moving 
down the stairs on the orderly evacuation of lower floors.  The decedent analysis in NIST NCSTAR 1-7 
estimates the number of people in Windows on the World at 188.  The early hour of the attacks saw much 
fewer patrons (such as the early arrivals for a breakfast meeting) that would have been expected later in 
the day.  The occupant load would have permitted more than 2,000 people on these two floors, from 
which there were no survivors. 

10.1.2 

Egress Provisions from Top of the World 

Similar to the Windows on the World facilities on the 106th and 107th floors of WTC 1, there was a 
public observation deck on the 107th floor of WTC 2 called Top of the World.  The observation deck was 
open to the public daily and was accessed by a dedicated, express elevator from the Concourse level after 
paying an entrance fee.  The facilities included several shops, food vendor, a small theater showing a 
6 min film of a helicopter tour of New York City, exhibits depicting life in the city, and a perimeter 
viewing area with telescopes and information on major landmarks visible along each face of the building.  
Visitors could also ascend two escalators to an open, roof-top deck which was raised to provide 
unobstructed views. 

Observation decks are Assembly Use spaces (Group F in the NYC Building Code) like restaurants and 
meeting spaces.  Thus, the occupant load/egress capacity issues identified for Windows on the World also 
existed for Top of the World.  That is, the occupant load for the observation deck was calculated as the 
net floor area times a load factor of 10 ft

2

 per person.  This clearly far exceeded the 390 people total 

capacity for the three stairways.  Since NIST did not find any documentation of the arrangement of the 
space prior to 1995, it is unclear whether this deficiency existed from the original opening of the building 
until it was addressed in 1996. 

NIST has correspondence between Andrew Renter (STV/Silver & Ziskind, an Architectural/Engineering 
Design firm) and Victor Weisberg (Ogden Series Corporation, the tenant and operator of the facility) 
dated February 5, 1996, and referencing comments received from Port Authority on January 19, 1996.  
This letter and the drawings referenced in it (which are also in NIST’s possession) detail a proposed space 
arrangement that parallels the solution applied to Windows on the World the year before.  The letter and 
drawings are part of a Tenant Alteration submittal to Port Authority that was approved on January 5, 
1996.  STV proposes dividing the floor into three areas of refuge, each containing an existing stairway, by 
2 h fire rated partitions.  The drawings show the existing space arrangement of the floor and calculates the 
occupant load for each using the load factors specified in the NYC Building Code.  Their calculations 
reveal that the occupant load of the 107th floor was 1,751, which before the subdivision of the space into 
three areas of refuge, was 4½ times the maximum number of occupants permitted under the 
NYC Building Code. 

After the proposed subdivision, the floor had an area of refuge of 5,610 ft

2

 net (incorporating Stairway A) 

with an occupant load of 935 people, a second area of 2,430 net ft

2

 (incorporating Stairway B) with an 

occupant load of 343 people, and a third area of 2,940 net ft

2

 (incorporating Stairway C) with an occupant 

load of 473 people.  STV observed that the occupant load of the perimeter gallery alone is 1,267 people, 

background image

Draft for Public Comment 

 

Influence of Codes and Standards 

NIST NCSTAR 1-1, WTC Investigation 

157

 

which exceeds the stairway capacity of 1,170 after subdivision.  Under Sec. 27-367 of NYC Building 
Code, the stair capacities are tripled with the provision of three areas of refuge, taking the capacities to 
360 (Stairways A and C) and 450 (Stairway B) for a total of 1,170 people.  Thus, even after the 
subdivision, only the area incorporating Stairway B had an occupant load less than the maximum capacity 
of the stair, and one area had an occupant load more than 2½ times the stair capacity. 

These load calculations do not include the occupant load of the roof-top deck.  Since these occupants 
were required to return to the 107th floor to exit the facility, this load also needed to be accommodated by 
the stairways and the refuge space provided on that floor.  This fact is simply not addressed.  As to the 
fact that the proposed solution still does not provide sufficient egress capacity for the occupant load under 
the NYC Building Code, STV’s position appears to be that this is an existing condition and the solution 
(in their opinion) meets the intent of the Code, even though the problem existed from the time the 
building first opened against the 1968 NYC Building Code.  Taking advantage of a New York City 
building code provision which permits a lower basis for occupant load, the PANYNJ permitted a 
maximum occupant load of 1,170 on the floor, which was enforced by the lessee of the space with 
periodic oversight by the PANYNJ. 

NIST inquired of PANYNJ whether there was any means to limit the number of visitors to the 
observation deck.  The following response was received:

49

 

For controlling the number of occupants on the observation level in 
WTC 2, there were turnstiles on the mezzanine before the entrance to the 
elevators that were used to count the number of people going up, but 
since the patrons exited via a different route & location, there was no 
way to count the number of people leaving - and thereby calculate the 
number actually on the deck.  Since the turnstiles were not very effective, 
their use was discontinued later and the number of ticket sales was used 
for controlling the number of occupants.  The length of the line waiting 
for the elevators to take people down were constantly observed by staff. 
If the crowds grew too large, ticket sales were halted until the crowd size 
was reduced. 

Fewer than ten people who were present on the observation level perished on September 11th.  The 
number of perople who were present and managed to evaculate is unknown. 

10.2 ELEVATORS 

Local Law (LL) 5 (1973) required that elevators be provided with an emergency recall system.  This 
requirement was incorporated subsequently into the American Society of Mechanical Engineers (ASME) 
A17.1, Safety Code for Elevators and Escalators, that governs elevator design and operation in all 
building codes. The ASME Code requires that:  

 

All passenger elevators be marked with signs stating that they cannot be used during a fire;  

                                                      

49

 Email from Saroj Bhol, PANYNJ, to Shyam Sunder, NIST, dated March 15, 2005. 

background image

Chapter 10 

 

Draft for Public Comment 

158

 

NIST NCSTAR 1-1, WTC Investigation

 

 

Fire detectors installed in every elevator lobby and machine room be arranged to initiate a 
recall of the elevators to the ground floor where the doors open and the elevator is taken out 
of service; and 

 

Fire service personnel can use a special key to operate any individual car in a manual mode as 
long as they feel it is safe to do so. 

The elevator and building codes require that at least one elevator serving every floor be connected to 
emergency power.  Currently, there are no U.S. building codes that permit elevators to be used as a means 
of occupant egress in emergencies, and ASME A17.1 (ASME 2000) requires signs at all elevators 
warning that they shall not be used in fires.  There are some recent exceptions to this general rule, but 
these are limited to special cases.  For example, NFPA 5000 permits protected elevators as a secondary 
means of egress for air traffic control towers, and the City of Las Vegas accepted elevators as a primary 
means of occupant egress from Stratosphere Tower based on a performance-based design 
(Bukowski 2003).   

The United States’ building codes (including New York City) require 

accessible elevators

 as part of a 

means of egress that may be used by the fire service to evacuate people with disabilities.  These elevators 
must comply with the emergency operation requirements of ASME A17.1 (Phase II emergency operation 
by the fire service), be provided with emergency power, be accessible from an area of refuge or a 
horizontal exit (unless the building is fully sprinklered), and operate in a smoke protected hoistway.  
Phase II operation involves the use of an elevator by a firefighter for fire service access or for rescue of 
people with disabilities performed under manual control (with the use of a special key). 

10.3 

ACTIVE FIRE PROTECTION SYSTEMS 

10.3.1 Fire 

Alarm 

Systems 

At the time of design and construction of the WTC towers, most building codes did not require a fire 
alarm or required only a manual fire alarm system in buildings where occupants do not sleep.  Also, 
concerns about smoke recirculation through heating, ventilating, and air conditioning (HVAC) systems 
resulted in codes being amended to require smoke detectors positioned at return air grilles to stop fans and 
prevent such recirculation.   

In the 1970s (shortly after the adoption of LL 5/73), discussions of phased evacuation of tall buildings led 
to the concept of high-rise emergency voice communications systems and fire command centers from 
which incident commanders would manage fire incidents.  The NFPA Committee on Protective Signaling 
Systems developed a guide (later made a standard), NFPA 72F, for such systems that paralleled LL 5/73 
requirements (see NIST NCSTAR 1-1G for a complete discussion of the requirements of LL 5/73). 

10.3.2 Fire 

Sprinklers 

Neither the 1968 NYC Building Code nor any of the other contemporaneous codes that were examined 
required sprinklers in tall buildings except for underground spaces.  Thus, only the parking garage under 
WTC 1 and WTC 2 was originally sprinklered.  Although Local Law 16, adopted in 1984, required 
sprinklers in new office occupancies, it was not retroactive.  The incentive to retrofit for sprinklers (as 
explained below) was the passage of Local Law 5 in 1973, which was retroactive. 

background image

Draft for Public Comment 

 

Influence of Codes and Standards 

NIST NCSTAR 1-1, WTC Investigation 

159

 

In the 1968 NYC Building Code, Class 1B construction for business occupancies had no limit on floor 
area.  Local Law 5 required compartmentation of large floor areas in existing business occupancies over 
100 ft in height by the installation of fire rated partitions in accordance with the following:  

 

Compartmentation to 7,500 ft

2

 with 1 h partitions; or  

 

Compartmentation to 10,000 ft

2

 with 2 h partitions; or  

 

Compartmentation to 15,000 ft

2

 with 2 h partitions and smoke detectors. 

Compartmentation was not required, however, if  “complete sprinkler protection” was provided. 
Compliance dates for these provisions were revised in 1979 by Local Law 84, so that one-third of the 
total area of buildings had to be in compliance by December 13, 1981, two-third of the total area had to 
comply by August 7, 1984, and full compliance was required by February 7, 1988. 

Following the February 13, 1975, fire in the lower stories of WTC 1 (Powers 1975), an independent 
consultant was retained to review WTC life-safety provisions, including response to Local Law 5.  It is 
reported that the “consultant concluded that the existing structural fire retardants of the building are 
sufficient to make the probability of serious structural damage extremely remote and the degree of 
vertical compartmentation provided sufficiently limits the spread of fire in the structures but that the 
spread of smoke requires attention from a life safety standpoint (PONYA 1976).”  The consultant 
reported that “…either of the two fire protection options provided for under Local Law 5 would provide a 
good level of occupant life safety within the World Trade Center complex, provided that whichever is 
selected is supplemented by certain additional measures.”  The consultant provided a series of 
recommendations to supplement either the compartmentation option or the sprinklering option. 

The Port Authority initially decided to adopt the compartmentation option in response to Local Law 5.  
The summary of the January 1976 report on the 

Fire Safety of the World Trade Center

 lists the following 

actions to be implemented to enhance the fire safety of the WTC towers (PONYA 1976): 

1.  The openings between floors of telephone closets, which was a 

source of fire spread during the February 13, 1975, fire should be 
closed.  This work has been accomplished to prevent any 
reoccurrences of a similar condition. 

2. In addition, the Port Authority will proceed with the 

compartmentation option of Local Law 5, including all of its 
requirements for fire alarm, communications, and stairway 
pressurization. 

3.  Sprinklering of all storage rooms, janitor closets, mail rooms and file 

rooms in the central core of each floor. 

4.  Building additional sprinkler capacity and provisions for extension 

of a sprinkler system to any area of such usage requiring it in the 
event of an occupancy change. 

5.  Equipping those doors which are normally kept open to the corridor 

system, such as doors at consumer service areas, with 

background image

Chapter 10 

 

Draft for Public Comment 

160

 

NIST NCSTAR 1-1, WTC Investigation

 

electromagnetic ‘hold open’ devices which would be activated by 
smoke detectors to close the doors. 

6.  Providing fail-safe automatic door closers, arranged to close upon 

activation by smoke detectors, for the overhead rolling fire doors 
separating the below-grade truck dock from the elevator lobby. 

7.  Developing an optimum mode of operation of the building air-

conditioning system to remove smoke from the central core 
compartments without contaminating adjacent areas. 

Thus, while the Port Authority initially chose to implement the compartmentation option, it also chose to 
provide “for extension of sprinkler system to any area of such usage requiring it.”  According to the 
1993 joint report written by the NYC Fire Commissioner and Commissioner of Buildings, in the 1980s 
the Port Authority began “a program to fully sprinkler the tower buildings (Rivera and Rinaldi 1993).”  
The report goes on to state that by March 1993 sprinklering was “ nearly complete in tower 2 and 
85 percent complete in tower 1.”  The report also included a table that summarized “the major system 
requirements of Local Laws 5/73 and 16/84 with conditions in place when the 1993 explosion occurred.”   

The tenant alteration guidelines issued in 1998, contained the following requirement and information 
(PANYNJ 1998): 

All tenant spaces shall be sprinklered. Except for a few areas, most 
tenant floors in The World Trade Center are provided with wet-pipe 
sprinkler systems.  New tenants normally require a new sprinkler system. 
For renovations of existing spaces, modifications to the existing system 
are normally needed to comply with any new partition configuration. 

Because Local Law 16 required that business occupancies taller than 100 ft be sprinklered, WTC 7 was 
sprinklered during the original construction. 

Section 6 of Local Law 5 adopted by New York City in 1973, required the subdivision of unsprinklered 
space in new office occupancies and in existing offices over 100 ft in height by fire rated partitions.  
Local Law 5 was challenged in the courts and was eventually upheld, although the original compliance 
dates were amended by Local Law 86 (1979) so that full compliance was required by February 7, 1988.   

10.3.3 Smoke 

Management 

New York City has historically had fewer requirements for active smoke control than many other codes 
and has required passive techniques such as venting of shafts and openable skylights in stairways in the 
local laws amending the NYC Building Code.  For high-rise buildings there is a requirement for a smoke 
purge system to be used manually by the fire department to remove smoke after the fire is extinguished 
and for the ability to pressurize corridors with 100 percent fresh air (NYC Building Code Sec. 504.15(c)).  
Pressurized stairways are not required in sprinklered buildings.  These features of WTC 1 and WTC 2 
were confirmed in a March 1993 joint report from the fire and buildings departments on compliance with 
LL 5/73 and LL 16/84 (Rivera and Rinaldi 1993).  For details of the smoke management systems see 
NIST NCSTAR 1-4D. 

background image

Draft for Public Comment 

 

Influence of Codes and Standards 

NIST NCSTAR 1-1, WTC Investigation 

161

 

10.4 

DESIGN AND CONSTRUCTION OF FIRE SAFETY AND EGRESS 
SYSTEMS 

10.4.1 Construction 

Classification 

No contemporaneous documentation has been found that provides the rationale for the decision to select 
Class 1B for the WTC towers.  This decision, however, appears to have been made by the architect-of-
record on the basis of economics.  In a 1987 memorandum on the subject of fire rating of the WTC 
buildings, the following statement was included (Feld 1987): 

For office buildings there is no [underline is in the original document] 
economic advantage in using Class 1A Construction, and ER&S [Emery 
Roth & Sons] used Class 1B Construction for the WTC Towers and 
Plaza Buildings which are Occupancy Group “E” (Business) with a fire 
index of 2 hours. 

An interoffice memorandum between staff of the general contractor written in 1969 is the only 
contemporaneous document found to date that refers to the classification of the WTC towers 
(Bracco 1969).  The following statement is included in that memorandum: 

The WTC towers would be classified, by our interpretation of the code, 
as occupancy Group E, Business; Construction Group 1, Non-
combustible; and Construction Classification 1-B (since there are no area 
or height limitations applicable). 

10.4.2 Occupancy 

Group 

As stated above, the primary occupancy group was Group B (Business) with the Windows on the World 
space in WTC 1 being Group F (Assembly).  While there was a Port Authority cafeteria on the 44th floor, 
employee cafeterias not open to the public are specifically exempted from assembly classification because 
they do not increase occupant load and are only used intermittently.  Incidental mercantile spaces such as 
news stands and coffee bars at the concourse level are also exempt from reclassification in most building 
codes. 

10.4.3 

Compartmentation of WTC 1 and WTC 2 

Due to their innovative structural design, WTC 1 and WTC 2 featured large, open office spaces devoid of 
columns.  Tenants could (and often did) utilize open plan office layouts that allowed impressive views of 
the Manhattan skyline from the perimeter windows.   

The NYC Building Code and Port Authority practice required partitions to separate tenant spaces from 
each other and from common spaces, such as the corridors that served the elevators, stairs and other 
common spaces in the building core.  Fire rated partitions are intended to limit fire spread on a floor and 
to prevent spread of fire in one tenant space to another.  Partitions separating tenant space from exit 
access corridors were permitted to be 1 h, although the PANYNJ specified them to be 2 h, allowing dead 
ends to extend to 100 ft (rather than 50 ft with 1 h partitions), which allowed more flexibility in tenant 
layouts.  Partitions separating tenant spaces (so-called demising walls) were required to be 1 h (see 
Sec. 9.2.5).  Enclosures for vertical shafts, including stairways and transfer corridors, elevator hoistways, 

background image

Chapter 10 

 

Draft for Public Comment 

162

 

NIST NCSTAR 1-1, WTC Investigation

 

and mechanical or utility shafts were required to be of 2 h fire rated construction.  Protection of vertical 
shafts was intended to limit the spread of fire and smoke from floor to floor. 

Another influence on compartmentation of the buildings was the adoption of Local Law 5 (1973) 
amending the NYC Building Code.  While it did not legally apply to the buildings, PANYNJ policy was 
to follow the NYC Building Code requirements voluntarily.  Local Law 5 (1973) required 
compartmentation of unsprinklered spaces in existing office buildings over 100 ft in height “having air-
conditioning and/or mechanical ventilation systems that serve more than the floor on which the equipment 
is located,” to be subdivided by 1 h fire separations into spaces or compartments not to exceed 7,500 ft

2

.  

Floor areas could be increased up to 15,000 ft

2

 if protected by 2 h fire resistive construction and smoke 

detectors.  Regardless of the floor area, compartmentation is not required when complete sprinkler 
protection is provided (LL 5, Section 6) 

Shortly after the adoption of LL 5 (1973), the PANYNJ began to add the required compartmentation as a 
part of new tenant layouts as evidenced by several tenant alteration contracts at this time.  Following the 
1975 fire, a fire safety consultant report recommended to the PANYNJ that the buildings be retrofit with 
sprinklers to address possible smoke problems, and the PANYNJ realized that this would also obviate the 
need for compartmentation and permit the unobstructed views for which the buildings were known.  The 
decision to sprinkler left the arrangement again with the only required partitions being those separating 
tenant spaces from each other and from exit access corridors or common spaces in the core, and with shaft 
enclosures. 

10.4.4 

Construction of Partitions and Shaft Enclosures 

Vertical shafts surrounding stairs, mechanical shafts 
(carrying supply and return air), elevator hoistways, 
and utility shafts were all contained within the 
building core, and were enclosed by gypsum 
planking similar to fire separations commonly used 
today in single-family attached housing.  While 
similar to other gypsum shaft wall systems and 
firewalls, this system was unique and innovative in 
that it eliminated the need for any framing.  The 
gypsum planks were solid 2 in. thick (2½ in. on 
floors with 16 ft ceiling heights) and 16 in. wide, 
with metal tongue or groove channels attached to 
the long sides that served as wall studs (see  
Fig. 10–3).  Where planks were cut to a narrower 
width, the cut edge was covered with a 2 in. by 
2 in. metal C channel fastened with drywall screws at the top and bottom.  Each plank had a mesh layer at 
its mid thickness and were likely custom fabricated for this job as NIST found no mention of similar 
products in gypsum industry literature of the time or since.  Planks were provided in 12 ft, 14 ft, and 16 ft 
lengths to run full height.  The planks were placed into metal L channels at the bottom and into metal top 
channels of various shapes depending on the construction element with which it needed to interface (see 
Fig. 10–4).  

Figure 10–3.  Gypsum plank shaft partition.

 

 

Source:

 WTC 1&2 drawing A*A*209.  Reproduced with 

permission of The Port Authority of New York and 
New Jersey.

 

background image

Draft for Public Comment 

 

Influence of Codes and Standards 

NIST NCSTAR 1-1, WTC Investigation 

163

 

Source:

 WTC 1&2 drawing A*A*209.  Reproduced with 

permission from The Port Authority of New York and 
New Jersey. 

 

Source:

 WTC 1&2 drawing A*A*209.  Reproduced with permission of The Port Authority of New York and 

New Jersey. 

Figure 10–4.  Gypsum plank installation. 

 

A large number of detail drawings were provided 
for attaching the planks to various ceiling 
constructions (A*A* 209 through A*A*212, see 
Fig. 10–5).  Finish layers were either one or two 
layers of ½ in. gypsum board (moisture resistant 
was specified in some locations).  Two layers on 
one side were specified in locations where the 
other side was a shaft or other unoccupied space, 
and two layers on one side with a single layer on 
the other was specified where both sides were in 
occupied spaces.  The required number of layers 
was indicated on construction drawings 
(e.g., A*A*20, A*A* 50) by the numbers 1 or 2 in 
triangles (see Fig. 10–6).   

 

 

Source:

 WTC 1&2 26th Floor Core Plan drawing A*A*50.  Reproduced with permission of The 

Port Authority of New York and New Jersey. 

Figure 10–6.  Stairway detail at 26th floor.

 

Figure 10–5.  Typical finish details. 

background image

Chapter 10 

 

Draft for Public Comment 

164

 

NIST NCSTAR 1-1, WTC Investigation

 

The 1978 edition of the Gypsum Association (GA) Fire Resistance Design Manual lists several, similar 
shaft wall constructions utilizing 2 in. gypsum layers consisting of two 1 in. gypsum core board panels 
with “metal channels on long edges.”  The GA Manual lists shaft walls of a single 2 in. metal edged plank 
(WP7015) having a 1 h fire rating, a single 2 in. metal edged plank with one layer of Type X gypsum 
board on the unexposed side (WP7112) having a 2 h fire rating, and a single 2 in. metal edged plank with 
two layers of Type X gypsum board on the unexposed side (WP 7575) having a 3 h fire rating. 

Partitions separating tenant spaces from other tenant spaces on the same floor were constructed of two 
layers of 5/8 in. Type X gypsum board on each side of steel studs, and ran slab to slab.  This construction 
is commonly recognized as a 2 h fire separation.  Above the ceiling, penetrations for ducts or to allow for 
return airflow were fitted with rated fire dampers to preserve the fire rating.  This construction was not 
used in the original design but was specified later by the PANYNJ as tenant spaces were altered.   

Interior partitions not separating spaces occupied by different tenants were constructed of single or double 
layers of 5/8 in. Type X gypsum board on each side of steel studs and ran from the slab to the suspended 
ceiling but not above.  Double layers of gypsum board were used when the tenant desired additional 
sound attenuation.  These partitions were not required to be fire rated and did not utilize fire rated doors.  
However, a single layer of 5/8 in. Type X gypsum board on each side of steel studs (16 in. on center) is 
generally considered to have a 1 h fire rating, and two layers of 5/8 in. Type X gypsum on each side of 
steel studs (16 in. on center) is considered to have a 2 h fire rating.  For a ceiling high partition to be 
considered as having a fire rating, the ceiling itself would have to be rated as well.  The ceiling system 
used throughout these buildings was not fire rated. 

10.4.5 

Tenant Separation Walls 

Section C26-504.3(a) of the 1968 NYC Building Code required that tenant spaces be separated “by fire 
separations having at least the fire resistance rating prescribed in Table 5–1, but in no case less than 1 h, 
and shall continue through any concealed spaces of the floor or roof construction above.”  The Port 
Authority chose to stop tenant (demising) partitions (walls separating spaces occupied by different 
tenants) at the bottom of the suspended ceiling and use 10 ft strips of 1 h rated ceiling on either side of the 
partition (Solomon 1969).  The general contractor stated in a letter to the Port Authority “…we have been 
unable to find any precedent for the fire rated ceiling 10’ on either side of the demising partitions beyond 
the one you described from your construction experience on Port Authority hangers [sic] (Endler 1969).” 

In a code compliance evaluation report written in 1997, it was stated “Tenant demising partitions, 
including separations from the public corridor, do not in all cases meet the requirement of being built to 
the slab above (Coty 1997).”  The author of the report recommended that: “Generally, this condition has 
been and will continue to be remediated as a requirement of new tenant alterations.  However, it is 
recommended that the Port Authority develop and implement a survey program to ensure that this 
remediation process occurs as quickly as possible.” 

The tenant alteration guidelines issued in 1998 required that tenant partitions have a 1 h fire rating, and 
the standard details for fire rated partitions indicated a continuous fire barrier from top of floor to bottom 
of slab (PANYNJ 1998).  There were no requirements in the codes or in the PANYNJ guidelines for 
partitions wholly within tenant spaces. 

background image

Draft for Public Comment 

 

Influence of Codes and Standards 

NIST NCSTAR 1-1, WTC Investigation 

165

 

10.4.6 Egress 

Systems 

The primary egress system for the office spaces was the three stairways located in the building core.  
These included two 44 in. (designated A and C) and one 56 in. wide (designated B) stairs which provided 
exactly the code required capacity for an occupant load of 390 per floor (39,000 ft

2

 net at 100 ft

2

 per 

person).  The layout within the building core was consistent with the building code requirements for 
maximum travel distance (200 ft unsprinklered, 300 ft sprinklered) and, while the separation was 
consistent with New York City requirements (15 ft and later 30 ft), it was short of the more common 
requirements found in all current building codes (one half the diagonal of the space served if 
unsprinklered, or one-third the diagonal if sprinklered) on some of the floors where the transfer corridors 
brought the stair access closer together. 

The NYC Building Code uses the older “units of exit width” method for specifying exit capacity.  Each 
22 in. unit of exit width in an office stair provides the capacity for 60 people.  Thus, each 44 in. stair 
provides for 120 people and the 56 in. stair provides 2½ units, or 150 people, for a total occupant load per 
floor of 390.  Also, the PANYNJ made a design decision to use 2 h corridor walls to permit longer dead 
ends (100 ft rather than the 50 ft limit if the walls had been the minimum 1 h rating) to provide additional 
flexibility in tenant layouts.  For a detailed description of the stairways, see NIST NCSTAR 1-7. 

10.4.7 Elevators 

There were 99 passenger elevators and 7 freight elevators in each tower, arranged in three vertical zones 
to move occupants in stages to skylobbies on the 44th and 78th floors.  The elevators were arranged as 
express (generally larger cars that moved at higher speeds) and local elevators in an innovative system 
first introduced in WTC 1 and WTC 2.  There were eight express elevators from the concourse to 44 and 
ten express elevators from the concourse to 78 as well as 24 local elevators per zone, which served groups 
of floors in those zones.  There were seven freight elevators, only one of which served all floors.  All 
elevators had been upgraded to incorporate firefighter emergency operation consistent with ASME A17.1 
and Local Law 5 (1973).  See also NIST NCSTAR 1-7. 

10.4.8 Active 

Systems 

Fire Alarm Systems 

Consistent with practice at the time, the original fire alarm system in WTC 1 and WTC 2 was a manual 
system with four smoke detectors on each tenant floor, positioned to monitor smoke entering the HVAC 
returns and arranged to stop the fans and prevent smoke circulation to non-fire areas.  Local Law 5 (1973) 
included retroactive requirements for fire alarm systems and emergency voice communication systems in 
business occupancies over 100 ft in height.  Subsequently, such systems were installed in WTC 1 and 
WTC 2 with the required fire command center located in the underground parking garage where it was 
destroyed by the blast in the 1993 bombing rendering most fire safety features inoperable.  Following the 
1993 bombing, the fire command stations were relocated to the tower building lobbies with a third 
monitoring location in the Port Authority offices.  The lobby location (within sight of the elevators) is 
specified in the NYC Building Code for fire command centers required in high-rise buildings.  There are 
no code requirements for off-site monitoring of fire alarm systems in this occupancy.  For a detailed 

background image

Chapter 10 

 

Draft for Public Comment 

166

 

NIST NCSTAR 1-1, WTC Investigation

 

description of the towers’ fire alarm system on September 11, 2001, and prior systems back to the 
original, see NIST NCSTAR 1-4C. 

Fire Sprinkler Systems 

After the passage of Local Law 5, the Port Authority implemented a program to retrofit sprinklers and to 
offer tenants the option of sprinklering or compartmentation consistent with Local Law 5 provisions.  
Sprinklering of WTC 1 and WTC 2 was undertaken in three phases: Phase 1 was the sprinklering of 
below grade spaces completed with the original construction.  Phase 2 was begun after Local Law 5 was 
adopted and included the installation of sprinkler risers and other infrastructure, and the installation of 
sprinklers in corridors, storage rooms, lobbies, and smaller tenant spaces for tenants not selecting the 
compartmentation option.  Phase 3 involved sprinklering the remaining tenant spaces, initially as tenants 
changed, and later on negotiated schedules.  This process was underway when, in 1984, Local Law 16 
was adopted, which required sprinklers in high-rise buildings, including new offices and new or existing 
hotels.  Following the settlement of legal challenges to LL 5 (1973), LL 84 (1979) changed the effective 
date for compliance with LL 5 (1973) to February 8, 1988.  By the new date, high-rise office buildings 
had to either be subdivided in accordance with the compartmentation requirement or sprinklered.  A 1997 
report states that there were four floors and the skylobbies (all in WTC 1) left to be sprinklered, and that 
the installation of sprinklers at these floors was underway (Coty 1997).  In an October 1999 report, it is 
stated that sprinklering of the tenant floors was completed and sprinklering of the skylobbies was 
“currently underway” (PANYNJ 1999). 

The sprinkler system in the towers was a high-quality, state-of-the-art system with a few features 
following New York City practice that differed from practice in the rest of the country.  An example of 
the quality is the decision by the PANYNJ to install separate risers rather than to use the existing 
standpipes as was permitted.  An example of New York City practice is the use of manually operated fire 
pumps and a so-called “standpipe telephone system” to communicate with the pump operator.  Most 
codes and standards require automatic fire pumps.  On September 11, 2001, the fire department was 
unable to deploy operators to the pumps, so they were not used.  Since the risers were breached by the 
aircraft impact, the lack of pumps may have been inconsequential.  For a detailed description of the 
towers sprinkler system see NIST NCSTAR 1-4B. 

Smoke Management 

The towers were originally constructed with vents in elevator and utility shafts in accordance with NYC 
Reference Standard RS 18-1.  In addition, smoke detectors were installed at each of the four return vents 
on each floor to stop fans and prevent recirculation of smoke.   

Later, LL 5 (1973) Section 7 (revised by LL 86, Sec. 2) added a requirement for smoke shafts (new) or 
pressurized stairways (existing) with an exemption for fully sprinklered buildings.  The 1976 decision to 
sprinkler the towers relieved the need to add stair pressurization. 

Local Law 16 (1984) Section 53 contained requirements for segregation of ventilation systems and a 
smoke purge capability.  These were addressed through the design and installation of an active system of 
smoke management that provided a manually activated smoke purge and pressurization of corridors with 
100 percent outside air.  These systems are described in detail in NIST NCSTAR 1-4C. 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

167

 

Chapter 11 

M

AINTENANCE AND 

M

ODIFICATIONS TO 

F

IRE 

S

AFETY 

S

YSTEMS

 

The Port Authority of New York and New Jersey (PANYNJ or Port Authority) was very conscientious in 
providing guidance to tenants about their use of space in the World Trade Center (WTC) buildings.  The 
Port Authority published tenant alteration manuals that detailed how tenant space could be fitted.  There 
were manuals for interfacing with the building fire alarm system, the building fire sprinkler system, and 
other special systems installed in the buildings.  National Institute of Standards and Technology (NIST) 
located at least partial copies of most of these manuals. 

When a tenant space was remodeled, such as to accommodate the needs of a new tenant, the process was 
for the tenant to hire an architect or interior designer to design the space, following the tenant alteration 
manual.  If the tenant occupied less than an entire floor, they could opt to have the PANYNJ handle most 
of the modifications through their existing contracts, or they could contract independently as the larger 
tenants generally did.  Creation or movement of interior partitions often required moving of sprinkler 
heads or fire detectors.  Also, whenever the suspended ceiling was pulled the PANYNJ required that the 
spray applied fireproofing be inspected and upgraded (if needed) after the other trades had finished and 
before the ceiling was reinstalled.  The PANYNJ office reviewed and approved plans at the start of a 
tenant project and conducted inspections prior to the tenant moving in. 

Whenever work was done in the buildings, a project number was assigned by the PANYNJ under which 
all contracts, drawings, and correspondence were filed.  These numbers are of the format W(yy)-1234 
(where yy is the year initiated and 1234 is a 4 digit number).  The reports include these numbers as 
reference for individual projects, and files retained by the PANYNJ are identified by these numbers. 

The PANYNJ also conducted numerous inspections and condition surveys which were beyond any 
requirements in New York City and other codes and practices, and generally implemented corrective 
action to address problems identified.   

11.1 

LOCAL LAWS 5 (1973) AND 16 (1984) 

In general, buildings are governed by the building code in force at the time the building permits are 
issued, except in the rare case of the adoption of retroactive requirements.  Local Laws (LLs) 5 (1973) 
and 16 (1984) were adopted after completion of WTC 1 and WTC 2 but did contain some retroactive 
provisions.  However, the PANYNJ chose to implement virtually all of the provisions of LL 5 (1973) and 
LL 16 (1984), which drove most of the modifications to the fire and life safety systems that occurred over 
the life of the buildings.  These modifications included the complete sprinklering of the buildings and 
several upgrades to the fire alarm system. 

Several requirements in LL 5 (1973) were retroactive to existing office buildings over 100 ft in height.  
These included evacuation drills and planning, fire safety directors and wardens, and requirements for re-
entry from stairs every four floors with signs in the stairs identifying re-entry floors.  Provisions regarding 
compartmentation requirements for unsprinklered spaces, smoke and heat venting, sprinklers in 

background image

Chapter 11 

 

Draft for Public Comment 

168

 

NIST NCSTAR 1-1, WTC Investigation

 

showrooms, permitting standpipes to be used as sprinkler risers, fire alarm and voice communication 
systems with a fire command center, and one elevator serving every floor supplied with emergency power 
that can be used by the fire department were also included.  LL 16 (1984) extended retroactive provisions 
for sprinklers, fire alarm and communication systems (with fire command center), a fire service elevator 
connected to emergency power, and exit lighting and signage, to most occupancy types.  LL 16 (1984) 
added construction class 1C (sprinklered high rise) and removed the compartmentation requirement added 
by LL 5 (1973), since these buildings were now required to be sprinklered.   

11.2 

CODE COMPLIANCE SUMMARY FOLLOWING THE 1993 BOMBING 

In the aftermath of the 1993 bombing, the exemption of PANYNJ facilities from regulation under the 
NYC Building Code was once more being questioned.  The Fire Commissioner and Commissioner of 
Buildings co-authored a report on the state of various properties in New York City that were exempt from 
City oversight (Rivera and Rinaldi 1993).  They recommended that the States of New York and New 
Jersey enact legislation making all Public Benefit Corporations, including the Urban Development 
Corporation and The PANYNJ, subject to the New York City building regulations.  The City had even 
drafted such legislation and submitted it to Albany in 1975 (Rivera and Rinaldi 1993, Attachment I).  
They report that as of the date of their report the legislation had not been enacted. 

The Rivera and Rinaldi report includes a summary of code compliance at the WTC, including the history 
of code compliance discussions between City departments and PANYNJ, and that “the trend in recent 
years has been towards cooperation,” citing the sprinklering of the towers (Rivera and Rinaldi 1993, 
page 6).  The report goes on to say that, “since its compliance with fire code requirements was dependent 
upon economic and design feasibility, the PA[NYNJ] agreed to comply with selected provisions of the 
code, but has not fully done so.  Moreover, it was difficult for the Fire Department to monitor code 
compliance by the WTC because the WTC consistently asserted its legal exemption from local law.  Fire 
officials relied on persuasion and negotiation to gain compliance.” (Rivera and Rinaldi 1993, page 6). 

Regarding compliance at the time of the explosion, Rivera and Rinaldi report that “a preliminary review 
by the NYC Department of Buildings generally indicates that the WTC complies with the specific 
provisions of Local Law 5/73 and Local Law 16/84, or provides acceptable equivalent systems.” (Rivera 
and Rinaldi 1993, page 7)  They go on to say that the WTC exceeds the requirements of these local laws 
in several areas, including emergency power, smoke purge, and corridor pressurization.  They cite the fire 
alarm system as a “major departure” from the requirements of the local laws because each building does 
not have its own fire command station, they have only one pull station per floor, and they do not provide 
public address to all areas on all floors.  These deficiencies were addressed by the PANYNJ as discussed 
in NIST NCSTAR 1-4C.  Several newly discovered deficiencies regarding occupant egress provisions are 
also mentioned (Rivera and Rinaldi 1993, page 10). 

The position of the PANYNJ was summarized in a statement by Stanly Brezenhoff, Executive Director 
PANYNJ before the New York City Council, Committee on Housing and Buildings on March 26, 1993 
(Rivera and Rinaldi 1993, Attachment F).  On page 8 of his statement, Brezenhoff states that the 
PANYNJ has a “tradition of designing for high standards of structural integrity, and our policy of 
 
voluntarily meeting or even exceeding code requirements.”  Brezenhoff goes on to give examples of 
meeting or exceeding building code standards for structural integrity such as,  

background image

Draft for Public Comment 

 

Maintenance and Modifications to Fire Safety Systems 

NIST NCSTAR 1-1, WTC Investigation 

169

 

 

The towers have three stairs for fire egress, rather than two required by code 

 

The towers comply with or exceed code provisions controlling fire protection of structural 
members, floors and partitions, and enclosure of shafts 

 

The office floors can support 100 lb/ft

2

, twice the code requirement 

 

The towers were designed for wind speeds approximately twice those in the code. 

11.3 

WTC DUE DILIGENCE STUDY OF NOVEMBER 22, 1996 

In late 1996, the PANYNJ contracted with Rolf Jensen & Associates (RJA) and Jaros, Baum & Bolles 
(JB&B) to conduct a study of code compliance at the WTC buildings.  These reports, along with issues 
identified by the World Trade Department of PANYNJ, were summarized in a report dated October 15, 
1999 (PANYNJ 1999).  This study appears to be related to the Memorandum of Understanding between 
PANYNJ and the New York City Department of Buildings which provides for oversight by professionals 
licensed to practice in New York State reporting to PANYNJ with these reports available for review by 
the City. 

Of particular interest is the division of the items identified in the report into categories: 

 

Category A was non-conforming code items which will remain as such or for which no plans 
will be prepared to accommodate the code, 

 

Category B was non-conforming items which have been remedied, or are currently in 
progress, 

 

Category C was non-conforming code items whose remediation plans are currently being 
prepared or will be prepared in the near future, and  

 

Category D was items of policy, business, leases, repair, and operations (RJA report only). 

Items in Category A included the issue of the discharge of Stairways A and C on the mezzanine level 
when the Code required exit stair discharge to a level “opening onto a public way.”  This was resolved by 
an agreement between the PANYNJ and the NYC Department of Buildings that the Plaza was like a 
public way, and the Concourse was an “underground street.”  Also in this category is the issue of exit stair 
venting.   

Category B included structural fireproofing, which was “judged adequate” by RJA providing that all 
floors in both towers were sprinklered and re-fireproofing “to the appropriate thickness for a 2 h rating” 
was continued.  The 1997 RJA report (which is Attachment A to PANYNJ 1999) actually states, “… the 
protection provided by the automatic sprinkler systems will mitigate the fact that the towers’ structural 
steel fireproofing fall somewhat short of that required to provide a 2 h rating.”  The RJA report also states 
that it is their understanding that the PANYNJ “has been currently been [sic] installing and will continue 
to install 1½ in. thick steel fireproofing based on UL Design No. G508.” 

background image

Chapter 11 

 

Draft for Public Comment 

170

 

NIST NCSTAR 1-1, WTC Investigation

 

This category also includes the topic “remediating tenant separation walls and public corridor walls to 
conform to code requirements.”  Here the RJA report states that “Tenant demising partitions, including 
separations from the public corridor, do not in all cases meet the requirement of being built to the slab 
above.”   

Items also in this category that were mentioned by Rivera and Rinaldi as major departures from the local 
laws with regard to the fire alarm system included the lack of individual fire command stations for each 
building, additional manual stations and public address speakers needed. 

Category C included mechanical rooms with doors directly into egress stairs (which is expressly 
prohibited), location of standpipe hose stations on some floors (as the stairways move closer together the 
standpipe connection may exceed the 145 ft distance limit to any point on a floor), and egress issues at the 
Mall and B-1 levels. 

The JB&B report identified firestopping (at penetrations of fire rated assemblies such as pipes passing 
through floors) in Category C as a general issue in the towers.  Their report also identified a number of 
electrical safety issues throughout the complex. 

Category D included smoke control on the PATH mezzanine to prevent smoke from reaching the Mall, 
formal responsibility for overseeing code conformance for both base building and Tenant projects, and 
the lack of a Certificate of Occupancy for the buildings. 

 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

171

 

Chapter 12 

WTC

 

7

 

F

UEL 

S

YSTEM

 

World Trade Center (WTC) 7 was constructed and owned by Silverstein Properties (Silverstein) on land 
owned by the Port Authority of New York and New Jersey (Port Authority).  It was built and operated by 
Silverstein as a Port Authority tenant alteration.  Many of the tenants conducted critical business 
operations in the building and required uninterruptible power to prevent the loss of information or 
operational continuity in the event of a power failure.  Backup power was provided by diesel generators 
located in the mechanical spaces of the building.  These generators were designed to start automatically in 
the event of an interruption of the utility supply.  The total generator capacity and quantity of fuel stored 
in the building was sized to tenant needs. 

12.1 CODE 

REQUIREMENTS 

Design and installation of the WTC 7 emergency power and associated fuel systems was consistent with 
the 1968 New York City (NYC) Building Code.  The base system was installed in 1987 with 
modifications occurring in 1990, 1994, and 1999.  Over the period 1987 to 1999, the NYC Building Code 
provisions discussed below were not changed, so all systems were installed to the same requirements.  
Some of the key code provisions for the construction and location of fuel storage tanks, piping, and 
controls are discussed here, and additional details are contained in NIST NCSTAR 1-1A. 

12.1.1 

Tanks (27-828 and 27-829)

 50

 

All tanks must be fabricated of steel and coated to prevent corrosion.  Minimum thicknesses are specified 
by tank diameter for storage tanks and for so-called “day tanks” (60 gal or 275 gal).  Large storage tanks 
(up to 20,000 gal) may be buried inside or outside the building or on the lowers floor of the building with 
protection related to the tank capacity.  For example, tanks from 550 gal to 1,100 gal must be enclosed in 
2 h fire rated, noncombustible construction and tanks larger than 1,100 gal in 3 h construction.  

Tanks on floors above the lowest floor are limited to 275 gal and one such tank per story.  These “day 
tanks” must be surrounded by a concrete curb or steel pan with the capacity to hold twice the volume of 
the tank in the event of a leak.  The curb or pan must be provided with a float switch to sound an alarm 
and shut off the transfer pump in case of tank failure.  Appropriate controls (generally a float switch in the 
day tank) must be provided to transfer fuel from the storage tanks to the day tank through a transfer pump 
and piping, with only one such transfer pump and piping network per day tank.  

12.1.2 Piping 

(27-830)

37

 

Piping from transfer pumps to day tanks is required to be enclosed in a shaft of 4 in. thick concrete or 
masonry with a 4 in. clearance to the fuel pipe.  Horizontal offsets may be enclosed in a steel sleeve two 

                                                      

50

 Sections of the NYC Building Code in which these requirements are found.  These provisions are found in the subchapter on 

“Heating and Combustion Equipment.” 

background image

Chapter 12 

 

Draft for Public Comment 

172

 

NIST NCSTAR 1-1, WTC Investigation

 

(pipe) sizes larger and enclosed in 2 h fire rated construction.  The spaces between the fuel pipe and 
sleeve or shaft must lead to an open sight drain or an open sump so leaks can be detected. 

12.1.3 

Power Systems Designs 

National Institute of Standards and Technology (NIST) located and reviewed specifications and drawings 
for each of the emergency power systems.  Some of the fuel risers were installed in existing shafts 
containing other utilities.  The NYC Building Code requires that pipe shafts containing piping from the 
transfer pump to storage tanks above the lower floors not be penetrated by or contain other piping or ducts 
(27-830(f)(5)).  Correspondence relating to the system for the Mayor’s Office of Emergency Management 
shows that this system was reviewed and inspected by the New York City Fire Department (FDNY), a list 
of needed corrections was produced, and each item was initialed as the corrections were verified. 

12.2 

BASE BUILDING SYSTEM 

The initial base emergency power system was installed in 1987, and consisted of two 900 kW generators 
and a 275 gal day tank located on floor 5.  Main fuel storage was in two 12,000 gal tanks buried under the 
loading dock on the south side of the building.  The tanks were double wall fiberglass

51

 with leak 

detectors between the walls.  

Fuel was transferred by one of the two pumps through a 2 in. supply line in an existing shaft containing 
other utilities, near the west bank of passenger elevators.  The transfer pump was controlled by a float 
switch in the day tank with a low (pump on) and a high (pump off) position.  An alarm would be sounded 
if the fuel level in the day tank fell below the low level or went above the high level.  The day tank was 
located within a 550 gal pan fitted with an alarm and another pump cutoff.  The vent for the day tank 
terminated outside the south wall. 

The 2 in. fuel lines were encased in a second pipe covered with 2 in. of calcium silicate to provide the 
required 2 h fire rating.  Pipe supports were located approximately 10 ft apart, and inspection plugs were 
provided approximately 50 ft apart.  Mechanical equipment rooms were sprinklered (ordinary hazard 
group I), and the fuel pump room was sprinklered (ordinary hazard group III).  The generator area on 
floor 5 was not sprinklered. 

12.2.1 

Modifications to System 

From 1990 to 1999, four major modifications (additions) were made to the base emergency power 
system.  These modifications are summarized in Table 12–1.  Of significance are the 1990 modification 
(Salomon Brothers) that required a pressurized fuel supply system, because a day tank already existed on 
floor 5, and the 1999 modification (Mayors’ Office of Emergency Management) that required a separate 
6,000 gal tank on the first floor.  Figure 12–1 is a schematic of the locations of the various components of 
the base system and the four major modifications. 

                                                      

51

 While the NYC Building Code  requires steel tanks, effective in November 1985 the U.S. Environmental Protection Agency 

required (40CFR280) that all new underground fuel storage tanks be double wall fiberglass and that any steel tanks older than 
20 years be replaced by double wall fiberglass. 

background image

Draft for Public Comment 

 

WTC 7 Fuel System 

NIST NCSTAR 1-1, WTC Investigation 

173

 

For the Salomon Brothers system, the transfer pumps were powered from the output of the generators.  In 
the event of a failure of utility power, all nine generators were started automatically to ensure that if any 
of the nine did not start there would be enough power.  Once the generators were up to speed, the control 
system would shut down those that were not needed, but these could be restarted later if power demand 
increased.  There was enough fuel and residual pressure in the lines to start the generators and to run them 
for a few minutes, but once running, the fuel pumps were powered to supply fuel.  As long as any one 
generator was running, the pumps ran at full capacity. 

Table 12–1.  Summary of modifications to base emergency power system in WTC 7. 

Year 

Day Tank/Generator 

Storage Tank 

Piping 

Comments 

1990 

No day tank permitted since 
base design included one on 
floor 5/nine generators on 
floor 5, 1,750 kW combined 
capacity 

Two 6,000 gal next to 
base tanks. 

Two 2½ in. pipes in 
separate rated shaft  

50 psi pressurized 
fuel system 

1994 

50 gal/125 kW on floor 9; 
generator room sprinklered 

Used existing base 
tanks 

1¼ in. in new 2 h 
rated dedicated shaft 

New transfer pump 
connected to existing 
storage tanks 

1994 

275 gal/350 kW on floor 8; 
generator room sprinklered 

Used existing base 
tanks 

2 in. in same 
dedicated shaft as 
above 

New transfer pump 
connected to existing 
storage tanks 

1999 

275 gal/three 500 kW on 
floor 7; smoke detectors in 
generator room 

6,000 gal on floor 1, in 
4 h rated enclosure; 
gaseous (clean) fire 
suppression system; 
space below tank 
sprinklered 

10 gauge conduit in 
2 h rated enclosure 

Storage tank kept 
filled from base 
storage tanks. 

 

 

background image

Chapter 12 

 

Draft for Public Comment 

174

 

NIST NCSTAR 1-1, WTC Investigation

 

5TH FLOOR

4TH FLOOR

3RD FLOOR

2ND FLOOR

1ST FLOOR

DISTRIBUTION SYSTEM

BASE BULDING

9TH FLOOR

8TH FLOOR

6TH FLOOR

7TH FLOOR

AMERICAN EXPRESS
DISTRIBUTION SYSTEM

DISTRIBUTION SYSTEM

AMBASSADOR CONSTRUCTION

SALOMON BROTHERS
DISTRIBUTION SYSTEM

MAYOR'S OFFICE
DISTRIBUTION SYSTEM

(QTY. OF 2)

(QTY. OF 9)

(QTY. OF 3)

DAY TANK

STORAGE TANK

EMERGENCY GENERATOR

PUMP SET

LEGEND

 

Figure 12–1.  Section plan showing the final locations of the fuel oil distribution 

components.  

background image

Draft for Public Comment 

 

WTC 7 Fuel System 

NIST NCSTAR 1-1, WTC Investigation 

175

 

12.2.2 Ambassador 

Modification 

The Ambassador modification to the base system was performed in 1994.  A new transfer pump set 
(145 gph at 100 psi) was installed and connected to the existing main storage tanks.  A new 1¼ in. supply 
riser was located in a new 2 h shaft dedicated for the fuel distribution system, constructed of 4 in. 
masonry and located at the south end of the center bank of passenger elevators.  The line ran to a single 
125 kW generator with a 50 gal day tank mounted in a 100 gal basin on the 9th floor.  Controls and 
alarms were the same as the base system.  The transfer pipes were the same double wall design and, 
outside the masonry shaft, were covered with a 2 h vermiculite.  The area of the generator on the 9th floor 
was sprinklered.  No design criteria were located, but the pipe sizes for the entire 9th floor are consistent 
with a light hazard pipe schedule design. 

12.2.3 

American Express Modification 

At about the same time in 1994, American Express installed a system to supply their operations.  Another 
new pump set rated 170 gph (at 100 psi) was installed on the first floor and was tapped into the existing 
base system pipes and tanks.  Another 2 in. supply pipe ran in the same masonry shaft used for the 
Ambassador system to a 275 gal day tank and a single 350 kW generator on the 8th floor.  Controls and 
alarms were the same as the base system.  The 8th floor generator room was protected with sprinklers 
designed to light hazard criteria.   

12.2.4 

Mayor’s Office of Emergency Management (OEM) Modification 

In 1999, the Mayor’s Office of Emergency Management was constructed on the 7th floor.  This system 
differed from the others because the specifications were to provide an independent source of power for 
full operations for at least one week, requiring the installation of a new, 6,000 gal storage tank and three 
500 kW generators fed from a single 275 gal day tank on the 7th floor.  The main storage tank was 
located on the 1st floor of the building in an existing storage room adjacent to the elevators.  The room 
was modified by installing a raised structure on which the tank was installed, enclosed in 4 h masonry 
(8 in. concrete masonry unit) construction. 

A new fill pump set rated 2,000 gph at a design pressure of 125 psi was located in the 1st floor pump 
room along with a transfer pump set rated 700 gpm at a design pressure of 125 psi.  The 6,000 gal OEM 
tank was kept filled from the two 12,000 gal base system tanks by means of the fill pump.  The 1st floor 
tank room was protected with an Intergen suppression system with the space below the tank still 
sprinklered (high hazard).  The 7th floor generator room was not sprinklered but was protected by smoke 
detectors connected to the building alarm system. 

12.2.5 

Salomon Brothers Emergency Power System 

In 1990 Salomon Brothers installed a system to provide emergency power to their trading floor that was 
independent from the other systems in the building.  The Salomon Brothers system involved two 
6,000 gal tanks identical to and buried adjacent to the base system tanks under the loading dock on the 
south side of the building.  Salomon Brothers had a contract with a fuel delivery service who always 

background image

Chapter 12 

 

Draft for Public Comment 

176

 

NIST NCSTAR 1-1, WTC Investigation

 

maintained the tanks full.

52

  Therefore, both tanks likely contained 6,000 gal of fuel on 

September 11, 2001. 

The system utilized nine generators on the 5th floor with a combined capacity of 1,750 kW.  Seven 
cooling fan sets (four fans per set) were installed to provide cooling and combustion air to the generators.  
Three fan sets were installed on the north end of the east wall and four fan sets on the north end of the 
west wall.  There were exhaust louvers on the south end of the west wall.  These fans were arranged to 
come on when the generators were running. 

Since there was already a 275 gal day tank on the 5th floor associated with the base system, the New 
York City (NYC) Building Code did not permit another tank on that floor.  The Salomon Brothers system 
was designed with a pressurized fuel system without a storage tank near the generators.  Two 70 gpm at 
50 psi total head pumps were located in a separate enclosure in the existing fire pump room (not in the 
fuel pump room with the other transfer pumps).  A double supply and return pipe (each 2½ in. covered in 
2 in. of calcium silicate) were run in a separate shaft to the 5th floor where the pipes ran outside the 
mechanical room to the generators in three groups.  At the end of the pipe run, where the fuel supply pipe 
ended and the fuel return pipe began, there was a valve box containing a backpressure regulator, gauges, 
and a by-pass line.  This liquid tight valve box was mounted to the underside of the floor slab for the 
6th floor near generator #1. 

The transfer pumps were powered from the output of the generators.  In the event of a failure of utility 
power, all nine generators were started automatically.  This is to ensure that if any did not start there 
would be enough power.  Once up to speed, the control system would shut down generators that were not 
needed, but they could be restarted later if demand increased.  There was enough fuel and residual 
pressure in the lines to start the generators and to run them for a few minutes, but once running, the fuel 
pumps were powered to supply fuel.  As long as any one generator was running, the pumps ran at full 
capacity.   

The system also included cooling fan units (each consisting of four fans) with three units (rated 
30,000 cfm per fan, 12 fans) installed in the northeast corner of the 5th floor near generators 1 through 4, 
six units (rated 38,000 cfm per fan, 24 fans) in the northwest corner near generators 8 and 9, and exhaust 
louvers in the southwest corner near generators 5 through 7.  The fans were powered from the generators 
and ran whenever the generators were running.  They brought outside air into the building and across the 
generators.   

12.3 POSSIBLE 

FAILURE 

MODES 

Fuel oil piping systems like these are fairly common and are used to operate diesel generators and oil 
fired furnaces in many applications.  The systems generally use day tanks at the appliance kept filled from 
storage remote tanks through transfer pumps and piping.  The pipe-in-pipe design used in WTC 7 is quite 
robust and reliable in preventing leaking fuel from escaping the system.   

At the time WTC 7 was designed and built there were no seismic design requirements for buildings in 
New York City much less for piping systems.  More recent research into the failure of fire sprinkler 

                                                      

52

 Interview with Mike Catalano, maintenance person for Salomon Brothers, who was responsible for these systems. 

background image

Draft for Public Comment 

 

WTC 7 Fuel System 

NIST NCSTAR 1-1, WTC Investigation 

177

 

systems in earthquakes has resulted in seismic design requirements for critical piping systems in seismic 
zones.  The research on sprinkler systems has shown the need for lateral bracing to prevent the failure of 
the piping systems due to differential movement between the pipes and the building in an earthquake.   

A working hypothesis is that the impact sustained by WTC 7 from the collapse of WTC 1 resulted in 
fractures in the fuel piping system (both the fuel pipe and the containment pipe) especially at the point 
where the pipes entered the valve box, which was rigidly mounted to the underside of the floor slab.  With 
the base system and all of the modifications thereto, such a fracture would result in a small leak of 
residual fuel in the pipes at the point of the fracture.  A fracture of the pipe at the valve box would release 
fuel under pressure that, if ignited, could produce a spray fire and/or a pool fire very near column 79.   

Rupture of a day tank would release more fuel, but it would be contained by the overflow pan.  Not until 
the generators ran for long enough to drain the day tank to its low fuel level and bring on the transfer 
pumps would additional fuel and pressure in the transfer lines cause a more significant fuel leak.  
Depending on the number of generators connected to the day tank, this would require several hours. 

The Salomon Brothers pressurized system is different.  If the supply or return pipes were fractured along 
with the containment pipe and the generators started, the fuel pipes would be continuously pressurized, 
and any leak would continue until the storage tanks were empty as long as any one generator was running.   

NIST reviewed the report of an environmental contractor (Langan 2002) hired in the months after the 
collapse of WTC 7 to recover remaining fuel and to mitigate any environmental damage from the 
Salomon Brothers tanks.  The Salomon Brothers tanks were damaged and appeared to be empty, “ … 
Neither the UST’s (underground storage tanks) nor their associated piping contained any residual 
petroleum product.  No residual free product or sludge was observed in either UST.”   

The tanks were installed on a concrete slab over existing silty sand.  A layer of bedding gravel on the slab 
provided a foundation for the tank.  Examination of the gravel below the tanks and the sand below the 
slab showed some fuel contamination but none was observed in the organic marine silt/clay layer below.  
Also, the sand and soil below the slab was continuous below the adjacent base system tanks, which 
contained a total of 24,000 gal of fuel.  Thus, it is likely that a fuel leak in any of the tanks would result in 
fuel contamination in this soil. 

background image

Chapter 12 

 

Draft for Public Comment 

178

 

NIST NCSTAR 1-1, WTC Investigation

 

 

This page intentionally left blank. 

 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

179

 

Chapter 13 

F

INDINGS 

 

13.1 FINDINGS 

13.1.1 General 

Finding 1:

 The NYC Department of Buildings reviewed the WTC tower drawings in 1968 and provided 

comments to the PANYNJ concerning the plans in relation to the 1938 NYC Building Code.  The 
architect-of-record submitted to the PANYNJ responses to those comments, noting how the drawings 
conformed to the 1968 NYC Building Code.  All six comments made by the NYC Department of 
Buildings dealt with egress issues, but none questioned the large occupant loads for Windows on the 
World in WTC 1 or Top of the World in WTC 2.  

Finding 2:

 In 1993, the PANYNJ and the NYC Department of Buildings entered into a memorandum of 

understanding that restated the PANYNJ’s long-standing stated policy to ensure that its facilities in the 
City of New York meet and, where appropriate, exceed the requirements of the NYC Building Code.  The 
agreement also provided specific commitments to the NYC Department of Buildings regarding 
procedures to be undertaken by the PANYNJ to ensure that buildings owned or operated by the PANYNJ 
are in conformance with the Building Standards contained in the NYC Building Code.  Some salient 
points included in this agreement and the 1995 enhancement to the agreement are: 

 

Each project would be reviewed and examined for compliance with the Code. 

 

All plans would be prepared, sealed, and reviewed by New York State licensed professional 
engineers or architects. 

 

The PANYNJ engineer or architect approving the plans would be licensed in the State of 
New York and would not have assisted in the preparation of the plans.  

 

The person or firm performing the review and certification of plans for WTC tenants may be 
the same person or firm providing certification that the project had been constructed in 
accordance with the plans and specifications unless the proposed alteration would “change 
the character of the occupancy group under paragraph 27-237 of the New York City Building 
Code which would have been applicable to such space had such space been located in a 
privately owned building.” 

 

Variances from the Code, acceptable to the PANYNJ, would be submitted to the NYC 
Department of Buildings for review and concurrence. Disagreements between the PANYNJ 
and the NYC Department of Buildings over such variances from the Code would be referred 
to the Port Authority Board of Commissioners for resolution. 

Finding 3: 

While the PANYNJ entered into agreements with the NYC Department of Buildings in the 

1990s with regard to conformance of PANYNJ buildings constructed in New York City to the NYC 

background image

Chapter 13 

 

Draft for Public Comment 

180

 

NIST NCSTAR 1-1, WTC Investigation

 

Building Code and sought review and concurrence as required by the agreements, the PANYNJ was not 
required to yield, and appears not have yielded, approval authority to New York City.  The PANYNJ was 
created as an interstate entity “body corporate and politic,” under its charter, pursuant to Article 1 
Section 10 of the U.S. Constitution permitting compacts between states, and like many other 
nongovernmental and quasi-governmental entities in the United States is not subject to building and fire 
safety code requirements of any governmental jurisdiction.   

Finding 4:  

State and local jurisdictions do not require retention of documents related to the design, 

construction, operation, maintenance, and modifications of buildings, with few exceptions.  These 
documents are in the possession of building owners, contractors, architects, engineers, and consultants.  
Such documents are not archived for more than about 6 to 7 years, and there are no requirements that they 
be kept in safe custody physically remote from the building throughout its service life.  In the case of the 
WTC towers, the PANYNJ and its contractors and consultants maintained an unusually comprehensive 
set of documents, a significant portion of which had not been destroyed in the collapse of the buildings 
but could be assembled and provided to the investigation.  In the case of WTC 7, several key documents 
could not be reviewed since they were lost in the collapse of the building.   

Finding 5:

  Consistent with the practice at the time the (code) architect was responsible for specifying the 

fire protection and designing the egress system in accordance with the prescriptive provisions of the 
building code.  The architect and owner engaged the services of structural engineers to perform the 
structural design and to ensure that his/her design was properly implemented.  At that time the fire 
protection engineering profession was not sufficiently mature to require the same standard of care 
employed with the structural design.  There is no reason to believe that the involvement of a fire 
protection engineer at that time would have resulted in any differences in the design or performance of the 
fire protection systems.  However, the technical base and sophistication of the practice of fire protection 
engineering today is well advanced of where it was then.  Today, particularly when designing a building 
employing innovative features, the involvement of a fire protection engineer in a role similar to the 
structural engineer, and under the overall coordination of the Design Professional in Responsible Charge 
is central to the standard of care. Further, when designing the structure of selected tall buildings or 
selected other buildings to resist fires, or evaluating the fire resistance of such structures, it is essential for 
the structural engineer and the fire protection engineer to jointly provide the needed standard of care. 

13.1.2 Structural 

Safety 

Applicable Building Codes 

Finding 6:

 Although not required to conform to NYC codes, the PANYNJ adopted the provisions of the 

proposed 1968 edition of the NYC Building Code, more than three years before it went into effect.  The 
proposed 1968 edition allowed the PANYNJ to take advantage of less restrictive provisions and of 
technological advances compared with the 1938 edition, which was in effect when design began for the 
WTC towers in 1962.  The 1968 code: 

 

Changed partition loads from 20 psf to one based on weight of partitions per unit length (that 
reduced such loads for many buildings including the WTC buildings); and 

 

Permitted wind tunnel tests using models to establish design values for the wind load. 

background image

Draft for Public Comment 

 

Findings 

NIST NCSTAR 1-1, WTC Investigation 

181

 

Many of these newer requirements, instituted in the 1968 NYC Building Code, are contained in current 
model codes and building regulations. 

Structural Integrity 

Finding 7: Building codes lack 

 explicit structural integrity provisions to mitigate progressive collapse.  

Federal agencies have developed guidelines to mitigate progressive collapse and routinely incorporate 
such requirements in the construction of new federal buildings.  The United Kingdom incorporates such 
code requirements for all buildings.  New York City adopted by rule in 1973 a requirement for buildings 
to resist progressive collapse under extreme local loads.  The rules, which were adopted after the WTC 
towers were built but before WTC 7 was built, applied specifically to buildings that used precast concrete 
wall panels and not to other types of buildings.   

Finding 8: 

Building Codes lack minimum structural integrity provisions for the means of egress 

(stairwells and elevator shafts) in the building core that are critical to life safety.  In most tall buildings the 
core is designed to be part of the vertical gravity load carrying system of the structure.  However, in many 
of those buildings, especially in regions where earthquakes are not dominant, the core may not be part of 
the lateral load carrying system of the structure.  Thus, the core may be designed to carry only vertical 
gravity loads with no capacity to resist lateral loads, i.e., overturning moment and shear loads.  In such 
situations, the structural designer may prefer the use of partition walls over structural walls in the core 
area to reduce building weight.  The decision to have the core carry a specified fraction of the lateral 
design loads or be made part of a dual system to carry lateral loads, each of which would enhance the 
structural integrity of the core if structural walls were used, is left to the discretion of the structural 
engineer. Alternatively, stairway/elevator cores built with concrete or reinforced concrete block, which 
are not part of the lateral load carrying system, may be able to provide sufficient structural integrity if 
they meet, for example, ASTM E1996-03, or other more appropriate test for impact resistance.  In the 
case of the WTC towers, the core had 2 h fire-rated partition walls with little structural integrity and the 
core framing was required to carry only gravity loads.  Had there been a minimum structural integrity 
requirement to satisfy normal building and fire safety considerations, it is conceivable that the damage to 
stairways, especially above the floors of impact, may have been less extensive. 

Finding 9: 

Standards and code provisions for conducting wind tunnel tests and for the methods used in 

practice to estimate design wind loads from test results do not exist.  Building codes allow the 
determination of wind pressures from wind tunnel tests for use in design.  Such tests are frequently used 
in the design of tall buildings.  Results of two sets of wind tunnel tests conducted for the WTC towers in 
2002 by independent commercial laboratories as part of insurance litigation, and voluntarily provided to 
NIST by the parties to the litigation, show large differences, of as much as about 40 percent, in resultant 
forces on the structures, i.e., overturning moments and base shears.  Independent reviews by a NIST 
expert on wind effects on structures and a leading engineering design firm contracted by NIST indicated 
that the documentation of the test results did not provide sufficient basis to reconcile the differences. 
Wind loads were a major governing factor in the design of structural components that made up the frame-
tube steel framing system. 

background image

Chapter 13 

 

Draft for Public Comment 

182

 

NIST NCSTAR 1-1, WTC Investigation

 

13.1.3 Fire 

Safety 

Applicable Building Codes 

Finding 10: 

Although not required to conform to NYC codes, the PANYNJ adopted the provisions of the 

proposed 1968 edition of the NYC Building Code, more than three years before it went into effect.  The 
1968 edition allowed the PANYNJ to take advantage of less restrictive provisions compared  
with the 1938 edition that was in effect when design began for the WTC towers in 1962.  The 1968 code: 

 

Eliminated a fire tower

53

 as a required means of fire department access; 

 

Reduced the number of required stairwells from 6 to 3 and the size of doors leading to the 
stairs from 44 in. to 36 in. (by increasing stairway and door capacity allowances); 

 

Reduced the required fire rating of the shaft walls in the building core from 3 h to 2 h; and 

 

Permitted a 1 h reduction in fire rating for all structural components (columns from 4 h to 3 h 
and floor framing members from 3 h to 2 h) by allowing the owner/architect to select Class 
1B construction for business occupancy and unlimited building height. 

Many of these newer requirements, instituted in the 1968 NYC Building Code, are contained in current 
codes. 

Finding 11:

 In 1993, the PANYNJ adopted a policy providing for implementation of fire safety 

recommendations made by local government fire departments after a fire safety inspection of a PANYNJ 
facility and for the prior review by local fire safety agencies of fire safety systems to be introduced or 
added to a facility.  Later that year, the PANYNJ entered into an agreement with FDNY which reiterated 
the policy adopted by the PANYNJ, recognized the right of FDNY to conduct fire safety inspections of 
PANYNJ properties in the City of New York, provided guidelines for FDNY to communicate needed 
corrective actions to the PANYNJ, ensured that new or modified fire safety systems are in compliance 
with local codes and regulations, and required third-party review of such systems by a New York State 
licensed architect or engineer. 

Standard Fire-Resistance Tests 

Finding 12: 

Code provisions with detailed procedures to analyze and evaluate data from fire resistance 

tests of other building components and assemblies to qualify an untested building element do not exist.  
Based on available data and records, no technical basis has been found for selecting the spray-applied fire 
resistive material (SFRM) used (two competing materials were under evaluation) or its thickness for the 
large-span open-web floor trusses of the WTC towers.  The assessment of the fireproofing thickness 
needed to meet the 2 h fire rating requirement for the untested WTC floor system evolved over time: 

 

In October 1969, the PANYNJ directed the fireproofing contractor to apply ½ in. of 
fireproofing to the floor trusses.   

                                                      

53

 A fire tower (also called a smoke-proof stair) is a stairway that is accessed through an enclosed vestibule that is open to the 

outside or to an open ventilation shaft providing natural ventilation that prevents any accumulation of smoke without the need 
for mechanical pressurization. 

background image

Draft for Public Comment 

 

Findings 

NIST NCSTAR 1-1, WTC Investigation 

183

 

 

In 1999, the PANYNJ issued guidelines requiring that fireproofing be upgraded to 1½ in. for 
full floors undergoing alterations.   

 

Unrelated to the WTC buildings, an International Conference of Building Officials (ICBO) 
Evaluation Service report (ER-1244), re-issued June 1, 2001, using the same SFRM 
recommends a minimum thickness of 2 in. for “unrestrained steel joists” with “lightweight 
concrete” slab. 

Finding 13: 

Code provisions that require the conduct of a fire resistance test if adequate data do not exist 

from other building components and assemblies to qualify an untested building element are needed.  
Instead, several alternate methods based on other fire-resistance designs or calculations or alternative 
protection methods are permitted with limited guidance on detailed procedures to be followed.  Both the 
architect-of-record (in 1966) and the structural-engineer-of-record (in 1975) stated that the fire rating of 
the floor system of the WTC towers could not be determined without testing.  NIST has not found 
evidence indicating that such a test was conducted to determine the fire rating of the WTC floor system.  
The PANYNJ has informed NIST that there are no such test records in its files.   

Finding 14: 

Use of the “structural frame” approach, in conjunction with the prescriptive fire rating, 

would have required the floor trusses, the core floor framing, and perimeter spandrels in the WTC towers 
to be 3 h fire-rated, like the columns for Class 1B construction in the 1968 NYC Building Code.  Neither 
the 1968 edition of the NYC Building Code which was used in the design of the WTC towers, nor the 
2001 edition of the code, adopted the “structural frame” requirement.   The “structural frame” approach to 
fire resistance ratings requires structural members, other than columns, that are essential to the stability of 
the building as a whole to be fire protected to the same rating as columns.  This approach, which appeared 
in the Uniform Building Code (a model building code) as early as 1953, was carried into the 2000 
International Building Code (one of two current model codes) which states: “The structural frame shall be 
considered to be the columns and the girders, beams, trusses and spandrels having direct connections to 
the columns and bracing members designed to carry gravity loads.”  The WTC floor system was essential 
to the stability of the building as a whole since it provided lateral stability to the columns and diaphragm 
action to distribute wind loads to the columns of the frame-tube system. 

Finding 15: 

A technical basis to establish whether the construction classification and fire rating 

requirements in modern building codes are risk-consistent with respect to the design-basis hazard and the 
consequences of that hazard is needed.  The fire rating requirements, which were originally developed 
based on experience with buildings less than about 20 stories in height, have generally decreased over the 
past 80 years since historical fire data for buildings suggested considerable conservatism in those 
requirements.  However, for tall buildings, the likely consequences of a given threat to an occupant on the 
upper floors are more severe than the consequences to an occupant, say, on the first floor.  It is not 
apparent how the current height and area tables in building codes consider the technical basis for the 
progressively increasing risk to an occupant on the upper floors of tall buildings that are much greater 
than about 20 stories in height where access by firefighters without the availability of firefighter elevators 
is limited by physiological factors.  The maximum required fire rating in current codes applies to any 
building more than about 12 stories in height.  There are no additional categories for buildings above, for 
example, 40 stories and 80 stories, where different building classification and fire ratings requirements 
may be appropriate, recognizing factors such as the time required for stairwell evacuation without 
functioning elevators (e.g., due to power failure or major water leakage), the time required for first 
responder access without functioning elevators, the presence of sky lobbies and/or refuge floors, and 

background image

Chapter 13 

 

Draft for Public Comment 

184

 

NIST NCSTAR 1-1, WTC Investigation

 

limitations on the height of elevator shafts.  The 110-story WTC towers, initially classified as Class IA 
based on the 1938 NYC Building Code, were classified as Class 1B before being built to take advantage 
of the provisions in the 1968 edition of the code.  This re-classification permitted a reduction of 1 h in the 
fire rating of the components (columns from 4 h to 3 h and floor framing members from 3 h to 2 h). 

Fire Performance of Structures 

Finding 16:

 Rigorous field application and inspection provisions and regulatory requirements to ensure 

that the as-built condition of the passive fire protection, such as SFRM, conforms to conditions found in 
fire resistance tests of building components and assemblies is needed.  For example, provisions are not 
available to ensure that the as-applied average fireproofing thickness and variability (reflecting the quality 
of application) is thermally equivalent to the specified minimum fireproofing thickness.  In addition, 
requirements are not available for in-service inspections of passive fire protection during the life of the 
building.  The adequacy of the fireproofing of the WTC towers posed an issue of some concern to the 
PANYNJ over the life of the buildings, and the availability of accepted requirements and procedures for 
conducting in-service inspections would have provided useful guidance 

Finding 17: 

Structural design does not consider fire as a design condition, as it does the effects of dead 

loads, live loads, wind loads, and earthquake loads.  Current prescriptive code provisions for determining 
fire resistance of structures—used in the design of the WTC towers and WTC 7— are based on tests using 
a standard fire that may be adequate for many simple structures and for comparing the relative 
performance of structural components in more complex structures.  A building system with 3 h rated 
columns and 2 h rated girders and floors could last longer than 3 h or shorter than 2 h depending upon the 
performance of the structure as a 3-dimensional system in a real fire.  The standard tests cannot be used to 
evaluate the actual performance (i.e., load carrying capacity) in a real fire of the structural component, or 
the structure as a whole system, including the connections between components.  Performance-based code 
provisions and standards are not available for use by engineers, as an alternative to the current 
prescriptive fire rating approach, to (1) evaluate the system performance of tall-building structures under 
real fire scenarios, and (2) enable risk consistent design with appropriate thickness of  passive protection 
being provided where it is needed on the structure.  Standards development organizations, including the 
American Institute of Steel Construction, have initiated development of performance-based provisions to 
consider fire effects in structural design. 

Finding 18: 

Detailed procedures to select appropriate design-basis fire scenarios to be considered in the 

performance-based design of the sprinkler system, compartmentation, and passive protection of the 
structure are needed.  The standard fire in current prescriptive fire resistance tests is not adequate for use 
in performance-based design.  While the NFPA 5000 model building code contains general guidance on 
design fire scenarios (the IBC Performance Code contains no such guidance), the details of the scenarios 
are left to the fire engineer and regulatory official.  The three major scenarios that are not considered 
adequately are: frequent but low severity events (for design of sprinkler system), moderate but less 
frequent events (for design of compartmentation), and a maximum credible fire (for design of passive fire 
protection on the structure).  The maximum credible fire scenario for passive protection of structures 
would assume that the sprinkler system is compromised or overwhelmed and that there is no active 
firefighting, as is explicitly considered for US Department of Energy facilities.  These building-specific 
representative fire scenarios are similar in concept, though not identical, to the approach used in building 
design where the performance objectives and design-basis of the hazard are better defined (e.g., a two-

background image

Draft for Public Comment 

 

Findings 

NIST NCSTAR 1-1, WTC Investigation 

185

 

level design that includes an operational event with a 10 percent probability of occurrence in 50 years and 
a life safety event with a 2 percent probability of occurrence in 50 years). The design-basis fire hazards 
for the WTC towers and WTC 7 are unknown, and it is difficult to evaluate the performance of the fire 
protection systems in these buildings under specific fire scenarios. 

Finding 19: 

Code provisions to ensure that structural connections are provided the same degree of fire 

protection as the more restrictive protection of the connected elements are needed.  The provisions that 
were used for the WTC towers and WTC 7 did not require specification of a fire-rating requirement for 
connections separate from those for the connected elements. It is not clear what the fire rating of the 
connections were when the connecting elements had different fire ratings and whether the applied 
fireproofing achieved that rating.  

Finding 20: 

A technical basis to establish whether the minimum mechanical and durability related 

properties of SFRM are sufficient to ensure acceptable in-service performance in buildings is needed.  
While minimum bond strength requirements exist, there are no serviceability requirements for such 
materials to withstand typical shock, impact, vibration, or abrasion effects over the life of a building.  
There are existing testing standards for determining many of these properties, but the technical basis is 
insufficient to establish serviceability requirements.  Knowledge of such serviceability requirements is 
relevant to determine the post-impact fireproofing condition of the WTC towers. 

Finding 21: 

Validated and verified tools for use in performance-based design practice to analyze the 

dynamics of building fires and their effects on the structural system that would allow engineers to 
evaluate structural performance under alternative fire scenarios and fire protection strategies are needed.  
Existing tools are either too simplified to adequately capture the performance of interest or too complex 
and computationally demanding and lack adequate validation.  While considerable progress has been 
made in recent years, significant work remains to be done before adequate tools are available for use in 
routine practice. NIST has had to further develop and validate existing tools to investigate the fire 
performance of the WTC towers and WTC 7. 

Compartmentation and Sprinklers 

Finding 22

: Building fire protection is based on a four-level hierarchical strategy comprising detection, 

suppression (sprinklers and firefighting), compartmentation, and passive protection of the structure.   

 

Detectors are typically used to activate fire alarms and notify building occupants and 
emergency services.   

 

Sprinklers are designed to control small and medium fires and to prevent fire spread beyond 
the typical water supply design area of about 1,500 ft

2

 

Compartmentation mitigates the horizontal spread of more severe but less frequent fires and 
typically requires fire-rated partitions for areas of about 7,500 ft

2

.  Active firefighting 

measures also cover up to about 5,000 ft

2

 to 7,500 ft

2

.   

 

Passive protection of the structure seeks to ensure that a maximum credible fire scenario, with 
sprinklers compromised or overwhelmed and no active firefighting, results in burnout, not 
overall building collapse.  The intent of building codes is also for the building to withstand 

background image

Chapter 13 

 

Draft for Public Comment 

186

 

NIST NCSTAR 1-1, WTC Investigation

 

local structural collapse until occupants can escape and the fire service can complete search 
and rescue operations.   

Compartmentation of spaces is a key building fire safety requirement to limit fire spread.  The WTC 
towers initially had 1 h fire-rated partitions separating tenants (demising walls) that extended from the 
floor to the suspended ceiling, not the floor above (the ceiling tiles were not fire rated).  Over the years, 
these partitions were replaced with partitions that were continuous from floor to floor (separation wall) as 
required by the 1968 NYC Building Code.  Some partitions had not been upgraded by 1997, and a 
consultant recommended to the PANYNJ that it develop and implement a survey program to ensure that 
the remediation process occurred as quickly as possible.  It appears that with few exceptions, nearly all of 
the floors not upgraded were occupied by a single tenant, and it is not clear whether separation walls 
would have mattered in terms of meeting the 1968 code.  The PANYNJ adopted guidelines in 1998 that 
required such partitions to provide a continuous fire barrier from top of floor to underside of slab. 

Finding 23: 

Building codes typically require 1 h fire-rated tenant separations but do not impose minimum 

compartmentation requirements (e.g., 13,000 ft

2

) for buildings with large open floor plans to mitigate the 

horizontal spread of fire.  This is the case with both the 1968 NYC Building Code, which did not require 
sprinklers in occupied spaces on or above the ground floor, and the 2001 NYC Building Code, which 
requires sprinklers in Group E (Business) buildings over 100 feet in height.  The sprinkler option was 
chosen for the WTC towers in preference to the compartmentation option in meeting the subsequent 
requirements of Local Law 5 adopted by New York City in 1973.  Thus, if there was only one tenant on a 
WTC floor there would be no horizontal compartmentation requirement.  Conversely, if there were a 
large number of tenants on a WTC floor, it would be highly compartmented with separation walls.  The 
affected floors in the WTC towers were mostly open—with a modest number of perimeter offices and 
conference rooms and an occasional special purpose area.  Some floors had two tenants and those spaces, 
like the core areas, were partitioned (slab to slab).  Photographic and videographic evidence confirms that 
even non-tenant space partitions (such as those that divided spaces to provide corner conference rooms) 
provided substantial resistance to fire spread in the affected floors.  For the duration of about 50 min to 
100 min prior to collapse of the WTC towers that the fires were active, the presence of undamaged 1 h 
fire-rated compartments may have assisted in mitigating fire spread and consequent thermal weakening of 
structural components. 

Finding 24: 

State and local building regulations are needed that require installation of sprinklers in 

existing buildings on a reasonable time schedule, not as an option in lieu of compartmentation. 
Functioning sprinklers can provide significant improvement in safety for most common building fires and 
prevent them from becoming large fires.  NYC promulgated local laws in 1973 and 1984 to encourage 
installation of sprinklers in new buildings and is now considering a law to require sprinklers in existing 
buildings.  The WTC towers were fully sprinklered by 2001, about 30 years after their construction.  
Sprinklering of the tenant floors in the WTC towers was completed by October 1999, while sprinklering 
of the skylobbies was still underway at that time.  The sprinkler system was installed in three phases.  
Phase 1 was completed during initial building construction and included the sub-grade areas.  Phase 2 was 
completed in 1976, in compliance with Local Law 5, and included sprinklering the corridors, storage 
rooms, lobbies, and certain tenant spaces.  Phase 3 was begun in 1983 and completed in 2001 and resulted 
in fully sprinklering the buildings. 

Finding 25: 

Modern building codes allow a lower fire rating for structural elements when a building is 

sprinklered.  This trade-off provides an economic incentive to encourage installation of sprinklers.  

background image

Draft for Public Comment 

 

Findings 

NIST NCSTAR 1-1, WTC Investigation 

187

 

Sprinklers provide better intervention against small and medium fires, fires which are more likely to occur 
than a WTC disaster, as long as the water supply is not compromised and there is redundant technology in 
place.  The required technical basis is not available to establish whether the “sprinkler trade-off” in 
current codes adequately considers fire safety risk factors such as: (1) the complementary functions of 
sprinklers and fire-protected structural elements, (2) the different fire scenarios for which each system is 
designed to provide protection, and (3) the need for redundancy should one system fail.  It is noteworthy 
that the British Standards Institution has established a group to review all the sprinkler trade-offs 
contained in their standards.  No such formal review has yet been initiated in the United States.  Although 
the classification and fire rating of the WTC towers did not take advantage of the sprinkler-tradeoff since 
such provisions were not contained in the 1968 NYC Building Code, had such provisions existed, they 
would have permitted a lower fire rating for many WTC building elements.   

Use of Elevators in Emergencies 

Finding 26: 

With a few special exceptions, building codes in the United States do not permit the use of 

fire-protected elevators for routine emergency access by first responders or as a secondary method (after 
stairwells) for emergency evacuation of building occupants.  The use of elevators by first responders 
would additionally mitigate counterflow problems in stairwells.  While the United States conducted 
research on specially protected elevators in the late 1970s, the United Kingdom along with several other 
countries that typically utilize British standards have required such “firefighter lifts,” located in protected 
shafts, for a number of years.  Without functioning elevators (e.g., due to a power failure or major water 
leakage), first responders carrying gear typically require about a minute per floor to reach an incident 
using the stairs.  While it is difficult to maintain this pace for more than about the first 20 stories, it would 
take a first responder about an hour to reach, for example, the 60th floor of a tall building if that pace 
could be maintained.  Such a delay, combined with the resulting fatigue and physical effects on first 
responders that were reported on September 11, 2001, would make firefighting and rescue efforts difficult 
even in tall building emergencies not involving a terrorist attack.  Each of the WTC towers had 
106 elevators, and WTC 7 had 38 elevators. By code, the elevators could not be used for fire service 
access or occupant egress during an emergency since they were not fire-protected, nor were they located 
in protected shafts.  The elevators were equipped through normal modernization with fire service recall.  
Most were damaged by the aircraft impacts; though prior to the impact in WTC 2 the elevators were 
functioning and contributed greatly to the much faster initial evacuation rate in WTC 2. 

 

background image

Chapter 13 

 

Draft for Public Comment 

188

 

NIST NCSTAR 1-1, WTC Investigation

 

 

This page intentionally left blank. 

 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

189

 

Chapter 14 

R

EFERENCES

 

AIA (American Institute of Architects).  2000.  AIA Masterspec Section 07811, Sprayed Fire-Resisting 

Materials. Washington DC. 

AWCI (Association of Wall and Ceiling Industries).  1997.  Technical Manual 12-A, 3rd ed.  Standard 

Practice for the Testing and Inspection of Field Applied Sprayed Fire-Resistive Materials; An 
Annotated Guide.  Falls Church, VA. 

ASME (ASTM International).  2000.  Safety Code for Elevators and Escalators ASME 17.1, American 

Society of Mechanical Engineers, New York, NY. 

Bell and Stanton, Public Relations. 1964. Polytechnic Institute of Brooklyn, 757 Third Avenue, New 

York, NY. 

BOCA/BBC (Building Officials and Code Administrators/Basic Building Code).  1965.  BOCA Basic 

Building Code,

 

Fourth Edition, Building Officials Conference of America, Chicago, IL.   

Bhol, S.  2005.  Email from Saroj Bhol to Richard Bukowski confirming the dates that Windows on the 

World opened and when it reopened following the bombing.  March 25. 

Bukowski, R.W.  2003.  Protective Elevators for Egress and Access During Fires in Tall Buildings, 

Proceedings of the CIB-CTBUH Conference on Tall Buildings, Kuala Lumpur, Malaysia.  
October 20-23. 

Coty, Eric H. (Rolf Jensen & Associates).  1997.  Included as Attachment A to World Trade Center – 

Code Compliance Evaluation compiled by PANYNJ October 15, 1999, March 14. 

CTB&UH (Council on Tall Buildings and Urban Habitat).  1980.  Monograph on Planning and Design of 

Tall Buildings, Volume CL-Tall Building Criteria and Loading, American Society of Civil Engineers, 
Reston, VA. 

ENR (Engineering News Record). 1964.  Tall Towers, 

Engineering News Record

, July 9, McGraw-Hills 

Construction Weekly, New York, NY.  

Fasullo, E. (Port Authority of New York and New Jersey).  1995.  Letter to R. Visconti, Deputy 

Commissioner, New York City Department of Buildings, confirmation of December 6, 1994, meeting 
on agreement for plan regarding egress requirements from World Trade Center 1, floors 106 and 107, 
January 29 (WTCI-159-P). 

Field, L.S. 1987.  Memorandum from Lester S. Field to Robert J. Linn, Deputy Director for Physical 

Facilities, WTD, January 15 (WTCI-19-P). 

background image

Chapter 13 

 

Draft for Public Comment 

190

 

NIST NCSTAR 1-1, WTC Investigation

 

IBC (International Building Code). 2000.  International Building Code, International Code Council, Falls 

Church, VA. 

Kahn, Fazlur R. and El Nimeiri, Mahjoub M. 1983. Structural Systems for Multi-Use High-Rise 

Buildings, Volume SC-1, Developments in Tall Buildings, Council on Tall Buildings and Urban 
Habitat, Huchinson Ross Publishing Company, Stroudsburg, PA. 

Langan. 2002. Oversight Report for Removal of Salomon Smith Barney, Inc. UST’s Former 7 World 

Trade Center Building New York, New York prepared by Langan Engineering & Environmental 
Services, P.C., for Silverstein Properties, Inc., Langan Project 5544403, August 22. 

LERA (Leslie E. Robertson Associates).  1996.  One and Two World Trade Center Damper Testing.  

May (WTCI-230-L). 

MCC (Municipal Code of Chicago).  1967.  Municipal Code of Chicago Relating to Buildings

 

(As 

Amended to and including January 1, 1967), Index Publishing Corp., Chicago, IL. 

NBS (National Bureau of Standards).  1935.  Design and Construction of Building Exits, National Bureau 

of Standards Miscellaneous Publication M151, U.S. Government Printing Office, Washington, DC. 

NFPA (National Fire Protection Association).  1966.  Life Safety Code, NFPA 101, Quincy, MA. 

NFPA (National Fire Protection Association).  2003.  Building Construction and Safety Code, 

NFPA 5000, Quincy, MA. 

NYCBC (New York City Building Code).  1968.  Building Code—Local Law 76 of the City of New 

York, New York, NY. 

NYCBC (New York City Building Code).  2001.  Building Code of the City of New York,

 

2001 Edition, 

Gould Publications, Binghamton, NY. 

NYSBC (New York State Building Code).  1964.  State Building Construction Code Applicable to 

General Building Construction, Building Code Bureau, State of New York, New York, NY, 
December 1. 

PANYNJ (Port Authority of New York and New Jersey).  1997.  Port Authority Facility Condition 

Survey Program – 7 World Trade Center. Engineering Quality Assurance Division, Engineering 
Department.  April.  (WTCI-122-P). 

PANYNJ (Port Authority of New York and New Jersey).  1999.  World Trade Center – Code Compliance 

Evaluation, October 15 (WTCI-161-P). 

Rivera and Rinaldi.  1993. Report on Fire and Building Codes and the Jurisdiction and Compliance of 

Federal, State, State Authorities and Foreign Government Buildings, Carlos M. Rivera, Fire 
Commissioner and Rudolph J. Rinaldi, Commissioner of Buildings, March 25. 

background image

Draft for Public Comment 

 

Findings 

NIST NCSTAR 1-1, WTC Investigation 

191

 

Robertson, Leslie, and See, Saw-Teen. 1987. Preliminary Design of High-Rise Buildings, Chapter 11, 

Building Structural Design Handbook, Richard White and Charles Salmon, editors, John Wiley & 
Sons, New York, NY. 

Schaffner, Charles E.  1964.  The New Building Code for New York City – The Performance 

specification, 

The Magazine of Standards, 

October. 

SHCR (Skilling, Helle, Christiansen, & Robertson).  1967.  Viscoelastic Damping Units, The World 

Trade Center Report No. DU-3 (WTCI-1006-L). 

Simiu, Emil, and Scanlan, Robert H.  1996.  

Wind Effects on Structures

, John Wiley & Sons, Inc, New 

York, NY. 

Solomon, Joseph H.  (Emery Roth & Sons).  1975.  Letter to Malcolm P. Levy (General Manager, World 

Trade Center Operations), February 18. 

Sullivan, Richard C. 1964. New Concept in Vertical Transport, 

Westsider, 

29, Fall. 

UBC (Uniform Building Code).  1988.  Uniform Building Code, International Conference of Building 

Officials, Whittier, CA. 

UL (Underwriters’ Laboratories).  2001.  Fire Resistance Directory 2001, Underwriters Laboratories, Inc. 

Northbrook, IL 60062. 

 

background image

Chapter 13 

 

Draft for Public Comment 

192

 

NIST NCSTAR 1-1, WTC Investigation

 

 

This page intentionally left blank. 

background image

 

NIST NCSTAR 1-1, WTC Investigation 

193

 

Appendix A 

S

UPPORTING 

D

OCUMENTS FOR 

C

HAPTER 

This appendix contains the supporting documents that are referenced in Chapter 1 of this report.  All of 
the documents contained in this appendix are reproduced with permission of The Port Authority of New 
York and New Jersey.  Table A–1 contains a summary of supporting documents and their location within 
this appendix.  The footnote numbers given in the table correspond to those in Chapter 1. 

Table A–1.  Supporting documents for Chapter 1. 

Footnote 

Number Document 

Title Page(s) 

Letter dated May 15, 1963, from Malcolm P. Levy (Chief, 
Planning Division, World Trade Department) to Minoru Yamasaki 
(Minoru Yamasaki & Associates) 

194 

Letter dated September 29, 1965, from Malcolm P. Levy (Chief, 
Planning Division, World Trade Department) to Minoru Yamasaki 
(Minoru Yamasaki & Associates) 

195 

Memorandum dated June 22, 1965, from John M. Kyle (Chief 
Engineer, PANYNJ) to Malcolm P. Levy (Chief, Planning 
Division, World Trade Department) 

196 

Memorandum dated January 15, 1987, from Lester S. Feld (Chief 
Structural Engineer, World Trade Department) to Robert J. Linn 
(Deputy Director for Physical Facilities, World Trade Department) 

197 

Letter dated February 18,1975, from Joseph H. Solomon (Emery 
Roth & Sons) to Malcolm P. Levy (Chief, Planning Division, 
World Trade Department) 

199 

 

background image

Appendix A 

 

Draft for Public Comment 

194

 

NIST NCSTAR 1-1, WTC Investigation

 

 
 

background image

Draft for Public Comment 

 

Supporting Documents for Chapter 1  

NIST NCSTAR 1-1, WTC Investigation 

195

 

 

background image

Appendix A 

 

Draft for Public Comment 

196

 

NIST NCSTAR 1-1, WTC Investigation

 

 

 

background image

Draft for Public Comment 

 

Supporting Documents for Chapter 1  

NIST NCSTAR 1-1, WTC Investigation 

197

 

 

 

background image

Appendix A 

 

Draft for Public Comment 

198

 

NIST NCSTAR 1-1, WTC Investigation

 

 

 

 

background image

Draft for Public Comment 

 

Supporting Documents for Chapter 1  

NIST NCSTAR 1-1, WTC Investigation 

199

 

 

background image

Appendix A 

 

Draft for Public Comment 

200

 

NIST NCSTAR 1-1, WTC Investigation

 

 

 

background image

Draft for Public Comment 

 

Supporting Documents for Chapter 1  

NIST NCSTAR 1-1, WTC Investigation 

201

 

 

 

background image

Appendix A 

 

Draft for Public Comment 

202

 

NIST NCSTAR 1-1, WTC Investigation

 

 

This page intentionally left blank.

background image

 

NIST NCSTAR 1-1, WTC Investigation 

203

 

Appendix B 

S

UPPORTING 

D

OCUMENTS FOR 

C

HAPTERS 

2

 AND 

This appendix contains the supporting documents that are referenced in Chapters 2 and 3 of this report.  
All of the documents contained in this appendix are reproduced with permission of The Port Authority of 
New York and New Jersey.  Table B–1 contains a summary of supporting documents and their location 
within this appendix.  The footnote numbers given in the table correspond to those in Chapters 2 and 3. 

Table B–1.  Supporting documents for Chapter 3. 

Footnote 

Number Document 

Title Page(s) 

13 

Memorandum of Understanding Between the New York City 
Department of Buildings and the PANYNJ 1993 (WTCI-160-P) 

204 

14 

Supplement to Memorandum of Understanding Between the New 
York City Department of Buildings and the PANYNJ 1995 
(WTCI-113-P) 

208 

15 

Original letter dated January 25, 1968 from Joseph H. Solomon 
(Emery Roth & Son) to Malcolm P. Levy (General Manager, 
World Trade Center Operations). Illegible copy received from 
PANYNJ. 

212 

15 

Letter dated January 25, 1968, from Joseph H. Solomon (Emery 
Roth & Son) to Malcolm P. Levy (General Manager, World Trade 
Center Operations) reconstructed by NIST. 

214 

 

background image

Appendix B 

 

Draft for Public Comment 

204

 

NIST NCSTAR 1-1, WTC Investigation

 

 

background image

Draft for Public Comment 

 

Supporting Documents for Chapters 2 and 3  

NIST NCSTAR 1-1, WTC Investigation 

205

 

 

 

background image

Appendix B 

 

Draft for Public Comment 

206

 

NIST NCSTAR 1-1, WTC Investigation

 

 

background image

Draft for Public Comment 

 

Supporting Documents for Chapters 2 and 3  

NIST NCSTAR 1-1, WTC Investigation 

207

 

 

 

background image

Appendix B 

 

Draft for Public Comment 

208

 

NIST NCSTAR 1-1, WTC Investigation

 

background image

Draft for Public Comment 

 

Supporting Documents for Chapters 2 and 3  

NIST NCSTAR 1-1, WTC Investigation 

209

 

 

background image

Appendix B 

 

Draft for Public Comment 

210

 

NIST NCSTAR 1-1, WTC Investigation

 

 

background image

Draft for Public Comment 

 

Supporting Documents for Chapters 2 and 3  

NIST NCSTAR 1-1, WTC Investigation 

211

 

 

background image

Appendix B 

 

Draft for Public Comment 

212

 

NIST NCSTAR 1-1, WTC Investigation

 

 

 
 

background image

Draft for Public Comment 

 

Supporting Documents for Chapters 2 and 3  

NIST NCSTAR 1-1, WTC Investigation 

213

 

 

 

 

background image

Appendix B 

 

Draft for Public Comment 

214

 

NIST NCSTAR 1-1, WTC Investigation

 

 

January 25, 1968 

 

Mr. Malcolm P. Levy, Chief 

Planning and Construction Division 

The World Trade Center 

111 Eighth Avenue 

New York, New York 

 

Re: The World Trade Center Building Department Review 

 

Dear Mal, 

 

We have reviewed the comments submitted by Commissioner Ferro with regard to conformance of the World 
Trade Center with the Building Code.  The Tower plans adhere to the Proposed Building Code with respect to 
all five points noted. 

 

1.

 

The Proposed Code provides for a stair capacity of 60 persons per 22 inch unit of exit width.  Each 
Tower floor has two 3’ 8” stairs (two units each) and one 4’ 8” stair (two and one half units) for a total 
of 6 ½ units. The stairs, therefore, have a capacity of 390 persons per floor.  The largest floor area is 
about 36,500 square feet net on the 106

th

 floor.  At one person per hundred square feet, there will be 

365 persons per floor, well within the permissible maximum. 

2.

 

The maximum distance ---corner of the --- is about 140---.  The Proposed Code permits a maximum 
travel distance of 200 feet in an unsprinklered building in occupancy group classification E (business). 

3.

 

No fire tower is required under the Proposed Code. 

4.

 

All cellar stairs are completely enclosed in two hour fire-rated masonry construction as required by the 
Proposed Code.  Each cellar stair is contained in a continuous enclosure leading directly to the street, 
the street floor lobby, or the Concourse floor landing to the street.  The Concourse floor is considered 
as an underground street in accordance with the interpretation made by the Port Authority. 

5.

 

The cellar stairs that are to be used for tenant storage are less than ten percent of the total area of the 
building.  In accordance with the Proposed Code, therefore, they are treated the same as office 
building with regard to egress requirements. 

 

The garage spaces are limited to storage of cars with a maximum tank capacity of 26 gallons.  There will be

 

no 

servicing of cars or dispensing of fuel.  All garage areas will be sprinklered.  The Proposed Code limits the 
maximum distance to stairs for this type of garage to 150 feet without distinction to garages above or below 
grade.  The World Trade Center is in conformance with these requirements. 

 

Cordially, 

Signed by Joseph H. Solomon 

Emory Roth & Sons 

background image

Draft for Public Comment 

 

Supporting Documents for Chapters 2 and 3  

NIST NCSTAR 1-1, WTC Investigation 

215

 

 

This page intentionally left blank.